PEKERJAAN KAYU
KODE
ANALISA
HARGA
INDEK
SAT
URAIAN
BAHAN
UPAH
( Rp )
( Rp )
A.2
0.0200 M3
Balok ulin
5,000,000.00
0.5100 OH
tukang kayu
70,000.00
100,000.00
35,700.00
0.8750 OH
pekerja
55,000.00
48,125.00
0.0510 OH
kepala tukang
75,000.00
3,825.00
0.0440 OH
mandor
75,000.00
3,300.00
JUMLAH
100,000.00
400,000.00
90,950.00
190,950.00
A.3
0.0800 M3
Balok ulin
5,000,000.00
0.5100 OH
tukang kayu
70,000.00
35,700.00
0.8750 OH
pekerja
55,000.00
48,125.00
0.0510 OH
kepala tukang
75,000.00
3,825.00
0.0440 OH
mandor
75,000.00
400,000.00
200,000.00
0.0400 M3
Balok ulin
5,000,000.00
0.5100 OH
tukang kayu
70,000.00
35,700.00
0.8750 OH
pekerja
55,000.00
48,125.00
0.0510 OH
kepala tukang
75,000.00
3,825.00
0.0440 OH
mandor
75,000.00
490,950.00
3,300.00
200,000.00
90,950.00
290,950.00
5,400,000.00
5,940,000.00
3.0000 kg
paku ulin
19,125.00
57,375.00
tukang kayu
70,000.00
1,050,000.00
4.0000 OH
pekerja
55,000.00
220,000.00
1.5000 OH
kepala tukang
75,000.00
112,500.00
0.2000 OH
mandor
75,000.00
15.0000 OH
A. 5
90,950.00
JUMLAH
A. 4
3,300.00
JUMLAH
15,000.00
JUMLAH
5,997,375.00
5,500,000.00
1,397,500.00
7,394,875.00
balok ky ulin
5,000,000.00
15.0000 OH
tukang kayu
70,000.00
1,050,000.00
5.0000 OH
pekerja
55,000.00
275,000.00
1.5000 OH
kepala tukang
75,000.00
112,500.00
0.2500 OH
mandor
75,000.00
18,750.00
JUMLAH
5,500,000.00
1,456,250.00
6,956,250.00
5,000,000.00
5,500,000.00
10.0000 Kg
1.1000 M3
paku ulin
19,125.00
191,250.00
15.0000 OH
tukang kayu
70,000.00
1,050,000.00
5.0000 OH
pekerja
55,000.00
275,000.00
1.5000 OH
kepala tukang
75,000.00
112,500.00
0.2500 OH
mandor
75,000.00
JUMLAH
B. 2
1,456,250.00
7,147,500.00
5,400,000.00
137,160.00
0.2500 Kg
paku ulin
19,125.00
4,781.25
0.8000 OH
tukang kayu
70,000.00
56,000.00
0.2800 OH
pekerja
55,000.00
15,400.00
0.0800 OH
kepala tukang
75,000.00
6,000.00
0.0140 OH
mandor
75,000.00
JUMLAH
B. 3
18,750.00
5,691,250.00
1,050.00
141,941.25
78,450.00
220,391.25
2,300,000.00
58,420.00
0.2500 Kg
paku biasa
15,583.33
3,895.83
0.8000 OH
tukang kayu
70,000.00
56,000.00
0.2800 OH
pekerja
55,000.00
15,400.00
0.0800 OH
kepala tukang
75,000.00
6,000.00
0.0140 OH
mandor
75,000.00
JUMLAH
1,050.00
62,315.83
78,450.00
140,765.83
B. 5
balok ky ulin
5,000,000.00
5,500,000.00
5.0000 Kg
paku ulin
19,125.00
95,625.00
20.0000 OH
tukang kayu
70,000.00
1,400,000.00
10.0000 OH
pekerja
55,000.00
550,000.00
2.0000 OH
kepala tukang
75,000.00
150,000.00
0.5000 OH
mandor
75,000.00
5,595,625.00
1.1000 M3
balok ky meranti
2,200,000.00
2,420,000.00
5.0000 Kg
paku biasa
15,583.33
77,916.67
20.0000 OH
tukang kayu
70,000.00
1,400,000.00
10.0000 OH
pekerja
55,000.00
550,000.00
2.0000 OH
kepala tukang
75,000.00
150,000.00
0.5000 OH
mandor
75,000.00
B. 8
B. 9
B. 10
7,733,125.00
37,500.00
2,497,916.67
2,137,500.00
4,635,416.67
5,400,000.00
129,600.00
0.2000 Kg
paku ulin
19,125.00
3,825.00
0.8000 OH
tukang kayu
70,000.00
56,000.00
0.2800 OH
pekerja
55,000.00
15,400.00
0.0800 OH
kepala tukang
75,000.00
6,000.00
0.0100 OH
mandor
75,000.00
JUMLAH
B. 7
2,137,500.00
JUMLAH
B. 6
37,500.00
JUMLAH
750.00
133,425.00
78,150.00
211,575.00
2,300,000.00
55,200.00
0.2000 Kg
paku biasa
15,583.33
3,116.67
0.8000 OH
tukang kayu
70,000.00
56,000.00
0.2800 OH
pekerja
55,000.00
15,400.00
0.0800 OH
kepala tukang
75,000.00
6,000.00
0.0100 OH
mandor
75,000.00
750.00
JUMLAH
58,316.67
78,150.00
136,466.67
2,300,000.00
57,500.00
0.1500 Kg
paku biasa
15,583.33
2,337.50
0.4000 OH
tukang kayu
70,000.00
28,000.00
0.1400 OH
pekerja
55,000.00
7,700.00
0.0400 OH
kepala tukang
75,000.00
3,000.00
0.0070 OH
mandor
75,000.00
525.00
JUMLAH
59,837.50
39,225.00
99,062.50
2,300,000.00
57,500.00
0.2000 Kg
paku biasa
15,583.33
3,116.67
0.8000 OH
tukang kayu
70,000.00
56,000.00
0.2800 OH
pekerja
55,000.00
15,400.00
0.0800 OH
kepala tukang
75,000.00
6,000.00
0.0100 OH
mandor
75,000.00
750.00
JUMLAH
60,616.67
78,150.00
138,766.67
2,300,000.00
48,300.00
0.7000 LBR
Multiplek 9 mm
129,000.00
90,300.00
0.0400 KG
Paku biasa
15,583.33
623.33
0.0400 KG
Paku plywood
23,750.00
950.00
0.0150 OH
Tukang kayu
70,000.00
1,050.00
0.8000 OH
Pekerja
55,000.00
44,000.00
0.0150 OH
kepala tukang
75,000.00
1,125.00
0.0400 OH
Mandor
75,000.00
JUMLAH
3,000.00
140,173.33
49,175.00
189,348.33
URAIAN PEKERJAAN
A. PEKERJAAN PERSIAPAN
A. 6.6.1
196,405.33
A. 6.6.2
244,372.00
A. 6.6.3
A. 6.6.4
A. 6.6.5
A. 6.6.6
695,062.50
A. 6.6.7
756,095.83
A. 6.6.8
A. 6.6.9
2,032,530.67
51,036.67
3,090,209.83
9,250.00
732,787.50
110,359.17
29,335.00
117,517.50
391,660.00
391,660.00
52,268.20
147,098.00
B. PEKERJAAN TANAH
B. 6.6.1
25,000.00
B. 6.6.2
32,830.00
B. 6.6.3
45,900.00
NO
URAIAN PEKERJAAN
B. 6.6.4
39,025.00
B. 6.6.5
78,125.00
B. 6.6.6
51,490.00
B. 6.6.7
3,125.00
B. 6.6.8
32,130.00
B. 6.6.9
1 M3 URUGAN KEMBALI
11,985.00
B. 6.6.10
PEMADATAN TANAH
31,250.00
B. 6.6.11
1 M3 URUGAN TANAH
109,155.00
110,780.00
B. 6.6.12
133,602.12
B. 6.6.13
B. 6.6.14
B. 6.6.15
1 M3 URUGAN SIRTU
345,385.00
B. 6.6.16
142,125.00
84,085.00
9,375.00
C. PEKERJAAN PONDASI
C.6.6.1
959,665.00
C.6.6.2
825,415.00
C.6.6.3
959,665.00
C.6.6.4
755,415.00
C.6.6.5
713,465.00
C.6.6.5.a
617,005.00
C.6.6.5.b
711,025.00
684,365.00
C.6.6.6
NO
URAIAN PEKERJAAN
C.6.6.7
663,915.00
C.6.6.8
630,115.00
C.6.6.9
481,899.60
C.6.6.10
457,058.00
C.6.6.11
711,525.00
C.6.6.12
574,600.00
C.6.6.13
556,270.00
C. 6.6.14
350,100.00
C. 6.6.15
C. 6.6.16
909,790.00
C. 6.6.17
863,536.10
C. 6.6.18
669,565.40
1,479,595.00
D. PEKERJAAN DINDING
D.6.6.1
247,489.00
D.6.6.2
226,050.00
D.6.6.3
215,085.00
D.6.6.4
207,265.00
D.6.6.5
203,860.00
D.6.6.6
203,860.00
D.6.6.7
185,866.50
D.6.6.8
117,615.00
D. 6.6.9
108,610.00
D. 6.6.10
103,156.00
NO
D. 6.6.11
URAIAN PEKERJAAN
1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA, 1 pc ; 4 ps
D. 6.6.11.a 1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA, 1 pc ; 4 ps (Pasir Putih Lokal)
92,198.50
D. 6.6.11.b 1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA, 1 pc ; 4 ps (Pasir Putih Sepaku)
99,100.00
D. 6.6.12
98,309.00
D. 6.6.13
97,541.00
D. 6.6.14
95,425.00
D. 6.6.15
92,900.00
D. 6.6.16
79,088.40
D. 6.6.17
81,563.20
D. 6.6.18
91,200.00
D. 6.6.19
237,797.50
D. 6.6.20
229,662.50
D. 6.6.21
264,372.50
D. 6.6.22
231,211.33
D. 6.6.23
233,802.75
D. 6.6.24
D. 6.6.25
207,140.00
D. 6.6.26
267,595.00
D. 6.6.27
43,212.00
D. 6.6.28
91,605.00
173,808.33
E. PEKERJAAN PLESTERAN
E. 6.6.1
43,421.00
E. 6.6.2
38,701.00
NO
URAIAN PEKERJAAN
E. 6.6.3
36,549.00
E. 6.6.4
35,135.00
E. 6.6.4.a
31,425.00
E. 6.6.4.b
34,635.00
E. 6.6.5
30,410.00
E. 6.6.6
29,642.50
E. 6.6.7
33,119.00
E. 6.6.8
34,128.00
E. 6.6.9
29,297.00
E. 6.6.10
32,050.00
E. 6.6.11
25,681.70
