WORK

PERMIT
A.K.SINGH, CMFS
INDIANOIL CORPORATION LTD.
MATHURA REFINERY,
ROAD MAP
:The session will include the following
■ Presentation on MR Work Permit
system followed by discussion
■ Role of Issuing & Executing Authority
■ Exercise how to fill the permit
■ Questionnaire/QUIZ
WHY WORK PERMIT?
■ Petroleum Refinery handles
Hydrocarbons and toxic materials -
poses special risks.
■ Maint. Personnel are not adequately
familiar with process conditions.
■ Operation will determine that it is
safe to perform the designated job.
■ Basic purpose of permit system is to
prevent injuries to personnel.
WHY WORK PERMIT
Following Oil Industry Safety Directorates Standards are in Indian
Petroleum Rules :2002
OISD -105))Work permit system
OISD-116Fire Protection facilities for Petroleum Refineries and Oil/Gas Processing Plants
OISD- 117)Fire Protection Facilities for Petroleum Depots and Terminals and pipeline installations
OISD-118))Layouts for Oil and Gas Installations
OISD-141 ))Design and Construction requirements for cross country hydrocarbon pipelines
OISD –156) )Fire Protection Facilities for Ports Handling Hydrocarbons

OISD Standard“ means technical standards formulated by OISD“


and approved by Safety Council constituted under the Ministry of
Petroleum and Natural Gas to ensure safety in Oil and Gas Industry
.))as amended from time to time
■ Protect property from damage
■ Avoid fire
■ Ensure that all work is carried out in
safest possible manner.
■ permit specifies the conditions and
procedure for safe execution.
WORK PERMIT REQUIRMENT
Permit is required for the following
jobs :
■ Major & Minor Maint. work.
■ Inspection.
■ Construction.
■ Alteration.
■ Process Equip. cleaning
■ Entry into confined space.
■ Excavation
■ Vehicle entry into hazardous areas etc.
WORKS -
PERMIT NOT REQUIRED
■ Works carried out by Oprs. Dept. as a part
of routine operation.
BLANKET PERMIT
ONE MONTH
■ WORK SHOP
■ INSTRUMENT LAB/WORKSHOP
■ LABORATORY
■ INSPECTION
TYPES OF PERMITS
6 types of work permit with specific colors.
HOT WORK ,VESSEL ENTRY/VESSEL BOX UP/EXCAVATION/ VEHICLE ENTRY
PERMIT (PINK& WHITE- three copies) For use of or generates local source of
ignition, vehicle & engine operated equip. entry to hazardous areas. (FS/F-1 Rev 3)
COLD WORK PERMIT (YELLOW & WHITE) FS/F-23, Rev-1
(For all general Maint. works (no ignition source)

EXCAVATION CLEARANCE(PINK ,WHITE & YELLOW) FS/F-1/C

ROAD CUTTING & BLOCKAGE PERMIT

PERMIT FOR WORKING AT HEIGHT ( PINK & WHITE) (IOCL/MATHURA


REFINERY/WAH Permit)

