Infrastructure growth remains the overriding priority for India Power Sector has a pivotal role to play Present Power Scenario
Installed Capacity Peak Power Demand Peak availability : : : 159,400 MW 118,000 MW 103,000 MW
Generation Mix
Thermal 102450 MW(64%) Hydro Nuclear RES 36860 MW
(23%)
TOTAL 159400 MW
159400 MW
Transmission network spread geographically over 3.3 million sq kms 765kV/400kV lines: 1,00,916 ckms 220kV lines: 1,28,000 ckms HVDC Bipole (500kV) : 7,500 ckms National Grid Inter-regional capacity: 20,800MW
1
EASTER N REGION
NORTHEASTER N REGION
WESTER NREGIO N
SOUTHE RN REGION
NER
SALAKATI BONGAIGAON
BIHARSHARIFF MALDA
SASARAM
ER
WR
KOLHAPUR
SR
XI Plan
36874 28600
57000
XII Plan
26783 14400 15043
State Sector
26783(34%) 14400(15%)
NR
RAPP Jaipur
Delhi
NEPAL
Partabpur Lucknow Patna Vindhyachal
SIKKIM
BHUTAN
Guwahati
CHICKEN NECK
NER
BANGLA DESH
MY AN MM AR
ER
Kolkata
WR
Tarapur Mumbai
Hyderabad
Vizag Simhadri
LEGEND
Generation Coal Load-Centre
SR
Kaiga Kozhikode Mangalore Bangalore Krishnapatnam Ennore South Madras Chennai Cuddalore Kayamkulam Thiruvananthapuram
Hydro
Lignite Coastal
Kudankulam
COLOMBO
Nuclear
SRI LANKA
Technology
: 500kV 800kV
Increase the capacity of trans. corridor through HSIL/re-conductoring with HTLS /Upgradation Utilisation of transmission lines upto full thermal capacity Series capacitors, SVC, FACTS Optimization of Tower design tall tower, multi-ckt. tower GIS substation
Voltage (kV)
765kV
800kV HVDC
1977
1990
2000
2012 Year
2016
Complexities with high voltage AC system Reactive Power Management Availability of switchgear Corona Loss Sustainability of grid during contingencies
Development Plan
URI SALALI&II
JAMMU SARNA DASUYA AMRITSAR JALANDHAR LUDHIANA MALERKOTLA MOGA KAITHAL PANIPAT FATEHBAD HISSAR
K'WANGTOO
TEHRI
KURUKSHETRA
PANCHKULA
SONIPAT
BAWANA
DELHI BHIWANI JATTI KALAN BAHDURGARH MAHRANIBAGH RATANGARH MANESAR DADRI BALLABGARH GURGAON SIKAR GNOIDA
POOLING STN DHAULIGANGA SAHARANPUR DEHRADUN BAGPAT ROORKEE KASHIPUR MEERUT MANDAULA
(UP)
B'SAHAR (PG)
BAREILLY
ZIRO FROM SIKKIM BHUTAN MELLI KAMENG TEESTA-V TALA PUNATSANGCHU-I RANGANADI
RANGIT GANGTOK RAMMAM MELLI
LOWER SUBANSIRI
NEEMRANA
JODHPUR
JAIPUR AGRA
AURAIYA
CHUKHA BALIPARA
TEZPUR
ITANAGAR GOHPUR
KATHALGUR DEOMALI
BIRPARA BONGAIGAON
SAMAGURI
GWALIOR
ANTA RAPP-C&D RAPP-B
ORAI
KOTA
CHITTORGARH
BINA
UDAIPUR
SHUJALPUR
PIRANA
LIMBDI
RAJKOT AMRELI
BHOPAL
ITARSI SATPURA
RAJGARH
INDORE
KHANDWA
JETPUR
KAWAS
LOKTAK JIRIBAM KOLASIB NKSTPP AGARTALA AIZWAL BOKARO DURGAPUR RIHAND POOL AGARTALA GPP ZEMABAWK VINDHYACHAL MEJIA B'SPUR JEERAT PALLATANA JABALPUR KORBA(W) KORBA GBPP SUBHASGRAM JAMSHEDPUR WR POOL STPS KOLAGHAT BUDHIPADAR SEONI SIPAT J
DAMOH
KOPILI KHANDONG