E. 6.6.12
27,169.10
E. 6.6.13
54,501.50
E. 6.6.14
50,727.50
E. 6.6.15
48,471.50
E. 6.6.16
46,664.50
E. 6.6.17
45,799.50
E. 6.6.18
34,744.20
E. 6.6.19
56,375.00
E. 6.6.20
57,000.00
E. 6.6.21
54,799.00
E. 6.6.22
53,047.00
E. 6.6.23
71,095.00
NO
URAIAN PEKERJAAN
E. 6.6.24
66,245.00
E. 6.6.25
63,394.00
E. 6.6.26
59,997.00
E. 6.6.27
28,716.00
E. 6.6.28
27,396.00
E. 6.6.29
34,495.00
E. 6.6.30
32,346.00
E. 6.6.31
E. 6.6.32
231,091.00
E. 6.6.33
218,951.67
E. 6.6.34
32,241.00
E. 6.6.35
16,466.00
E. 6.6.36
40,495.00
9,945.00
F. PEKERJAAN KAYU
F.6.6.1
7,402,500.00
F.6.6.2
8,362,500.00
F.6.6.3
7,762,500.00
F.6.6.4
4,402,500.00
F.6.6.5
318,754.17
F.6.6.6
297,331.25
F.6.6.7
532,500.00
F.6.6.8
492,500.00
F.6.6.9
447,000.00
NO
URAIAN PEKERJAAN
F.6.6.10
412,000.00
F.6.6.11
391,000.00
F.6.6.12
758,000.00
F.6.6.13
694,000.00
F.6.6.14
387,167.50
F.6.6.15
367,567.50
F.6.6.16
606,712.50
F.6.6.17
546,712.50
F.6.6.18
355,913.75
F.6.6.19
392,437.50
F.6.6.20
367,673.75
F.6.6.21
447,250.83
F.6.6.22
427,650.83
F.6.6.23
452,350.83
F.6.6.24
450,250.83
F.6.6.25
544,917.50
F.6.6.26
525,317.50
F.6.6.27
7,154,466.67
F.6.6.28
7,704,466.67
F.6.6.29
7,154,466.67
F.6.6.30
4,074,466.67
F.6.6.31
81,962.50
F.6.6.32
76,493.75
NO
URAIAN PEKERJAAN
F.6.6.33
85,962.50
F.6.6.34
92,962.50
F.6.6.35
92,962.50
F.6.6.36
926,966.67
F.6.6.37
927,675.00
F.6.6.38
F.6.6.39
F.6.6.40
F.6.6.41
F.6.6.42
74,237.90
F.6.6.43
87,937.50
F.6.6.44
179,929.17
F.6.6.45
193,429.17
F.6.6.46
104,329.17
F.6.6.47
72,929.17
F.6.6.48
65,729.17
F.6.6.49
F.6.6.50
F.6.6.51
121,185.00
F.6.6.52
69,535.00
F. 6.6.53.
64,375.00
F. 6.6.54
199,558.33
F. 6.6.55
189,808.33
94,808.33
100,808.33
95,162.50
144,673.75
101,254.17
47,767.46
NO
URAIAN PEKERJAAN
F. 6.6.56
199,558.33
F. 6.6.57
271,991.67
F. 6.6.58
214,308.33
F. 6.6.59
30,064.17
F. 6.6.60
15,090.00
G. PEKERJAAN BETON
G.6.6.1
1 M3 BETON TUMBUK 1 pc ; 3 ps ; 5 kr
834,025.00
G.6.6.2
1 M3 BETON TUMBUK 1 pc ; 3 ps ; 6 kr
818,725.00
G.6.6.3
1 M3 BETON TUMBUK 1 pc ; 4 ps ; 6 kr
788,025.00
G.6.6.4
100,150.00
G.6.6.5.
820,725.00
G.6.6.5.a
871,425.00
G.6.6.5.
888,975.00
G.6.6.6
907,625.00
G.6.6.7
958,725.00
G.6.6.8
874,225.00
G.6.6.9
1,008,425.00
G.6.6.10
1,090,325.00
G.6.6.11
1,093,125.00
G.6.6.12
G.6.6.13
1,067,425.00
1,120,075.00
G.6.6.13.a
971,425.00
1,138,300.00
NO
URAIAN PEKERJAAN
G.6.6.14
1,033,425.00
G.6.6.15
1,107,225.00
G.6.6.16
1,132,125.00
G.6.6.17
1,323,625.00
G.6.6.18
1,132,125.00
G.6.6.19
5,225.00
G.6.6.20
5,612.50
G.6.6.21
32,925.00
G.6.6.22
32,925.00
G.6.6.23
32,925.00
G.6.6.24
5,350.00
G.6.6.25
11,750.00
G.6.6.25
13,587.50
G.6.6.26
11,385.00
G.6.6.27
48,442.00
G.6.6.28
130,900.00
G. 6.6.29
121,650.00
G. 6.6.30
216,762.50
G. 6.6.31
224,462.50
G. 6.6.32
255,862.50
G. 6.6.33
447,222.50
G. 6.6.34
213,262.50
G. 6.6.35
1,431,650.00
NO
URAIAN PEKERJAAN
G. 6.6.36
G. 6.6.37
G. 6.6.38
3,337,925.00
G. 6.6.39
4,137,091.67
G. 6.6.40
6,786,575.00
G. 6.6.41
5,246,625.00
G. 6.6.42
4,801,975.00
G. 6.6.43
4,614,875.00
G. 6.6.44
4,892,333.33
G. 6.6.45
62,570.83
G. 6.6.46
73,601.67
1,403,000.00
84,830.00
H. 6.6.1
14,700.00
H. 6.6.2
77,200.00
H. 6.6.3
13,500.00
H. 6.6.4
56,970.00
H. 6.6.5
74,470.00
H. 6.6.6
45,186.14
H. 6.6.7
11,416.25
H. 6.6.8
29,686.67
H. 6.6.9
29,820.00
H. 6.6.10
29,670.00
H. 6.6.11
33,120.00
NO
URAIAN PEKERJAAN
H. 6.6.12
23,920.00
H. 6.6.13
25,530.00
H. 6.6.14
25,430.00
H. 6.6.15
27,040.00
H. 6.6.16
33,710.00
H. 6.6.17
23,820.00
H. 6.6.18
24,050.00
H. 6.6.19
25,890.00
H. 6.6.20
26,580.00
H. 6.6.21
28,420.00
H. 6.6.22
134,645.00
H. 6.6.23
134,645.00
H. 6.6.24
134,645.00
H. 6.6.25
134,645.00
H. 6.6.26
134,645.00
H. 6.6.27
134,645.00
H. 6.6.28
137,275.00
H. 6.6.29
137,275.00
H. 6.6.30
58,467.50
H. 6.6.31
79,292.50
H. 6.6.32
81,325.00
H. 6.6.33
H. 6.6.34
122,221.67
90,805.83
NO
URAIAN PEKERJAAN
H. 6.6.35
40,633.33
H. 6.6.36
27,129.17
H. 6.6.37
56,946.67
H. 6.6.38
39,580.83
H. 6.6.39
79,500.00
H. 6.6.40
62,293.33
H. 6.6.41
77,986.67
H. 6.6.42
I. PEKERJAAN PLAFOND
485,225.00
-
I. 6.6.1
39,765.00
I. 6.6.2
39,765.00
I. 6.6.3
89,925.00
I. 6.6.4
89,925.00
I. 6.6.5
22,112.50
I. 6.6.6
12,462.50
I. 6.6.7
12,462.50
I. 6.6.8
32,375.00
I. 6.6.9
57,425.00
I. 6.6.10
29,215.63
I. 6.6.11
42,575.00
I. 6.6.12
48,323.00
I. 6.6.13
57,650.00
I. 6.6.14
199,405.83
NO
URAIAN PEKERJAAN
I. 6.6.15
86,605.83
I. 6.6.16
I. 6.6.17
41,442.50
I. 6.6.18
47,562.50
I. 6.6.19
18,335.83
I. 6.6.20
145,210.00
I. 6.6.21
122,147.50
I. 6.6.22
100,110.00
I. 6.6.23
114,972.50
I. 6.6.24
175,405.83
35,610.00
J. PEKERJAAN SANITAIR
J. 6.6.1
J. 6.6.2
427,170.83
J. 6.6.3
305,270.83
J. 6.6.4
MEMASANG 1 BH URINOIR
2,575,737.50
J. 6.6.5
MEMASANG 1 BH WASTAFEL
2,621,987.50
J. 6.6.6
377,087.50
J. 6.6.7
525,550.00
J. 6.6.8
J. 6.6.9
J. 6.6.10
J. 6.6.11
J. 6.6.12
MEMASANG 1M' PIPA PENYALUR AIR LIMBAH JENIS PIPA TANAH, DIA.15 CM
1,940,075.00
1,796,945.00
80,250.00
17,881,412.50
1,119,000.00
10,891.15
NO
URAIAN PEKERJAAN
J. 6.6.13
MEMASANG 1M' PIPA PENYALUR AIR LIMBAH JENIS PIPA TANAH, DIA.20 CM
13,785.10
J. 6.6.14
35,623.20
J. 6.6.15
71,464.85
J. 6.6.16
MEMASANG 1BH BAK KONTROL PAS. BATU BATA UKURAN (30X30)CM TINGGI 35 CM
374,601.00
J. 6.6.17
MEMASANG 1BH BAK KONTROL PAS. BATU BATA UKURAN (45X45)CM TINGGI 50 CM
301,492.50
J. 6.6.18
MEMASANG 1BH BAK KONTROL PAS. BATU BATA UKURAN (60 x 60)CM TINGGI 65 CM
475,165.80
J. 6.6.19
92,725.00
J. 6.6.20
160,852.50
J. 6.6.21
J. 6.6.22
151,890.00
J. 6.6.23
298,496.50
J. 6.6.24
427,287.50
J. 6.6.25
36,860.83
J. 6.6.26
14,837.92
J. 6.6.27
16,872.29
J. 6.6.28
26,075.42
J. 6.6.29
46,716.25
J. 6.6.30
26,075.42
J. 6.6.31
74,900.00
J. 6.6.32
73,672.92
J. 6.6.33
255,012.50
J. 6.6.34
409,625.00
J. 6.6.35
92,725.00
33,775.00
NO
J. 6.6.36
URAIAN PEKERJAAN
MEMASANG 1BH FLOOR DRAIN
5,819.17
K. 6.6.2
4,192.50
K. 6.6.3
139,518.75
K. 6.6.4
149,660.00
K. 6.6.5
159,450.00
K. 6.6.6
K. 6.6.7
K. 6.6.8
171,015.00
K. 6.6.9
139,515.00
K. 6.6.10
46,506.25
K. 6.6.11
46,506.25
K. 6.6.12
K. 6.6.13
54,254.13
K. 6.6.14
45,239.17
K. 6.6.15
26,264.17
K. 6.6.16
142,429.17
K. 6.6.17
387,051.67
K. 6.6.18
122,625.83
K. 6.6.19
169,219.17
K. 6.6.20
161,527.08
K. 6.6.21
167,459.17
4,192.50
66,700.00
516,645.00
NO
URAIAN PEKERJAAN
50,025.00
L. 6.6.2
5,175.00
L. 6.6.3
35,837.50
L. 6.6.4
28,040.00
L. 6.6.5
40,034.03
L. 6.6.6
23,754.17
L. 6.6.7
17,350.00
L. 6.6.8
12,506.25
L. 6.6.9
24,506.25
L. 6.6.10
41,687.50
L. 6.6.11
16,675.00
L. 6.6.12
41,687.50
L. 6.6.13
L. 6.6.14
50,025.00
L. 6.6.15
45,843.75
L. 6.6.16
105,676.25
L. 6.6.17
125,036.25
L. 6.6.18
153,451.25
L. 6.6.19
162,293.75
L. 6.6.20
137,906.25
L. 6.6.21
137,906.25
L. 6.6.22
165,755.00
8,337.50
NO
URAIAN PEKERJAAN
L. 6.6.23
L. 6.6.24
92,220.63