RADIATION WORK PERMIT( Light Blue & White) FS.F-24, Rev-1


FEATURES OF WORK
PERMIT FORM
Work Permit form generally consists of
the following features:
THE ORIGINIAL AND COPIES
■ Original is unmarked and belongs to
“Executing Authority”-pink copy
■ Printed serial number
■ FORM NO. …………………..
■ Special instructions printed on the
permit
PROCEDURE FOR WORK PERMIT
(SYSTEM(WPS
■ WPS OPERATE ON OWNER IN CHERGE CONCEPT(UNITS-
CPNM,LAB-CQCM,TPS-CPUM, STORES-SMTM)
■ PERMIT IN PRINTED FORM
■ SEPARATE PERMIT FOR COLD & HOT WORK
■ PERMIT COLOUR CODED, SERIAL NUMBER
■ DEPTL. OR CONTRACTOR JOB:PERMIT RECEIVING BY
MN/PJ/CONSTRN. SUPERVISOR OF IOCL.
■ PERMIT INITIATION BY MN/PJ SUEPRVISOR.
■ ALL PERMITS TO BE WRITTEN IN CAPITAL LETTERS
■ WORK ORDER/LOA NO. TO BE MENTIONED ON PERMIT
■ LOCATION DRAWING/SKETCH TO BE GIVEN ALONG WITH
PERMIT.
■ RISK EVALUATION CHECKLIST TO BE TICKED BY ISSUER
(GSI(HOT WORK), SUPERVISOR. NOT BY EXECUTOR.
PROCEDURE FOR WORK PERMIT
(SYSTEM(WPS
HOT WORKPERMIT
■ EXECUTOR TO INITIATE THE FIRE PERMIT-
DUATION,LOCATION, EQUP.TAG NO., NATURE OF WORK,
NAME & SIGNATURE. ECECUTOR NOT LESS THAN “A”
GRADE OFFICER
■ GSI( B GRADE AND ABOVE)-CHECK THE PERMIT,
EVALUATE THE RISK,TICK A. General Points ( 13 items)
B.For Hot Work/ENTRY INTO CONFINE SPACE91o ITESM)
,C. FOR VEHICLE ENTRY (1 ITEM) ITEMS AS APPLICABLE,
SPECIAL INSTRUCTION IN SPACE PROVIDED IN PERMIT
TO PREPARE THE AREA /EQUIPMENT TO CARRY OUT
THE HOT WORK.
■ SHIFT IN CHRAGE IN E/N SHIFT TO FOLLOW UP & DIRECT
PREPARATIONS. N/SHIFT TO INSPECT THE AREA
/EQUIPMENT JUST BEFORE THE SHIFT CHANGE AND
LEAVE MESSAGE FOR FPS(C GRADE AND ABOVE)IN
PROCEDURE FOR WORK PERMIT
(SYSTEM(WPS
HOT WORKPERMIT
■ EXECUTOR TO INITIATE THE FIRE PERMIT-
DUATION,LOCATION, EQUP.TAG NO., NATURE OF WORK,
NAME & SIGNATURE. ECECUTOR NOT LESS THAN “A”
GRADE OFFICER
■ GSI ( B GRADE AND ABOVE)-CHECK THE PERMIT,
EVALUATE THE RISK.TICK as folows:
- A. General Points ( 13 items)
- B. For Hot Work/ entry into confined space(10 items)
-C. for vehicle entry (1 item)
-D. for excavation works (4 items)
PROCEDURE FOR WORK PERMIT
(SYSTEM(WPS
HOT WORKPERMIT
■ FPS AFTER GOING THROUGH LOG BOOK ,ACCOMPANIED
BY GSI & EXECUTOR INSPECT THE AREA, SATISFY
HIMSELF WITH PREPARTIONS AND THEN SIGN THE
PERMIT.
■ PERMIT TO BE RECEIVED BY EXECUTOR BY SIGNING.
■ REGISTRATION AT FIRE STATION.
■ PINK COPY FOR EXECUTOR/ WHITE FOR ISSUER
■ ISSUER REPRESENTATIVE-SHIFT PNE/SPNE/SPUE TO
CARRY OUT GAS TEST, INSPECT THE AREA, ENSURE
COMPLIANCE OF ALL SAFETY PRECAUTION GIVEN IN
PERMIT , THEN ISSUE CLEARENCE CERTIFICATE TO
START THE JOB.
VALIDITY OF HOT WORK PERMIT
HOT WORK PERMIT
■ NORMAL 8 HOURS( 8AM-5 PM). BEYOND 5 PM
RENEWABLE AFTER AUTHORISATION FROM HOD.RENEW
AT FIRE STATION ON EXTENSION.
■ NORMAL HOT JOBS IN NIGHT SHIFT NOT ALLOWED
UNLESS JOB IS URGENT, PERMISSION FROM HOD REQD.
■ FOR EACH LOCATION/EQUIPMENT SEPARATE HOT
WORK PERMIT REQUIRED IN PROCESS UNITS
■ IN OFFSITE:DISTANCE EXCEEDING 15 METERS,
SEPARATE FIRE PERMIT.
WHO CAN SIGN A WORK
PERMIT
■ Personnel who are authorized to sign on
the Work Permit shall have thorough
knowledge of the work to be performed
and the conditions under which the work
will be performed.
■ DGM(PN) AUTHORISES GSI & FPS AND LIST IS
CIRCULATED.
ISSUING AUTHORITY OF
WORK PERMIT
■ Issuing authority is responsible for
preparation and handing over of the
equipment in safe condition to
perform the work.
■ Authority to issue all types of work
permits is generally granted to shift
supervisor(PNE/SPNE, UTE,ELE)
level of OFFICERS and above.
EXECUTING AUTHORITY
OF WORK PERMIT
■ Request for a work permit by executing
authority. He shall indicate types of
tools and equipment necessary for
performing the work.
■ He shall also ensure his tools,
equipment and accessories are in good
condition and all his workers are
provided with proper PPE.
PREPARATION OF THE
EQUIPMENT
■ Equipment electrically isolated
■ Inspection tested(for cold & hot job)
■ Isolated from steam,air & gas
■ Depressurized
■ Drained
■ Positively isolated/blinded
■ Steamed & water flushed
PREPARATION OF EQUIP.
.CONTD

