Critical Path Method (CPM) Problem Question Using the table of data provided, answer the following questions:

: 1. What is the minimum time required to complete the project?


Activity Dependencies Duration

A B C D E F G H I J

A, F B C, D, E D, G E G

2 2 4 8 3 4 3 2 7 6

2. What is the Critical Path for this project?

3. What is the Early Start (ES) date for activity E?

4. What is the Late Start (LS) date for activity A?

5. What is the Late Finish (LF) date for activity F?

6. What is the Total Float / Slack for activity H?

7. What is the Free Float / Slack between activities D & G?

Example prepared by Bradford Peyton Oct 2008

Critical Path Method (CPM) Problem Solution


4 0 4 0 2 6 6 6 2 9 9 9 11

A 2

E 3

I 7

16 18

0 0 0

0 2 2 2 2

B 2

F 4

6 6

S
0 5

0 4 9 9 9

0 12 12 12 12

F
18 18

C 4

G 3

J 6

1 0 1

4 8 9 12 16

D 8

H 2

14 18

Free Float/Slack = Answers =

Early Start (successor) Early Finish (predecessor) (1) 18 days / (2) BFEGJ / (3) 6 days / (4) 4 days / (5) 6 days / (6) 4 days / (7) 1 day

Example prepared by Bradford Peyton Oct 2008