M.6.6.2
84,955.63
M.6.6.3
87,220.63
M.6.6.4
92,259.88
M.6.6.5
80,019.88
M.6.6.6
89,489.88
M.6.6.7
105,673.75
M.6.6.8
118,175.42
M.6.6.9
149,202.92
M.6.6.10
153,707.50
M.6.6.11
43,952.92
M.6.6.12
45,172.03
M.6.6.13
49,126.17
M.6.6.14
76,805.42
M.6.6.15
90,365.63
M.6.6.16
17,793.00
M.6.6.17
12,778.56
M.6.6.18
13,660.52
M.6.6.19
15,414.58
M.6.6.20
13,330.32
NO
URAIAN PEKERJAAN
M.6.6.21
16,125.85
M.6.6.22
19,592.58
M.6.6.23
26,654.58
M.6.6.24
28,017.08
M.6.6.25
70,822.83
M.6.6.26
60,832.83
M.6.6.27
60,832.83
M.6.6.28
60,832.83
M.6.6.29
59,190.11
M.6.6.30
60,832.83
M.6.6.31
56,812.50
M.6.6.32
56,812.50
M.6.6.33
38,637.50
M.6.6.34
164,726.50
M.6.6.35
184,643.17
M.6.6.36
164,726.50
M.6.6.37
22,282.83
M.6.6.38
20,229.50
M.6.6.39
17,767.42
M.6.6.40
M.6.6.41
M.6.6.42
139,622.50
M.6.6.43
142,126.50
103,448.25
10,900.00
NO
URAIAN PEKERJAAN
M.6.6.44
169,726.50
M.6.6.45
148,726.50
M.6.6.46
178,296.50
M.6.6.47
146,477.34
M.6.6.48
154,979.03
M.6.6.49
104,726.50
M.6.6.50
112,407.92
M.6.6.51
633,147.92
M.6.6.52
23,162.50
M.6.6.53
23,162.50
M.6.6.54
16,350.00
M.6.6.55
23,162.50
M.6.6.56
18,530.00
M.6.6.57
1 M2 PASANG GYMFLOOR
65,312.50
M.6.6.58
106,957.50
M.6.6.59
106,957.50
M.6.6.60
174,640.21
M.6.6.61
227,982.50
M.6.6.62
226,982.50
M.6.6.63
222,140.00
M.6.6.64
201,982.50
M.6.6.65
151,982.50
M.6.6.66
153,371.39
NO
URAIAN PEKERJAAN
M.6.6.67
140,232.50
M.6.6.68
129,806.57
M.6.6.69
128,183.89
M.6.6.70
180,490.75
M.6.6.71
109,232.42
M.6.6.72
148,590.75
M.6.6.73
90,856.25
M.6.6.74
88,506.25
M.6.6.75
20,437.50
M.6.6.76
20,437.50
M.6.6.77
20,437.50
M.6.6.78
20,437.50
M.6.6.79
55,062.50
M.6.6.80
16,350.00
M.6.6.81
16,350.00
M.6.6.82
1 M2 PLINT KAYU 2 X 10 CM
34,150.00
14,250.00
N. 6.6.2
14,775.00
N. 6.6.3
14,775.00
N. 6.6.4
14,775.00
N. 6.6.5
N. 6.6.6
792,197.11
7,622.08
NO
URAIAN PEKERJAAN
N. 6.6.7
22,329.17
N. 6.6.8
24,539.17
N. 6.6.9
35,016.67
N. 6.6.10
24,950.50
N. 6.6.11
29,912.00
N. 6.6.12
N. 6.6.13
24,333.33
N. 6.6.14
11,266.00
N. 6.6.15
7,631.30
N. 6.6.16
4,982.50
N. 6.6.17
15,027.50
N. 6.6.18
10,375.00
N. 6.6.19
17,437.50
N. 6.6.20
19,480.00
N. 6.6.21
38,480.00
N. 6.6.22
7,600.00
N. 6.6.23
5,880.00
N. 6.6.24
121,000.00
N. 6.6.25
101,000.00
6,610.00
NO
URAIAN PEKERJAAN
G. PEKERJAAN BETON
G.6.6.1
1 M3 BETON TUMBUK 1 pc ; 3 ps ; 5 kr
834,025.00
G.6.6.2
1 M3 BETON TUMBUK 1 pc ; 3 ps ; 6 kr
818,725.00
G.6.6.3
1 M3 BETON TUMBUK 1 pc ; 4 ps ; 6 kr
788,025.00
G.6.6.4
100,150.00
G.6.6.5.
820,725.00
G.6.6.6
907,625.00
G.6.6.7
958,725.00
G.6.6.8
G.6.6.9
1,008,425.00
G.6.6.10
1,090,325.00
G.6.6.11
1,093,125.00
G.6.6.12
G.6.6.13
1,067,425.00
G.6.6.14
1,033,425.00
G.6.6.15
1,107,225.00
G.6.6.16
1,132,125.00
G.6.6.17
1,323,625.00
G.6.6.18
1,132,125.00
G.6.6.19
G.6.6.20
5,612.50
G.6.6.21
32,925.00
G.6.6.22
32,925.00
G.6.6.23
32,925.00
G.6.6.24
G.6.6.25
11,750.00
G.6.6.25
13,587.50
G.6.6.26
11,385.00
G.6.6.27
G.6.6.28
130,900.00
G. 6.6.29
121,650.00
G. 6.6.30
216,762.50
874,225.00
971,425.00
5,225.00
5,350.00
48,442.00
NO
URAIAN PEKERJAAN
G. 6.6.31
224,462.50
G. 6.6.32
255,862.50
G. 6.6.33
447,222.50
G. 6.6.34
213,262.50
G. 6.6.35
1,431,650.00
G. 6.6.36
1,403,000.00
G. 6.6.37
G. 6.6.38
3,337,925.00
G. 6.6.39
4,137,091.67
G. 6.6.40
6,786,575.00
G. 6.6.41
5,246,625.00
G. 6.6.42
4,801,975.00
G. 6.6.43
4,614,875.00
G. 6.6.44
4,892,333.33
G. 6.6.45
62,570.83
G. 6.6.46
73,601.67
84,830.00
14,700.00
H. 6.6.2
77,200.00
H. 6.6.3
13,500.00
H. 6.6.4
56,970.00
H. 6.6.5
74,470.00
H. 6.6.6
45,186.14
H. 6.6.7
11,416.25
H. 6.6.8
29,686.67
H. 6.6.9
29,820.00
H. 6.6.10
29,670.00
H. 6.6.11
33,120.00
H. 6.6.12
23,920.00
H. 6.6.13
25,530.00
H. 6.6.14
25,430.00
H. 6.6.15
27,040.00
H. 6.6.16
33,710.00
NO
URAIAN PEKERJAAN
H. 6.6.17
23,820.00
H. 6.6.18
24,050.00
H. 6.6.19
25,890.00
H. 6.6.20
26,580.00
H. 6.6.21
H. 6.6.22
134,645.00
H. 6.6.23
134,645.00
H. 6.6.24
134,645.00
H. 6.6.25
134,645.00
H. 6.6.26
134,645.00
H. 6.6.27
134,645.00
H. 6.6.28
137,275.00
H. 6.6.29
137,275.00
H. 6.6.30
58,467.50
H. 6.6.31
79,292.50
H. 6.6.32
H. 6.6.33
H. 6.6.34
90,805.83
H. 6.6.35
40,633.33
H. 6.6.36
27,129.17
H. 6.6.37
56,946.67
H. 6.6.38
39,580.83
H. 6.6.39
79,500.00
H. 6.6.40
62,293.33
H. 6.6.41
H. 6.6.42
28,420.00
81,325.00
122,221.67
77,986.67
485,225.00
I. PEKERJAAN PLAFOND
I. 6.6.1
39,765.00
I. 6.6.2
39,765.00
I. 6.6.3
89,925.00
I. 6.6.4
89,925.00
I. 6.6.5
22,112.50
I. 6.6.6
12,462.50
NO
URAIAN PEKERJAAN
I. 6.6.7
12,462.50
I. 6.6.8
32,375.00
I. 6.6.9
57,425.00
I. 6.6.10
29,215.63
I. 6.6.11
42,575.00
I. 6.6.12
48,323.00
I. 6.6.13
I. 6.6.14
I. 6.6.15
I. 6.6.16
I. 6.6.17
41,442.50
I. 6.6.18
47,562.50
I. 6.6.19
I. 6.6.20
145,210.00
I. 6.6.21
122,147.50
I. 6.6.22
100,110.00
I. 6.6.23
114,972.50
I. 6.6.24
57,650.00
199,405.83
86,605.83
175,405.83
18,335.83
35,610.00
J. PEKERJAAN SANITAIR
J. 6.6.1
J. 6.6.2
1,940,075.00
J. 6.6.3
J. 6.6.4
MEMASANG 1 BH URINOIR
2,575,737.50
J. 6.6.5
MEMASANG 1 BH WASTAFEL
2,621,987.50
J. 6.6.6
377,087.50
J. 6.6.7
525,550.00
J. 6.6.8
J. 6.6.9
427,170.83
305,270.83
1,796,945.00
80,250.00
J. 6.6.10
17,881,412.50
J. 6.6.11
J. 6.6.12
MEMASANG 1M' PIPA PENYALUR AIR LIMBAH JENIS PIPA TANAH, DIA.15 CM
10,891.15
J. 6.6.13
MEMASANG 1M' PIPA PENYALUR AIR LIMBAH JENIS PIPA TANAH, DIA.20 CM
13,785.10
J. 6.6.14
1,119,000.00
35,623.20
Hal : 520
NO
URAIAN PEKERJAAN
J. 6.6.15
J. 6.6.16
MEMASANG 1BH BAK KONTROL PAS. BATU BATA UKURAN (30X30)CM TINGGI 35 CM
374,601.00
71,464.85
J. 6.6.17
MEMASANG 1BH BAK KONTROL PAS. BATU BATA UKURAN (45X45)CM TINGGI 50 CM
301,492.50
J. 6.6.18
MEMASANG 1BH BAK KONTROL PAS. BATU BATA UKURAN (60 x 60)CM TINGGI 65 CM
475,165.80
J. 6.6.19
92,725.00
J. 6.6.20
160,852.50
J. 6.6.21
J. 6.6.22
151,890.00
J. 6.6.23
298,496.50
J. 6.6.24
427,287.50
J. 6.6.25
36,860.83
J. 6.6.26
14,837.92
J. 6.6.27
16,872.29
J. 6.6.28
26,075.42
J. 6.6.29
46,716.25
J. 6.6.30
26,075.42
J. 6.6.31
74,900.00
J. 6.6.32
J. 6.6.33
255,012.50
J. 6.6.34
409,625.00
J. 6.6.35
33,775.00
J. 6.6.36
43,675.00
92,725.00
73,672.92
K. PEKERJAAN BESI
K. 6.6.1
K. 6.6.2
5,819.17
K. 6.6.3
139,518.75
K. 6.6.4
149,660.00
K. 6.6.5
159,450.00
K. 6.6.6
K. 6.6.7
K. 6.6.8
171,015.00
K. 6.6.9
139,515.00
K. 6.6.10
4,192.50
4,192.50
66,700.00
46,506.25
NO
URAIAN PEKERJAAN
K. 6.6.11
K. 6.6.12
46,506.25
K. 6.6.13
54,254.13
K. 6.6.14
45,239.17
K. 6.6.15
K. 6.6.16
142,429.17
K. 6.6.17
387,051.67
K. 6.6.18
122,625.83
K. 6.6.19
169,219.17
K. 6.6.20
161,527.08
K. 6.6.21
167,459.17
516,645.00
26,264.17
L. 6.6.2
50,025.00
L. 6.6.3
35,837.50
L. 6.6.4
28,040.00
L. 6.6.5
40,034.03
L. 6.6.6
23,754.17
L. 6.6.7
17,350.00
L. 6.6.8
12,506.25
L. 6.6.9
5,175.00
24,506.25
L. 6.6.10
41,687.50
L. 6.6.11
16,675.00
L. 6.6.12
