Você está na página 1de 95

131127367.xls.

ms_office

Pgina 1 de 95

GOBIERNO DEL ESTADO DE QUINTANA ROO


COMISION DE AGUA POTABLE Y ALCANTARILLADO
PRESUPUESTO DE CONSTRUCCION
OBRA:
AMPLIACIN DE RED DE DISTRIBUCIN DE AGUA POTABLE
LOCALIDAD: MANUEL VILA CAMACHO
MUNICIPIO:
OTHON P. BLANCO, Q.ROO
CLAVE

CONCEPTO

UNIDAD

CANT.

PRELIMINARES
LIMPIEZA, TRAZO Y NIVELACION DEL TERRENO PARA TENDIDO DE TUBERIA,
ESTABLECIENDO EJES CON TRANSITO. INCLUYE: MATERIALES, MANO DE OBRA
Y HERRAMIENTA

ML

2,433.10

1.102

SONDEOS PARA DETECCION DE DUCTOS DE AGUA POTABLE, ELECTRICIDAD,


TELEFONIA O CUALQUIER OTRO. INCLUYE: EXCAVACION EN CUALQUIER TIPO
DE MATERIAL CON DIMENSIONES DE 80X80 CMS., RELLENO DE CEPA, MANO DE
OBRA, HERRAMIENTA Y EQUIPO.

PZA

30.00

1.103

CORTE CON MAQUINA CORTADORA Y REPOSICION DE CARPETA ASFALTICA


ELABORADA CON EL SISTEMA DE 2 RIEGOS DE SELLO CON EMULSION
ASFALTICA PARA IMPREGNACION Y DE ROMPIMIENTO RAPIDO Y MATERIAL 2 Y
3B EN PROPORCIONES DE 1.7,1.7,12 Y 12 LTS/M2

M2

1
1.10
1.101

1.20
1.201

1.30
1.301

P.U.

IMPORTE

RED DE DISTRIBUCIN

EXCAVACIONES
EXCAVACION DE ZANJAS EN CUALQUIER TIPO DE MATERIAL HASTA 2.00 M DE
PROFUNDIDAD, CON USO DE EQUIPO MECANICO O ZANJADORA,
DEPOSITANDO EL MATERIAL A LADO DE LA ZANJA. INCLUYE: AFINE DE FONDO
Y TALUDES, EQUIPO, MANO DE OBRA Y HTA.

PLANTILLAS
PLANTILLA CON MATERIAL PRODUCTO DE BANCO SELECCIONADO MEDIANTE
USO DE CRIBA, APISONADO MANUALMENTE. INCLUYE SUMINISTRO DE
MATERIALES, ACARREOS, MANO DE OBRA Y HTA.

M3

M3

1.40
1.401

RELLENOS
RELLENO EN ZANJAS CON MATERIAL PRODUCTO DE EXCAVACION DE
ZANJADORA CRIBADO, COMPACTADO POR UNIDAD DE OBRA TERMINADA CON
USO DE EQUIPO MECANICO. INCLUYE: AGUA PARA HUMEDAD, SUMINISTRO,
ACARREO Y APLICACION DE TODOS LOS MATERIALES, EQUIPO, MANO DE
OBRA Y HERRAMIENTA.

M3

1.402

RELLENO DE ZANJAS CON MATERIAL PRODUCTO DE BANCO, COMPACTADO


CON PISON DE MANO EN CAPAS DE 20 CM. INCLUYE SUMINISTRO DE
MATERIALES, ACARREOS, MANO DE OBRA Y HTA.

M3

10.50 $

13,239.90

0.00
$
184.60 $
SUB TOTAL PRELIMINARES : $

38,787.45

1,519.68
$
226.56 $
SUB TOTAL EXCAVACIONES : $

344,298.70

138.08
$
272.09 $
SUB TOTAL PLANTILLAS : $

37,570.19

818.80

441.33

25,547.55

344,298.70

37,570.19

143.65 $

117,620.62

545.87
$
280.54 $
SUB TOTAL RELLENOS : $

270,758.99

153,138.37

1.50
1.500

SUMINISTRO DE TUBERAS DE PVC


SUMINISTRO DE TUBERIA DE P.V.C. RD-41 S.I. TIPO ANGER. INCLUYE: FLETES
HASTA LA OBRA, CARGA Y DESCARGA, ACARREOS Y MANIOBRAS LOCALES.

1.501

DE 8" DE DIAMETRO

ML

0.00

485.10 $

1.502

DE 6" DE DIAMETRO

ML

0.00

288.51 $

1.503

DE 4" DE DIAMETRO

ML

1,993.90

133.60 $

266,385.04

1.504

DE 3" DE DIAMETRO

ML

16.10

81.57 $

1,313.28

1.505

DE 2 1/2" DE DIAMETRO

ML
423.10
$
57.06 $
SUB TOTAL SUM. TUBERIAS PVC : $

291,840.41

24,142.09

1.55
1.550

INSTALACIN DE TUBERAS DE PVC


INSTALACION, JUNTEO Y PRUEBA HIDROSTTICA DE TUBERIA DE P.V.C. RD-41
S.I. TIPO ANGER. INCLUYE: FLETES HASTA LA OBRA, CARGA Y DESCARGA,
ACARREOS, MANIOBRAS LOCALES, MANO DE OBRA Y HERRAMIENTA.

1.501

DE 8" DE DIAMETRO

ML

0.00

174.64 $

1.502

DE 6" DE DIAMETRO

ML

0.00

103.86 $

1.503

DE 4" DE DIAMETRO

ML

1,993.90

48.10 $

95,906.59

1.504

DE 3" DE DIAMETRO

ML

16.10

29.37 $

472.86

1.505

DE 2 1/2" DE DIAMETRO

ML
423.10
$
20.54 $
SUB TOTAL INST. TUBERIAS PVC : $

105,069.92

1.60
1.600

SUMINISTRO DE PIEZAS ESPECIALES DE PVC


SUMINISTRO DE PIEZAS ESPECIALES DE PVC. INCLUYE: MATERIALES, FLETES
HASTA LA OBRA, CARGA, DESCARGA Y MANIOBRAS LOCALES.

8,690.47

131127367.xls.ms_office

Pgina 2 de 95

GOBIERNO DEL ESTADO DE QUINTANA ROO


COMISION DE AGUA POTABLE Y ALCANTARILLADO
PRESUPUESTO DE CONSTRUCCION
OBRA:
AMPLIACIN DE RED DE DISTRIBUCIN DE AGUA POTABLE
LOCALIDAD: MANUEL VILA CAMACHO
MUNICIPIO:
OTHON P. BLANCO, Q.ROO
CLAVE

UNIDAD

CANT.

1.601

CODO DE 45 X 2 1/2" DE DIAMETRO

CONCEPTO

PZA

4.00

P.U.
147.29 $

IMPORTE
589.16

1.602

CODO DE 90 X 2 1/2" DE DIAMETRO

PZA

10.00

161.85 $

1,618.50

1.603

COPLE DE REPARACIN DE 2 1/2" DE DIAMETRO

PZA

23.00

79.69 $

1,832.87

1.604

COPLE DE REPARACIN DE 4" DE DIAMETRO

PZA

4.00

184.08 $

736.32

1.605

CRUZ DE 2 1/2" X 2 1/2" DE DIAMETRO

PZA

5.00

227.63 $

1,138.15

1.606

CRUZ DE 4" X 4" DE DIAMETRO

PZA

1.00

680.94 $

680.94

1.607

EXTREMIDAD CAMPANA DE 2 1/2" DE DIAMETRO

PZA

2.00

184.08 $

368.16

1.608

EXTREMIDAD ESPIGA DE 4" DE DIAMETRO

PZA

2.00

322.14 $

644.28

1.609

REDUCCIN CAMPANA DE 4" X 2 1/2" DE DIAMETRO

PZA

3.00

239.33 $

717.99

1.610

TAPN CAMPANA DE 2 1/2" DE DIAMETRO

PZA

8.00

82.81 $

662.48

1.611

TEE DE 2 1/2" X 2 1/2" DE DIAMETRO

PZA

11.00

270.53 $

2,975.83

1.612

TEE DE 4" X 4" DE DIAMETRO

PZA
1.00
$
616.59 $
SUB TOTAL SUM. PIEZAS ESP. PVC : $

12,581.27

616.59

1.65
1.650

INSTALACIN DE PIEZAS ESPECIALES DE PVC


INSTALACION DE PIEZAS ESPECIALES DE PVC. INCLUYE: MANO DE OBRA,
FLETES HASTA LA OBRA, CARGA, DESCARGA Y MANIOBRAS LOCALES.

1.651

CODO DE 45 X 2 1/2" DE DIAMETRO

PZA

4.00

53.02 $

212.08

1.652

CODO DE 90 X 2 1/2" DE DIAMETRO

PZA

10.00

58.27 $

582.70

1.653

COPLE DE REPARACIN DE 2 1/2" DE DIAMETRO

PZA

23.00

28.69 $

659.87

1.654

COPLE DE REPARACIN DE 4" DE DIAMETRO

PZA

4.00

66.27 $

265.08

1.655

CRUZ DE 2 1/2" X 2 1/2" DE DIAMETRO

PZA

5.00

81.95 $

409.75

1.656

CRUZ DE 4" X 4" DE DIAMETRO

PZA

1.00

245.14 $

245.14

1.657

EXTREMIDAD CAMPANA DE 2 1/2" DE DIAMETRO

PZA

2.00

66.27 $

132.54

1.658

EXTREMIDAD ESPIGA DE 4" DE DIAMETRO

PZA

2.00

115.97 $

231.94

1.659

REDUCCIN CAMPANA DE 4" X 2 1/2" DE DIAMETRO

PZA

3.00

86.16 $

258.48

1.660

TAPN CAMPANA DE 2 1/2" DE DIAMETRO

PZA

8.00

29.81 $

238.48

1.661

TEE DE 2 1/2" X 2 1/2" DE DIAMETRO

PZA

11.00

97.39 $

1,071.29

1.662

TEE DE 4" X 4" DE DIAMETRO

PZA
1.00
$
221.97 $
SUB TOTAL INST. PIEZAS ESP. PVC : $

4,529.32

1.70
1.701

1.702

1.75
1.751

SUMINISTRO DE PIEZAS ESPECIALES DE FO.FO.


SUMINISTRO DE VALVULA DE SECCIONAMIENTO DE VASTAGO FIJO DE 4" DE .
INCLUYE: TORNILLERIA, EMPAQUES, ACARREOS, FLETES HASTA LA OBRA,
CARGA, DESCARGA Y MANIOBRAS LOCALES.

5,063.76 $

5,063.76

SUMINISTRO DE VALVULA DE SECCIONAMIENTO DE VASTAGO FIJO DE 2 1/2" DE


. INCLUYE: TORNILLERIA, EMPAQUES, ACARREOS, FLETES HASTA LA OBRA,
CARGA, DESCARGA Y MANIOBRAS LOCALES.
PZA
1.00
$ 2,910.96 $
SUB TOTAL SUM. PIEZAS ESP. FO.FO. : $

7,974.72

INSTALACIN DE PIEZAS ESPECIALES DE FO.FO.


INSTALACIN DE VALVULA DE SECCIONAMIENTO DE VASTAGO FIJO DE 4" DE
. INCLUYE: TORNILLERIA, EMPAQUES, MANO DE OBRA Y HTA.

PZA

1.00

2,910.96

1,822.95 $

1,822.95

INSTALACIN DE VALVULA DE SECCIONAMIENTO DE VASTAGO FIJO DE 2 1/2"


DE . INCLUYE: TORNILLERIA, EMPAQUES, MANO DE OBRA Y HTA.
PZA
1.00
$ 1,047.95 $
SUB TOTAL INST. PIEZAS ESP. FO.FO. : $

2,870.90

1.80
1.801

TOMAS DOMICILIARIAS
SUMINISTRO E INSTALACION DE TUBO RAMAL DE POLIETILENO DE ALTA
DENSIDAD CLASE 10 KG/CM2 DE 13 MM. DE LA ABRAZADERA AL CUADRO DE
MEDICION. INCLUYE: EXCAVACION, RELLENO DE ZANJAS, MATERIALES, MANO
DE OBRA Y HTA.

ML

728.00

47.17 $

34,339.76

1.802

SUMINISTRO E INTERCONEXION DE ABRAZADERA DE PVC HIDRAULICO TIPO


OMEGA DE 13 MM x 2 A 4". INCLUYE: MATERIALES, MANO DE OBRA Y HTA.

PZA

56.00

165.86 $

9,288.16

1.803

SUMINISTRO E INSTALACION DE ADAPTADOR DE COMPRESION DE 13 X 16 MM


(OMEGA). INCLUYE: MATERIALES, MANO DE OBRA Y HTA.

PZA

112.00

42.49 $

4,758.88

1.752

PZA

1.00

221.97

1,047.95

131127367.xls.ms_office

Pgina 3 de 95

GOBIERNO DEL ESTADO DE QUINTANA ROO


COMISION DE AGUA POTABLE Y ALCANTARILLADO
PRESUPUESTO DE CONSTRUCCION
OBRA:
AMPLIACIN DE RED DE DISTRIBUCIN DE AGUA POTABLE
LOCALIDAD: MANUEL VILA CAMACHO
MUNICIPIO:
OTHON P. BLANCO, Q.ROO
CLAVE

CONCEPTO

UNIDAD

CANT.

1.804

SUMINISTRO Y COLOCACION DE HIDRANTE CONSTRUIDO A BASE DE NIPLE


GALVANIZADO DE 60 CM X 13 MM ROSCADO EN AMBOS ESTREMOS. INCLUYE: DOS
CODOS DE 90 X 13 MM, NIPLE DE 10CMX13MM ROSCADO EN AMBOS EXTREMOS,
ADAPTADOR DE COMPRESION DE 16MM, LLAVE PARA JARDIN, BASE DE CONCRETO
DE 15X25X15 CM. MATERIAL DE CONSUMO, MATERIALES, MANO DE OBRA Y
HERRAMIENTA.

PZA

56.00

1.805

REPARACION DE TOMA DOMICILIARIA. INCLUYE: SUSTITUCION DE TUBO RAMAL


DE POLIETILENO DE ALTA DENSIDAD 1/2" DE DIAMETRO.

1.90
1.901

COMPLEMENTARIOS
CARGA Y ACARREO DE MATERIAL EXCEDENTE PRODUCTO DE LA EXCAVACION
(MEDIDO COMPACTO) HASTA UNA DISTANCIA MAXIMA DE 5 KMS. SOBRE
TERRACERIAS LOMERIO SUAVE REVESTIDO, LOMERIO PRONUNCIADO.
INCLUYE: ABUNDAMIENTO ESPERADO, MANO DE OBRA, EQUIPO Y MANIOBRAS
LOCALES.

1.902

LIMPIEZA DEL SITIO DE LA OBRA CON MAQUINARIA, ALMACENANDO EL


MATERIAL PRODUCTO DE LA EXCAVACION NO UTILIZADO EN RELLENOS Y LA
MERMA POR CRIBADO DEL MATERIAL DE BANCO, PARA SU POSTERIOR CARGA
Y ACARREO. INCLUYE: MANO DE OBRA, EQUIPO Y HERRAMIENTA.

2
2.10
2.101

P.U.

145.57 $

8,151.92

PZA
30.00
$
179.40 $
SUB TOTAL TOMAS DOMICILIARIAS : $

61,920.72

M3

508.21

IMPORTE

5,382.00

85.72 $

43,563.76

LTE
1.00
$ 2,500.00 $
SUB TOTAL COMPLEMENTARIOS : $

2,500.00
46,063.76

SUB TOTAL RED DE DISTRIBUCIN : $

1,224,266.35

ADECUACIN DE CASETA DE CLORACIN


PRELIMINARES
TRAZO Y NIVELACIN DEL TERRENO PARA CONSTRUCCIN, ESTABLECIENDO
NIVELES Y EJES DE REFERENCIA. INCLUYE: DESMONTE Y DESENRACE,
EQUIPO, MATERIALES DE CONSUMO, MANO DE OBRA Y HTA.