■ Ventilated & gas freed


■ Continuous inert gas flow / continuous
adequate ventilation arranged.
■ Vehicle/equipment in good condition
with spark arrested
■ Radiation source removed(Confined
space entry)
RESIDUAL HAZARDS
■ Lack of oxygen
■ H2S and/or any other toxic gases
■ Combustible gases
■ Corrosive chemicals
■ Steam / Condensate
■ Pyrophoric iron
■ High humidity
PROTECTION MEASURES
■ Protective clothing
■ Hearing protection
■ Safety Harness
■ Eye protection
■ Face protection
■ Respiratory protection
■ Keep fire equipment stand-by
PROTECTIVE MEASURES
.CONTD
■ Barricade the area
■ Remove flammable and combustible
■ Cover with fire retardant tarpaulin
■ Crane with basket stand-by
■ Attendance with Airline set
■ keep man ways open
■ Allow minimum possible no. of persons
inside confined space
PROTECTIVE MEASURES
.CONTD
■ To ensure positive isolation & maintain
it all through
■ Ensure adequate ventilation all through
■ Display copy of entry permit near entry
manhole
GAS TEST FOR WORK
PERMIT
Why gas test is required ?
■ Most of the gases are unwanted
Hazards involved -
■ Flammability(Fire & Explosion)
■ Toxicity(health hazard)
■ Oxygen Deficiency
GAS TESTCONTD
Common flammable gases/liquids in
refinery are -
■ All petroleum products,Crude and
intermediates
■ Hydrogen
■ LPG
■ Common toxic gases in refinery -
■ H2S, CO,NH3,CL2, etc.
.GAS TEST CONTD
COMMON TERMINOLOGIES :
For flammable substances:
■ Flash Point :

Minimum temp. at which a liquid gives off


sufficient vapor to form an ignitable mix. It
.will give a flash, flame will not continue
:.Auto Ignition Temp
The lowest temp. to which a substance
.will ignite without a spark or flame
GAS TEST.CONTD
■ Explosive limit :
The concentration range of vapor in air
when propagation of flame(ignition)
occurs in presence of an ignition
source.
■ LEL (Lower Explosive Limit) :

The minimum concentration of vapor to


air required to propagate(ignite) flame.
GAS TEST.CONTD

UEL(Upper Explosive Limit) :