41,687.50
L. 6.6.13
L. 6.6.14
L. 6.6.15
L. 6.6.16
105,676.25
L. 6.6.17
125,036.25
L. 6.6.18
153,451.25
L. 6.6.19
162,293.75
L. 6.6.20
137,906.25
L. 6.6.21
137,906.25
8,337.50
50,025.00
45,843.75
NO
URAIAN PEKERJAAN
L. 6.6.22
L. 6.6.23
L. 6.6.24
92,220.63
M.6.6.2
84,955.63
M.6.6.3
87,220.63
M.6.6.4
92,259.88
M.6.6.5
80,019.88
M.6.6.6
M.6.6.7
105,673.75
M.6.6.8
118,175.42
89,489.88
M.6.6.9
149,202.92
M.6.6.10
153,707.50
M.6.6.11
43,952.92
M.6.6.12
45,172.03
M.6.6.13
49,126.17
M.6.6.14
76,805.42
M.6.6.15
90,365.63
M.6.6.16
17,793.00
M.6.6.17
12,778.56
M.6.6.18
13,660.52
M.6.6.19
15,414.58
M.6.6.20
13,330.32
M.6.6.21
16,125.85
M.6.6.22
19,592.58
M.6.6.23
26,654.58
M.6.6.24
28,017.08
M.6.6.25
70,822.83
M.6.6.26
60,832.83
M.6.6.27
60,832.83
M.6.6.28
60,832.83
M.6.6.29
59,190.11
NO
URAIAN PEKERJAAN
M.6.6.30
60,832.83
M.6.6.31
56,812.50
M.6.6.32
56,812.50
M.6.6.33
M.6.6.34
164,726.50
M.6.6.35
184,643.17
M.6.6.36
164,726.50
M.6.6.37
22,282.83
M.6.6.38
20,229.50
M.6.6.39
17,767.42
M.6.6.40
M.6.6.41
M.6.6.42
139,622.50
M.6.6.43
142,126.50
M.6.6.44
169,726.50
M.6.6.45
148,726.50
M.6.6.46
178,296.50
M.6.6.47
146,477.34
M.6.6.48
154,979.03
M.6.6.49
104,726.50
M.6.6.50
112,407.92
M.6.6.51
633,147.92
M.6.6.52
23,162.50
M.6.6.53
23,162.50
M.6.6.54
16,350.00
M.6.6.55
23,162.50
M.6.6.56
18,530.00
M.6.6.57
1 M2 PASANG GYMFLOOR
M.6.6.58
106,957.50
M.6.6.59
106,957.50
M.6.6.60
174,640.21
M.6.6.61
227,982.50
M.6.6.62
226,982.50
38,637.50
103,448.25
10,900.00
65,312.50
NO
URAIAN PEKERJAAN
M.6.6.63
222,140.00
M.6.6.64
201,982.50
M.6.6.65
151,982.50
M.6.6.66
153,371.39
M.6.6.67
140,232.50
M.6.6.68
129,806.57
M.6.6.69
128,183.89
M.6.6.70
180,490.75
M.6.6.71
109,232.42
M.6.6.72
148,590.75
M.6.6.73
90,856.25
M.6.6.74
88,506.25
M.6.6.75
20,437.50
M.6.6.76
20,437.50
M.6.6.77
20,437.50
M.6.6.78
20,437.50
M.6.6.79
55,062.50
M.6.6.80
16,350.00
M.6.6.81
16,350.00
M.6.6.82
1 M2 PLINT KAYU 2 X 10 CM
34,150.00
14,250.00
N. 6.6.2
14,775.00
N. 6.6.3
14,775.00
N. 6.6.4
N. 6.6.5
N. 6.6.6
N. 6.6.7
22,329.17
N. 6.6.8
24,539.17
N. 6.6.9
14,775.00
792,197.11
7,622.08
35,016.67
N. 6.6.10
24,950.50
N. 6.6.11
29,912.00
N. 6.6.12
6,610.00
NO
URAIAN PEKERJAAN
N. 6.6.13
24,333.33
N. 6.6.14
11,266.00
N. 6.6.15
7,631.30
N. 6.6.16
4,982.50
N. 6.6.17
15,027.50
N. 6.6.18
10,375.00
N. 6.6.19
17,437.50
N. 6.6.20
19,480.00
N. 6.6.21
38,480.00
N. 6.6.22
N. 6.6.23
5,880.00
N. 6.6.24
121,000.00
N. 6.6.25
101,000.00
7,600.00
834,025.00
TRUE
818,725.00
TRUE
788,025.00
TRUE
100,150.00
TRUE
820,725.00
TRUE
907,625.00
TRUE
958,725.00
TRUE
874,225.00
TRUE
1,008,425.00
TRUE
1,090,325.00
TRUE
1,093,125.00
TRUE
971,425.00
TRUE
1,067,425.00
TRUE
1,033,425.00
TRUE
1,107,225.00
TRUE
1,132,125.00
TRUE
1,323,625.00
TRUE
1,132,125.00
TRUE
5,225.00
TRUE
5,612.50
TRUE
32,925.00
TRUE
32,925.00
TRUE
32,925.00
TRUE
5,350.00
TRUE
11,750.00
TRUE
13,587.50
TRUE
11,385.00
TRUE
48,442.00
TRUE
130,900.00
TRUE
121,650.00
TRUE
216,762.50
TRUE
TRUE
TRUE
FALSE
224,462.50
TRUE
255,862.50
TRUE
447,222.50
TRUE
213,262.50
TRUE
1,431,650.00
TRUE
1,403,000.00
TRUE
84,830.00
TRUE
3,337,925.00
TRUE
4,137,091.67
TRUE
6,786,575.00
TRUE
5,246,625.00
TRUE
4,801,975.00
TRUE
4,614,875.00
TRUE
4,892,333.33
TRUE
62,570.83
TRUE
73,601.67
TRUE
TRUE
14,700.00
TRUE
77,200.00
TRUE
13,500.00
TRUE
56,970.00
TRUE
74,470.00
TRUE
45,186.14
TRUE
11,416.25
TRUE
29,686.67
TRUE
29,820.00
TRUE
29,670.00
TRUE
33,120.00
TRUE
23,920.00
TRUE
25,530.00
TRUE
25,430.00
TRUE
27,040.00
TRUE
33,710.00
TRUE
TRUE
TRUE
FALSE
23,820.00
TRUE
24,050.00
TRUE
25,890.00
TRUE
26,580.00
TRUE
28,420.00
TRUE
134,645.00
TRUE
134,645.00
TRUE
134,645.00
TRUE
134,645.00
TRUE
134,645.00
TRUE
134,645.00
TRUE
137,275.00
TRUE
137,275.00
TRUE
58,467.50
TRUE
79,292.50
TRUE
81,325.00
TRUE
122,221.67
TRUE
90,805.83
TRUE
40,633.33
TRUE
27,129.17
TRUE
56,946.67
TRUE
39,580.83
TRUE
79,500.00
TRUE
62,293.33
TRUE
77,986.67
TRUE
485,225.00
TRUE
TRUE
39,765.00
TRUE
39,765.00
TRUE
89,925.00
TRUE
89,925.00
TRUE
22,112.50
TRUE
12,462.50
TRUE
TRUE
TRUE
FALSE
12,462.50
TRUE
32,375.00
TRUE
57,425.00
TRUE
29,215.63
TRUE
42,575.00
TRUE
48,323.00
TRUE
57,650.00
TRUE
199,405.83
TRUE
86,605.83
TRUE
175,405.83
TRUE
41,442.50
TRUE
47,562.50
TRUE
18,335.83
TRUE
145,210.00
TRUE
122,147.50
TRUE
100,110.00
TRUE
114,972.50
TRUE
35,610.00
TRUE
TRUE
1,940,075.00
TRUE
427,170.83
TRUE
305,270.83
TRUE
2,575,737.50
TRUE
2,621,987.50
TRUE
377,087.50
TRUE
525,550.00
TRUE
1,796,945.00
TRUE
80,250.00
TRUE
17,881,412.50
TRUE
1,119,000.00
TRUE
10,891.15
TRUE
13,785.10
TRUE
35,623.20
TRUE
FALSE
TRUE
FALSE
71,464.85
TRUE
374,601.00
TRUE
301,492.50
TRUE
475,165.80
TRUE
92,725.00
TRUE
160,852.50
TRUE
92,725.00
TRUE
151,890.00
TRUE
298,496.50
TRUE
427,287.50
TRUE
36,860.83
TRUE
14,837.92
TRUE
16,872.29
TRUE
26,075.42
TRUE
46,716.25
TRUE
26,075.42
TRUE
74,900.00
TRUE
73,672.92
TRUE
255,012.50
TRUE
409,625.00
TRUE
33,775.00
TRUE
43,675.00
TRUE
TRUE
5,819.17
TRUE
4,192.50
TRUE
139,518.75
TRUE
149,660.00
TRUE
159,450.00
TRUE
4,192.50
TRUE
66,700.00
TRUE
171,015.00
TRUE
139,515.00
TRUE
46,506.25
TRUE
TRUE
TRUE
FALSE
46,506.25
TRUE
516,645.00
TRUE
54,254.13
TRUE
45,239.17
TRUE
26,264.17
TRUE
142,429.17
TRUE
387,051.67
TRUE
122,625.83
TRUE
169,219.17
TRUE
161,527.08
TRUE
167,459.17
TRUE
TRUE
50,025.00
TRUE
5,175.00
TRUE
35,837.50
TRUE
28,040.00
TRUE
40,034.03
TRUE
23,754.17
TRUE
17,350.00
TRUE
12,506.25
TRUE
24,506.25
TRUE
41,687.50
TRUE
16,675.00
TRUE
41,687.50
TRUE
8,337.50
TRUE
50,025.00
TRUE
45,843.75
TRUE
105,676.25
TRUE
125,036.25
TRUE
153,451.25
TRUE
162,293.75
TRUE
137,906.25
TRUE
137,906.25
TRUE
TRUE
TRUE
FALSE
165,755.00
TRUE
12,506.25
TRUE
452,506.25
TRUE
TRUE
92,220.63
TRUE
84,955.63
TRUE
87,220.63
TRUE
92,259.88
TRUE
80,019.88
TRUE
89,489.88
TRUE
105,673.75
TRUE
118,175.42
TRUE
149,202.92
TRUE
153,707.50
TRUE
43,952.92
TRUE
45,172.03
TRUE
49,126.17
TRUE
76,805.42
TRUE
90,365.63
TRUE
17,793.00
TRUE
12,778.56
TRUE
13,660.52
TRUE
15,414.58
TRUE
13,330.32
TRUE
16,125.85
TRUE
19,592.58
TRUE
26,654.58
TRUE
28,017.08
TRUE
70,822.83
TRUE
60,832.83
TRUE
60,832.83
TRUE
60,832.83
TRUE
59,190.11
TRUE
TRUE
TRUE
FALSE
60,832.83
TRUE
56,812.50
TRUE
56,812.50
TRUE
38,637.50
TRUE
164,726.50
TRUE
184,643.17
TRUE
164,726.50
TRUE
22,282.83
TRUE
20,229.50
TRUE
17,767.42
TRUE
103,448.25
TRUE
10,900.00
TRUE
139,622.50
TRUE
142,126.50
TRUE
169,726.50
TRUE
148,726.50
TRUE
178,296.50
TRUE
146,477.34
TRUE
154,979.03
TRUE
104,726.50
TRUE
112,407.92
TRUE
633,147.92
TRUE
23,162.50
TRUE
23,162.50
TRUE
16,350.00
TRUE
23,162.50
TRUE
18,530.00
TRUE
65,312.50
TRUE
106,957.50
TRUE
106,957.50
TRUE
174,640.21
TRUE
227,982.50
TRUE
226,982.50