M2

1.95

7.15 $

13.94

2.102

DEMOLICIN DE PISO DE CONCRETO POR MEDIOS MANUALES. INCLUYE:


RETIRO DEL MATERIAL PRODUCTO DE LA DEMOLICIN A 10 MTS. FUERA DEL
REA DE LOS TRABAJOS. INCLUYE: MANIOBRAS LOCALES, MANO DE OBRA Y
HTA.

M2

1.84

54.60 $

100.46

2.103

DEMOLICIN DE MUROS DE BLOCK DE 15X20X40 CMS. POR MEDIOS


MANUALES. INCLUYE: RETIRO DEL MATERIAL PRODUCTO DE LA DEMOLICIN
HASTA 10 MTS. FUERA DEL REA DE LOS TRABAJOS, LIMPIEZA GENERAL AL
FINALIZAR, MANO DE OBRA, EQUIPO Y HTA.

M2

3.10
$
39.00 $
SUBTOTAL PRELIMINARES : $

235.30

0.70
$
245.60 $
SUBTOTAL EXCAVACIN : $

171.92

0.06
$
107.25 $
SUBTOTAL PLANTILLAS : $

6.44

2.20
2.201

2.30
2.301

2.40
2.401

EXCAVACIN
EXCAVACIN EN ZANJAS HASTA 2 MTS. DE PROFUNDIDAD EN MAT.
CLASIFICADO EN OBRA CON HERRAMIENTA MANUAL, PARA EL DESPLANTE DE
ESTRUCTURAS, DEPOSITANDO EL PRODUCTO A UN LADO DE LA ZANJA PARA
SU APROVECHAMIENTO POSTERIOR. INCLUYE: MANO DE OBRA, HERRAMIENTA
Y EQUIPO.
PLANTILLAS
FABRICACIN Y COLOCACIN DE CONCRETO SIMPLE F'C=100 KG/CM2 EN
PLANTILLA DE CIMENTACIN DE 5 CM DE ESPESOR. INCLUYE: CIMBRADO,
DESCIMBRADO, NIVELADO, VIBRADO, Y CURADO; TODOS LOS MATERIALES,
MANO DE OBRA, HTA. Y EQUIPO.

M3

M2

120.90

171.92

6.44

CIMENTACIN
CONSTRUCCIN DE MAMPOSTERA PARA CIMENTACIN, DE 0.30 A 0.60
METROS EN SU SECCIN HORIZONTAL, REALIZADA CON PIEDRA DE HILADA DE
LA REGIN Y MORTERO 1:2:7. INCLUYE: MATERIAL, MANO DE OBRA Y HTA.
M3

0.53

967.20 $

512.62

2.402

CONSTRUCCIN DE CADENA DE CIMENTACIN CON ARMEX 15 - 20 DE 4 HILOS


Y CONCRETO F'C=200 KG/CM2, INCLUYE: CIMBRA COMN Y DESCIMBRA,
MATERIAL, MANO DE OBRA Y HTA.

ML

1.95

145.16 $

283.06

2.403

IMPERMEABILIZACIN DE CADENA DE CONCRETO A BASE DE MICROFEST


APLICADO EN FRO CON BROCHA EN TRES CARAS. INCLUYE: MATERIAL, MANO
DE OBRA Y HTA.

ML

1.95

39.90 $

77.81

131127367.xls.ms_office

Pgina 4 de 95

GOBIERNO DEL ESTADO DE QUINTANA ROO


COMISION DE AGUA POTABLE Y ALCANTARILLADO
PRESUPUESTO DE CONSTRUCCION
OBRA:
AMPLIACIN DE RED DE DISTRIBUCIN DE AGUA POTABLE
LOCALIDAD: MANUEL VILA CAMACHO
MUNICIPIO:
OTHON P. BLANCO, Q.ROO
CLAVE

CONCEPTO

UNIDAD

3.404

RELLENO CON MATERIAL PRODUCTO DE EXCAVACIN COMPACTADO EN


CAPAS DE 20 CMS CON EQUIPO MANUAL. INCLUYE: NIVEL TERMINADO,
ACARREOS, AGUA, MATERIAL, MANO DE OBRA, HTA. Y EQUIPO.

M3

2.50
2.501

2.502

2.55
2.551

288.60 $

1,125.54

MURO DE BLOCK DE CELOSA TIPO CRUZ MAYA DE 20 X 20 CMS. ASENTADO


CON MORTERO 1:2:7 (C:C:P), A PLOMO Y NIVEL HASTA 5 M. DE ALTURA.
INCLUYE: ANDAMIAJE, TODOS LOS MATERIALES, MANO DE OBRA,
HERRAMIENTA Y EQUIPO.

M2

7.00
$
331.50 $
SUBTOTAL MUROS : $

3,446.04

4.40
$
183.75 $
SUBTOTAL ESTRUCTURA : $

808.50

ESTRUCTURA
CONSTRUCCIN DE CASTILLO K-1 DE CONC. F'C=150 KG/CM2 ARMADO CON
ARMEX 15X15-4 DE 15X15 CMS. DE SECCIN, CIMBRA COMN. INCLUYE:
CIMBRA, ANDAMIAJE, VIBRADO, CURADO, DESCIMBRADO, MATERIAL, MANO DE
OBRA, HERRAMIENTA Y EQUIPO.

ML

APLANADO EN MUROS Y PLAFONES A BASE DE RICH-EMPARCHE-ESTUCO A


PLOMO Y NIVEL, CON MORTERO EN PROPORCIN 1:2.5, 1:4:12 Y 1:18:9
RESPECTIVAMENTE. INCLUYE: ANDAMIOS, MATERIAL, MANO DE OBRA Y HTA.

2.603

PERFILACION Y BOQUILLAS EN CASTILLOS, COLUMNAS, TRABES, VANOS DE


PUERTAS Y VENTANAS CON MORTERO CEMENTO-POLVO DE PIEDRA Y
MASILLA EN PROPORCIN 1:6 Y 1:18:9 RESPECTIVAMENTE. INCLUYE: CIMBRA,
ANDAMIAJE, MATERIAL, MANO DE OBRA Y HERRAMIENTA.

2.604

SUMINISTRO Y COLOCACIN DE PUERTA DE ALUMINIO, MEDIA HOJA EN


CRISTAL Y MEDIA EN ALUMINIO, CON DIMENSIONES DE 1.00 MT. DE ANCHO Y
2.05 MTS. DE ALTURA. INCLUYE: MARCO, CERRADURA, BRAZO HIDRULICO,
MATERIAL, MANO DE OBRA Y HTA.

PZA.

2.703

2.75

873.49

3.90

2.602

2.702

0.00
$
132.60 $
SUBTOTAL CIMENTACIN : $

IMPORTE

M2

ACABADOS
PREPARACIN DE MUROS Y PLAFONES PREVIA A LA APLICACIN DE
APLANADO. INCLUYE: PICADO, RASPADO, RETIRO DE DESPERDICIO,
MATERIALES, MANO DE OBRA, HERRAMIENTA Y EQUIPO.

2.70
2.701

P.U.

MUROS
MURO DE BLOCK DE 15X20X40 CM ASENTADO CON MORTERO 1:2:7 (CEMENTOCAL-POLVO), A PLOMO. INCLUYE: ANDAMIAJE, TODOS LOS MATERIALES, MANO
DE OBRA, HTA. Y EQUIPO.

2.60
2.601

2.65
2.651

CANT.

PISOS
FORJADO DE CANALN DE CONC F'C=200 KG/CM2 PERIMETRAL A LOS
DEPSITOS DE 250 LTS DE HIPOCLORITO, DE 10 CMS. DE ESPESOR, 0.65 M DE
ANCHO x 0.20 MTS DE ALTURA PROMEDIO POR LA PENDIENTE DEL PISO, Y LA
LONG. DE 2.50 MTS, REFORZADA CON MALLA ELECTROSOLDADA 6-6-10/10,
ACABADO ESCOBILLADO. INC.: VIBRADO, CURADO, MATERIAL, M. DE OBRA,
HTA. Y EQUIPO.

PINTURA Y LIMPIEZA
SUMINISTRO Y APLICACIN DE PINTURA VINLICA VINIMEX DE COMEX O
SIMILAR EN MUROS, COLUMNAS, TRABES Y LOSAS, HASTA UNA ALTURA DE 6
MTS. INCLUYE: PREPARACIN DE LA SUPERFICIE, UNA APLICACIN DE
SELLADOR, DOS MANOS DE PINTURA, MATERIAL, MANO DE OBRA Y HTA.
ROTULACIN Y PINTURA DE EDIFICIO DE 40 CM, DE IDENTIFICACIN, COMO SE
MUESTRA EN DETALLE. INCL.: ANDAMIAJE, MATERIALES, MANO DE OBRA Y
HTAS.
LIMPIEZA GENERAL DE LA OBRA. INCLUYE: DESALOJO DE DESPERDICIOS
FUERA DE LA OBRA, M.O. Y HTA.
RAMPA DE ACCESO

2,320.50

808.50

M2

69.87

39.00 $

2,724.93

M2

69.87

90.48 $

6,321.84

ML

10.13

37.44 $

379.27

2.00
$ 3,291.28 $
SUBTOTAL ACABADOS : $

16,008.60

3.50
$
137.11 $
SUBTOTAL PISOS : $

479.89

ML

6,582.56

479.89

M2

66.22

60.45 $

4,003.00

LOTE

1.00

1,017.73 $

1,017.73

M2
12.96
$
14.50 $
SUBTOTAL PINTURA Y LIMPIEZA : $

5,208.65

187.92

131127367.xls.ms_office

Pgina 5 de 95

GOBIERNO DEL ESTADO DE QUINTANA ROO


COMISION DE AGUA POTABLE Y ALCANTARILLADO
PRESUPUESTO DE CONSTRUCCION
OBRA:
AMPLIACIN DE RED DE DISTRIBUCIN DE AGUA POTABLE
LOCALIDAD: MANUEL VILA CAMACHO
MUNICIPIO:
OTHON P. BLANCO, Q.ROO
CLAVE

CONCEPTO

2.751

COLOCACIN DE RAMPA DE ACCESO A CASETA DE CLORACIN, CON PISO DE


CONCRETO F'C=150 KG/CM2 DE 8 CMS DE ESPESOR DE 1X1.40 MTS,
REFORZADA
CON
MALLA
ELECTROSOLDADA
6-6-10/10,
ACABADO
ESCOBILLADO (INMEDIATAMENTE DESPUS DEL COLADO). INCLUYE: CIMBRA
COMN PERIMETRAL, DESCIMBRA, SUMINISTRO, ACARREO, AGUA, MATERIAL,
MANO DE OBRA Y HTA.

UNIDAD

CANT.

P.U.

PZA.
1.00
$ 1,103.81 $
SUBTOTAL RAMPA DE ACCESO : $

IMPORTE

1,103.81

1,103.81

2.80
2.801

INSTALACIN ELCTRICA
SUMINISTRO E INSTALACIN DE CONEXIN DE CABLE CAL. 4/0 A VARILLA
COPPERWELD DE 5/8" DE DIMETRO. INCLUYE: CARGA #90 (USRA MOLDE GTC312C), TRASLADO, MATERIALES DE CONSUMO, MANO DE OBRA Y HTA. MENOR
PZA.

1.00

223.66 $

223.66

2.802

SUMINISTRO E INSTALACIN DE CONEXIN TIPO HTA, DE CABLE DE PASO CAL.


1/0 A CABLE DERIVACIN CAL. 2. INCLUYE: CARGA # 45 (USAR MOLDA TAC2C1V), TRASLADOS, MATERIALES DE CONSUMO, MANO DE OBRA Y HTA.
MENOR

PZA.

2.00

115.21 $

230.42

2.803

SUMINISTRO E INSTALACIN DE SALIDA DE CENTRO PARA ALUMBRADO


INTERIOR CON P.V.C. PESADO DE 13 mm DE DIMETRO, CABLE THHW DE 10 12 AWG, CHALUPA DE P.V.C. CON PLACAS Y APAGADORES, MCA. BTICINO,
INCLUYE: BASE, NEUTRO Y TIERRA FSICA, MANO DE OBRA, HTA. Y PRUEBA
PARA GARANTIZAR SU CORRECTO FUNCIONAMIENTO

PZA.

3.00

546.00 $

1,638.00

2.804

SUMINISTRO E INSTALACIN DE SALIDA DE CENTRO PARA CONTACTO CON


P.V.C. PESADO DE 13 mm DE DIMETRO, CABLE THHW DE 10-12 AWG,
CHALUPA DE P.V.C. CON PLACAS Y APAGADORES, MCA. BTICINO. INCLUYE:
BASE, NEUTRO Y TIERRA FSICA, MANO DE OBRA, HTA. Y PRUEBA PARA
GARANTIZAR SU CORRECTO FUNCIONAMIENTO

PZA.

3.00

546.00 $

1,638.00

SUMINISTRO E INSTALACIN DE LUMINARIA CIRCULAR DE 8 W, 110 V


AHORRADORAS DE ENERGA INCLUYE: TRASLADO, MATERIALES DE
CONSUMO, MANO DE OBRA Y HTA. MENOR
PZA.
2.00
$
222.14 $
SUBTOTAL INSTALACIN ELCTRICA : $

4,174.36

2.805

444.28

2.85
2.851

VARIOS
SUMINISTRO Y COLOCACIN DE ESTACIN PORTTIL DOBLE DE LAVA OJOS.
INCLUYE: DOS BOTES DE REPUESTO DE 32 ONZAS DE SOLUCIN LAVA OJOS,
FLETES, CARGA Y DESCARGA.

PZA.

1.00

1,326.00 $

1,326.00

2.852

SUMINISTRO Y COLOCACIN DE EXTINGUIDOR DE POLVO SECO CON


CAPACIDAD DE 6 KG. INCLUYE: SOPORTE, FLETES, CARGA Y DESCARGA.

PZA.

1.00

904.80 $

904.80

SUMINISTRO Y COLOCACIN DE BOTIQUN PORTTIL DE PRIMEROS AUXILIOS.


INCLUYE: FLETES, CARGA Y DESCARGA.

PZA.

1.00
$
351.00 $
SUBTOTAL VARIOS : $

2,581.80

SUBTOTAL ADECUACIN DE CASETA DE CLORACIN : $

35,098.80

2.853

3
3.101

3.102

4
4.101

4.102

351.00

LNEA DE CLORACIN
SUMINISTRO E INSTALACIN DE TUBERIA P.A.D. DE 19 MM DE (3/4") PARA
CANALIZACIN DE DUCTO DE CLORACIN. INCLUYE FIJACION CON HERRAJES
DE PLATINA DE 1/2"X 1/8" X 10 CMS EN OMEGA, PINT. ANTICORROSIVA A 2
MANOS, MAT., M.O., HERR. Y EQUIPO.

ML

10.00

40.05 $

400.50

ML

10.00

343.10 $

3,431.00

SUB TOTAL LNEA DE CLORACIN : $

3,831.50

FORJADO DE BASE TRAPEZOIDAL DE CONCRETO SIMPLE F'C=150 K/CM2 DE 15


X 10 CMS (BASES) X 25 CM DE ALTURA PARA SOPORTE DE ENCAMISADO DE
MANGUERA DOSIFICADORA. INCLUYE EXCAVACION (15 CMS. DE PROF. EN
PROM.), CIMBRA Y DESCIMBRA COMUN, MAT., M.O., HERR. Y EQUIPO.

SELLO SANITARIO
CONSTRUCCION DE BANQUETA DE CONCRETO F'C=150 KG/CM2 DE 8 CM DE
ESPESOR, ACABADO ESCOBILLADO; INCLUYE: CIMBRADO Y POSTERIOR
DESCIMBRADO, MATERIAL, MANO DE OBRA Y HERRAMIENTA.

6.25

269.84 $

1,686.50

RELLENO CON MATERIAL DE BANCO COMPACTADO CON PIZON A MANO, EN


CAPAS DE 20 CMS; INCLUYE: ACARREO HASTA EL SITIO, MATERIAL, MANO DE
OBRA, HERRAMIENTA Y EQUIPO.

