Escolar Documentos
Profissional Documentos
Cultura Documentos
Ajay Gupta
Ted Williams Tunnel: Connects I-90, I-93, and Logan International Airport. Leonard P. Zakim Bunker Hill Bridge: I-93 Bridge over the Charles River.
Rose Kennedy Greenway in the space vacated by the previous I-93 elevated roadway.
B A E F F T O E R E R
Before: 2003
After: 2005
1959
Early 1990
Funding Sources
Federal
Interstate Highway Program
Intermodal Surface Transportation Efficiency Act (ISTEA) National Economic Crossroads Transportation Efficiency Act (NEXTEA)
Big Dig
Mass. Highway Dept. formerly (Mass. Dept. of Public Works) Mass. Transportation Authority Mass. Turnpike Authority Mass. Port Authority State Bonds (Issuing authority unknown)
State
In 2003 Dollars Original Cost Estimate: 1982 Dollars Project Features: New Charles River Crossing Estimated cost $2.5 Billion Actual Cost $8.08 Billion Actual Cost $14.6 Billion Completion 1998 Completed Date: - 2007 Joint Venture Contract
Other
14,000
10,841
7,658 5,810
7,886
7,972
8,000
5,193 3,409
3,708
5,187
5,597
4,000
2,564 2,564
3,175 3,175
2,000
0 1985 EIS 1987 ICE 1989 ICE 1991 ICE 1991 APF 1992 APF 1992 APF w/ NCRC 1994 CSU6 w/ Inflation 1994 CSU6 1997 Rebaseline 2000 CSU7 2001 CSU8 2002 CSU8 2002 CSU9
2003 Dollars
1982 Dollars
Source: Completing the Big Dig: Managing the Final Stages of Bostons Central Artery/Tunnel Project (2003).
2004
2004 2004 2004
1998
1998 1998 1998 2000 2002 2004 2006
Source: Completing the Big Dig: Managing the Final Stages of Bostons Central Artery/Tunnel Project (2003).
Mitigation
Scope Growth
15%
55%
8% 7% 5% 5% 2% 3%
Source: Completing the Big Dig: Managing the Final Stages of Bostons Central Artery/Tunnel Project (2003).
Mitigations
Opportunity to turn complaint into benefits
Rats Fish Fire Boats Memorials Parks
Final number.
$22 billion and wont be paid until 2038.
Including interest on debt. Interim borrowing.
Principal repayment.
Possible future growth of the bottom line for construction and support contracts.
Commonwealths taxpayers and toll payers will foot a bill for the remaining $9 billion over the life of the bonds. This sum is equivalent to $1,500 for each of the Commonwealths six million citizens.
Conclusion
The original estimate was developed in 1982 dollars, without allowance for inflation or mitigation. Mitigation costs are expected to be very high. Requirements for significant mitigation were identified in the original 1985 cost estimates, but the costs were not identified. Other factors that increase costs and delay schedules should and could have been anticipated and addressed through additional planning and design, site analysis, and cost and schedule contingencies. Other Projects could benefit from the lesson learnt from Big Dig.
THANK YOU !