TRUE
TRUE
TRUE
FALSE
222,140.00
TRUE
201,982.50
TRUE
151,982.50
TRUE
153,371.39
TRUE
140,232.50
TRUE
129,806.57
TRUE
128,183.89
TRUE
180,490.75
TRUE
109,232.42
TRUE
148,590.75
TRUE
90,856.25
TRUE
88,506.25
TRUE
20,437.50
TRUE
20,437.50
TRUE
20,437.50
TRUE
20,437.50
TRUE
55,062.50
TRUE
16,350.00
TRUE
16,350.00
TRUE
34,150.00
TRUE
TRUE
14,250.00
TRUE
14,775.00
TRUE
14,775.00
TRUE
14,775.00
TRUE
792,197.11
TRUE
7,622.08
TRUE
22,329.17
TRUE
24,539.17
TRUE
35,016.67
TRUE
24,950.50
TRUE
29,912.00
TRUE
6,610.00
TRUE
TRUE
TRUE
FALSE
24,333.33
TRUE
11,266.00
TRUE
7,631.30
TRUE
4,982.50
TRUE
15,027.50
TRUE
10,375.00
TRUE
17,437.50
TRUE
19,480.00
TRUE
38,480.00
TRUE
7,600.00
TRUE
5,880.00
TRUE
121,000.00
TRUE
101,000.00
TRUE
TRUE
G. PEKERJAAN BETON
G.6.6.1
1 M3 BETON TUMBUK 1 pc ; 3 ps ; 5 kr
218.0000 kg
semen portland
1,300.00
283,400.00
0.5200 m3
pasir beton
250,000.00
130,000.00
0.8700 m3
350,000.00
304,500.00
1.6500 oh
pekerja
55,000.00
90,750.00
0.2500 oh
tukang batu
70,000.00
17,500.00
0.0250 oh
kepala tukang
75,000.00
1,875.00
0.0800 oh
mandor
75,000.00
6,000.00
717,900.00
G.6.6.2
semen portland
1,300.00
256,100.00
0.4700 m3
pasir beton
250,000.00
117,500.00
0.9400 m3
350,000.00
329,000.00
1.6500 oh
pekerja
55,000.00
90,750.00
0.2500 oh
tukang batu
70,000.00
17,500.00
0.0250 oh
kepala tukang
75,000.00
1,875.00
0.0800 oh
mandor
75,000.00
6,000.00
702,600.00
116,125.00
818,725.00
1 M3 BETON TUMBUK 1 pc ; 4 ps ; 6 kr
173.0000 kg
semen portland
1,300.00
224,900.00
0.5700 m3
pasir beton
250,000.00
142,500.00
0.8700 m3
350,000.00
304,500.00
1.6500 oh
pekerja
55,000.00
90,750.00
0.2500 oh
tukang batu
70,000.00
17,500.00
0.0250 oh
kepala tukang
75,000.00
1,875.00
0.0800 oh
mandor
75,000.00
6,000.00
671,900.00
G.6.6.4
834,025.00
1 M3 BETON TUMBUK 1 pc ; 3 ps ; 6 kr
197.0000 kg
G.6.6.3
116,125.00
116,125.00
788,025.00
semen portland
1,300.00
0.0260 m3
pasir beton
250,000.00
13,000.00
6,500.00
0.0440 m3
350,000.00
15,400.00
1.1500 oh
pekerja
55,000.00
63,250.00
0.0200 oh
tukang batu
70,000.00
1,400.00
0.0020 oh
kepala tukang
75,000.00
150.00
0.0060 oh
mandor
75,000.00
450.00
34,900.00
65,250.00
100,150.00
G.6.6.5.
semen portland
1,300.00
301,600.00
0.52 m3
pasir beton
250,000.00
130,000.00
0.78 m3
350,000.00
273,000.00
1.65 oh
pekerja
55,000.00
90,750.00
0.25 oh
tukang batu
70,000.00
17,500.00
0.03 oh
kepala tukang
75,000.00
1,875.00
0.08 oh
mandor
75,000.00
JUMLAH
G.6.6.5..a
semen portland
1,300.00
301,600.00
0.52 m3
pasir beton
250,000.00
130,000.00
0.78 m3
415,000.00
323,700.00
1.65 oh
pekerja
55,000.00
90,750.00
0.25 oh
tukang batu
70,000.00
17,500.00
0.03 oh
kepala tukang
75,000.00
1,875.00
0.08 oh
mandor
75,000.00
JUMLAH
116,125.00
semen portland
1,300.00
301,600.00
pasir beton
250,000.00
130,000.00
0.78 m3
437,500.00
341,250.00
1.65 oh
pekerja
55,000.00
90,750.00
0.25 oh
tukang batu
70,000.00
17,500.00
0.03 oh
kepala tukang
75,000.00
1,875.00
0.08 oh
mandor
75,000.00
871,425.00
6,000.00
772,850.00
116,125.00
888,975.00
semen portland
1,300.00
364,000.00
0.4500 m3
pasir beton
250,000.00
112,500.00
0.9000 m3
350,000.00
315,000.00
1.6500 oh
pekerja
55,000.00
90,750.00
0.2500 oh
tukang batu
70,000.00
17,500.00
0.0250 oh
kepala tukang
75,000.00
1,875.00
0.0800 oh
mandor
75,000.00
JUMLAH
6,000.00
791,500.00
116,125.00
907,625.00
semen portland
1,300.00
457,600.00
0.5600 m3
pasir beton
250,000.00
140,000.00
0.7000 m3
350,000.00
245,000.00
1.6500 oh
pekerja
55,000.00
90,750.00
0.2500 oh
tukang batu
70,000.00
17,500.00
0.0250 oh
kepala tukang
75,000.00
1,875.00
0.0800 oh
mandor
75,000.00
JUMLAH
G.6.6.8
6,000.00
755,300.00
0.52 m3
JUMLAH
G.6.6.7
820,725.00
G.6.6.6
116,125.00
G.6.6.5.b
6,000.00
704,600.00
6,000.00
842,600.00
semen portland
1,300.00
464,100.00
0.4200 m3
pasir beton
250,000.00
105,000.00
0.5400 m3
350,000.00
189,000.00
116,125.00
958,725.00
1.6500 oh
pekerja
55,000.00
90,750.00
0.2500 oh
tukang batu
70,000.00
17,500.00
0.0250 oh
kepala tukang
75,000.00
1,875.00
0.0800 oh
mandor
75,000.00
JUMLAH
G.6.6.9
6,000.00
758,100.00
116,125.00
874,225.00
semen portland
1,300.00
501,800.00
0.4700 m3
pasir beton
250,000.00
117,500.00
0.7800 m3
350,000.00
273,000.00
1.6500 oh
pekerja
55,000.00
90,750.00
0.2500 oh
tukang batu
70,000.00
17,500.00
0.0250 oh
kepala tukang
75,000.00
1,875.00
0.0800 oh
mandor
75,000.00
JUMLAH
6,000.00
892,300.00
116,125.00
1,008,425.00
G.6.6.10
semen portland
1,300.00
0.3700 m3
pasir beton
250,000.00
92,500.00
0.7400 m3
350,000.00
259,000.00
1.6500 oh
pekerja
55,000.00
90,750.00
0.2500 oh
tukang batu
70,000.00
17,500.00
0.0250 oh
kepala tukang
75,000.00
1,875.00
0.0800 oh
mandor
75,000.00
JUMLAH
G.6.6.11
semen portland
1,300.00
572,000.00
pasir beton
250,000.00
125,000.00
0.8000 m3
350,000.00
280,000.00
2.4600 galon
Rapidrant
26,000.00
1.6500 oh
pekerja
55,000.00
90,750.00
0.2500 oh
tukang batu
70,000.00
17,500.00
0.0250 oh
kepala tukang
75,000.00
1,875.00
0.0800 oh
mandor
75,000.00
6,000.00
977,000.00
116,125.00
semen portland
1,300.00
436,800.00
0.5400 m3
pasir beton
250,000.00
135,000.00
0.8100 m3
350,000.00
283,500.00
1.0000 ltr
puzzdith - 100 XR
1.6500 oh
pekerja
55,000.00
1,093,125.00
90,750.00
0.2500 oh
tukang batu
70,000.00
17,500.00
0.0250 oh
kepala tukang
75,000.00
1,875.00
0.0800 oh
mandor
75,000.00
JUMLAH
6,000.00
855,300.00
116,125.00
971,425.00
semen portland
1,300.00
436,800.00
0.5400 m3
pasir beton
250,000.00
135,000.00
0.8100 m3
350,000.00
283,500.00
2.0000 oh
pekerja
55,000.00
110,000.00
0.3500 oh
tukang batu
70,000.00
24,500.00
0.0350 oh
kepala tukang
75,000.00
2,625.00
1.0000 oh
mandor
75,000.00
75,000.00
JUMLAH
855,300.00
212,125.00
1,067,425.00
semen portland
1,300.00
436,800.00
0.5400 m3
pasir beton
250,000.00
135,000.00
0.8100 m3
415,000.00
336,150.00
2.0000 oh
pekerja
55,000.00
110,000.00
0.3500 oh
tukang batu
70,000.00
24,500.00
0.0350 oh
kepala tukang
75,000.00
2,625.00
1.0000 oh
mandor
75,000.00
75,000.00
JUMLAH
G.6.6.13.b
1,090,325.00
G.6.6.13.a
116,125.00
0.5000 m3
JUMLAH
G.6.6.13
6,000.00
974,200.00
G.6.6.12
622,700.00
907,950.00
semen portland
1,300.00
436,800.00
212,125.00
1,120,075.00
0.5400 m3
pasir beton
250,000.00
135,000.00
0.8100 m3
437,500.00
354,375.00
2.0000 oh
pekerja
55,000.00
110,000.00
0.3500 oh
tukang batu
70,000.00
24,500.00
0.0350 oh
kepala tukang
75,000.00
2,625.00
1.0000 oh
mandor
75,000.00
75,000.00
JUMLAH
G.6.6.14
926,175.00
212,125.00
1,138,300.00
semen portland
1,300.00
378,300.00
0.4700 m3
pasir beton
250,000.00
117,500.00
0.9300 m3
350,000.00
325,500.00
2.0000 oh
pekerja
55,000.00
110,000.00
0.3500 oh
tukang batu
70,000.00
24,500.00
0.0350 oh