0.63

312.65 $

196.97

131127367.xls.ms_office

Pgina 6 de 95

GOBIERNO DEL ESTADO DE QUINTANA ROO


COMISION DE AGUA POTABLE Y ALCANTARILLADO
PRESUPUESTO DE CONSTRUCCION
OBRA:
AMPLIACIN DE RED DE DISTRIBUCIN DE AGUA POTABLE
LOCALIDAD: MANUEL VILA CAMACHO
MUNICIPIO:
OTHON P. BLANCO, Q.ROO
CLAVE

CONCEPTO

4.103

RENIVELACIN DE PISO EXISTENTE, MEDIANTE LA APLICACIN, UNA CAPA DE


CONCRETO F'C=150 KG/CM2 DE 5 CMS DE ESPESOR PROMEDIO; INCLUYE:
PREPARACION DE LA SUPERFICIE, MATERIAL, MANO DE OBRA, HERRAMIENTA
Y EQUIPO.

UNIDAD

CANT.

25.00

P.U.

IMPORTE

155.73 $

3,893.25

SUB TOTAL SELLO SANITARIO : $

5,776.72

EQUIPAMIENTO ELECTROMECANICO

5.101

SUMINISTRO E INSTALACIN DE BOMBA SUMERGIBLE MOD. 150S75-4, 58.5


MCA, 5 LPS MARCA GRUNDFOS O SIMILAR. INCLUYE: MATERIALES, MANO DE
OBRA Y HERRAMIENTAS.

PZA.

1.00

$ 33,759.04 $

33,759.04

5.102

SUMINISTRO E INSTALACIN DE MOTOR ELCTRICO SUMERGIBLE DE 6" DE


DIMETRO MS4000, DE 7.5 HP, 220 V, 3F MCA. GRUNDFOS O SIMILAR. INCLUYE:
MATERIALES, MANO DE OBRA Y HERRAMIENTAS.

PZA.

1.00

$ 28,399.02 $

28,399.02

5.103

SUMINISTRO E INSTALACIN DE ARRANCADOR MAGNTICO COMBINADO A


TENSIN PLENA DE 10 HP, 220V, 3F. INCLUYE: MATERIALES, MANO DE OBRA Y
HTAS.

PZA.

1.00

$ 38,308.76 $

38,308.76

5.104

SUMINISTRO, TENDIDO E INSTALACIN DE CABLE SUMERGIBLE DE 3X14 AWG.


INCLUYE: MATERIALES, MANO DE OBRA Y HERRAMIENTAS.

ML

55.00

62.88 $

SUMINISTRO E INSTALACIN DE TUBO DE FIERRO NEGRO PARA COLUMNA DE


4" DE DIAMETRO DE 3.05 M. DE LONG. INCLUYE: MATERIALES, MANO DE OBRA
Y HTAS.

PZA

17.00

2,892.70 $

49,175.90

SUBTOTAL DE EQUIPAMIENTO ELECTROMECANICO : $

153,101.12

5.105

6
6.101

6.102

3,458.40

ACOMETIDA ELCTRICA
CONSTRUCCION DE MURETE DE ACOMETIDA DE 2.20X2.05X0.40 M. A BASE DE
MURO DE BLOCK DE 15X20X40 CM, ACABADO A TRES CAPAS CON MORTERO
CEM-CAL-POLVO DE PIEDRA EN PROPORCION 1:2:7; LOSA DE CONCRETO
F'C=150 KG/CM2 DE 10 CMS. DE ESPESOR REFORZADA CON VARILLA DEL # 3 @
20 CM. EN AMBOS SENTIDOS. INCLUYE: CIMENTACION DE MAMPOSTERIA CON
PIEDRA DE LA REGION, CADENA DE DESPLANTE Y DE NIVELACION ARMADAS
CON ARMEX DE 15-20, DADOS DE CONCRETO DE 30X60 CM, PUERTAS DE
BATIENTES LAMINA DUNCAN, CON MARCO ANGULAR DE 1/2", BISAGRAS Y
PASADOR PORTA CANDADO, BASE PARA MEDICION CFE TRIFASICA, PINTURA A
DOS MANOS, LIMPIEZA Y TRAZO DEL TERRENO, MATERIALES, MANO DE OBRA
Y HTA.

PZA

1.00

$ 10,159.71 $

SUMINISTRO E INSTALACION DE BASE DE MEDICION 7-200 MARCA CUTTLER


HAMMER O SIMILAR. INCLUYE: FIJACION EN PARED, CABLE THW #6 AL 8,
CABLEADO CON CANALIZACION CON TUBO CONDUIT DE FoGa DE 2" ,
FIJACION, TODOS LOS MATERIALES, MANO DE OBRA Y HERAMIENTAS, HASTA
UNA DISTANCIA NO MAXIMA DE 30 MTS

LTE

1.00

10,159.71

8,534.14 $

8,534.14

SUB TOTAL ACOMETIDA ELCTRICA : $

18,693.85

DEMOLICIN DE TANQUE ELEVADO

7.101

DEMOLICIN DE CANASTA (COLUMNAS, TRABES, LOSAS) HASTA UNA ALTURA


DE 20 M. SOBRE EL TERRENO NATURAL. INCLUYE: CARGA, RETIRO DE
MATERIAL PRODUCTO DE LA DEMOLICION HASTA 5 KM DE LA OBRA, ACARREO,
ANDAMIOS, MAQUINARIA, EQUIPO, MANO DE OBRA Y HTAS.

7.102

DEMOLICIN DE FUSTE (MURO DE BLOCK, COLUMNAS, ETC.) HASTA UNA


ALTURA DE 20 M. SOBRE EL TERRENO NATURAL. INCLUYE: CARGA, RETIRO DE
MATERIAL PRODUCTO DE LA DEMOLICION A UNA DISTANCIA DE HASTA 5 KM
DE LA OBRA, ANDAMIOS, MAQUINARIA, EQUIPO, MANO DE OBRA Y HTAS.

7.103

DEMOLICIN DE BASE (CIMENTACIN, BASE DE CONCRETO, ETC.) INCLUYE:


CARGA, RETIRO DE MATERIAL PRODUCTO DE LA DEMOLICION A UNA
DISTANCIA DE HASTA 5 KM FUERA DE LUGAR DE LA OBRA, ANDAMIOS,
MAQUINARIA, EQUIPO, MANO DE OBRA Y HERRAMIENTAS.

7.104

DESMANTELAMIENTO Y RETIRO DE ESCALERA MARINA CONTRUIDA A BASE DE


TUBO GALVANIZADO EMPOTRADA A TANQUE A UNA ALTURA DE HASTA 20 M
SOBRE EL TERRENO NATURAL. INCLUYE: ANDAMIOS, EQUIPO, HERRAMIENTA,
MANIOBRAS, MANO DE OBRA, CARGA Y ACARREO A UNA DISTANCIA DE HASTA
5 KM FUERA DEL LUGAR DE LOS TRABAJOS.

LTE

1.00

$ 32,483.80 $

32,483.80

LTE

1.00

$ 24,743.20 $

24,743.20

LTE

1.00

$ 19,876.00 $

19,876.00

LTE

1.00

2,483.00 $

2,483.00

131127367.xls.ms_office

Pgina 7 de 95

GOBIERNO DEL ESTADO DE QUINTANA ROO


COMISION DE AGUA POTABLE Y ALCANTARILLADO
PRESUPUESTO DE CONSTRUCCION
OBRA:
AMPLIACIN DE RED DE DISTRIBUCIN DE AGUA POTABLE
LOCALIDAD: MANUEL VILA CAMACHO
MUNICIPIO:
OTHON P. BLANCO, Q.ROO
CLAVE

CONCEPTO

7.105

DESMANTELAMIENTO Y RETIRO DE TUBERIA DE ALIMENTACION Y DESCARGA


DEL TANQUE A UNA ALTURA DE HASTA 20 MT SOBRE EL TERRENO NATURAL.
INCLUYE: CARGA, ACARREO A UNA DISTANCIA DE HASTA 5 KM DEL SITIO DE
LOS TRABAJOS, ANDAMIOS, MAQUINARIA, EQUIPO, MANO DE OBRA Y
HERRAMIENTAS HASTA UNA ALTURA DE 20 M.

UNIDAD

CANT.

LTE

2.00

P.U.

IMPORTE

1,482.00 $

2,964.00

SUBTOTAL DEMOLICIN DE TANQUE ELEVADO : $

82,550.00

131127367.xls.ms_office

Pgina 8 de 95

GOBIERNO DEL ESTADO DE QUINTANA ROO


COMISION DE AGUA POTABLE Y ALCANTARILLADO
PRESUPUESTO DE CONSTRUCCION
OBRA:
AMPLIACIN DE RED DE DISTRIBUCIN DE AGUA POTABLE
LOCALIDAD: MANUEL VILA CAMACHO
MUNICIPIO:
OTHON P. BLANCO, Q.ROO
CLAVE

CONCEPTO

UNIDAD

CANT.

P.U.

IMPORTE

RESUMEN DE PARTIDAS
1
2
3
4
5
6
7

RED DE DISTRIBUCIN
ADECUACIN DE CASETA DE CLORACIN
LNEA DE CLORACIN
SELLO SANITARIO
EQUIPAMIENTO ELECTROMECANICO
ACOMETIDA ELCTRICA
DEMOLICIN DE TANQUE ELEVADO

$
$
$
$
$
$
$

1,224,266.35
35,098.80
3,831.50
5,776.72
153,101.12
18,693.85
82,550.00

SUB TOTAL : $
10% I.V.A. : $
TOTAL : $

1,523,318.34
152,331.83
1,675,650.17

Dimetro
Pulgadas
Metros
Area
Longitud
Ao

Gasto (Q)
m3/seg
0
1
2
3
4

0.01061

6
0.1524
0.018241469
4200
Velocidad (V)
m/seg
0.582

V2/2g
m
0.017

Reynolds

88642.20

0.018377

Hf
m

Hs
m
8.733

0.437

Hd
m
9.187

Eficiencia

0.7

Potencia
Hp
1.83

145V
#REF!
#REF!
#REF!

Ead
#REF!
#REF!
#REF!

Precio Unitario
852
1135
5610
1363
1722
973
3450

Importe
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!

K. W. H.

#REF!
#REF!
#REF!

Costo Hora

#REF!
#REF!
#REF!

Ead/Ete
#REF!
#REF!
#REF!

A
#REF!
#REF!
#REF!

Cantidad
Precio Unitario
5133.6
852
2139
1135
1283.4
5610
607.2
1363
4800
2020
7948.640957
973
4800
4140

Costo de const.

45009314
52131107.5
62760710.5

Amortizacin

11252328.5
13032776.88
15690177.63
11252328.5

25
0.25

B
#REF!
#REF!
#REF!

Importe
4373827.2
2427765
7199874
827613.6
9696000
7734027.651
19872000
52131107.45

Costo Oper.

#REF!
#REF!
#REF!

h
#REF!
#REF!
#REF!

Unidad
m3
m3
m3
m3
ml
m3
ml

0.8h
#REF!
#REF!
#REF!

0.2h
#REF!
#REF!
#REF!

Cantidad Precio Unitario


6177.6
852
2574
1135
1544.4
5610
811.2
1363
4800
2182
9484.641
973
4800
5230

Solucin: 24"

Ht
#REF!
#REF!
#REF!

Importe
5263315.2
2921490
8664084
1105665.6
10473600
9228555.65
25104000
62760710.5

Anlisis de Dimetro Econmico


Qmed = (2850 hab * 230 l/hab/da) / 86400 = 7.58 lps

Datos:
QMD:
L:
D=

10.61 LPS

QMD = 1.4 * 7.58 lps = 10.61 lps

4200 M
3.30

QMH = 1.55 * 10.92 lps =16.44 lps.

Funcionamiento hidrulico
Dimetro Nominal (d)
pulgadas
m
6
8
10

0.1524
0.2032
0.254

rea (A)
m2
0.018241469
0.032429279
0.050670748

Gasto (Q)
m3/seg

Velocidad (V)
m/seg

0.01061
0.01061
0.01061

V2/2g
m

0.582
0.327
0.209

Longitud (L)
m

0.017
0.005
0.002

4200
4200
4200

Reynolds

88642.20
66481.65
53185.32

Hf
m

0.018377479
0.019526
0.020500035

Hs
m
8.733
2.202
0.758

0.437
0.110
0.038

Hd
m

Eficiencia

9.187
2.317
0.798

0.7
0.7
0.7

Golpe de Ariete
Clase

Dimetro

RD-41
RD-41
RD-42

15.24
20.32
25.4

Espesor e

0.41
0.53
0.53

145V

0.582
0.327
0.209

84.33805299
47.44015481
30.36169908

Ead

Ete

315010.8
420014.4
525018

12874
16642
16642

Ead/Ete

24.46875874
25.23821656
31.5477707

25.46875874
26.23821656
32.5477707

h
5.047 16.711663
5.122 9.261449
5.705 5.3218845

0.8h

0.2h

13.3693308 3.342332691
7.40915923 1.852289808
4.25750763 1.064376907

Costos de Construccin
DIAMETRO 4

DIAMETRO 6

Concepto
Excavacin material de
cualquier tipo
Plantilla
Instalacin de tub.
Relleno
Suministro de tubera
Sumas

Importe

Unidad

Cantidad

Precio Unitario

Unidad

Cantidad

Precio Unitario

Importe

Unidad

m3

4,019.40

237.06

952,838.96

m3

4,491.90

237.06

1,064,849.81

m3

5,405.40

237.06

m3
ml
m3
ml

272.09
4,200.00
3,747.15
4,200.00

272.09
48.10
424.19
133.60

74,032.97
202,020.00
1,589,503.96
561,120.00
3,379,515.90

m3
ml
m3
ml

531.30
4,200.00
3,960.44
4,200.00

272.09
103.86
424.19
288.51

144,561.42
436,212.00
1,679,979.45
1,211,742.00

m3
ml
m3
ml

709.80
4,200.00
4,695.44
4,200.00

272.09
174.64
424.19
485.10

4,537,344.68

Costos de Operacin
Clase
RD-41
RD-41
RD-41

Dimetro nominal
6
8
10

Potencia
15.24
20.32
25.4

1.83
0.46
0.16

K. W. H.
2.229779528
0.562460813
0.193592897

Costo Hora
44.60
11.25
3.87

Cargo anual
390,657.37
98,543.13
33,917.48

Costo de const.

Amortizacin

3,379,515.90
4,537,344.68
6,237,200.71

844,878.97
1,134,336.17
1,559,300.18

Costo Oper.
1,235,536.35
1,232,879.30
1,593,217.65

7000000
6000000
5000000
4000000

tasa de amortizacion

DIAMETRO 8
Precio
Cantidad
Unitario

8.685 TIIE

3379515.896

3000000
2000000

Cargo adicional por la energa consumida (kwh)

2.1 Cargo fijo, independiente de la energa consumida


2.2 Cargo adicional por la energa consumida

1.217

8
10
221.4
1.217 por cada kilowatt-hora.

4537344.68
6237200.705

2000000
1000000
0
0

Potencia
Hp
1.83
0.46
0.16

Ht
12.529
4.170
1.862

DIAMETRO 8
Importe
1,281,404.12
193,129.48
733,488.00
1,991,759.10
2,037,420.00
6,237,200.71

y = 67753x2 - 369633x + 3E+06


R = 1
Series1
Poly. (Series1)

Poly. (Series1)

10

12

Qmed = (2850 hab * 230 l/hab/da) / 86400 = 7.58 lps

Datos:
QMD:

Aos

Gasto (Q)
m3/seg
0.35

L:
8000 M
D=
3.30
Dimetro Nominal (d)
rea (A)
pulgadas
m
m2
20

QMD = 1.4 * 7.58 lps = 10.61 lps

350 LPS

0.508

0.202682992

QMH = 1.55 * 10.92 lps =16.44 lps.


Velocidad (V)
m/seg
1.727

V2/2g
m
0.152

Longitud (L)
m
8000

Reynolds
877231.97

Hf
m

Hs
m

Hd
m

#REF!

#REF!

#REF!

#REF!

Golpe de Ariete
Clase
AC-5
AC-5
AC-5

Dimetro

Espesor e

50.8
#REF!
#REF!

0.41
0.53
0.53

145V
#REF!
#REF!
#REF!

Ead

Ete

1050036
#REF!
#REF!