The maximum vapor to air conc.above


which propagation of a flame will not
occur(will not ignite).
GAS TEST.CONTD
(Material LEL UEL F Pt.(C) AIT(C
Hydrogen 4 75 Gas
585
Methane 5 15 Gas
538
Propane 2 9.5 - 104
466
Naphtha 1.1 5.9 - 18
288
ATK/ATF 0.7 5.0 35-50
210
GAS TEST.CONTD
: Toxic substances
TLV (Threshold Limit Value /
: (PEL(Permissible Exposure Limit
The maximum permissible conc. of a toxic
substance to which exposure of a person
will have no adverse effect on health for
.working 8 hrs per day
STEL: ((Short Term Exposure Limit
Maximum conc. to which worker can be
exposed for a period of 15 mins. without
.any adverse effect to health
. GAS TESTCONTD
IDLH((Immediate Danger to Life & Health
■ A maximum conc. from which one can
escape within 30 mins. without
irreversible health effect.

■ HYDROGEN SULPHIDE (H2S)


Highly toxic, combustible, colorless.
Smells like rotten egg.
GAS TEST -H2S
EFFECTS ON HUMAN BODY
PHYSICAL EFFECT (CONC.(PPM
Can be smelled as rotten egg 0.13
TLV 10
STEL 15
Smelling sense will dry within 150 - 200
2 mins, burning sensation in
eye & throat
. GAS TEST -H2S CONTD
PHYSICAL EFFECT (CONC(PPM
IDLH(Loss of smelling sense, 300
,heavy breathing, dizziness
headache,and total collapse
(within 1 to 4 Hrs
Dizziness,headache,lungs 450
problem and total collapse within 30 to
60 mins.
.GAS TEST-H2S CONTD
(PHYSICAL EFFECT CONC(PPM
Slow down of heart beats, 700
,heavy breathing with coughing
then death, if not rescued

Fatal emergency over 700

Explosive limits : 4.6 to 46%, it gives blue


.flame when ignited
.GAS TEST-H2S CONTD
: FIRST AID
- IF INHALED
Remove exposed person to fresh air and
.administer oxygen immediately
:PROTECTION
Use fresh air mask in case conc.
exceeds 10 PPM
TOXIC GAS -CO
TOXIC AS WELL AS FLAMMABLE
TLV - 50 PPM
STEL - 400 PPM
IDLH - 1500 PPM
LEL - 12.5%
% UEL - 74
GAS TEST - CO
:HEALTH HAZARDS
CO combines with hemoglobin of blood
.and make it unable to carry oxygen
Symptoms : Headache, dizziness to
.unconscious and ultimately death
: First Aid
Remove to fresh air and apply oxygen at
.the earliest
OTHER TOXIC GASES

TOXIC GAS TLV STEL IDLH

NH3 25 35 -
SO2 2 5 -
CL2 0.5 1 30
GAS TEST CONTD.
For hot work the gas test results shall be :
■ Combustible - Below 1 % LEL

( Preferably NIL)
For confined space entry :
■ Oxygen - 19.5% minimum
■ Combustible - 10 % LEL Max.
■ Toxic gases - below TLV
. GAS TESTCONTD
Confined space With BA protection :
■ Combustible - 20% of LEL maximum
■ H2S - Less than 100 PPM
■ CO - Less than 500 PPM

However, no hot job can be carried out


inside the confined space at this
condition.
WORKS NEED GAS TEST
■ Gas tests are required for all hot
work/vehicle entry and confined space
entry permits & some cold permits also.
■ Issuing authority shall determine the
requirement of gas test & frequency of re-
checking.
■ Trained Gas tester only shall carry out the
test.
RESPONSIBILIES OF GAS
TESTING AUTHORITY
■ To check & confirm that the gas testing
instrument is working in perfect condition
before proceeding for the area/equipment
■ To carry out gas test at all critical
locations/positions
■ To advise on safe method to work inside/at
the location i.e., further gas freeing , use of
PPE etc.
ELECTRICAL ISOLATION
■ Before issuing a Work Permit, it is
essential to ensure that the equipment /
facility to be worked on is electrically safe
and electrical power is isolated to the
extent necessary for the safe conduct of
the authorized work.
■ Issuing, Executing authorities and
Electrical Maintenance shall jointly decide
the extent of isolation required.
■ ‘DO NOT OPERATE’ tag shall be used
when isolation by local switch is decided
as adequate protection.
■ Multi-lock systems to be used when
different crafts are involved.(this is
towards best safety practices)
SPECIAL REQUIREMENT FOR -
WORKING WITH RADIOGRAPHY