kepala tukang
75,000.00
2,625.00
1.0000 oh
mandor
75,000.00
75,000.00
JUMLAH
821,300.00
212,125.00
1,033,425.00
G.6.6.15
semen portland
1,300.00
477,100.00
0.4400 m3
pasir beton
250,000.00
110,000.00
0.8800 m3
350,000.00
308,000.00
2.0000 oh
pekerja
55,000.00
110,000.00
0.3500 oh
tukang batu
70,000.00
24,500.00
0.0350 oh
kepala tukang
75,000.00
2,625.00
1.0000 oh
mandor
75,000.00
75,000.00
JUMLAH
G.6.6.16
400.0000 kg
semen portland
1,300.00
520,000.00
pasir beton
250,000.00
120,000.00
0.8000 m3
350,000.00
280,000.00
2.0000 oh
pekerja
55,000.00
110,000.00
0.3500 oh
tukang batu
70,000.00
24,500.00
0.0350 oh
kepala tukang
75,000.00
2,625.00
1.0000 oh
mandor
75,000.00
75,000.00
920,000.00
212,125.00
semen portland
1,300.00
799,500.00
0.5200 m3
pasir beton
250,000.00
130,000.00
0.5200 m3
350,000.00
182,000.00
2.0000 oh
pekerja
55,000.00
110,000.00
0.3500 oh
tukang batu
70,000.00
24,500.00
0.0350 oh
kepala tukang
75,000.00
2,625.00
1.0000 oh
mandor
75,000.00
75,000.00
JUMLAH
1,132,125.00
1,111,500.00
212,125.00
1,323,625.00
semen portland
1,300.00
520,000.00
0.4800 m3
pasir beton
250,000.00
120,000.00
0.8000 m3
350,000.00
280,000.00
1.2000 Kg
Strorox - 100
2.0000 oh
pekerja
55,000.00
110,000.00
0.3500 oh
tukang batu
70,000.00
24,500.00
0.0350 oh
kepala tukang
75,000.00
2,625.00
1.0000 oh
mandor
75,000.00
75,000.00
JUMLAH
G.6.6.19
1,107,225.00
G.6.6.18
212,125.00
0.4800 m3
JUMLAH
G.6.6.17
895,100.00
920,000.00
212,125.00
1,132,125.00
0.0500 oh
pekerja
55,000.00
2,750.00
0.0300 oh
tukang batu
70,000.00
2,100.00
0.0030 oh
kepala tukang
75,000.00
225.00
0.0020 oh
mandor
75,000.00
JUMLAH
150.00
-
5,225.00
5,225.00
G.6.6.20
0.0500 oh
pekerja
55,000.00
2,750.00
0.0350 oh
tukang batu
70,000.00
2,450.00
0.0035 oh
kepala tukang
75,000.00
262.50
0.0020 oh
mandor
75,000.00
JUMLAH
G.6.6.21
1.0500 m'
0.5500 oh
pekerja
55,000.00
30,250.00
0.0350 oh
tukang batu
70,000.00
2,450.00
0.0030 oh
mandor
75,000.00
1.0500 m'
0.5500 oh
pekerja
55,000.00
30,250.00
0.0350 oh
tukang batu
70,000.00
2,450.00
0.0030 oh
mandor
75,000.00
225.00
-
32,925.00
1.0500 m'
0.5500 oh
pekerja
55,000.00
30,250.00
0.0350 oh
tukang batu
70,000.00
2,450.00
0.0030 oh
mandor
75,000.00
32,925.00
225.00
-
32,925.00
32,925.00
0.0500 oh
pekerja
55,000.00
2,750.00
0.0350 oh
tukang batu
70,000.00
2,450.00
0.0020 oh
mandor
75,000.00
150.00
-
5,350.00
5,350.00
Besi beton
10,000.00
10,500.00
0.0150 Kg
Kawat beton
20,000.00
300.00
0.0070 OH
pekerja
55,000.00
385.00
0.0070 OH
tukang besi
70,000.00
490.00
0.0007 OH
kepala tukang
75,000.00
52.50
0.0003 OH
mandor
75,000.00
@
G.6.6.25
32,925.00
JUMLAH
G.6.6.25
225.00
32,925.00
JUMLAH
G.6.6.24
5,612.50
JUMLAH
G.6.6.23
5,612.50
JUMLAH
G.6.6.22
150.00
-
JUMLAH
22.50
10,800.00
950.00
11,750.00
Besi beton
11,750.00
12,337.50
0.0150 Kg
Kawat beton
20,000.00
300.00
0.0070 OH
pekerja
55,000.00
385.00
0.0070 OH
tukang besi
70,000.00
490.00
0.0007 OH
kepala tukang
75,000.00
52.50
0.0003 OH
mandor
75,000.00
JUMLAH
22.50
12,637.50
950.00
13,587.50
G.6.6.26
10,000.00
10,500.00
0.0100 Kg
Kawat beton
20,000.00
200.00
0.0050 OH
pekerja
55,000.00
275.00
0.0050 OH
tukang besi
70,000.00
350.00
0.0005 OH
kepala tukang
75,000.00
37.50
0.0003 OH
mandor
75,000.00
JUMLAH
G.6.6.27
G. 6.6.29
1.0200 Kg
28,350.00
28,917.00
0.8050 Kg
Kawat beton
20,000.00
16,100.00
0.0250 OH
pekerja
55,000.00
1,375.00
0.0250 OH
tukang besi
70,000.00
1,750.00
0.0025 OH
kepala tukang
75,000.00
187.50
0.0015 OH
mandor
75,000.00
11,385.00
112.50
45,017.00
3,425.00
48,442.00
kayu terentang
2,200,000.00
88,000.00
0.3000 Kg
15,583.33
4,675.00
0.1000 lt
minyak bekisting
12,000.00
1,200.00
0.3000 OH
pekerja
55,000.00
16,500.00
0.2600 OH
tukang besi
70,000.00
18,200.00
0.0260 OH
kepala tukang
75,000.00
1,950.00
0.0050 OH
mandor
75,000.00
375.00
JUMLAH
93,875.00
37,025.00
130,900.00
1,750,000.00
78,750.00
0.3000 kg
15,583.33
4,675.00
0.1000 lt
minyak bekisting
12,000.00
1,200.00
0.3000 OH
pekerja
55,000.00
16,500.00
0.2600 OH
tukang kayu
70,000.00
18,200.00
0.0260 OH
kepala tukang
75,000.00
1,950.00
0.0050 OH
mandor
75,000.00
JUMLAH
G. 6.6.30
685.00
JUMLAH
G.6.6.28
22.50
10,700.00
375.00
84,625.00
37,025.00
121,650.00
1,750,000.00
70,000.00
0.4000 kg
15,583.33
6,233.33
0.2000 lt
minyak bekisting
12,000.00
2,400.00
0.0150 m3
2,200,000.00
33,000.00
0.3500 lbr
plywood tebal 9 mm
124,583.33
43,604.17
2.0000 btg
9,500.00
19,000.00
0.3000 oh
pekerja
55,000.00
16,500.00
0.3300 oh
tukang kayu
70,000.00
23,100.00
0.0330 oh
kepala tukang
75,000.00
2,475.00
0.0060 oh
mandor
75,000.00
JUMLAH
450.00
174,237.50
42,525.00
216,762.50
G. 6.6.31
1,750,000.00
70,000.00
0.4000 kg
15,583.33
6,233.33
0.2000 lt
minyak bekisting
12,000.00
2,400.00
0.0180 m3
2,200,000.00
39,600.00
0.3500 lbr
plywood tebal 9 mm
124,583.33
43,604.17
2.0000 btg
9,500.00
19,000.00
0.3200 oh
pekerja
55,000.00
17,600.00
0.3300 oh
tukang kayu
70,000.00
23,100.00
0.0330 oh
kepala tukang
75,000.00
2,475.00
0.0060 oh
mandor
75,000.00
450.00
118,233.33
G. 6.6.32
224,462.50
1,750,000.00
70,000.00
0.4000 kg
15,583.33
6,233.33
0.2000 lt
minyak bekisting
12,000.00
2,400.00
0.0150 m3
2,200,000.00
33,000.00
0.3500 lbr
plywood tebal 9 mm
124,583.33
43,604.17
6.0000 btg
9,500.00
57,000.00
0.3200 oh
pekerja
55,000.00
17,600.00
0.3300 oh
tukang kayu
70,000.00
23,100.00
0.0330 oh
kepala tukang
75,000.00
2,475.00
0.0060 oh
mandor
75,000.00
JUMLAH
G. 6.6.33
106,229.17
450.00
111,633.33
144,229.17
255,862.50
1,750,000.00
52,500.00
0.4000 kg
15,583.33
6,233.33
0.2000 lt
minyak bekisting
12,000.00
2,400.00
0.0200 m3
2,200,000.00
44,000.00
0.3500 lbr
plywood tebal 9 mm
124,583.33
43,604.17
3.0000 btg
9,500.00
28,500.00
4.0000 bh
formtie/penjaga jarak/spacer
55,000.00
220,000.00
0.3200 oh
pekerja
70,000.00
22,400.00
0.3300 oh
tukang kayu
75,000.00
24,750.00
0.0330 oh
kepala tukang
75,000.00
2,475.00
0.0060 oh
mandor
60,000.00
JUMLAH
360.00
397,237.50
49,985.00
447,222.50
G. 6.6.34
kayu terentang
2,200,000.00
66,000.00
0.4000 kg
15,583.33
6,233.33
0.1500 lt
minyak bekisting
12,000.00
1,800.00
0.0150 m3
2,200,000.00
33,000.00
0.3500 lbr
plywood tebal 9 mm
124,583.33
43,604.17
2.0000 btg
9,500.00
19,000.00
0.3200 oh
pekerja
55,000.00
17,600.00
0.3300 oh
tukang kayu
70,000.00
23,100.00
0.0330 oh
kepala tukang
75,000.00
2,475.00
0.0060 oh
mandor
75,000.00
JUMLAH
G. 6.6.35
Semen portland
1,300.00
504,400.00
0.6500 m3
Pasir beton
415,000.00
269,750.00
0.6500 m3
350,000.00
227,500.00
6.0000 oh
pekerja
55,000.00
330,000.00
1.0000 oh
tukang kayu
70,000.00
70,000.00
0.1000 oh
kepala tukang
75,000.00
7,500.00
0.3000 oh
mandor
75,000.00
22,500.00
JUMLAH
213,262.50
1,001,650.00