12874
16642
16642

Ead/Ete
81.56252913
#REF!
#REF!

82.56252913
#REF!
#REF!

9.086
#REF!
#REF!

0.8h

#REF!
#REF!
#REF!

#REF!
#REF!
#REF!

Costos de Construccin
DIAMETRO 4

DIAMETRO 6

DIAMETRO 8

Concepto
Unidad
Excavacin material de
cualquier tipo
Plantilla
Instalacin de tub.
Relleno
Suministro de tubera
Sumas

Precio Unitario

Cantidad

Precio Unitario

Importe

Unidad

m3

237.06

#REF!

m3

8556

237.06

Importe
2,028,285.36

Unidad
m3

Cantidad
10296

m3
ml
m3
ml

272.09
48.1
424.19
133.6

#REF!
#REF!
#REF!
#REF!
#REF!

m3
ml
m3
ml

1012
8000
7543.84
8000

272.09
103.86
424.19
288.51

275,355.08
830,880.00
3,200,021.90
2,308,080.00
8,642,622.34

m3
ml
m3
ml

1352
8000
8943.84
8000

Costos de Operacin
Clase
RD-41
RD-41
RD-41

Dimetro nominal
20
#REF!
#REF!

50.8
#REF!
#REF!

K. W. H.
#REF!
#REF!
#REF!

Costo Hora
#REF!
#REF!
#REF!

Cargo anual
#REF!
#REF!
#REF!

tasa de amortizacion
8.685
Cargo adicional por la energa consumida (kwh) 1.217

2.1 Cargo fijo, independiente de la energa consumida


2.2 Cargo adicional por la energa consumida
Reynolds

221.4
1.217 por cada kilowatt-hora.

Costo de const.
#REF!
8,642,622.34
11,880,443.34

Amortizacin
#REF!
2,160,655.58
2,970,110.83

Costo Oper.
#REF!
#REF!
#REF!

Solucin: 64"

4000
######
3000000

v miu

##########
3000000
100000000

4.555
6.732
8.982

0.00001 m2/s
0.025 mm

Reynolds
4000
100000
3000000

v miu

100000
3000000
100000000

g
4.555
6.732
8.982

0.00001 m2/s
0.025 mm

Eficiencia
0.7

Potencia
Hp
#REF!

0.2h

Ht

#REF!
#REF!
#REF!

#REF!
#REF!
#REF!

DIAMETRO 8
Precio
Unitario

Solucin: 64"

Importe

237.06

2,440,769.76

272.09
174.64
424.19
485.1

367,865.68
1,397,120.00
3,793,887.90
3,880,800.00
11,880,443.34

Anlisis de Dimetro Econmico


Funcionamiento hidrulico
Dimetro Nominal (d)

rea (A)

Gasto (Q)

Vel.(V)

Long. (L)

m3/seg

m/seg

Friccin

Constante

Prdidas

He+ha

Hs

Ht

friccin

Eficiencia

Potencia

pulgadas

m2

Hp

20

0.5

0.1963

0.35

1.783

8000

0.01

0.04153

40.696

18.000

2.035

60.731

70%

399.55

24

0.6

0.2827

0.35

1.238

8000

0.01

0.01570

15.391

18.000

0.770

34.160

70%

224.74

30

0.75

0.4418

0.35

0.792

8000

0.01

0.00478

4.682

18.000

0.234

22.916

70%

150.76

Golpe de Ariete
Clase

A-7

Dimetro

Espesor e

145V

Ead

Ete

Ead/Ete

Sobrepres.

SPresVal

SPresTub

Presin Oper.

1+(Ead/Ete)

raizcuad.(A)

h=145v/B

0.8h

0.2h

0.2h+Ht

0.5

A-5

0.6

A-5

0.75

A
Concepto
Unidad
Excavacin material de
cualquier tipo
Plantilla

DIAMETRO 20
Precio
Cantidad
Unitario

DIAMETRO 24
Importe

Unidad

Cantidad

Precio Unitario

Importe

Unidad

m3

m3

m3

m3

m3

m3

Instalacin de tub.

ml

ml

ml

Relleno

m3

m3

m3

Suministro de tubera

ml

ml

ml

Sumas

Costos de Operacin
Clase

Dimetro nominal

Potencia

K. W. H.

Costo Hora

Cargo anual Costo de const. Amortizacin

Costo Oper.

DIAMETRO 30
Precio
Cantidad
Unitario

Importe

d1

d2
600

q
c
l
h
s1
s2

L1
L2

350
140
14305
130
0.00195406
0.00474877

- 22,209.49
36,514.49

500

Anlisis de Dimetro Econmico


Datos:
QMD:
L:
D=

Velocidad
Q=

350 LPS
8000 M
3.30

1.5 m/s
0.55

Funcionamiento hidrulico
Dimetro Nominal (d)
pulgadas
m
20
24
30

0.508
0.6096
0.762

rea (A)
m2

Gasto (Q)
m3/seg

0.202682992
0.291863508
0.456036731

Velocidad (V)
m/seg

0.35
0.35
0.35

Longitud (L)
m

1.727
1.199
0.767

Coeficiente
Friccin

8000
8000
8000

0.009
0.013
0.013

Constante

Prdidas
friccin

0.03091
0.02439
0.00742

He
m

30.288
23.899
7.270

Hs
m
17.000
17.000
17.000

Ht
m
0.850
0.850
0.850

48.138
41.749
25.120

Eficiencia
0.7
0.7
0.7

Golpe de Ariete
Clase
AC-5
AC-5
AC-5

Dimetro

Espesor e

50.8
60.96
76.2

0.049
0.06
0.072

145V

1.727
1.199
0.767

Ead

250.391015
173.8826493
111.2848956

1050036
1260043.2
1575054

Ete
1607.2
1968
2361.6

Ead/Ete
653.3325037
640.2658537
666.9435976

A
1+(Ead/Ete)
654.3325037
641.2658537
667.9435976

B
raizcuad.(A)
25.580
25.323
25.845

Sobrepres.
h=145v/B

SPresVal
0.8h

SPresTub
0.2h

9.788575469
6.866527932
4.305923669

7.83086037 1.957715094
5.49322235 1.373305586
3.44473894 0.861184734

Unidad

DIAMETRO 30
Precio
Cantidad
Unitario

Costos de Construccin
DIAMETRO 20

DIAMETRO 24

Concepto
Unidad
Excavacin material de
cualquier tipo
Plantilla
Instalacin de tub.
Relleno
Suministro de tubera
Sumas

Cantidad Precio Unitario

Importe

Unidad

Cantidad

Precio Unitario

Importe

m3

7656

300

2,296,800.00

m3

8556

300

2,566,800.00

m3

10296

300

m3
ml
m3
ml

272.09
8000
7383.75
8000

150
4200
180
4200

40,813.50
33,600,000.00
1,329,075.17
33,600,000.00
70,866,688.67

m3
ml
m3
ml

1012
8000
7543.84
8000

272.09
5300
180
5300

275,355.08
42,400,000.00
1,357,891.37
42,400,000.00
89,000,046.45

m3
ml
m3
ml

1352
8000
8943.84
8000

272.09
7200
180
7200

Costos de Operacin
Clase
RD-41
RD-41
RD-41

Dimetro nominal
20
24
30

tasa de amortizacion

Potencia
50.8
60.96
76.2

12% TIIE

316.70
274.66
165.26

K. W. H.
236.1627982
204.8165326
123.2358401

Costo Hora
4,723.26
4,096.33
2,464.72

Cargo anual
41,375,722.25
35,883,856.51
21,590,919.18

Costo de const.
70,866,688.67
89,000,046.45
120,266,557.05

Amortizacin
10,404,947.68
13,067,364.15
17,658,045.79

Costo Oper.
51,780,669.93
48,951,220.66
39,248,964.98

Cargo adicional por la energa consumida (kwh)

1.217

2.1 Cargo fijo, independiente de la energa consumida


2.2 Cargo adicional por la energa consumida

Diametro
18
20
30

0.4572
0.508
0.762

Costo
340
377.78
566.67

Longitud $/m2
1.44
1.60
2.39

221.4
1.217 por cada kilowatt-hora.

236.71

Potencia
Hp
316.70
274.66
165.26

Presin Oper.
0.2h+Ht
50.096
43.122
25.981

METRO 30
Importe
3,088,800.00
367,865.68
57,600,000.00
1,609,891.37
57,600,000.00
120,266,557.05

Anlisis de Dimetro Econmico


Funcionamiento hidrulico
Dimetro Nominal (d)

rea (A)

Gasto (Q)

Vel.(V)

Long. (L)

m3/seg

m/seg

Friccin

Constante

Prdidas

He+ha

Hs

Ht

friccin

Eficiencia

pulgadas

m2

20

0.5

0.1963

1.283

8000

0.01

0.04153

21.086

18.000

1.054

40.140

70%

24

0.6

0.2827

0.35

1.238

8000

0.01

0.01570

15.391

18.000

0.770

34.160

70%

30

0.75

0.4418

0.35

0.792

8000

0.01

0.00478

4.682

18.000

0.234

22.916

70%

0.25

Golpe de Ariete
Clase

Dimetro

Espesor e

145V

Ead

Ete

Ead/Ete

Sobrepres.

SPresVal

SPresTub

1+(Ead/Ete)

raizcuad.(A)

h=145v/B

0.8h

0.2h

A-7

0.5

0.057

1.283

186.05

10335

18696

0.55

1.55

1.25

149.30

119.44

29.86

A-5

0.6

0.055

1.238

179.49

12402

18040

0.69

1.69

1.30

138.17

110.54

27.63

A-5

0.75

0.068

0.792

114.87

15502.5

22304

0.70

1.70

1.30

88.23

70.59

17.65

A
Concepto
Unidad

DIAMETRO 20
Precio
Cantidad
Unitario

DIAMETRO 24
Importe

Unidad

Cantidad

Precio Unitario

Importe

Unidad

DIAMETRO 30
Precio
Cantidad
Unitario

Excavacin material de
cualquier tipo

m3

14,240.00

300

4,272,000.00

m3

17200

300

5,160,000.00

m3

22160

300

Plantilla

m3

1,012.00

150

151,800.00

m3

1352

1012

1,368,224.00

m3

1680

1012
10285

Instalacin de tub.

ml

8000

5000

40,000,000.00

ml

8000

Relleno

m3

11278.65

180

2,030,156.65

m3

13152.36

Suministro de tubera

ml

8000

5000

40,000,000.00

ml

8000

Sumas

5,714.29
180
5,714.29

86,453,956.65

45,714,285.71

ml

8000

2,367,424.80

m3

16275.77

180

45,714,285.71

ml

8000.00

10285

100,324,220.23

Costos de Operacin
Clase

Dimetro nominal

Potencia

K. W. H.

Costo Hora

Cargo anual

Costo de const.

Amortizacin

Costo Oper.

A-7

20

0.5

190.09

141.7483417

212.62

1,862,573.21

86,453,956.65

12,693,536.45

14,556,109.66

A-5

24

0.6

224.74

167.5870982

251.38

2,202,094.47

100,324,220.23

14,730,027.35

16,932,121.82

A-5

30

0.75

150.76

112.4230125

168.63

1,477,238.38

175,837,798.60

r
Costo kwh1.5

25,817,251.08

12%

27,294,489.47

Potencia
Hp
190.09
224.74
150.76

Presin Oper.
0.2h+Ht
70.00
61.79
40.56

IAMETRO 30
Importe
6,648,000.00
1,700,160.00
82,280,000.00
2,929,638.60
82,280,000.00
175,837,798.60

Anlisis de Dimetro Econmico


Funcionamiento hidrulico
Dimetro Nominal (d)
pulgadas

rea (A)

Gasto (Q)

Vel.(V)

Long. (L)

m2

m3/seg

m/seg

Friccin

Constante

Prdidas

He+ha

Hs

Ht

friccin

Eficiencia

0.2032

0.0324

0.04

1.233

8000

0.01

5.05721

64.732

18.000

3.237

85.969

70%

10

0.254

0.0507

0.04

0.789

8000

0.01

1.53836

19.691

18.000

0.985

38.676

70%

12

0.3048

0.0730

0.04

0.548

8000

0.01

0.58178

7.447

18.000

0.372

25.819

70%

14

0.3556

0.0993

0.04

0.403

8000

0.01

0.25569

3.273

18.000

0.164

21.436

70%

16

0.4064

0.1297

0.04

0.308

8000

0.01

0.12543

1.606

18.000

0.080

19.686

70%

18

0.4572

0.1642

0.04

0.244

8000

0.01

0.06693

0.857

18.000

0.043

18.900

70%

20

0.508

0.2027

0.04

0.197

8000

0.01

0.03816

0.488

18.000

0.024

18.513

70%

24

0.6096

0.2919

0.04

0.137

8000

0.01

0.01443

0.185

18.000

0.009

18.194

70%

30

0.762

0.4560

0.04

0.088

8000

0.01

0.00439

0.056

18.000

0.003

18.059

70%

Dimetro

Espesor e

A-14

0.2032

0.057

1.233

178.85

4200.144

18696

0.22

1.22

1.11

161.62

129.29

32.32

A-5

0.254

0.055

0.789

114.46

5250.18

18040

0.29

1.29

1.14

100.74

80.59

20.15

A-5

0.3048

0.068

0.548

79.49

6300.216

22304

0.28

1.28

1.13

70.19

56.15

14.04

Golpe de Ariete
Clase

145V

Ead

Ete

Ead/Ete

1+(Ead/Ete)

raizcuad.(A)

Sobrepres.

SPresVal

SPresTub

h=145v/B

0.8h

0.2h

Costos de Operacin
Clase

Dimetro nominal

Potencia

K. W. H.

Costo Hora

Cargo anual

Costo Unitario de Costo


const. const.

CAUE

Costo Oper.

0.2032

64.64

48.20074377

72.30

633,357.77 $

1,300.93

10,407,416.16

1,528,060.96

2,161,418.74

10

0.254

29.08

21.68446875

32.53

284,933.92 $

1,530.38

12,243,016.08

1,797,571.53

2,082,505.45

12

0.3048

19.41

14.47616682

21.71

190,216.83 $

1,882.71

15,061,696.16

2,211,422.09

2,401,638.92

14

0.3556

16.12

12.01890508

18.03

157,928.41 $

2,199.12

17,592,992.64

2,583,077.77

2,741,006.18

16

0.4064

14.80

11.03739254

16.56

145,031.34 $

2,567.17

20,537,333.52

3,015,378.38

3,160,409.72

18

0.4572

14.21

10.59651162

15.89

139,238.16 $

3,050.43

24,403,443.28

3,583,017.00

3,722,255.17

20

0.508

13.92

10.37970562

15.57

136,389.33 $

3,543.49

28,347,881.76

4,162,156.18

4,298,545.52

24

0.6096

13.68

10.20091708

15.30

134,040.05 $

4,989.77

39,918,141.76

5,860,950.81

5,994,990.86

30

0.762

13.58

10.12525717

15.19

133,045.88 $

6,802.93

54,423,400.34

7,990,674.37

8,123,720.25

12%

8,000.00

Costo kwh1.5

7,000.00
D
8
10
12
14
16
18
20
24
30

Energa El
79.17
35.62
23.78
19.74
18.13
17.40
17.05
16.76
16.63

CAUE
1300.93
1530.38
1882.71
2199.12
2567.17
3050.43
3543.49
4989.77
6802.93

Costo Total
1,380.10
1,565.99
1,906.49
2,218.87
2,585.30
3,067.84
3,560.53
5,006.52
6,819.56

6,000.00
5,000.00

Energa El

4,000.00

CAUE

3,000.00

Costo Total

2,000.00
1,000.00
0

10

15

20

25

30

35

Potencia
Hp
64.64
29.08
19.41
16.12
14.80
14.21
13.92
13.68
13.58

Presin Oper.
0.2h+Ht
118.29
58.82
39.86

Anlisis de Dimetro Econmico


Funcionamiento hidrulico
Dimetro Nominal (d) rea (A)
m2

Gasto (Q)

Vel.(V)

Long. (L)

m3/seg

m/seg

Friccin

Constante

Prdidas

He+ha

Hs

friccin

Eficiencia

Potencia

pulgadas

Hp

18

0.45

0.1590

0.375

2.358

4800

0.01

0.07284

49.167

44.700

93.867

70%

661.66

20

0.5

0.1963

0.375

1.910

4800

0.01

0.04153

28.031

44.700

72.731

70%

512.67

24

0.6

0.2827

0.375

1.326

4800

0.01

0.01570

10.601

44.700

55.301

70%

389.81

Golpe de Ariete
Clase

Dimetro

Espesor e

145V

Ead

Ete

Ead/Ete

1+(Ead/Ete)
14

0.45

14
10

raizcuad.(A)

Sobrepres.