■ Risk assessment through checklist


■ Barricade the area and provide adequate
warning signs.
■ Film badges and Dosimeters shall be
worn by personnel handling radiography
equip.
■ job preferably during night time or with least or
no person around.
■ Continuous monitoring of cordoned off area
SPECIAL REQUIREMENTS
FOR HOT WORK
■ The person who authorizes the Hot Work
Permit is responsible for ensuring that the
site and the equipment are properly
prepared to prevent the danger of fire &
explosion involving flammable material.
■ The equipment shall be emptied and
cleaned of flammable materials and
isolated from sources of hydrocarbons by
means of disconnection, blanking or
insertion of blinds.
■ Equipment and surrounding areas shall be
checked to ensure that they are free from
any combustible gas.Carry out gas test.
■ Any heavy oil deposit, dried vegetation or
other flammable / combustible materials
within 8 m of a hot work site shall be
cleared away.
■ No hot work shall be allowed within a
radius of 15 m of any sample point, drain
or relief valve outlet unless precautions
have been taken to prevent the escape of
flammable liquids and vapors.
■ The outlet of all units drain seals within 15
m of the hot work shall be plugged.
■ If welding or grinding is to be done at
height, then precautions shall be taken to
prevent the spread of sparks and molten
metal to the surrounding of the work area
with fire-resisting or flame-retarding
tarpaulin.
■ A hose capable of reaching up to the hot
work point and connected to fire water
main.
■ Fire Station (333/5989) shall be informed
of hot work.
VEHICLE ENTRY
■ A Hot Work / Vehicle Entry Permit is required
for entry of all vehicles in hazardous areas.
Such areas shall be clearly demarcated with
signs indicating “No Entry without Vehicle
Entry Permit” and/or with removable chain.
■ The signatory authorities shall ensure that all
vehicles / equipment exhaust are equipped
with spark arrestors of approved type.
■ Entry shall only be allowed for loading and
unloading of materials and not for passenger
transport.
REQUIREMENTS FOR
CONFINED SPACE ENTRY
■ The process vessel / equipment is to be
positively isolated by blinding.
■ Shall be made safe for entry by
depressurizing, venting, draining,
steaming, washing and ventilating.
Radiation sources ,if any, shall be
removed.
■ The atmosphere within the confined
space shall be checked initially and
periodically(gas test).
EXCAVATION
AUTHORIZATION
■ An excavation authorization is required for
all excavations. Detail drawings of the
underground facilities shall remain
attached with the authorization if available.
■ In addition to an Excavation Authorization
a Cold / Hot work Permit is required to
work.
■ For excavations more than 1.2 meter deep
confined space entry permit is required.
Gas tests shall be done as per entry permit
requirements.
SUSPENSION OF WORK
PERMIT
■ All work shall immediately stop when
a fire or emergency alarm is sounded
or accident of any kind occurs.
Approval from the F&S shall be
obtained after necessary preliminary
investigations, to resume such work.

