2 Safety Information 3 Specification of the Cabinets Modules in the Cabinets 4 Installation Scenarios 4 Installation Tools 5 1. Installation Procedure 6 2. Installing the Cabinets 7 3. Earth Grounding the Cabinets 13 4. Installing the Optional Modules 14 5. Installing the Cables 17 6. Sealing the Cable Holes 22 7. Installing the Batteries and their Cables 23 8. Checklist for the Installation 24 9. Checking the Power-On Status 26 27 10. Appendix 11. Change History 32
Safety Information
Following All Safety Precautions
Before any operation, read the instructions and precautions in this document carefully to minimize the possibility of accidents. The Danger, Caution, and Note items in the documents do not cover all the safety precautions that must be followed. They only provide the generic safety precautions for operations. When operating Huawei products and equipment, you must comply with safety precautions and special safety instructions related to corresponding equipment provided by Huawei. The safety precautions in the document are related only to Huawei products. Huawei is not liable for any consequence that results from the violation of universal regulations for safety operations and safety codes on design, production, and equipment use.
Symbols
DANGER WARNING CAUTION TIP NOTE
Indicates a hazard with a high level of risk, which if not avoided, will result in death or serious injury. Indicates a hazard with a medium or low level of risk, which if not avoided, could result in minor or moderate injury. Indicates a potentially hazardous situation, which if not avoided, could result in equipment damage, data loss, performance degradation, or unexpected results. Indicates a tip that may help you solve a problem or save time. Provides additional information to emphasize or supplement important points of the main text.
Safety of Personnel
The high voltage power supply provides power for running the system. Direct contact with the high voltage power supply or contact through damp objects may result in fatal danger. Non-standard and improper high voltage operations may result in fire and electric shock. In a thunderstorm, do not perform operations on high voltage and AC power supply facilities or on a steel tower and mast. Ground the device before powering on the device. Otherwise, the personnel and device are in danger. Power off the device before performing operations on the power supply equipment. High power radio-frequency signals are harmful to human body. Before installing or maintaining an antenna on a steel tower or mast with a large number of transmitter antennas, the operator should coordinate with all parties to ensure that the transmitter antennas are shut down. When handling optical fibers, do not stand close to, or look into the optical fiber outlet with unaided eyes. Protect yourself when drilling holes. Flying dust may hurt your eyes or you may inhale the dust. Power off the batteries before connecting the cables to the batteries. Otherwise, casualties may occur. When working at a height, be cautious about falling objects.
Device Safety
Check the electrical connection of the device before operation and ensure that the device is reliably grounded. The static electricity generated by the human body may damage the electrostatic sensitive components on the circuit board, such as the large-scale integrated circuit (LIC). Wear an ESD wrist strap or ESD gloves when performing the operation. When working on batteries, take measures to prevent short circuits in the batteries and electrolyte spill/loss. The electrolyte may erode metal and boards, or even cause rust of the equipment or short circuits in the boards. When the cabinet is unpacked, it must be powered on in seven days. The maximum duration of the power-off state of the cabinet is 48 hours during maintenance.
Cabinet dimensions (excluding the TEC cool hood of the IBBS200T): 600 mm x 700 mm x 480 mm (W x H x D)
Cabinets
Item
Specification Remarks Including the cabinet frame, inner air circulation fan box, outer air circulation fan box, core of the heat-exchanger, EPS subrack, and related cables. Excluding the BBU, customer equipment, PMU, PSUs, and batteries. Including the cabinet, one PMU, three PSUs, and one BBU. Excluding the customer equipment and batteries. Including the cabinet frame, inner air circulation fan box, outer air circulation fan box, and core of the heat-exchanger Excluding the customer equipment and batteries
91 kg
Cabinet weight 57 kg
IBBS200T
Cabinet weight 70 kg Battery 48 V 50 Ah or 48 V 92 Ah battery group that can be maintained from the front
Excluding the batteries Supporting 48 V 100 Ah backup power by connecting two 48 V 50 Ah battery groups in parallel Supporting 48 V 184 Ah backup power by connecting two 48 V 92 Ah battery groups in parallel
TEC cooler hood (Depth: 206 mm) IBBS200D Cabinet weight 50 kg Excluding the batteries
TMC11H
CMUA
DCDU-03 EPS PMU PSU Junction box EPS48100D Junction box Junction box
IBBS200D
Power distribution box
IBBS200T
Power distribution box
In this document, the equipment appearance is for reference only. The actual equipment may differ from what is shown in the figures.
CMUA
Power box of the heating film
CMUA
Installation Scenarios
Wall
APM30H APM30H
APM30H
IBBS200D
APM30H
IBBS200D
Pole Base
The scenario for the installation of the TMC11H is the same as that for the APM30H. The scenario for the installation of the IBBS200T is the same as that for the IBBS200D.
Installation Tools
Insulated screwdriver
Diagonal pliers
Socket wrench
Torque wrench
Wire cutter
Rubber hammer
Iron
Wire stripper
Heat gun
Level bar
Multimeter
Cleaner
Installation Procedure
Start
End
Maximum 120
> 800
The values in the figure are not for the concrete plinth. The recommended distance between the cabinets is 40 mm, and the maximum distance between the cabinets is 150 mm. If the Noise Reduction Module (NRM) is installed, the distance between the cabinets is 150 mm.