SPresVal

SPresTub

h=145v/B

0.8h

0.2h

2.36

341.98

930,150

1,640,000

0.57

1.57

1.25

273.18

218.54

54.64

0.5

5.8

1.91

277.00

1,033,500

1,902,400

0.54

1.54

1.24

222.98

178.38

44.60

0.6

4.9

1.33

192.34

1,240,200

1,607,200

0.77

1.77

1.33

144.51

115.60

28.90

Costos de Construccin
DIAMETRO 20

Concepto
Unidad

DIAMETRO 24

Cantidad Precio Unitario

Importe

Excavacin material
clase A

m3

4810

852.4

4,100,044.00

Excavacin material
clase B

m3

2004

1133.5

2,271,534.00

Excavacin material
clase A

m3

1202

5610

6,743,220.00

m3

272.09

1363.2

370,913.09

ml

8000

1722

Relleno Compactado

m3

4537.75

913.2

4,143,874.17

Relleno Volteo

m3

340.8

0.00

Plantilla Apisonada
Instalacin, Junteo y
Prueba de tubera

Atraques

Unidad

Cantidad

Precio Unitario

Importe

Unidad

DIAMETRO 30
Precio
Unitario
Cantidad

m3

8556

852.4

7,293,134.40

m3

10296

852.4

m3

1012

272.09

275,355.08

m3

1352

272.09

13,776,000.00

m3

0.00

ml

8000

5300

42,400,000.00

ml

8000

7200

m3

7543.84

913.2

6,889,035.56

m3

8943.84

913.2

Costo de tuberia

ml

Suministro de tubera

ml

8000

34500

0.00

1722

13,776,000.00

ml

8000

5300

42,400,000.00

ml

0.00

Acarreo
Sumas

45,181,585.26

99,257,525.04

Costos de Operacin
Clase

Dimetro nominal

Potencia

K. W. H.

Costo Hora

Cargo anual

Costo Unitario de Costo


const. const.

CAUE

Costo Oper.

18

0.45

661.66

493.3975666

740.10

6,483,244.03 $

1,300.93

6,244,449.70

916,836.58

7,400,080.60

20

0.5

512.67

382.2977011

573.45

5,023,391.79 $

1,530.38

7,345,809.65

1,078,542.92

6,101,934.71

24

0.6

389.81

290.6794742

436.02

3,819,528.29 $

1,882.71

9,037,017.70

1,326,853.25

5,146,381.54

r
3,000.00

Costo kwh1.5

2,500.00
D

Energa El

CAUE

Costo Total

2,000.00

12%

8000

7200

18
20
24
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!

1,350.68
1,046.54
795.74
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!

1300.93
1530.38
1882.71
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!

2,651.60
2,576.92
2,678.45
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!

2,000.00
1,500.00

Energa El
CAUE

1,000.00

Costo Total

500.00
-500.00
-5

10

15

20

25

30

Presin Oper.
0.2h+Ht
148.50
117.33
84.20

AMETRO 30
Importe
8,776,310.40

367,865.68

57,600,000.00
8,167,515.56

57,600,000.00

132,511,691.64

COSTO TOTAL DE ACUEDUCTO A VALOR PRESENTE


Ao

Costo ConstruccinCosto Bombeo Costo Anual VP


0
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20

Hest
n
r
l

#REF!

VP ACUMULADO
#REF!

455,798.34
504,416.89
556,564.21
612,460.85
672,327.36
736,384.29
804,852.18
877,951.58
955,903.05
1,038,927.13
1,127,244.37
1,221,075.31
1,320,640.51
1,426,160.51
1,537,855.86
1,655,947.12
1,780,654.82
1,912,199.52
2,050,801.76
2,350,061.08
-

$406,962.81
$402,118.06
$396,151.41
$389,229.94
$381,496.60
$373,075.20
$364,074.25
$354,589.92
$344,708.22
$334,506.73
$324,055.82
$313,419.62
$302,656.72
$291,820.70
$280,960.52
$270,120.85
$259,342.30
$248,661.64
$238,111.98
$243,623.23
6,519,686.50

COSTO TOTAL DE ACUEDUCTO A VALOR PRESEN


Ao

Q (lps)

Prdida de Carga Prdidad M

Carga de Bomba
5%

0
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20

150
160
170
180
190
200
210
220
230
240
250
260
270
280
290
300
310
320
330
350

Hest
n
r
l

2.29
2.61
2.94
3.30
3.67
4.07
4.49
4.93
5.38
5.86
6.36
6.88
7.42
7.98
8.56
9.16
9.78
10.42
11.08
12.47

17
70%
12%
8000

0.1145
0.1303
0.1471
0.1649
0.1837
0.2035
0.2244
0.2463
0.2692
0.2931
0.3180
0.3440
0.3709
0.3989
0.4279
0.4580
0.4890
0.5210
0.5541
0.6233

Diametro
n de material
Constante
$/kwr

19.40
19.74
20.09
20.46
20.86
21.27
21.71
22.17
22.65
23.15
23.68
24.22
24.79
25.38
25.99
26.62
27.27
27.94
28.64
30.09

600
0.009
0.0127
1.0595

COSTO TOTAL DE ACUEDUCTO A VALOR PRESEN


Ao

Q (lps)

Prdida de Carga Prdidad M

Carga de Bomba
5%

0
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17

150
160
170
180
190
200
210
220
230
240
250
260
270
280
290
300
310

6.05
6.89
7.78
8.72
9.71
10.76
11.87
13.02
14.24
15.50
16.82
18.19
19.62
21.10
22.63
24.22
25.86

0.3027
0.3444
0.3888
0.4359
0.4857
0.5382
0.5934
0.6512
0.7118
0.7750
0.8409
0.9095
0.9809
1.0549
1.1315
1.2109
1.2930

23.36
24.23
25.17
26.15
27.20
28.30
29.46
30.68
31.95
33.27
34.66
36.10
37.60
39.15
40.76
42.43
44.15

18
19
20

320
330
350

Hest
n
r
l

27.56
29.30
32.96

17
70%
12%
8000

1.3778
1.4652
1.6482

Diametro
n de material
Constante
$/kwr

45.93
47.77
51.61

500
0.009
0.0336
1.0595

COSTO TOTAL DE ACUEDUCTO A VALOR PRESEN


Ao

Q (lps)

Prdida de Carga Prdidad M

Carga de Bomba
5%

0
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20

150
160
170
180
190
200
210
220
230
240
250
260
270
280
290
300
310
320
330
350

Hest
n
r
l

10.62
12.08
13.64
15.29
17.04
18.88
20.82
22.84
24.97
27.19
29.50
31.91
34.41
37.01
39.70
42.48
45.36
48.33
51.40
57.82

17
70%
12%
8000

0.5310
0.6042
0.6820
0.7646
0.8520
0.9440
1.0408
1.1422
1.2485
1.3594
1.4750
1.5954
1.7205
1.8503
1.9848
2.1240
2.2680
2.4167
2.5701
2.8910

Diametro
n de material
Constante
$/kwr

28.15
29.69
31.32
33.06
34.89
36.82
38.86
40.99
43.22
45.55
47.98
50.50
53.13
55.86
58.68
61.60
64.63
67.75
70.97
77.71

450
0.009
0.0590
1.0595

COSTO TOTAL DE ACUEDUCTO A VALOR PRESEN


Ao

Q (lps)

Prdida de Carga Prdidad M

Carga de Bomba
5%

0
1

150

19.90

0.9952

37.90

2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20

160
170
180
190
200
210
220
230
240
250
260
270
280
290
300
310
320
330
350

Hest
n
r
l

22.65
25.57
28.66
31.93
35.38
39.01
42.82
46.80
50.95
55.29
59.80
64.49
69.35
74.40
79.62
85.01
90.59
96.34
108.37

17
70%
12%
8000

1.1323
1.2783
1.4331
1.5967
1.7692
1.9506
2.1408
2.3398
2.5477
2.7645
2.9900
3.2245
3.4677
3.7198
3.9808
4.2506
4.5293
4.8168
5.4183

Diametro
n de material
Constante
$/kwr

40.78
43.84
47.09
50.53
54.15
57.96
61.96
66.14
70.50
75.05
79.79
84.71
89.82
95.12
100.60
106.26
112.11
118.15
130.78

400
0.009
0.1106
1.0595

COSTO TOTAL DE ACUEDUCTO A VALOR PRESEN


Ao

Q (lps)

Prdida de Carga Prdidad M

Carga de Bomba
5%

0
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20

150
160
170
180
190
200
210
220
230
240
250
260
270
280
290
300
310
320
330
350

40.57
46.16
52.11
58.42
65.10
72.13
79.52
87.28
95.39
103.87
112.70
121.90
131.45
141.37
151.65
162.29
173.29
184.65
196.37
220.89

2.0286
2.3081
2.6057
2.9212
3.2548
3.6064
3.9761
4.3638
4.7695
5.1933
5.6351
6.0949
6.5727
7.0686
7.5826
8.1145
8.6645
9.2325
9.8185
11.0447

59.60
65.47
71.72
78.35
85.35
92.74
100.50
108.64
117.16
126.06
135.34
144.99
155.03
165.44
176.23
187.40
198.95
210.88
223.19
248.94

Hest
n
r
l

17
70%
12%
8000

Diametro
n de material
Constante
$/kwr

350
0.009
0.2254
1.0595

COSTO TOTAL DE ACUEDUCTO A VALOR PRESEN


Ao

Q (lps)

Prdida de Carga Prdidad M

Carga de Bomba
5%

0
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20

150
160
170
180
190
200
210
220
230
240
250
260
270
280
290
300
310
320
330
350

Hest
n
r
l

92.32
105.04
118.58
132.94
148.12
164.12
180.94
198.58
217.05
236.33
256.44
277.36
299.11
321.67
345.06
369.27
394.30
420.14
446.81
502.61

17
70%
12%
8000

4.6158
5.2518
5.9288
6.6468
7.4059
8.2060
9.0471
9.9292
10.8524
11.8166
12.8218
13.8681
14.9553
16.0837
17.2530
18.4634
19.7148
21.0072
22.3407
25.1307

Diametro
n de material
Constante
$/kwr

113.93
127.29
141.50
156.58
172.52
189.32
206.99
225.51
244.90
265.15
286.26
308.23
331.06
354.76
379.31
404.73
431.01
458.15
486.15
544.75

300
0.009
0.5129
1.0595

COSTO TOTAL DE ACUEDUCTO A VALOR PRESEN


Ao

Q (lps)

Prdida de Carga Prdidad M

Carga de Bomba
5%

0
1
2
3
4
5

150
160
170
180
190

244.11
277.74
313.54
351.51
391.66

12.2054
13.8870
15.6771
17.5757
19.5829

273.31
308.63
346.22
386.09
428.24

6
7
8
9
10
11
12
13
14
15
16
17
18
19
20

200
210
220
230
240
250
260
270
280
290
300
310
320
330
350

Hest
n
r
l

433.97
478.45
525.10
573.92
624.92
678.08
733.41
790.91
850.58
912.42
976.43
1,042.61
1,110.96
1,181.48
1,329.03

17
70%
12%
8000

21.6985
23.9225
26.2551
28.6962
31.2458
33.9038
36.6704
39.5454
42.5290
45.6210
48.8215
52.1305
55.5480
59.0740
66.4515

472.67
519.37
568.36
619.62
673.16
728.98
787.08
847.45
910.11
975.04
1,042.25
1,111.74
1,183.51
1,257.56
1,412.48

Diametro
n de material
Constante
$/kwr

250
0.009
1.3562
1.0595

COSTO TOTAL DE ACUEDUCTO A VALOR PRESEN


Ao
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20

Ao

D1
$338,086.16
$327,483.47
$316,221.58
$304,514.68
$292,538.21
$280,435.30
$268,322.23
$256,292.96
$244,422.87
$232,771.89
$221,387.14
$210,305.06
$199,553.27
$189,152.01
$179,115.48
$169,452.81
$160,168.96
$151,265.50
$142,741.14
$142,031.14

D1
1
2
3

D2
$406,962.81
$402,118.06
$396,151.41
$389,229.94
$381,496.60
$373,075.20
$364,074.25
$354,589.92
$344,708.22
$334,506.73
$324,055.82
$313,419.62
$302,656.72
$291,820.70
$280,960.52
$270,120.85
$259,342.30
$248,661.64
$238,111.98
$243,623.23

D2
$42.26
$40.94
$39.53

D3
490,485.3320
492,622.8887
493,077.4714
491,958.9964
489,371.0393
485,413.9793
480,186.9151
473,788.6761
466,318.1895
457,874.4005
448,555.9018
438,460.3878
427,684.0219
416,320.7796
404,461.8139
392,194.8716
379,603.7826
366,768.0309
353,762.4134
366,817.7938

D3
$50.87
$50.26
$49.52

D4
$660,330.66
$676,666.93
$690,179.25
$700,861.32
$708,736.65
$713,857.95
$716,305.18
$716,182.59
$713,615.36
$708,745.91
$701,730.21
$692,734.19
$681,930.44
$669,495.09
$655,605.06
$640,435.72
$624,158.78
$606,940.59
$588,940.71
$617,337.29

D4
$61.31
$61.58
$61.63

$82.54
$84.58
$86.27

4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20

$38.06
$36.57
$35.05
$33.54
$32.04
$30.55
$29.10
$27.67
$26.29
$24.94
$23.64
$22.39
$21.18
$20.02
$18.91
$17.84
$17.75
$578.28

Diametro
600
500
450
400
350
300
250

Diametro
8
10
12
14
16
18
20
24

Energa Elctrica
$578.28
$814.96
$1,101.97
$1,685.60
$2,984.91
$6,237.81
$15,780.07

$
$
$
$
$
$
$
$

Importe
1,300.93
1,530.38
1,882.71
2,199.12
2,567.17
3,050.43
3,543.49
4,989.77

$48.65
$47.69
$46.63
$45.51
$44.32
$43.09
$41.81
$40.51
$39.18
$37.83
$36.48
$35.12
$33.77
$32.42
$31.08
$29.76
$30.45
$814.96

$61.49
$61.17
$60.68
$60.02
$59.22
$58.29
$57.23
$56.07
$54.81
$53.46
$52.04
$50.56
$49.02
$47.45
$45.85
$44.22
$45.85
$1,101.97

Inversin
Costos Total
$
4,989.77 $
5,568.05
$
3,543.49 $
4,358.45
$
3,050.43 $
4,152.40
$
2,567.17 $
4,252.77
$
2,199.12 $
5,184.04
$
1,882.71 $
8,120.52
$
1,530.38 $
17,310.45

$87.61
$88.59
$89.23
$89.54
$89.52
$89.20
$88.59
$87.72
$86.59
$85.24
$83.69
$81.95
$80.05
$78.02
$75.87
$73.62
$77.17
$1,685.60

AL DE ACUEDUCTO A VALOR PRESENTE


Potencia
Hp

Potencia
kwh
54.71
59.35
64.19
69.23
74.49
79.98
85.71
91.69
97.93
104.46
111.27
118.39
125.81
133.57
141.66
150.10
158.90
168.07
177.63
197.96

Costo ConstruccinCosto Bombeo

40.80
44.26
47.87
51.63
55.55
59.64
63.91
68.37
73.03
77.89
82.97
88.28
93.82
99.60
105.63
111.93
118.49
125.33
132.46
147.62

378,656.50
410,795.27
444,268.55
479,159.75
515,552.28
553,529.55
593,174.97
634,571.94
677,803.86
722,954.15
770,106.22
819,343.47
870,749.30
924,407.13
980,400.36
1,038,812.40
1,099,726.66
1,163,226.54
1,229,395.46
1,370,074.01