JABALPUR POOL
JHARKHAND
TILAIYYA
KODERMA MAITHON
CHAMPA
BHILAI
RANCHI DHARAMJAYGARH
KORADI
RAIPUR
BHATAPARA
AURANGABAD PADGHE PARLI(N) RAMAGUNDAM PUNE PARLI GAJWEL WARANGAL LONIKHAND SOLAPUR(PG) KARAD
NAVI MUMBAI PUNE KALWA
SOLAPUR
ANGUL
EAST COAST
GAZUWAKA VEMAGIRI
KHAMMAM
KOLHAPUR
HYDERABAD N'SAGAR
RAICHUR
MUNIRABAD MAPUSA NARENDRA
VIJAYAWADA
MAHBOOB NAGAR
KURNOOL GOOTY
CUDDAPAH KRISHNAPATANAM UMPP NELLORE HIRIYUR
KRISHNAPATANAM IPP
LEGEND
Transmission Corridor for Orissa IPP's (Corridor - I) Transmission Corridor for Jharkhand IPP's (Corridor - II) Transmission Corridor for Sikkim IPP's (Corridor - III) Transmission Corridor for Chhattisgarh & MP IPP's (Corridor - IV Transmission Corridor for Chhattisgarh IPP's (Corridor - V) Transmission Corridor for Krishnapatnam IPP's (Corridor - VI) Transmission Corridor for Tuticorin IPP's (Corridor - VII) Transmission Corridor for Srikakulam IPP's (Corridor - VIII) Transmission Corridor for Southern Region IPP's (Corridor - IX)
BANGALORE
KOLAR ALAMANTHI TIRUVALAM NORTH CHENNAI JV HASSAN BANGALORE MADRAS HOSUR MALEKOTTAYUR MYSORE CHEYYUR UMPP PONDICHERRY BAHOOR CUDDALORE KOZIKODE ARASUR NEYVELI PUGALUR NORTH TRICHUR TRICHY UDUMALPET KARAIKUDI MUVATTAPUZHA MADURAI PALLOM
BANG_NEW
SALEM
75000
80000 60000 40000 20000 0 Present By 2011-12 By 2016-17
20800
32000
Road Road Map Map for Indian for Transmission Power System
400kV Transmission System Present Backbone 765kV Transmission system 2700 ckm under operation, about 7000 ckm under different stages of execution 765kV transmission lines are mostly double circuit HVDC system - 800kV 6000MW NER- Agra under execution 1200kV AC Transmission System development : expected operation by 2016-17 under
Plan Target
Transmission line 400kV & above (Ckm) No.of EHV substations(400kV & above) MVA capacity Investment (USD billion)
(*) Achieved in 2009-10
35500 45
17100 18
56000 12
25920 6.4
Transmission line 400kV/765kV & above (Ckm) No.of EHV substations (400kV & above) MVA capacity
80,000 90,000
Estimated
New Substations 90 - 100 Nos. 765/400kV 400/220/132kV 1200/765/400kV : 35 40 Nos. : 55 - 60 Nos. : 1 2 Nos.
Transformation Capacity (MVA)- 1,50,000 1,70,000 MVA 765/400kV 400/220/132kV : 80,000 90,000 MVA : 70,000 80,000 MVA
Asynchronous Interconnection between the two countries agreed in a meeting between Indian Delegation and BPDB & PGCB officials, Bangladesh on November 24, 2009 at Dhaka. Scope of Interconnection :
Establishment of 400kV Sw. Stn. at Baharampur(India) by LILO of Farakka-Jeerat 400kV S/c line Baharampur(India) Ishurdi/Bheramara(Bangladesh) 400kV D/c line. Installation of HVDC back-to-back station (400/230 kV) at Ishurdi/ Bheramara(Bangladesh).
