Purpose Use this procedure to adjust baseline of new product manually. Trigger Perform this transaction when you need to adjust baseline of new product manually. Menu Path Use the following SAP Easy Access menu path(s) to begin this transaction: Advanced Planning and Optimization > Demand Planning > Planning > /SAPAPO/SDP94
1/16
Work Instruction
Screen Flow
2/16
Work Instruction
Procedure 1. In SAP, start the transaction using the menu path or transaction code. SAP Easy Access mySAP Supply Chain Management
2. Double-click the Advanced Planning and Optimization node . 3. Double-click the Demand Planning node 4. Double-click the Planning node . .
3/16
Work Instruction
5. Double-click the /SAPAPO/SDP94 - Interactive Demand Planning node . You can also enter "/n/SAPAPO/SDP94" in the Commandfield " " and click Enter " transaction. Planning Book: [Live] GENERATE BASELINE FORECAST / GENERATE BASELINE F " to go directly to this
4/16
Work Instruction
5/16
Work Instruction
Note: You can choose the Product which you like to adjust the baseline. 9. Click the Change button . 10 As required, complete/review the following fields: . R Week R/O/C 50 of year 2008 Baseline Forecast Adj % R Week 49 of year 2008 Baseline Forecast Adj % R Week 48 of year 2008 Baseline Forecast Adj % Week 47 of year 2009 BAseline Forecast Adj %. Field Description
6/16
Work Instruction
Example: -50 W 50.2008 / Baseline Forecast Adj % Example: -50 W 49.2008 / Baseline Forecast Adj % Example: -50 W 48.2008 / Baseline Forecast Adj % Example: -50 R W 47.2008 / Baseline Forecast Adj %
7/16
Work Instruction
2008 Baseline Forecast Adj % Field Example: -30 R W 51.2008 / Baseline Forecast Adj %
8/16
Work Instruction
R Week 2 of year 2009 Baseline Forecast Adj %. R Refers to the Baseline Forecast Adj % of Week 01 of year 2009. Week 52 of year 2008 Baseline Forecast Adj % Field Example: -30 W 02.2009 / Baseline Forecast Adj % Example: -30 W 01.2009 / Baseline Forecast
R/O/C
Description
9/16
Work Instruction
14 As required, complete/review the following fields: . R Week R/O/C 06 of year 2009 Baseline Forecast Adj %. R Week 05 of year 2009 BAseline Forecast Adj % R Week 04 of year 2009 BAseline Forecast Adj %. Week 02 of year 2009 Description
10/16
Work Instruction
Baseline Forecast Adj %. Field Example: -10 W 06.2009 / Baseline Forecast Adj % Example: -10 W 05.2009 / Baseline Forecast Adj % Example: -10 W 04.2009 / Baseline Forecast Adj % Example: -10 R W 03.2009 / Baseline Forecast Adj %
11/16
Work Instruction
. . .
17 Click the Calculate Agreed Baseline Forecast button . 18 Click the Save button . .
12/16
Work Instruction
13/16
Work Instruction
14/16
Work Instruction
Scenario Instructions In this simulation you are required to: Create a baseline of a new product manually. Required Data This section provides the field data required to complete this exercise. Refer to this data sheet as necessary while performing the exercise. -10 -10 -10 -10 -30 -30 -30 -30 -50 -50 -50 -50 SSH180C TH_TEST_SSH180C_GT_OMT_MAK_KEY CUS U2AADPDV01 Field W 06.2009 / Baseline Forecast Adj % W 05.2009 / Baseline Forecast Adj % W 04.2009 / Baseline Forecast Adj % W 03.2009 / Baseline Forecast Adj % W 02.2009 / Baseline Forecast Adj % W 01.2009 / Baseline Forecast Adj % W 52.2008 / Baseline Forecast Adj % W 51.2008 / Baseline Forecast Adj % W 50.2008 / Baseline Forecast Adj % W 49.2008 / Baseline Forecast Adj % W 48.2008 / Baseline Forecast Adj % W 47.2008 / Baseline Forecast Adj % P9- Base Pack Selection Profile Data View Value