Costo Anual VP

$338,086.16
$327,483.47
$316,221.58
$304,514.68
$292,538.21
$280,435.30
$268,322.23
$256,292.96
$244,422.87
$232,771.89
$221,387.14
$210,305.06
$199,553.27
$189,152.01
$179,115.48
$169,452.81
$160,168.96
$151,265.50
$142,741.14
$142,031.14
4,626,261.87

AL DE ACUEDUCTO A VALOR PRESENTE


Potencia
Hp

Potencia
kwh

Costo ConstruccinCosto Bombeo

Costo Anual VP

#REF!
65.86
72.88
80.42
88.49
97.14
106.40
116.29
126.85
138.12
150.11
162.87
176.43
190.82
206.06
222.20
239.26
257.28

49.11
54.35
59.97
65.99
72.44
79.34
86.72
94.59
102.99
111.94
121.45
131.56
142.29
153.66
165.70
178.42
191.86

455,798.34
504,416.89
556,564.21
612,460.85
672,327.36
736,384.29
804,852.18
877,951.58
955,903.05
1,038,927.13
1,127,244.37
1,221,075.31
1,320,640.51
1,426,160.51
1,537,855.86
1,655,947.12
1,780,654.82

$406,962.81
$402,118.06
$396,151.41
$389,229.94
$381,496.60
$373,075.20
$364,074.25
$354,589.92
$344,708.22
$334,506.73
$324,055.82
$313,419.62
$302,656.72
$291,820.70
$280,960.52
$270,120.85
$259,342.30

276.29
296.32
339.55

206.03
220.96
253.21

1,912,199.52
2,050,801.76
2,350,061.08
-

$248,661.64
$238,111.98
$243,623.23
6,519,686.50

AL DE ACUEDUCTO A VALOR PRESENTE


Potencia
Hp

Potencia
kwh

Costo ConstruccinCosto Bombeo

Costo Anual VP

79.37
89.29
100.09
111.85
124.61
138.44
153.38
169.50
186.84
205.47
225.45
246.82
269.64
293.98
319.87
347.39
376.59
407.52
440.24
511.26

59.19
66.58
74.64
83.41
92.92
103.23
114.38
126.39
139.33
153.22
168.12
184.05
201.07
219.22
238.53
259.05
280.82
303.89
328.28
381.25

549,343.57
617,946.15
692,738.35
774,107.01
862,438.98
958,121.12
1,061,540.29
1,173,083.32
1,293,137.07
1,422,088.39
1,560,324.13
1,708,231.14
1,866,196.28
2,034,606.40
2,213,848.34
2,404,308.95
2,606,375.09
2,820,433.61
3,046,871.36
3,538,431.95
-

$490,485.33
$492,622.89
$493,077.47
$491,959.00
$489,371.04
$485,413.98
$480,186.92
$473,788.68
$466,318.19
$457,874.40
$448,555.90
$438,460.39
$427,684.02
$416,320.78
$404,461.81
$392,194.87
$379,603.78
$366,768.03
$353,762.41
$366,817.79
8,815,727.69

AL DE ACUEDUCTO A VALOR PRESENTE


Potencia
Hp

Potencia
kwh

Costo ConstruccinCosto Bombeo

Costo Anual VP

106.86

79.68

739,570.34

$660,330.66

122.64
140.10
159.34
180.47
203.59
228.80
256.21
285.93
318.05
352.69
389.95
429.94
472.75
518.49
567.28
619.20
674.37
732.90
860.43

91.45
104.47
118.82
134.58
151.82
170.62
191.06
213.22
237.17
263.00
290.79
320.60
352.53
386.64
423.02
461.74
502.88
546.52
641.62

848,810.99
969,652.16
1,102,818.86
1,249,036.14
1,409,029.02
1,583,522.54
1,773,241.72
1,978,911.61
2,201,257.23
2,441,003.61
2,698,875.79
2,975,598.79
3,271,897.66
3,588,497.41
3,926,123.09
4,285,499.73
4,667,352.35
5,072,405.99
5,955,016.45
-

$676,666.93
$690,179.25
$700,861.32
$708,736.65
$713,857.95
$716,305.18
$716,182.59
$713,615.36
$708,745.91
$701,730.21
$692,734.19
$681,930.44
$669,495.09
$655,605.06
$640,435.72
$624,158.78
$606,940.59
$588,940.71
$617,337.29
13,484,789.89

AL DE ACUEDUCTO A VALOR PRESENTE


Potencia
Hp

Potencia
kwh

Costo ConstruccinCosto Bombeo

Costo Anual VP

168.05
196.90
229.18
265.08
304.83
348.63
396.70
449.26
506.52
568.69
635.98
708.61
786.79
870.74
960.67
1,056.79
1,159.32
1,268.47
1,384.45
1,637.76

125.31
146.83
170.90
197.67
227.31
259.97
295.82
335.01
377.71
424.07
474.25
528.41
586.71
649.31
716.37
788.05
864.50
945.90
1,032.38
1,221.28

1,163,063.29
1,362,774.59
1,586,132.42
1,834,614.68
2,109,699.30
2,412,864.17
2,745,587.20
3,109,346.30
3,505,619.39
3,935,884.36
4,401,619.13
4,904,301.61
5,445,409.69
6,026,421.30
6,648,814.34
7,314,066.71
8,023,656.34
8,779,061.11
9,581,758.95
11,334,945.44
-

$1,038,449.37
$1,086,395.56
$1,128,977.72
$1,165,930.80
$1,197,100.04
$1,222,432.08
$1,241,964.21
$1,255,812.82
$1,264,161.50
$1,267,249.43
$1,265,360.32
$1,258,812.07
$1,247,947.36
$1,233,125.20
$1,214,713.52
$1,193,082.72
$1,168,600.14
$1,141,625.51
$1,112,507.15
$1,175,057.13
23,879,304.63

AL DE ACUEDUCTO A VALOR PRESENTE


Potencia
Hp

Potencia
kwh

Costo ConstruccinCosto Bombeo

Costo Anual VP

321.24
382.82
452.18
529.79
616.15
711.75
817.06
932.57
1,058.78
1,196.16
1,345.20
1,506.38
1,680.20
1,867.14
2,067.68
2,282.32
2,511.53
2,755.80
3,015.62
3,583.85

239.55
285.47
337.19
395.07
459.47
530.75
609.28
695.42
789.53
891.97
1,003.11
1,123.31
1,252.93
1,392.33
1,541.87
1,701.92
1,872.85
2,055.00
2,248.75
2,672.48

2,223,297.34
2,649,506.05
3,129,519.05
3,666,699.12
4,264,409.03
4,926,011.55
5,654,869.44
6,454,345.47
7,327,802.41
8,278,603.04
9,310,110.11
10,425,686.41
11,628,694.69
12,922,497.72
14,310,458.28
15,795,939.13
17,382,303.05
19,072,912.79
20,871,131.13
24,803,844.69
-

$1,985,086.91
$2,112,170.00
$2,227,529.85
$2,330,253.58
$2,419,740.21
$2,495,670.75
$2,557,975.75
$2,606,801.88
$2,642,479.01
$2,665,488.62
$2,676,434.18
$2,676,014.03
$2,664,996.69
$2,644,199.06
$2,614,467.22
$2,576,659.84
$2,531,634.07
$2,480,233.76
$2,423,279.77
$2,571,334.34
49,902,449.54

AL DE ACUEDUCTO A VALOR PRESENTE


Potencia
Hp

Potencia
kwh

Costo ConstruccinCosto Bombeo

Costo Anual VP

770.62
928.20
1,106.34
1,306.32
1,529.43

574.65
692.16
825.00
974.12
1,140.49

5,333,461.43
6,424,093.33
7,656,996.43
9,041,062.66
10,585,183.98

$4,762,019.13
$5,121,247.87
$5,450,098.81
$5,745,758.77
$6,006,317.66

1,776.95
2,050.16
2,350.35
2,678.81
3,036.82
3,425.66
3,846.62
4,300.99
4,790.04
5,315.07
5,877.36
6,478.19
7,118.85
7,800.62
9,292.64

1,325.07
1,528.80
1,752.66
1,997.59
2,264.56
2,554.52
2,868.43
3,207.25
3,571.94
3,963.45
4,382.75
4,830.79
5,308.53
5,816.92
6,929.53

12,298,252.34
14,189,159.68
16,266,797.96
18,540,059.12
21,017,835.12
23,709,017.90
26,622,499.41
29,767,171.61
33,151,926.44
36,785,655.85
40,677,251.79
44,835,606.21
49,269,611.05
53,988,158.28
64,314,447.66
-

AL DE ACUEDUCTO A VALOR PRESENTE


D5
$1,038,449.37
$1,086,395.56
$1,128,977.72
$1,165,930.80
$1,197,100.04
$1,222,432.08
$1,241,964.21
$1,255,812.82
$1,264,161.50
$1,267,249.43
$1,265,360.32
$1,258,812.07
$1,247,947.36
$1,233,125.20
$1,214,713.52
$1,193,082.72
$1,168,600.14
$1,141,625.51
$1,112,507.15
$1,175,057.13

D6
$1,985,086.91
$2,112,170.00
$2,227,529.85
$2,330,253.58
$2,419,740.21
$2,495,670.75
$2,557,975.75
$2,606,801.88
$2,642,479.01
$2,665,488.62
$2,676,434.18
$2,676,014.03
$2,664,996.69
$2,644,199.06
$2,614,467.22
$2,576,659.84
$2,531,634.07
$2,480,233.76
$2,423,279.77
$2,571,334.34

$4,762,019.13
$5,121,247.87
$5,450,098.81
$5,745,758.77
$6,006,317.66
$6,230,677.37
$6,418,455.25
$6,569,886.87
$6,685,731.18
$6,767,180.40
$6,815,776.10
$6,833,332.51
$6,821,867.45
$6,783,540.98
$6,720,601.79
$6,635,340.91
$6,530,052.32
$6,407,000.03
$6,268,391.05
$6,667,270.74

D5
$129.81
$135.80
$141.12

D6
$248.14
$264.02
$278.44

D7
$595.25
$640.16
$681.26

$6,230,677.37
$6,418,455.25
$6,569,886.87
$6,685,731.18
$6,767,180.40
$6,815,776.10
$6,833,332.51
$6,821,867.45
$6,783,540.98
$6,720,601.79
$6,635,340.91
$6,530,052.32
$6,407,000.03
$6,268,391.05
$6,667,270.74
126,240,547.17

$145.74
$149.64
$152.80
$155.25
$156.98
$158.02
$158.41
$158.17
$157.35
$155.99
$154.14
$151.84
$149.14
$146.08
$142.70
$139.06
$146.88
$2,984.91

$291.28
$302.47
$311.96
$319.75
$325.85
$330.31
$333.19
$334.55
$334.50
$333.12
$330.52
$326.81
$322.08
$316.45
$310.03
$302.91
$321.42
$6,237.81

$718.22
$750.79
$778.83
$802.31
$821.24
$835.72
$845.90
$851.97
$854.17
$852.73
$847.94
$840.08
$829.42
$816.26
$800.88
$783.55
$833.41
$15,780.07

$20,000.00

$18,000.00
$16,000.00

$14,000.00
$12,000.00
Energa Elctrica

$10,000.00

Inversin
Costos Total

$8,000.00

$6,000.00
$4,000.00

$2,000.00
$0.00
0

100

200

300

400

500

600

700

Ao

Q (lps)

Diametro Pul
Diametro en m
Velocidad
f

0
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20

Aos

150
160
170
180
190
200
210
220
230
240
250
260
270
280
290
300
310
320
330
350

Gasto (Q)
m3/seg
0.15

Hest
n
r
l

17
70%
12%
8000

Ao

Q (lps)
0
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20

150
160
170
180
190
200
210
220
230
240
250
260
270
280
290
300
310
320
330
350

Hest
n
r
l

17
70%
12%
8000

Ao

Q (lps)
0
1
2
3
4
5
6
7
8
9

150
160
170
180
190
200
210
220
230

10
11
12
13
14
15
16
17
18
19
20

240
250
260
270
280
290
300
310
320
330
350

Hest
n
r
l

17
70%
12%
8000

Ao

Q (lps)
0
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20

Hest
n
r
l

150
160
170
180
190
200
210
220
230
240
250
260
270
280
290
300
310
320
330
350

17
70%
12%
8000

Ao

Q (lps)
0
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20

150
160
170
180
190
200
210
220
230
240
250
260
270
280
290
300
310
320
330
350

Hest
n
r
l

17
70%
12%
8000

Ao

Q (lps)
0
1
2
3
4
5
6
7
8
9
10
11
12
13
14

150
160
170
180
190
200
210
220
230
240
250
260
270
280

15
16
17
18
19
20

290
300
310
320
330
350

Hest
n
r
l

17
70%
12%
8000

Ao

Q (lps)
0
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20

Hest
n
r
l

150
160
170
180
190
200
210
220
230
240
250
260
270
280
290
300
310
320
330
350

17
70%
12%
8000

Ao

D1
$338,086.16
$327,483.47
$316,221.58
$304,514.68
$292,538.21
$280,435.30
$268,322.23
$256,292.96
$244,422.87
$232,771.89
$221,387.14
$210,305.06
$199,553.27
$189,152.01
$179,115.48
$169,452.81
$160,168.96
$151,265.50
$142,741.14
$142,031.14

1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20

Ao

D1
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20

$42.26
$40.94
$39.53
$38.06
$36.57
$35.05
$33.54
$32.04
$30.55
$29.10
$27.67
$26.29
$24.94
$23.64
$22.39
$21.18
$20.02
$18.91
$17.84
$17.75
$578.28

Diametro
600
500
450
400
350
300
250

Energa Elctrica
$578.28
$814.96
$1,101.97
$1,685.60
$2,984.91
$6,237.81
$15,780.07

Diametro
8
10
12
14
16
18
20
24

$
$
$
$
$
$
$
$

cdl

Importe
1,300.93
1,530.38
1,882.71
2,199.12
2,567.17
3,050.43
3,543.49
4,989.77

10

12

14

16

18

COSTO TOTAL DE ACUEDUCTO A VALO

COSTO TOTAL DE ACUEDUCTO A VALO

COSTO TOTAL DE ACUEDUCTO A VALO

COSTO TOTAL DE ACUEDUCTO A VALO

COSTO TOTAL DE ACUEDUCTO A VALO

COSTO TOTAL DE ACUEDUCTO A VALO

COSTO TOTAL DE ACUEDUCTO A VALO

20

24

30 Prdida de Carga Prdidad M

5%

2.29
2.61
2.94
3.30
3.67
4.07
4.49
4.93
5.38
5.86
6.36
6.88
7.42
7.98
8.56
9.16
9.78
10.42
11.08
12.47

0.1145
0.1303
0.1471
0.1649
0.1837
0.2035
0.2244
0.2463
0.2692
0.2931
0.3180
0.3440
0.3709
0.3989
0.4279
0.4580
0.4890
0.5210
0.5541
0.6233

Datos:
QMD:

350

L:
D=
Dimetro Nominal (d)
pulgadas
m
20

0.508

Diametro
n de material
Constante
$/kwr

8000
3.30

O TOTAL DE ACUEDUCTO A VALOR PRESENTE


Prdida de Carga Prdidad M
5%
6.05
6.89
7.78
8.72
9.71
10.76
11.87
13.02
14.24
15.50
16.82
18.19
19.62
21.10
22.63
24.22
25.86
27.56
29.30
32.96

0.3027
0.3444
0.3888
0.4359
0.4857
0.5382
0.5934
0.6512
0.7118
0.7750
0.8409
0.9095
0.9809
1.0549
1.1315
1.2109
1.2930
1.3778
1.4652
1.6482

Diametro
n de material
Constante
$/kwr

O TOTAL DE ACUEDUCTO A VALOR PRESENTE


Prdida de Carga Prdidad M
5%
10.62
12.08
13.64
15.29
17.04
18.88
20.82
22.84
24.97