TALA
LHAO
KHUPI
KAMENG
CHUKHA
NECHIPHU
RAMMAM
LEBONG NBU BIRPARA(WB) SILIGURI BIRPARA SALAKATI MOINAGURI TEESTA LD ALIPURDUAR GOSAIGAON AZARA AMINGAON DHALIGAON SAMAGURI PANCHAGARH BORNAGAR RANGIA BONGAIGAON ROWTA TEJPUR MARIANI SINGIGAON BALIPARA
Purpose :
Exchange of Power between India and Bangladesh
PURNEA DALKHOLA
DALKHOLA (WBSEB) THAKURGAON (2x41+1x20) MVA LALMONIRHAT 40 MVA SAIDPUR 82 MVA RANGPUR 82 MVA
AGIA
ASSAM
LONGPI UMTRU
PURNEA(BSEB) KATIHAR
DALKHOLA(WBSEB)
PURBASADIPUR 33.4 MVA RAIGANJ
BOROPUKURIA
BYRNIHAT NEHU
TURA BALURGHAT
NANGAL BIBRA
MEGHALAYA
SHILLONG
Interconnection :
Baharampur(India)Bheramara(Bangladesh) 400kV D/c line
KAHALGAON MALDA
GANGARAMPUR
KHLIEHRIAT HAFLONG
BOGRA
KHEJURIA NIAMATPUR 82 MVA NAOGAON 82 MVA BOGRA SOUTH
FARRAKA
CH. NAWABGANJ 40 MVA
MYMENSINGH 82 MVA
DHULIAN
RAGHUNATHGANJ SAGARDIGHI
RAJSHAHI 53 MVA
SRIPUR(MODHUPUR) NATORE 40MVA SIRAJGANJ 40 MVA PABNA 82 MVA SHAHJAD PUR 40 MVA BAGHABARI TANGAIL 82 MVA KABIRPUR 82 MVA JOYDEVPUR 68 MVA
RAMPURHAT
ISHURDI
B. BARIA
ASHUGANJ
50 MVA B BARIA 100 MVA
BAKRESHWAR
DEBAGRAM KATWA BOLPUR
BEHRAMPUR
KUMARGHAT KAMALPUR EAST KANCHANBARI KHOWAI AMBASSA AGARTALA GPP SURYAMANINAGAR KOLASIB JIRIBAM
TONGI
MIRPUR BASUNDHARA KALYANPUR ULLON
GHORASAL
RAMPURA SIDDHIRGANJ HARIPUR
AMINBAZAR
AIZWAL
DURGAPUR
BIDHAN NAGAR MANKAR KRNAGAR
AGARTALA
COMILLA NORTH 40 MVA
HASNABAD
PALLATANA
MEGHNAGHAT COMILLA SOUTH 82 MVA
V 400k
2kV at 13
MIZORAM
AIZWAL (ZEMABAWK)
DPL ARAMBAG
BURDWAN
SATGACHIA
RANAGHAT
TRIPURA
W.PHAILENG
BTPS
KHANYAN BELMURI DHRMPR KALYANI BONGAON JESSORE 80 MVA NOAPARA 40 MVA
GOPALGANJ
CHANDPUR 40 MVA
KHAGRACHARI
SERCHIP
Type of connection :
Asynchronous(HVDC)
RISHRA
JEERAT
KHULNA CENTRAL 192 MVA BARASAT ASHOKNAGAR KHULNA SOUTH
MARPARA
ARAMBAG
DOMJUR HM
TITAGARH
GOALPARA
33.2 MVA
RANGAMATI
LUNGLEI
BARISAL
82 MVA KAWKHALI BAGERHAT 26.6 MVA BHANDARIA 13.3 MVA PATUAKHALI 40 MVA
RAUJAN BHOLA
63 MVA HATHAZARI LUNGSEN
BASIRHAT
KAPTAI
CHANDROGHONA 26.6 MVA MADANHAT 82 MVA
SUBHASGRAM
BURHANUDDIN
KOLAGHAT BARIPADA
TAMLUK HALDIA
SIKALBAHA
41 MVA DOHAZARI 80 MVA
SHAHMIRPUR
Transfer Capacity :
500MW (upgradable to 1000MW)
FALTA
Bay of Bengal
