Você está na página 1de 2

ANNEX 3 Charcoal Briquetting Project Total Area: 14 x 30 meters = 420 Sq.

meters

Materials Required for Renovation: 1) 2) 3) 4) 5) 84 pcs Rib Type Long Span Roofing @ 8 meters long 26 pcs C-Purlins @ 33 meters long Techscrew Security Grills for Door and Windows (Equipment Room) Labor

Rib-Type Long Span Roof Gauge 26 @ 8 meters 84 pieces x Php 2,800 C-Purlins C-Purlins@ 6 meters (standard cut) = Php 500.00 per piece = = Php 2,800 per piece Php 235,200

In 1 span of 33 meters, there is 5.5 cut of 6 meters each. (33 meters/6 meters = 5.5 meters) Therefore: 5.5 x 26 pieces 143 x Php 500 per piece Techscrew 2,000 pcs x Php 2.00 = Php 4,000 = = 143 pieces @ 6 meters standard cut Php 71,500

Labor: 4 days x Php 250 per day = Php 1,000 x 5 laborers Grills sub-contracted will be around Php 7,000 = Php 5,000

TOTAL:

PHP 322,700

Note: Materials costing are based on NCR Rate. Labor Rate is based on provincial rate. C-Purlins if to be welded to make 33 meters span will entail additional cost.

Você também pode gostar