434
16
unit: mm
Concrete plinth
Do not use the hammer drill to drill holes on the concrete plinth through the holes on the base. In this way, the paint on the base may be damaged.
Expansion tube
Adjust the base level by adding adjusting pads to the bolts between the base and the concrete plinth.
Remove the baffle plates from both sides of the base (by removing the plate on the left as an example).
of the base.
All the three cable holes on the base can be used for cabling. You can use the cable holes based on actual requirements.
Plastic screw
Lifting lug
Maximum 90
Before installing the plastic screws, clean the mounting holes to prevent scrap iron from entering.
To ensure the waterproof performance of the cabinet, keep well the cover plates for the round hole of the cabinet.
Cover plate
10
Pole
Trapezoidal rack
5. Move the cabinet on to the trapezoidal rack and attach them with the bolts.
Cover plate
Spring washer
When the APM30H is installed on a metal pole, grease must be covered. For details, see Appendix e on page 31.
11
280
Trapezoidal rack
Cover plate
12
APM30H
Grounding busbar
13
European standard
American standard
Multi-purpose UK standard
L2 PGND
SOU
N2
If both the SOU and the heater are installed in the cabinet, the heater is installed above the SOU, that is, in the 1 U space next to the SOU.
M6
PWR1
RS485 Information about the BBU, see BBU Installation Guide. Either the EMUA or the SLPU is installed.
PWR1
LOAD7
RS485
COM OUT
15
OUT0
M6
SLPU BBU
3. Install the external dry contact monitoring and alarm signal cable
Information about the BBU, see BBU Installation Guide. Either the EMUA or the SLPU is installed.
16
General principles for routing the cables 1 Different types of cables must be separately routed and cannot be bound in the same bundle. Cables in each bundle or any two bundles cannot be entangled. The cables must be bundled tightly and neatly. The jackets of the cables are not damaged. Labels or nameplates must be attached to the cables after they are installed. The cables of different types must be routed in parallel or separated by special objects. The bending radius of the cable is not less than five times of the diameter of the cable. If the length of the power cable is insufficient, replace the cable rather than adding connectors or soldering joints to lengthen the cable.
2 3 4 5 6
Install the input power cable for the TMC11H Install the input power cable for the APM30H
Remove the protecting cap of the power box of the DCDU-03. Connect the power cables. Recover the protecting cap. Remove the protecting cap of the power box of the EPS48100D. Connect the power cables. Recover the protecting cap.
NEG(-)
RTN(+) + -
17
110V AC mode
L PE N
L1 L2 N PE
2. APM30H-TMC11H
Power cables for the TMC11H Power cable for the junction box
NEG(-)
TMC
L N
L3
N3
RTN(+)
18
3. APM30H - IBBS200D/IBBS200T
Either the IBBS200D or the IBBS200T is installed. Add the power series 120 connector. For details, see "Appendix a" on page 27.
LOAD3
For details on how to assemble the easy power receptacle (pressfit type) connector, see "Appendix b" on page 28.
19
3. APM30H - IBBS200D/IBBS200T
Must route the power cables for the heating films in the IBBS200Ds into the power box of the heating film from the top down.
L1 N1
L2 N2
The power box of the heating film Prevent the wires from exposing out of the power box of the heating film.
From L2/N2
From L1/N1
If the LOAD2 is already occupied, it is recommended that the fuse for the LOAD4 terminals be changed to meet the output MCB requirements for the IBBS. For details, see "Appendix c" on page 29.
From LOAD2
From LOAD3
20
Principles for routing the monitoring signal cables When the signal cable is routed between cabinets, coil the extra length of the cable in the base if the cable is redundant.
UEIU COM_485 The installation procedure for connecting the monitoring signal cable to the IBBS200D or IBBS200T is the same. The only difference is that the position of the CMUA in the IBBS200D differs from the position of the CMUA in the IBBS200T. COM_IN MON0
CMUA
COM_IN
COM_IN CMUA
COM_OUT COM_IN
IBBD200T
IBBD200D
IBBD200D
21
The cable module for the IBBS200D, IBBS200T, or APM30H is the same as that for the TMC11H. When two IBBS200Ds or two IBBS200Ts are installed in stack mode, the installation of the cable module in the upper cabinet is not required.
Lead the cable through the cable hole with an aperture matching the cross-sectional area of the cable in order that the sealing is effective.
1. Close the cable holes on both sides and at the rear of the base.
Baffle plate
Fireproof clay Baffle plate Fireproof clay Baffle piece PVC corrugated pipe
The fireproof clay can be used to seal the cable holes of the base. It cannot be used to seal the cable holes of the cabinet.
22
Before installing the batteries, set the battery MCB labeled BAT to OFF to disconnect the equipment from the battery. During the installation of the batteries, use insulated tools such as wrenches and screwdrivers, and do not reversely connect the positive and negative poles. Otherwise, the batteries may burn, and the operations may cause human injuries.