0.5310
0.6042
0.6820
0.7646
0.8520
0.9440
1.0408
1.1422
1.2485

27.19
29.50
31.91
34.41
37.01
39.70
42.48
45.36
48.33
51.40
57.82

1.3594
1.4750
1.5954
1.7205
1.8503
1.9848
2.1240
2.2680
2.4167
2.5701
2.8910

Diametro
n de material
Constante
$/kwr

O TOTAL DE ACUEDUCTO A VALOR PRESENTE


Prdida de Carga Prdidad M
5%
19.90
22.65
25.57
28.66
31.93
35.38
39.01
42.82
46.80
50.95
55.29
59.80
64.49
69.35
74.40
79.62
85.01
90.59
96.34
108.37

0.9952
1.1323
1.2783
1.4331
1.5967
1.7692
1.9506
2.1408
2.3398
2.5477
2.7645
2.9900
3.2245
3.4677
3.7198
3.9808
4.2506
4.5293
4.8168
5.4183

Diametro
n de material
Constante
$/kwr

O TOTAL DE ACUEDUCTO A VALOR PRESENTE


Prdida de Carga Prdidad M
5%
40.57
46.16
52.11
58.42
65.10
72.13
79.52
87.28
95.39
103.87
112.70
121.90
131.45
141.37
151.65
162.29
173.29
184.65
196.37
220.89

2.0286
2.3081
2.6057
2.9212
3.2548
3.6064
3.9761
4.3638
4.7695
5.1933
5.6351
6.0949
6.5727
7.0686
7.5826
8.1145
8.6645
9.2325
9.8185
11.0447

Diametro
n de material
Constante
$/kwr

O TOTAL DE ACUEDUCTO A VALOR PRESENTE


Prdida de Carga Prdidad M
5%
92.32
105.04
118.58
132.94
148.12
164.12
180.94
198.58
217.05
236.33
256.44
277.36
299.11
321.67

4.6158
5.2518
5.9288
6.6468
7.4059
8.2060
9.0471
9.9292
10.8524
11.8166
12.8218
13.8681
14.9553
16.0837

345.06
369.27
394.30
420.14
446.81
502.61

17.2530
18.4634
19.7148
21.0072
22.3407
25.1307

Diametro
n de material
Constante
$/kwr

O TOTAL DE ACUEDUCTO A VALOR PRESENTE

O TOTAL DE ACUEDUCTO A VALOR PRESENTE

Prdida de Carga Prdidad M


5%
244.11
277.74
313.54
351.51
391.66
433.97
478.45
525.10
573.92
624.92
678.08
733.41
790.91
850.58
912.42
976.43
1,042.61
1,110.96
1,181.48
1,329.03

12.2054
13.8870
15.6771
17.5757
19.5829
21.6985
23.9225
26.2551
28.6962
31.2458
33.9038
36.6704
39.5454
42.5290
45.6210
48.8215
52.1305
55.5480
59.0740
66.4515

Diametro
n de material
Constante
$/kwr

D2
$406,962.81
$402,118.06
$396,151.41
$389,229.94
$381,496.60
$373,075.20
$364,074.25
$354,589.92
$344,708.22
$334,506.73
$324,055.82
$313,419.62
$302,656.72
$291,820.70
$280,960.52
$270,120.85
$259,342.30
$248,661.64
$238,111.98
$243,623.23

D2
$50.87
$50.26
$49.52
$48.65
$47.69
$46.63
$45.51
$44.32
$43.09
$41.81
$40.51
$39.18
$37.83
$36.48
$35.12
$33.77
$32.42
$31.08
$29.76
$30.45
$814.96

D3
490,485.3320
492,622.8887
493,077.4714
491,958.9964
489,371.0393
485,413.9793
480,186.9151
473,788.6761
466,318.1895
457,874.4005
448,555.9018
438,460.3878
427,684.0219
416,320.7796
404,461.8139
392,194.8716
379,603.7826
366,768.0309
353,762.4134
366,817.7938

D3
$61.31
$61.58
$61.63
$61.49
$61.17
$60.68
$60.02
$59.22
$58.29
$57.23
$56.07
$54.81
$53.46
$52.04
$50.56
$49.02
$47.45
$45.85
$44.22
$45.85
$1,101.97

Inversin
Costos Total
$
4,989.77 $
5,568.05
$
3,543.49 $
4,358.45
$
3,050.43 $
4,152.40
$
2,567.17 $
4,252.77
$
2,199.12 $
5,184.04
$
1,882.71 $
8,120.52
$
1,530.38 $
17,310.45

Carga de Bomba

19.40
19.74
20.09
20.46
20.86
21.27
21.71
22.17
22.65
23.15
23.68
24.22
24.79
25.38
25.99
26.62
27.27
27.94
28.64
30.09

Potencia

Potencia

Hp

kwh

54.71
59.35
64.19
69.23
74.49
79.98
85.71
91.69
97.93
104.46
111.27
118.39
125.81
133.57
141.66
150.10
158.90
168.07
177.63
197.96

Costo ConstruccinCosto Bombeo

40.80
44.26
47.87
51.63
55.55
59.64
63.91
68.37
73.03
77.89
82.97
88.28
93.82
99.60
105.63
111.93
118.49
125.33
132.46
147.62

378,656.50
410,795.27
444,268.55
479,159.75
515,552.28
553,529.55
593,174.97
634,571.94
677,803.86
722,954.15
770,106.22
819,343.47
870,749.30
924,407.13
980,400.36
1,038,812.40
1,099,726.66
1,163,226.54
1,229,395.46
1,370,074.01

Qmed = (2850 hab * 230 l/hab/da) / 86400 = 7.58 lps


LPS

QMD = 1.4 * 7.58 lps = 10.61 lps

QMH = 1.55 * 10.92 lps =16.44 lps.


rea (A)
m2
0.202682992

600
0.009
0.0127
1.0595

Velocidad (V)
m/seg
0.740

V2/2g
m

Longitud (L)
m
0.028 Prdidad M

Carga de Bomba

Potencia
Hp

Potencia
kwh

Costo ConstruccinCosto Bombeo


#REF!

23.36
24.23
25.17
26.15
27.20
28.30
29.46
30.68
31.95
33.27
34.66
36.10
37.60
39.15
40.76
42.43
44.15
45.93
47.77
51.61

65.86
72.88
80.42
88.49
97.14
106.40
116.29
126.85
138.12
150.11
162.87
176.43
190.82
206.06
222.20
239.26
257.28
276.29
296.32
339.55

49.11
54.35
59.97
65.99
72.44
79.34
86.72
94.59
102.99
111.94
121.45
131.56
142.29
153.66
165.70
178.42
191.86
206.03
220.96
253.21

455,798.34
504,416.89
556,564.21
612,460.85
672,327.36
736,384.29
804,852.18
877,951.58
955,903.05
1,038,927.13
1,127,244.37
1,221,075.31
1,320,640.51
1,426,160.51
1,537,855.86
1,655,947.12
1,780,654.82
1,912,199.52
2,050,801.76
2,350,061.08
-

500
0.009
0.0336
1.0595

Carga de Bomba

Potencia
Hp

Potencia
kwh

Costo ConstruccinCosto Bombeo


-

28.15
29.69
31.32
33.06
34.89
36.82
38.86
40.99
43.22

79.37
89.29
100.09
111.85
124.61
138.44
153.38
169.50
186.84

59.19
66.58
74.64
83.41
92.92
103.23
114.38
126.39
139.33

549,343.57
617,946.15
692,738.35
774,107.01
862,438.98
958,121.12
1,061,540.29
1,173,083.32
1,293,137.07

45.55
47.98
50.50
53.13
55.86
58.68
61.60
64.63
67.75
70.97
77.71

205.47
225.45
246.82
269.64
293.98
319.87
347.39
376.59
407.52
440.24
511.26

153.22
168.12
184.05
201.07
219.22
238.53
259.05
280.82
303.89
328.28
381.25

1,422,088.39
1,560,324.13
1,708,231.14
1,866,196.28
2,034,606.40
2,213,848.34
2,404,308.95
2,606,375.09
2,820,433.61
3,046,871.36
3,538,431.95
-

450
0.009
0.0590
1.0595

Carga de Bomba

Potencia
Hp

Potencia
kwh

Costo ConstruccinCosto Bombeo


-

37.90
40.78
43.84
47.09
50.53
54.15
57.96
61.96
66.14
70.50
75.05
79.79
84.71
89.82
95.12
100.60
106.26
112.11
118.15
130.78

400
0.009
0.1106
1.0595

106.86
122.64
140.10
159.34
180.47
203.59
228.80
256.21
285.93
318.05
352.69
389.95
429.94
472.75
518.49
567.28
619.20
674.37
732.90
860.43

79.68
91.45
104.47
118.82
134.58
151.82
170.62
191.06
213.22
237.17
263.00
290.79
320.60
352.53
386.64
423.02
461.74
502.88
546.52
641.62

739,570.34
848,810.99
969,652.16
1,102,818.86
1,249,036.14
1,409,029.02
1,583,522.54
1,773,241.72
1,978,911.61
2,201,257.23
2,441,003.61
2,698,875.79
2,975,598.79
3,271,897.66
3,588,497.41
3,926,123.09
4,285,499.73
4,667,352.35
5,072,405.99
5,955,016.45
-

Carga de Bomba

Potencia
Hp

Potencia
kwh

Costo ConstruccinCosto Bombeo


-

59.60
65.47
71.72
78.35
85.35
92.74
100.50
108.64
117.16
126.06
135.34
144.99
155.03
165.44
176.23
187.40
198.95
210.88
223.19
248.94

168.05
196.90
229.18
265.08
304.83
348.63
396.70
449.26
506.52
568.69
635.98
708.61
786.79
870.74
960.67
1,056.79
1,159.32
1,268.47
1,384.45
1,637.76

125.31
146.83
170.90
197.67
227.31
259.97
295.82
335.01
377.71
424.07
474.25
528.41
586.71
649.31
716.37
788.05
864.50
945.90
1,032.38
1,221.28

1,163,063.29
1,362,774.59
1,586,132.42
1,834,614.68
2,109,699.30
2,412,864.17
2,745,587.20
3,109,346.30
3,505,619.39
3,935,884.36
4,401,619.13
4,904,301.61
5,445,409.69
6,026,421.30
6,648,814.34
7,314,066.71
8,023,656.34
8,779,061.11
9,581,758.95
11,334,945.44
-

350
0.009
0.2254
1.0595

Carga de Bomba

Potencia
Hp

Potencia
kwh

Costo ConstruccinCosto Bombeo


-

113.93
127.29
141.50
156.58
172.52
189.32
206.99
225.51
244.90
265.15
286.26
308.23
331.06
354.76

321.24
382.82
452.18
529.79
616.15
711.75
817.06
932.57
1,058.78
1,196.16
1,345.20
1,506.38
1,680.20
1,867.14

239.55
285.47
337.19
395.07
459.47
530.75
609.28
695.42
789.53
891.97
1,003.11
1,123.31
1,252.93
1,392.33

2,223,297.34
2,649,506.05
3,129,519.05
3,666,699.12
4,264,409.03
4,926,011.55
5,654,869.44
6,454,345.47
7,327,802.41
8,278,603.04
9,310,110.11
10,425,686.41
11,628,694.69
12,922,497.72

379.31
404.73
431.01
458.15
486.15
544.75

2,067.68
2,282.32
2,511.53
2,755.80
3,015.62
3,583.85

1,541.87
1,701.92
1,872.85
2,055.00
2,248.75
2,672.48

14,310,458.28
15,795,939.13
17,382,303.05
19,072,912.79
20,871,131.13
24,803,844.69
-

300
0.009
0.5129
1.0595

Carga de Bomba

Potencia
Hp

Potencia
kwh

Costo ConstruccinCosto Bombeo


-

273.31
308.63
346.22
386.09
428.24
472.67
519.37
568.36
619.62
673.16
728.98
787.08
847.45
910.11
975.04
1,042.25
1,111.74
1,183.51
1,257.56
1,412.48

250
0.009
1.3562
1.0595

770.62
928.20
1,106.34
1,306.32
1,529.43
1,776.95
2,050.16
2,350.35
2,678.81
3,036.82
3,425.66
3,846.62
4,300.99
4,790.04
5,315.07
5,877.36
6,478.19
7,118.85
7,800.62
9,292.64

574.65
692.16
825.00
974.12
1,140.49
1,325.07
1,528.80
1,752.66
1,997.59
2,264.56
2,554.52
2,868.43
3,207.25
3,571.94
3,963.45
4,382.75
4,830.79
5,308.53
5,816.92
6,929.53

5,333,461.43
6,424,093.33
7,656,996.43
9,041,062.66
10,585,183.98
12,298,252.34
14,189,159.68
16,266,797.96
18,540,059.12
21,017,835.12
23,709,017.90
26,622,499.41
29,767,171.61
33,151,926.44
36,785,655.85
40,677,251.79
44,835,606.21
49,269,611.05
53,988,158.28
64,314,447.66
-

D4
$660,330.66
$676,666.93
$690,179.25
$700,861.32
$708,736.65
$713,857.95
$716,305.18
$716,182.59
$713,615.36
$708,745.91
$701,730.21
$692,734.19
$681,930.44
$669,495.09
$655,605.06
$640,435.72
$624,158.78
$606,940.59
$588,940.71
$617,337.29

D4
$82.54
$84.58
$86.27
$87.61
$88.59
$89.23
$89.54
$89.52
$89.20
$88.59
$87.72
$86.59
$85.24
$83.69
$81.95
$80.05
$78.02
$75.87
$73.62
$77.17
$1,685.60

D5
$1,038,449.37
$1,086,395.56
$1,128,977.72
$1,165,930.80
$1,197,100.04
$1,222,432.08
$1,241,964.21
$1,255,812.82
$1,264,161.50
$1,267,249.43
$1,265,360.32
$1,258,812.07
$1,247,947.36
$1,233,125.20
$1,214,713.52
$1,193,082.72
$1,168,600.14
$1,141,625.51
$1,112,507.15
$1,175,057.13

D6
$1,985,086.91
$2,112,170.00
$2,227,529.85
$2,330,253.58
$2,419,740.21
$2,495,670.75
$2,557,975.75
$2,606,801.88
$2,642,479.01
$2,665,488.62
$2,676,434.18
$2,676,014.03
$2,664,996.69
$2,644,199.06
$2,614,467.22
$2,576,659.84
$2,531,634.07
$2,480,233.76
$2,423,279.77
$2,571,334.34

$4,762,019.13
$5,121,247.87
$5,450,098.81
$5,745,758.77
$6,006,317.66
$6,230,677.37
$6,418,455.25
$6,569,886.87
$6,685,731.18
$6,767,180.40
$6,815,776.10
$6,833,332.51
$6,821,867.45
$6,783,540.98
$6,720,601.79
$6,635,340.91
$6,530,052.32
$6,407,000.03
$6,268,391.05
$6,667,270.74

D5
$129.81
$135.80
$141.12
$145.74
$149.64
$152.80
$155.25
$156.98
$158.02
$158.41
$158.17
$157.35
$155.99
$154.14
$151.84
$149.14
$146.08
$142.70
$139.06
$146.88
$2,984.91

D6
$248.14
$264.02
$278.44
$291.28
$302.47
$311.96
$319.75
$325.85
$330.31
$333.19
$334.55
$334.50
$333.12
$330.52
$326.81
$322.08
$316.45
$310.03
$302.91
$321.42
$6,237.81

D7
$595.25
$640.16
$681.26
$718.22
$750.79
$778.83
$802.31
$821.24
$835.72
$845.90
$851.97
$854.17
$852.73
$847.94
$840.08
$829.42
$816.26
$800.88
$783.55
$833.41
$15,780.07

$20,000.00

$18,000.00
$16,000.00

$14,000.00
$12,000.00

$10,000.00

$10,000.00
$8,000.00

$6,000.00
$4,000.00

$2,000.00
$0.00

200

400

600

800

Costo Anual VP

$338,086.16
$327,483.47
$316,221.58
$304,514.68
$292,538.21
$280,435.30
$268,322.23
$256,292.96
$244,422.87
$232,771.89
$221,387.14
$210,305.06
$199,553.27
$189,152.01
$179,115.48
$169,452.81
$160,168.96
$151,265.50
$142,741.14
$142,031.14
4,626,261.87

* 230 l/hab/da) / 86400 = 7.58 lps

Reynolds
375956.56

Hf
m

Hs
m

Hd
m

FALSE

#VALUE!