430,000.00
1,431,650.00
Semen portland
1,300.00
520,000.00
0.4000 m3
Pasir beton
415,000.00
166,000.00
0.8200 m3
350,000.00
287,000.00
6.0000 oh
pekerja
55,000.00
330,000.00
1.0000 oh
tukang kayu
70,000.00
70,000.00
0.1000 oh
kepala tukang
75,000.00
7,500.00
0.3000 oh
mandor
75,000.00
22,500.00
JUMLAH
G. 6.6.37
43,625.00
G. 6.6.36
450.00
169,637.50
973,000.00
430,000.00
1,403,000.00
kayu terentang
2,200,000.00
58,080.00
0.6000 kg
15,583.33
9,350.00
0.5000 btg
9,500.00
4,750.00
0.1500 oh
pekerja
55,000.00
8,250.00
0.0500 oh
tukang kayu
70,000.00
3,500.00
0.0050 oh
kepala tukang
75,000.00
375.00
0.0070 oh
mandor
75,000.00
JUMLAH
525.00
72,180.00
12,650.00
84,830.00
G. 6.6.38
kayu terentang
2,200,000.00
440,000.00
1.5000 kg
15,583.33
23,375.00
0.4000 lt
minyak bekisting
12,000.00
4,800.00
150.0000 kg
10,000.00
1,500,000.00
2.2500 kg
kawat beton
20,000.00
45,000.00
Semen portland
1,300.00
419,900.00
0.5200 m3
Pasir beton
415,000.00
215,800.00
0.7800 m3
350,000.00
273,000.00
3.9000 oh
pekerja
55,000.00
214,500.00
0.3500 oh
Tukang batu
70,000.00
24,500.00
1.0400 oh
tukang kayu
70,000.00
72,800.00
1.0500 oh
Tukang Besi
70,000.00
73,500.00
0.2450 oh
kepala tukang
75,000.00
18,375.00
0.1650 oh
mandor
75,000.00
323.0000 kg
JUMLAH
G. 6.6.39
12,375.00
2,921,875.00
416,050.00
3,337,925.00
kayu terentang
2,200,000.00
594,000.00
2.0000 kg
15,583.33
31,166.67
0.6000 lt
minyak bekisting
12,000.00
7,200.00
200.0000 kg
10,000.00
2,000,000.00
3.0000 kg
kawat beton
20,000.00
60,000.00
Semen portland
1,300.00
419,900.00
0.5200 m3
Pasir beton
415,000.00
215,800.00
0.7800 m3
350,000.00
273,000.00
4.8500 oh
pekerja
55,000.00
0.3500 oh
Tukang batu
70,000.00
24,500.00
1.5600 oh
tukang kayu
70,000.00
109,200.00
1.4000 oh
Tukang Besi
70,000.00
98,000.00
0.3310 oh
kepala tukang
75,000.00
24,825.00
0.1700 oh
mandor
75,000.00
323.0000 kg
JUMLAH
266,750.00
12,750.00
3,601,066.67
536,025.00
4,137,091.67
G. 6.6.40
kayu terentang
2,200,000.00
880,000.00
4.0000 kg
15,583.33
62,333.33
2.0000 lt
minyak bekisting
12,000.00
24,000.00
300.0000 kg
10,000.00
3,000,000.00
4.5000 kg
kawat beton
20,000.00
90,000.00
Semen portland
1,300.00
419,900.00
0.5200 m3
Pasir beton
415,000.00
215,800.00
0.7800 m3
350,000.00
273,000.00
0.1500 m3
2,200,000.00
330,000.00
3.5000 lbr
Plywood 9 mm
124,583.33
436,041.67
9,500.00
190,000.00
7.3000 oh
pekerja
55,000.00
0.3500 oh
Tukang batu
70,000.00
24,500.00
3.3000 oh
tukang kayu
70,000.00
231,000.00
2.1000 oh
Tukang Besi
70,000.00
147,000.00
0.5700 oh
kepala tukang
75,000.00
42,750.00
0.2500 oh
mandor
75,000.00
323.0000 kg
20.0000 Btg
JUMLAH
G. 6.6.41
401,500.00
18,750.00
5,921,075.00
865,500.00
6,786,575.00
kayu terentang
2,200,000.00
704,000.00
3.2000 kg
15,583.33
49,866.67
1.6000 lt
minyak bekisting
12,000.00
19,200.00
200.0000 kg
10,000.00
2,000,000.00
3.0000 kg
kawat beton
20,000.00
60,000.00
Semen portland
1,300.00
419,900.00
0.5200 m3
Pasir beton
415,000.00
215,800.00
0.7800 m3
350,000.00
273,000.00
0.1400 m3
2,200,000.00
308,000.00
2.8000 lbr
Plywood 9 mm
124,583.33
348,833.33
9,500.00
152,000.00
5.9600 oh
pekerja
55,000.00
0.3500 oh
Tukang batu
70,000.00
24,500.00
2.8000 oh
tukang kayu
70,000.00
196,000.00
1.4000 oh
Tukang Besi
70,000.00
98,000.00
0.4550 oh
kepala tukang
75,000.00
34,125.00
0.2080 oh
mandor
75,000.00
323.0000 kg
16.0000 Btg
JUMLAH
327,800.00
15,600.00
4,550,600.00
696,025.00
5,246,625.00
G. 6.6.42
kayu terentang
2,200,000.00
704,000.00
3.2000 kg
15,583.33
49,866.67
1.6000 lt
minyak bekisting
12,000.00
19,200.00
150.0000 kg
10,000.00
1,500,000.00
2.2500 kg
kawat beton
20,000.00
45,000.00
Semen portland
1,300.00
419,900.00
0.5200 m3
Pasir beton
415,000.00
215,800.00
0.7800 m3
350,000.00
273,000.00
0.1200 m3
2,200,000.00
264,000.00
2.8000 lbr
Plywood 9 mm
124,583.33
348,833.33
9,500.00
304,000.00
5.8000 oh
pekerja
55,000.00
0.3500 oh
Tukang batu
70,000.00
24,500.00
2.8000 oh
tukang kayu
70,000.00
196,000.00
1.0500 oh
Tukang Besi
70,000.00
73,500.00
0.4200 oh
kepala tukang
75,000.00
31,500.00
0.1850 oh
mandor
75,000.00
323.0000 kg
32.0000 Btg
JUMLAH
G. 6.6.43
319,000.00
13,875.00
4,143,600.00
658,375.00
4,801,975.00
kayu terentang
2,200,000.00
528,000.00
3.2000 kg
15,583.33
49,866.67
1.6000 lt
minyak bekisting
12,000.00
19,200.00
150.0000 kg
10,000.00
1,500,000.00
2.2500 kg
kawat beton
20,000.00
45,000.00
Semen portland
1,300.00
419,900.00
0.5200 m3
Pasir beton
415,000.00
215,800.00
0.7800 m3
350,000.00
273,000.00
0.1600 m3
2,200,000.00
352,000.00
2.8000 lbr
Plywood 9 mm
124,583.33
348,833.33
9,500.00
228,000.00
5.6000 oh
pekerja
55,000.00
0.3500 oh
Tukang batu
70,000.00
24,500.00
2.6400 oh
tukang kayu
70,000.00
184,800.00
1.0500 oh
Tukang Besi
70,000.00
73,500.00
0.4000 oh
kepala tukang
75,000.00
30,000.00
0.1930 oh
mandor
75,000.00
323.0000 kg
24.0000 Btg
JUMLAH
308,000.00
14,475.00
3,979,600.00
635,275.00
4,614,875.00
G. 6.6.44
kayu terentang
2,200,000.00
550,000.00
3.0000 kg
15,583.33
46,750.00
1.2000 lt
minyak bekisting
12,000.00
14,400.00
200.0000 kg
10,000.00
2,000,000.00
3.0000 kg
kawat beton
20,000.00
60,000.00
Semen portland
1,300.00
419,900.00
0.5200 m3
Pasir beton
415,000.00
215,800.00
0.7800 m3
350,000.00
273,000.00
0.1050 m3
2,200,000.00
231,000.00
2.5000 lbr
Plywood 9 mm
124,583.33
311,458.33
9,500.00
133,000.00
5.6000 oh
pekerja
55,000.00
0.3500 oh
Tukang batu
70,000.00
24,500.00
2.3000 oh
tukang kayu
70,000.00
161,000.00
1.4000 oh
Tukang Besi
70,000.00
98,000.00
0.4050 oh
kepala tukang
75,000.00
30,375.00
0.2020 oh
mandor
75,000.00
323.0000 kg
14.0000 Btg
JUMLAH
G. 6.6.45
308,000.00
15,150.00
4,255,308.33
637,025.00
4,892,333.33
kayu terentang
2,200,000.00
0.0100 kg
15,583.33
155.83
3.0000 kg
10,000.00
30,000.00
0.4500 kg
kawat beton
20,000.00
9,000.00
4.0000 kg
Semen portland
1,300.00
5,200.00
0.0060 m3
Pasir beton
415,000.00
2,490.00
0.0090 m3
350,000.00
3,150.00
0.0600 oh
pekerja
55,000.00
3,300.00
0.0200 oh
Tukang batu
70,000.00
1,400.00
0.0200 oh
tukang kayu
70,000.00
1,400.00
0.0200 oh
Tukang Besi
70,000.00
1,400.00
0.0060 oh
kepala tukang
75,000.00
450.00
0.0030 oh
mandor
75,000.00
JUMLAH
4,400.00
225.00
54,395.83
8,175.00
62,570.83
G. 6.6.46
2,200,000.00
0.0200 kg
15,583.33
311.67
3.6000 kg
10,000.00
36,000.00
0.0500 kg
kawat beton
20,000.00
1,000.00
5.5000 kg
Semen portland
1,300.00
7,150.00
0.0090 m3
Pasir beton
415,000.00
3,735.00
0.0150 m3
350,000.00
5,250.00
0.1000 oh
pekerja
55,000.00
5,500.00
0.0330 oh
Tukang batu
70,000.00
2,310.00
0.0330 oh
tukang kayu
70,000.00
2,310.00
0.0330 oh
Tukang Besi
70,000.00
2,310.00
0.0100 oh
kepala tukang
75,000.00
750.00
0.0050 oh
mandor