LEGEND
EXISTING FUTURE
230/220kV 132kV
COX'S BAZAR 20 MVA
BANDARBAN
BANGLADESH
MADHOPUR RAJSHAHI NATORE SIRAJGANJ BAHARAMPUR ISHURDI PABNA SHAHJAD PUR
DURGAPUR
GOKARNA
BAGHABARI GHORASAL
INDIA
KATWA BAKRESHWAR
BHERAMARA
BOTTAIL
FARIDPUR LEGEND THE PROJECT 400 kV 230 kV 132 kV Existing Under Constr. / Future
KHULNA (SOUTH)
132kV : Underground Cable 132kV Line 132kV Line (not in operation) 220/132 kV Sub Station 132kV GS Hydro Power Station Thermal Power Station
KILINOCHCHI
VAVUNIA
TRINCOMALEE
NEW ANURADHAPURA
PUTTALAM
Demand Growth : 8 % Hydro potential : 2000 MW, out of which 1000 MW already harnessed
HABARANA
PANNIPITIYA
BOWATENNA
MADAMPE RATMALANA
BOLAWATTA VEYANGODA KOTUGODA THULHIRIYA VICTORIA BIYAGAMA KOTMALE RANTEMBE KIRIBATHKUMBURA RANDENIGALA INGINIYAGALA
KELANITISSA
KOLONNAWA SAPUGASKANDA POLPITIYA SITHAWAKA RATMALANA PANADURA ORUWALA PANNIPITIYA KOSGAMA
DENIYAYA
EMBILIPITIYA
GALLE
HAMBANTOTA
MATARA
TO PONDA
KALINADI
ANANTAPUR
ALAMANTHI N MADRAS
BANGALORE
H HALLI TK HALLI
TN3
KASARAKODE
TN4
KANNUR
ENNORE SRIPERUMBUDUR KADAPERI MALEKOTTAIYUR ARANI TN2 SP KOIL KALPAKKAM ACHARAPAKKAM TN7 TN5 VILLUPURAM PONDICHERRY VILLIANNOR BAHOUR CUDDALORE
KOZHIKODE KE1 NORTH TRICHUR AP1. MYDUKUR L PERIYAR AP2. NANDYAL KALAMASSERI AP3. YERRAGUNTLA BRAHMAPURAM AP4. KALIKIRI
KA1. HIRIYUR KA2. GOWRIBIDANOOR KA3. DB PUR KE1. PALAKKAD KE2. KANIYAMPETAH TN1. THIRUVALEM TN2. VINNAMANGALAM TN3. HOSUR TN4. KRISHNAGIRI TN5. TV MALAI TN6. VILLUPURAM TN7. SINGARAPET TN8. PERAMBULUR TN9. SAMAYAPURAM TN10. KADAMPARAI TN11. SEMPATTY TN12. GC PALAYAM
IDUKKI PALLOM
KILINOCHCHI
VAVUNIA TRINCOMALEE
NAGARCOIL
KUDANKULAM
AMPARA
IN GIN IYAGALA
KOTUGODA
RANDENIGALA RANTEMBE
BAD ULLA WIMALASUR EN DRA
K OS GA MA
PANADURA
BALANGODA SAMANALAWEWA
MATUGAMA
DENIYAYA EMBILIPITIYA
185 Kms
Rameshwaram
50 Kms
Talaimannar
TRANSFORMER
OVERHEAD
TRANSFORMER
OVERHEAD
CABLE
OVERHEAD
VALVES
FILTER
FILTER
OVERHEAD CABLE
OVERHEAD
Major portion of power from the future generation projects in Bhutan is envisaged to be imported into Indian grid. The 1st of the future projects to be commissioned in Bhutan is Punatsangchu-I (1200 MW) in 2014-15.