■ The Work Permit shall be revalidated


to resume the work.
■ Any responsible member of the
PN.dept. or F&S is authorized to
suspend work and withdraw the
Work Permit if, safety regulations are
violated.
■ If work is not started or is stopped
for over two hours, the permit shall
be revalidated by the issuing
authority.
VALIDITY OF PERMIT
■ Work permit shall be initially issued
for a period of 8 hrs. and shall be
renewed for one more shift .
■ On need basis , permit can be given
for max. 7 days period.
■ Clearance to be obtained every shift.
■ Clearance to be given after
physically checking the site.
CLOSING AND FILING OF
USED WORK PERMITS
■ Permit Closure: Duly filled and signed by
both executing & issuing authority at
completion of work
■ Copies of the closed permits shall be
properly filed and kept with the respective
disciplines for at least one month from
the date of issue/closure. Different types
of permits shall be filed separately in
chronological order in box files.
BASIC RESPONSIBILITIES
OF ISSUING AUTHORITY
■ To prepare the equipment and properly
tick the checklist items
■ To identify & indicate any residual
hazard
■ To advise on protective measures &
mention
■ To carry out gas test wherever reqd.
and enter the result with sign,date &
time
RESPONSIBILITIES OF ISSUING
.AUTHORITY CONTD
■ To discuss & explain with/to executing
authority
■ Carry out electrical isolation whenever
reqd.
■ Close the permit when the job is
complete or end of permit duration,
which one is earlier.
■ To preserve the permit for next one
month.
BASIC RESPONSIBILITIES
OF EXECUTING AUTHORITY
■ To clearly understand the conditions of
the equipment and residual hazards
■ To discuss the above with issuing
authority and decide upon the protective
measures.
■ To describe the job and associated
hazards to the workmen
■ To ensure that safe procedure of
execution are being followed
RESPONSIBILITIES OF
EXECUTING AUTHORITY
■ To check all the hand tools / devices
/equipment and ensure that they are
healthy
■ To make the permit available at work
site all the time
■ To close the permit when the job is over
or at the end of permit duration,which
one is earlier.
■ To preserve the closed permit for next
one month
AUDITOR’S CHECK-LIST
An Auditor shall check the following:
■ Whether the exact location of area/unit
& equipment has been mentioned
clearly
■ Detail description of work is properly
written
■ Fire station has been informed and
properly ticked
AUDITOR’S CHECK- LIST
■ Permit issued to which Dept.,
Div.,Section & Craft - all mentioned
■ Equipment preparation - Equipment has
been properly prepared, all checklist
items area properly checked & ticked
■ Residual Hazards - Identified and
ticked/indicated
■ Protective Measures- Requirements
identified & properly marked
AUDITOR’S CHECK-LIST
■ Other details - like provision of
continuous ventilation, additional
precautions
■ GAS TEST:
■ Test for all probable gases carried out
and reading recorded with sign., date &
time etc.
■ Frequency of rechecking identified and
carried out
AUDITOR’S CHECK-LIST
■ Electrical isolation was reqd., carried
out and documented.
■ Both issuing & executing authority
signed mentioning name & signature,
date & time.
AUDITOR’S CHECK-LIST

■ Permit has been closed by both


issuing & executing authority with
date & time
■ Closed permits has been kept
properly filed and being preserved
for next one month
Clearence permit/certificate

■ for hot /cold work


■ issued against permit no…….
■ 14 checklist items to be critically
evaluated and ticked
■ issued for one shift maximum/renewed
shift wise.
■ Closure on job completion/ clearing the
area, signed , date, time, return to
issuer.
.Not meant for billing ■
Road cutting& blockage
permit
■ Request by executor(A grade and above)
by filling all the entries and attaching
sketch/indicating on reverse of permit
form
■ clearance from EL maint.
■ Clearence from Civil
■ Clearence from PN
■ Clearence from IS dept.
■ Clearence from F&S
■ Approved by DGM(T)
■ Permit registered at Fire Station.
Excavation & Dyke cutting

■ Request by executor(A grade and above)


by filling all the entries and attaching
sketch/indicating on permit form
■ clearance from EL maint./ Telecom.
■ Clearence from F&S
■ Clearence from CL
■ Clearence from PN/Area in charge
■ Registered at Fire Station.
■ Approved by GSI
■ On completion , permit closure and
return to Fire Station/ Area in charge.
Vessel Entry

■ Request by executor(A grade and above)


by filling all the entries clearance from
EL maint./ Telecom.
■ Critical evaluation of 10 checklist
items./ticking
■ Approved by GSI
■ Clearence from PN/Area in charge
■ On completion , permit closure and
return to Fire Station/ Area in charge.