#VALUE!

#VALUE!

Eficiencia
0.7

Potencia
Hp
#VALUE!

Costo Anual VP

$406,962.81
$402,118.06
$396,151.41
$389,229.94
$381,496.60
$373,075.20
$364,074.25
$354,589.92
$344,708.22
$334,506.73
$324,055.82
$313,419.62
$302,656.72
$291,820.70
$280,960.52
$270,120.85
$259,342.30
$248,661.64
$238,111.98
$243,623.23
6,519,686.50

Costo Anual VP

$490,485.33
$492,622.89
$493,077.47
$491,959.00
$489,371.04
$485,413.98
$480,186.92
$473,788.68
$466,318.19

$457,874.40
$448,555.90
$438,460.39
$427,684.02
$416,320.78
$404,461.81
$392,194.87
$379,603.78
$366,768.03
$353,762.41
$366,817.79
8,815,727.69

Costo Anual VP

$660,330.66
$676,666.93
$690,179.25
$700,861.32
$708,736.65
$713,857.95
$716,305.18
$716,182.59
$713,615.36
$708,745.91
$701,730.21
$692,734.19
$681,930.44
$669,495.09
$655,605.06
$640,435.72
$624,158.78
$606,940.59
$588,940.71
$617,337.29
13,484,789.89

Costo Anual VP

$1,038,449.37
$1,086,395.56
$1,128,977.72
$1,165,930.80
$1,197,100.04
$1,222,432.08
$1,241,964.21
$1,255,812.82
$1,264,161.50
$1,267,249.43
$1,265,360.32
$1,258,812.07
$1,247,947.36
$1,233,125.20
$1,214,713.52
$1,193,082.72
$1,168,600.14
$1,141,625.51
$1,112,507.15
$1,175,057.13
23,879,304.63

Costo Anual VP

$1,985,086.91
$2,112,170.00
$2,227,529.85
$2,330,253.58
$2,419,740.21
$2,495,670.75
$2,557,975.75
$2,606,801.88
$2,642,479.01
$2,665,488.62
$2,676,434.18
$2,676,014.03
$2,664,996.69
$2,644,199.06

$2,614,467.22
$2,576,659.84
$2,531,634.07
$2,480,233.76
$2,423,279.77
$2,571,334.34
49,902,449.54

Costo Anual VP

$4,762,019.13
$5,121,247.87
$5,450,098.81
$5,745,758.77
$6,006,317.66
$6,230,677.37
$6,418,455.25
$6,569,886.87
$6,685,731.18
$6,767,180.40
$6,815,776.10
$6,833,332.51
$6,821,867.45
$6,783,540.98
$6,720,601.79
$6,635,340.91
$6,530,052.32
$6,407,000.03
$6,268,391.05
$6,667,270.74
126,240,547.17

Energa Elctrica
Inversin

Energa Elctrica
Inversin
Costos Total

Anlisis de Dimetro Econmico


Funcionamiento hidrulico
Dimetro Nominal (d)

rea (A)

Gasto (Q)

Vel.(V)

Long. (L)

m2

m3/seg

m/seg

Friccin

Constante

Prdidas

He+ha

Hs

Ht

friccin

Eficiencia

pulgadas

20

0.25

0.0491

0.08

1.630

5000

0.01

1.67426

53.576

43.000

2.679

99.255

70%

24

0.3

0.0707

0.08

1.132

5000

0.01

0.63318

20.262

43.000

1.013

64.275

70%

30

0.35

0.0962

0.08

0.832

5000

0.01

0.27828

8.905

43.000

0.445

52.350

70%

Golpe de Ariete
Clase

Dimetro

Espesor e

145V

Ead

Ete

Ead/Ete

Sobrepres.

SPresVal

SPresTub

1+(Ead/Ete)

raizcuad.(A)

h=145v/B

0.8h

0.2h

A-7

0.25

0.057

1.630

236.31

5167.5

18696

0.28

1.28

1.13

209.17

167.33

41.83

A-5

0.3

0.055

1.132

164.11

6201

18040

0.34

1.34

1.16

141.57

113.26

28.31

A-5

0.35

0.068

0.832

120.57

7234.5

22304

0.32

1.32

1.15

104.77

83.81

20.95

A
Concepto
Unidad

DIAMETRO 20
Precio
Cantidad
Unitario

DIAMETRO 24
Importe

Unidad

Cantidad

Precio Unitario

Importe

Unidad

DIAMETRO 30
Precio
Cantidad
Unitario

Excavacin material de
cualquier tipo

m3

8,900.00

300

2,670,000.00

m3

10750

300

3,225,000.00

m3

22160

300

Plantilla

m3

632.50

150

94,875.00

m3

1352

632.5

855,140.00

m3

1680

632.5
10285

Instalacin de tub.

ml

5000

5000

25,000,000.00

ml

8000

Relleno

m3

7049.16

180

1,268,847.90

m3

13152.36

Suministro de tubera

ml

5000

5000

25,000,000.00

ml

8000

Sumas

5,714.29
180
5,714.29

54,033,722.90

45,714,285.71

ml

8000

2,367,424.80

m3

16275.77

180

45,714,285.71

ml

8000.00

10285

97,876,136.23

Costos de Operacin
Clase

Dimetro nominal

Potencia

K. W. H.

Costo Hora

Cargo anual

Costo de const.

Amortizacin

Costo Oper.

A-7

20

0.25

149.26

111.3002196

166.95

1,462,484.89

54,033,722.90

7,933,460.28

9,395,945.17

A-5

24

0.3

96.65

72.07463578

108.11

947,060.71

97,876,136.23

14,370,589.28

15,317,650.00

A-5

30

0.35

78.72

58.70289762

88.05

771,356.07

175,200,238.60

r
Costo kwh1.5

25,723,641.82

12%

26,494,997.89

Potencia
Hp
149.26
96.65
78.72

Presin Oper.
0.2h+Ht
141.09
92.59
73.30

IAMETRO 30
Importe
6,648,000.00
1,062,600.00
82,280,000.00
2,929,638.60
82,280,000.00
175,200,238.60

Anlisis de Dimetro Econmico


Funcionamiento hidrulico
Dimetro Nominal (d)

rea (A)

Gasto (Q)

Vel.(V)

Long. (L)

m3/seg

m/seg

Friccin

Constante

Prdidas

He+ha

Hs

Ht

friccin

Eficiencia

Potencia

pulgadas

m2

Hp

20

0.5

0.1963

0.2519335

1.283

8000

0.01

0.04153

21.086

18.000

1.054

40.140

70%

190.09

24

0.6

0.2827

0.35

1.238

8000

0.01

0.01570

15.391

18.000

0.770

34.160

70%

224.74

30

0.75

0.4418

0.35

0.792

8000

0.01

0.00478

4.682

18.000

0.234

22.916

70%

150.76

Golpe de Ariete
Clase

Dimetro

Espesor e

145V

Ead

Ete

Ead/Ete

Sobrepres.

SPresVal

SPresTub

Presin Oper.

1+(Ead/Ete)

raizcuad.(A)

h=145v/B

0.8h

0.2h

0.2h+Ht

A-7

0.5

0.057

1.283

186.05

10335

18696

0.55

1.55

1.25

149.30

119.44

29.86

70.00

A-5

0.6

0.055

1.238

179.49

12402

18040

0.69

1.69

1.30

138.17

110.54

27.63

61.79

A-5

0.75

0.068

0.792

114.87

15502.5

22304

0.70

1.70

1.30

88.23

70.59

17.65

40.56

A
Concepto
Unidad
Excavacin material de
cualquier tipo
Plantilla

DIAMETRO 20
Precio
Cantidad
Unitario

DIAMETRO 24
Importe

Unidad

Cantidad

Precio Unitario

Importe

Unidad

m3

m3

m3

m3

m3

m3

Instalacin de tub.

ml

ml

ml

Relleno

m3

m3

m3

Suministro de tubera

ml

ml

ml

Sumas

Costos de Operacin
Clase

Dimetro nominal

Potencia

K. W. H.

Costo Hora

Cargo anual Costo de const. Amortizacin

Costo Oper.

DIAMETRO 30
Precio
Cantidad
Unitario

Importe

Anlisis de Dimetro Econmico


Datos:
QMD:
L:
D=

Velocidad
Q=

350 LPS
8000 M
3.30

1.5 m/s
0.55

Funcionamiento hidrulico
Dimetro Nominal (d)
pulgadas
m
20
24
30

0.5
0.6
0.7

rea (A)
m2

Gasto (Q)
m3/seg

0.196349541
0.282743339
0.3848451

Velocidad (V)
m/seg

0.35
0.35
0.35

Longitud (L)
m

1.783
1.238
0.909

Coeficiente
Friccin

8000
8000
8000

0.01
0.01
0.01

Constante

Prdidas
friccin

0.04153
0.01570
0.00690

He
m

40.696
15.391
6.764

Hs
m
17.000
17.000
17.000

0.850
0.850
0.850

Ht
m
58.546
33.241
24.614

Eficiencia
0.7
0.7
0.7

Golpe de Ariete
Clase
AC-5
AC-5
AC-5

Dimetro

Espesor e

50
60
70

0.049
0.06
0.072

145V
1.783
1.238
0.909

Ead

258.4676276
179.491408
131.8712386

1033500
1240200
1446900

Ete
1607.2
1968
2361.6

Ead/Ete

A
1+(Ead/Ete)

643.0438029
630.1829268
612.6778455

644.0438029
631.1829268
613.6778455

B
raizcuad.(A)

Sobrepres. SPresVal
h=145v/B
0.8h

25.378
10.184705
25.123 7.14440463
24.773 5.32328677

SPresTub
0.2h

8.14776399 2.036940998
5.7155237 1.428880925
4.25862942 1.064657354

Costos de Construccin
DIAMETRO 20

DIAMETRO 24

Concepto
Unidad
Excavacin material de
cualquier tipo
Plantilla
Instalacin de tub.
Relleno
Suministro de tubera
Sumas

Cantidad

Precio Unitario

Importe

Unidad

Cantidad

Precio Unitario

Importe

m3

7656

300

2,296,800.00

m3

8556

300

2,566,800.00

m3

10296

300

m3
ml
m3
ml

272.09
8000
7383.75
8000

150
4200
180
4200

40,813.50
33,600,000.00
1,329,075.17
33,600,000.00
70,866,688.67

m3
ml
m3
ml

1012
8000
7543.84
8000

272.09
5700
180
5700

275,355.08
45,600,000.00
1,357,891.37
45,600,000.00
95,400,046.45

m3
ml
m3
ml

1352
8000
8943.84
8000

272.09
7200
180
10285

Costos de Operacin
Clase
RD-41
RD-41
RD-41

Dimetro nominal
20
24
30

tasa de amortizacion

Unidad

DIAMETRO 30
Precio
Cantidad
Unitario

Potencia
50
60
70

12 TIIE

385.17
218.69
161.93

K. W. H.
287.2243001
163.0759472
120.7546073

Costo Hora
5,744.49
3,261.52
2,415.09

Cargo anual
50,321,697.38
28,570,905.95
21,156,207.20

Costo de const.
70,866,688.67
95,400,046.45
144,946,557.05

Amortizacin
850,400,264.07
1,144,800,557.43
1,739,358,684.63

Costo Oper.
900,721,961.45
1,173,371,463.38
1,760,514,891.83

Cargo adicional por la energa consumida (kwh)

1.217

2.1 Cargo fijo, independiente de la energa consumida


2.2 Cargo adicional por la energa consumida

Diametro
18
20
30

0.4572
0.508
0.762

Espesor
Costo
Area
0.049
4,200.00
0.06
5,714.29
0.072 10,285.71

221.4
1.217 por cada kilowatt-hora.

1.44
1.60
2.39

Volumen
$/m3
0.070380472
59,675.64
0.095755744
0.172360339

Potencia
Hp
385.17
218.69
161.93

Presin Oper.
0.2h+Ht
60.583
34.670
25.679

DIAMETRO 30
Importe
3,088,800.00
367,865.68
57,600,000.00
1,609,891.37
82,280,000.00
144,946,557.05

COSTO TOTAL DE ACUEDUCTO A VAL


Ao

Hest
n
r
l

Planeacin
Anlisis Hidrulico
Q (lps) Prdida de Carga Prdidad M Carga de Bomba Potencia
Potencia
5%
Hp
kwh
0
1
150
7.47
0.3737
25.85
72.88
54.35
2
160
8.50
0.4252
26.93
80.99
60.40
3
170
9.60
0.4801
28.08
89.73
66.91
4
180
10.76
0.5382
29.30
99.14
73.93
5
190
11.99
0.5996
30.59
109.26
81.47
6
200
13.29
0.6644
31.95
120.12
89.58
7
210
14.65
0.7325
33.38
131.78
98.27
8
220
16.08
0.8040
34.88
144.25
107.57
9
230
17.57
0.8787
36.45
157.60
117.52
10
240
19.14
0.9568
38.09
171.85
128.15
11
250
20.76
1.0382
39.80
187.04
139.47
12
260
22.46
1.1229
41.58
203.21
151.54
13
270
24.22
1.2109
43.43
220.41
164.36
14
280
26.05
1.3023
45.35
238.67
177.98
15
290
27.94
1.3970
47.34
258.04
192.42
16
300
29.90
1.4950
49.39
278.54
207.71
17
310
31.93
1.5963
51.52
300.22
223.88
18
320
34.02
1.7009
53.72
323.13
240.96
19
330
36.18
1.8089
55.99
347.29
258.97
20
350
40.70
2.0348
60.73
399.55
297.94

18
70%
12%
8000

Diametro
n de material
Constante
$/kwr
Espesor Tubera

500
0.01
0.0415
1.0595
0.049

TOTAL DE ACUEDUCTO A VALOR PRESENTE


Sobrepresin Valvulas

Tubera

Presin Trabajo

Costo ConstruccinCosto Bombeo


20,000,000.00

86.42
92.18
97.94
103.70
109.46
115.22
120.99
126.75
132.51
138.27
144.03
149.79
155.55
161.31
167.08
172.84
178.60
184.36
190.12
201.64

69.13
73.74
78.35
82.96
87.57
92.18
96.79
101.40
106.01
110.62
115.22
119.83
124.44
129.05
133.66
138.27
142.88
147.49
152.10
161.31

17.28
18.44
19.59
20.74
21.89
23.04
24.20
25.35
26.50
27.65
28.81
29.96
31.11
32.26
33.42
34.57
35.72
36.87
38.02
40.33

43.13
45.37
47.67
50.04
52.49
55.00
57.58
60.23
62.95
65.75
68.61
71.54
74.54
77.61
80.75
83.96
87.24
90.59
94.01
101.06

9,281.22
9,281.22
9,281.22
9,281.22
9,281.22
9,281.22
9,281.22
9,281.22
9,281.22
9,281.22
9,281.22
9,281.22
9,281.22
9,281.22
9,281.22
9,281.22
9,281.22
9,281.22
9,281.22
9,281.22
9,281.22

Costo Anual VP
20,000,000.00
$8,286.80
$7,398.93
$6,606.19
$5,898.38
$5,266.41
$4,702.15
$4,198.35
$3,748.53
$3,346.90
$2,988.30
$2,668.13
$2,382.26
$2,127.02
$1,899.12
$1,695.64
$1,513.97
$1,351.76
$1,206.93
$1,077.61
$962.15
20,069,325.55

Dotacin
230 lt/hab/dia
Tasa Crec Pob
2.50%
Ao
Poblacin
Qmed
QMD
0
70000
1
71,750.00
191.00
267.40
2
73,543.75
195.78
274.09
3
75,382.34
200.67
280.94
4
77,266.90
205.69
287.96
5
79,198.57
210.83
295.16
6
81,178.54
216.10
302.54
7
83,208.00
221.50
310.10
8
85,288.20
227.04
317.86
9
87,420.41
232.72
325.80
10
89,605.92
238.53
333.95
11
91,846.07
244.50
342.30
12
94,142.22
250.61
350.85
13
96,495.77
256.88
359.63
14
98,908.17
263.30
368.62
15 101,380.87
269.88
377.83

Você também pode gostar