EPS
Push the baffle plate upwards until it is contact with the screws, and then tighten the screws.
23
7 8 9 10 11
b
1
3 4 5
6 7 8
24
c
1 2 3 4
25
End
End
The normal voltage range of the DC output power to the DCDU-03 is from: -43.2 V DC ~ -57 V DC The normal status of the indicators on the CMUA: RUN indicator: Blinking ALM indicator: OFF
The normal status of the indicators on the PMU: RUN indicator: Blinking ALM indicator: OFF The normal status of the indicators on the PSU: Power indicator: Steady green Protection indicator: OFF Fault indicator: OFF The normal voltage range of the output power to the EPS is from: -43.2 V DC ~ -57 V DC The normal status of the indicators on the CMUA: RUN indicator: Blinking ALM indicator: OFF
26
10 Appendix a
Assembling the Power Series 120 Connector
1. Material: power series 120 connector, contact terminal, heat-shrinkable tube, and cable. 2. Procedure for adding the contact terminal
Strip a part of the jacket off the cable so that the conductor with a length of L1 is exposed. Lead the cable through the heatshrinkable tube, and then place the contact terminal on the exposed conductor.
L1=23~25 mm
L2 L1
Conductor
When stripping the jacket off the cable, do not damage the metal conductor of the cable.
Contact terminal
Use the crimping tool to press the end of the contact terminal on the conductor.
The contact terminal should contact the end of the jacket of the cable. When placing the contact terminal on the conductor closely to the end of the jacket, ensure that the L2 part of the conductor which sticks out of the contact terminal should not exceed 2 mm.
Crimping tool
heat-shrinkable tube
L3
heatshrinkable tube
Heat-shrinkable tube
L3
Retaining spring
The heat-shrinkable tube cannot be exposed outside the power series 120 connector.
27
10 Appendix b
Assembling the Easy Power Receptacle (Pressfit Type) Connector
1. Material: Easy Power Receptacle (Pressfit Type) Connector, contact terminal, heat-shrinkable tube, and cable 2. Procedure for adding the contact terminal
Strip the jacket off the cable according to the scale on the equipment. Use a screwdriver to push the sliding block until the in-position mark is completely exposed.
Scale
In-position mark
7.5
+0.5 .0
Insert the conductors into the holes. That is, insert the red cable connected to the positive pole into hole 1 and blue cable connected to the negative pole into hole 2.
Hole for the conductor Sliding block
The conductor should be in the center of the holes. The conductor should be perpendicular to the holes. The depth of the conductor into the hole should be not less than 11 mm.
Push back the sliding blocks until they are in position. Then, check whether the conductors are secure by gently pulling the cables.
If the conductor slides outward or the wire of the conductor is exposed outside the hole for the conductor, remove the conductor, cut the split wires, and then strip the jacket and install the conductor again.
28
10 Appendix c
Replacing the Fuse
1. Remove the extraction tool.
Fuse EPS
29
10 Appendix d
Repairing the Damaged Paint
1. Codes of color samples
Object Color Name Huawei Color Code YB026 International Color Code RAL7035
RAL7035
YB030
Pontone 422U
Cleaning
Clean cotton cloth can be used to rub the stain or dust on the surface of the area to be polished or repaired.
Paint repair
Brushing paint of corresponding color should be applied according to the original coating. Prior to the repair, the paint should be shaken well. After that, use the small brush inside the bottle to absorb paint and evenly spread on the damaged area till the scratch/damage is covered. Note that the paint coating applied should be as thin as possible. Paint coating should not reveal any drops. The surface should be kept smooth.
Drying
The surface of the repair paint should be placed in indoor temperature for 30 minutes. After that, subsequent operations can proceed.
Quality
The color of the surface of the repair area should be consistent with that of the surrounding area, without obvious edges and bulge. Scratches and damages should be covered properly. There should not be dropped paint.
30
10 Appendix e
Covering the Equipment with Grease
1. Install the cable frame in the APM30H.
2. Before installing the rubber blocks for leading out the cables, cover the surface and gaps of the blocks with grease evenly, and then insert the three blocks into the cable frame.
Grease
3. Insert the rubber caps into the cable module after covering the caps with grease, and then cover the jackets of the cables with grease before leading the cable through the cable module.
31
10 Appendix f
Checking the DIP Switches
When the two PMUs are in the same monitoring line (MON0 or MON1), the monitoring address of the PMUs must be set to 3 and 4.
11 Chang History
This describes the changes in the APM30H &TMC11H&IBBS200D/T Installation Guide.
05 (2010-02-25) This is the fourth commercial release. Compared V200R003_05 with V200R003_04, Add the information about SLPU. 04 (2010-01-15) This is the third commercial release. Compared V200R003_04 with V200R003_03, Add the information about the SOU and the heater. 03 (2009-12-30) This is the second commercial release. Compared V200R003_03 with V200R003_02, Update the information about how to install the cabinets. 02 (2009-09-30) This is the first commercial release. 01 (2009-08-10) This is the draft release.