75,000.00
JUMLAH
6,600.00
375.00
60,046.67
13,555.00
73,601.67
genteng palentong
0.1500 oh
pekerja
55,000.00
8,250.00
0.0750 oh
tukang kayu
70,000.00
5,250.00
0.0080 oh
kepala tukang
75,000.00
600.00
0.0080 oh
mandor
75,000.00
JUMLAH
H. 6.6.2
genteng kodok
2,500.00
0.1500 oh
pekerja
55,000.00
8,250.00
0.0750 oh
tukang kayu
70,000.00
5,250.00
0.0080 oh
kepala tukang
75,000.00
600.00
0.0080 oh
mandor
75,000.00
JUMLAH
14,700.00
62,500.00
600.00
62,500.00
14,700.00
77,200.00
0.1500 oh
pekerja
55,000.00
8,250.00
0.0600 oh
tukang kayu
70,000.00
4,200.00
0.0060 oh
kepala tukang
75,000.00
450.00
0.0080 oh
mandor
75,000.00
JUMLAH
H. 6.6.4
14,700.00
H. 6.6.3
600.00
-
600.00
-
13,500.00
13,500.00
8.0000 kg
Semen Portland
1,300.00
10,400.00
0.0320 m3
Pasir pasang
278,750.00
8,920.00
0.4000 oh
pekerja
55,000.00
22,000.00
0.2000 oh
tukang kayu
70,000.00
14,000.00
0.0200 oh
kepala tukang
75,000.00
1,500.00
0.0020 oh
mandor
75,000.00
JUMLAH
150.00
19,320.00
37,650.00
56,970.00
H. 6.6.5
3,500.00
17,500.00
8.0000 kg
Semen Portland
1,300.00
10,400.00
0.0320 m3
Pasir pasang
278,750.00
8,920.00
0.4000 oh
pekerja
55,000.00
22,000.00
0.2000 oh
tukang kayu
70,000.00
14,000.00
0.0200 oh
kepala tukang
75,000.00
1,500.00
0.0020 oh
mandor
75,000.00
JUMLAH
H. 6.6.6
4.0000 bh
8.0000 kg
Semen Portland
1,300.00
10,400.00
0.0320 m3
Pasir pasang
278,750.00
8,920.00
0.4000 oh
pekerja
55,000.00
22,000.00
0.2000 oh
tukang kayu
70,000.00
14,000.00
0.0200 oh
kepala tukang
75,000.00
1,500.00
0.0020 oh
mandor
75,000.00
30,320.00
45,186.14
0.0500 kg
15,583.33
779.17
0.1400 oh
pekerja
55,000.00
7,700.00
0.0670 oh
tukang kayu
70,000.00
4,690.00
0.0070 oh
kepala tukang
75,000.00
525.00
0.0070 oh
mandor
75,000.00
525.00
591.25
10,825.00
11,416.25
asbes gelombang
27,333.33
13,666.67
0.1200 kg
15,583.33
1,870.00
0.1400 oh
pekerja
55,000.00
7,700.00
0.0750 oh
tukang kayu
70,000.00
5,250.00
0.0080 oh
kepala tukang
75,000.00
600.00
0.0080 oh
mandor
75,000.00
JUMLAH
H. 6.6.9
74,470.00
150.00
14,866.14
JUMLAH
H. 6.6.8
37,650.00
JUMLAH
H. 6.6.7
150.00
36,820.00
600.00
15,536.67
14,150.00
29,686.67
asbes gelombang
23,000.00
13,800.00
0.1200 kg
15,583.33
1,870.00
0.1400 oh
pekerja
55,000.00
7,700.00
0.0750 oh
tukang kayu
70,000.00
5,250.00
0.0080 oh
kepala tukang
75,000.00
600.00
0.0080 oh
mandor
75,000.00
JUMLAH
600.00
15,670.00
14,150.00
29,820.00
H. 6.6.10
asbes gelombang
23,000.00
13,800.00
0.1200 kg
15,583.33
1,870.00
0.1400 oh
pekerja
55,000.00
7,700.00
0.0750 oh
tukang kayu
70,000.00
5,250.00
0.0070 oh
kepala tukang
75,000.00
525.00
0.0070 oh
mandor
75,000.00
JUMLAH
H. 6.6.11
0.7500 lbr
asbes gelombang
23,000.00
17,250.00
0.1200 kg
15,583.33
1,870.00
0.1400 oh
pekerja
55,000.00
7,700.00
0.0750 oh
tukang kayu
70,000.00
5,250.00
0.0070 oh
kepala tukang
75,000.00
525.00
0.0070 oh
mandor
75,000.00
525.00
19,120.00
14,000.00
0.3500 lbr
asbes gelombang
23,000.00
8,050.00
0.1200 kg
15,583.33
1,870.00
0.1400 oh
pekerja
55,000.00
7,700.00
0.0750 oh
tukang kayu
70,000.00
5,250.00
0.0070 oh
kepala tukang
75,000.00
525.00
0.0070 oh
mandor
75,000.00
33,120.00
525.00
9,920.00
14,000.00
23,920.00
asbes gelombang
23,000.00
9,660.00
0.1200 kg
15,583.33
1,870.00
0.1400 oh
pekerja
55,000.00
7,700.00
0.0750 oh
tukang kayu
70,000.00
5,250.00
0.0070 oh
kepala tukang
75,000.00
525.00
0.0070 oh
mandor
75,000.00
JUMLAH
H. 6.6.14
29,670.00
JUMLAH
H. 6.6.13
14,000.00
JUMLAH
H. 6.6.12
525.00
15,670.00
525.00
11,530.00
14,000.00
25,530.00
asbes gelombang
23,000.00
10,120.00
0.1200 kg
15,583.33
1,870.00
0.1400 oh
pekerja
55,000.00
7,700.00
0.0670 oh
tukang kayu
70,000.00
4,690.00
0.0070 oh
kepala tukang
75,000.00
525.00
0.0070 oh
mandor
75,000.00
JUMLAH
525.00
11,990.00
13,440.00
25,430.00
H. 6.6.15
asbes gelombang
23,000.00
11,730.00
0.1200 kg
15,583.33
1,870.00
0.1400 oh
pekerja
55,000.00
7,700.00
0.0670 oh
tukang kayu
70,000.00
4,690.00
0.0070 oh
kepala tukang
75,000.00
525.00
0.0070 oh
mandor
75,000.00
JUMLAH
H. 6.6.16
0.8000 lbr
asbes gelombang
23,000.00
18,400.00
0.1200 kg
15,583.33
1,870.00
0.1400 oh
pekerja
55,000.00
7,700.00
0.0670 oh
tukang kayu
70,000.00
4,690.00
0.0070 oh
kepala tukang
75,000.00
525.00
0.0070 oh
mandor
75,000.00
525.00
20,270.00
13,440.00
0.3700 lbr
asbes gelombang
23,000.00
8,510.00
0.1200 kg
15,583.33
1,870.00
0.1400 oh
pekerja
55,000.00
7,700.00
0.0670 oh
tukang kayu
70,000.00
4,690.00
0.0070 oh
kepala tukang
75,000.00
525.00
0.0070 oh
mandor
75,000.00
33,710.00
525.00
10,380.00
13,440.00
23,820.00
asbes gelombang
23,000.00
8,740.00
0.1200 kg
15,583.33
1,870.00
0.1400 oh
pekerja
55,000.00
7,700.00
0.0670 oh
tukang kayu
70,000.00
4,690.00
0.0070 oh
kepala tukang
75,000.00
525.00
0.0070 oh
mandor
75,000.00
JUMLAH
H. 6.6.19
27,040.00
JUMLAH
H. 6.6.18
13,440.00
JUMLAH
H. 6.6.17
525.00
13,600.00
525.00
10,610.00
13,440.00
24,050.00
asbes gelombang
23,000.00
10,580.00
0.1200 kg
15,583.33
1,870.00
0.1400 oh
pekerja
55,000.00
7,700.00
0.0670 oh
tukang kayu
70,000.00
4,690.00
0.0070 oh
kepala tukang
75,000.00
525.00
0.0070 oh
mandor
75,000.00
JUMLAH
525.00
12,450.00
13,440.00
25,890.00
H. 6.6.20
asbes gelombang
23,000.00
11,270.00
0.1200 kg
15,583.33
1,870.00
0.1400 oh
pekerja
55,000.00
7,700.00
0.0670 oh
tukang kayu
70,000.00
4,690.00
0.0070 oh
kepala tukang
75,000.00
525.00
0.0070 oh
mandor
75,000.00
JUMLAH
H. 6.6.21
0.5700 lbr
asbes gelombang
23,000.00
13,110.00
0.1200 kg
15,583.33
1,870.00
0.1400 oh
pekerja
55,000.00
7,700.00
0.0670 oh
tukang kayu
70,000.00
4,690.00
0.0070 oh
kepala tukang
75,000.00
525.00
0.0070 oh
mandor
75,000.00
13,440.00
28,420.00
6.0000 bh
20,000.00
120,000.00
0.0840 oh
pekerja
55,000.00
4,620.00
0.1250 oh
tukang kayu
70,000.00
8,750.00
0.0130 oh
kepala tukang
75,000.00
975.00
0.0040 oh
mandor
75,000.00
300.00
120,000.00
14,645.00
134,645.00
6.0000 bh
20,000.00
120,000.00
0.0840 oh
pekerja
55,000.00
4,620.00
0.1250 oh
tukang kayu
70,000.00
8,750.00
0.0130 oh
kepala tukang
75,000.00
975.00
0.0040 oh
mandor
75,000.00
JUMLAH
H. 6.6.24
26,580.00
525.00
14,980.00
JUMLAH
H. 6.6.23
13,440.00
JUMLAH
H. 6.6.22
525.00
13,140.00
300.00
120,000.00
14,645.00
134,645.00
6.0000 bh
20,000.00
120,000.00
0.0840 oh
pekerja
55,000.00
4,620.00
0.1250 oh
tukang kayu
70,000.00
8,750.00
0.0130 oh
kepala tukang
75,000.00
975.00
0.0040 oh
mandor
75,000.00
JUMLAH
300.00
120,000.00
14,645.00
134,645.00
###
H. 6.6.25
nok paten
6.0000 bh
20,000.00
120,000.00
0.0840 oh
pekerja
55,000.00
4,620.00
0.1250 oh
tukang kayu
70,000.00
8,750.00
0.0130 oh
kepala tukang
75,000.00
975.00
0.0040 oh
mandor
75,000.00
JUMLAH
H. 6.6.26
1.2000 lbr
nok paten
6.0000 bh
20,000.00
120,000.00
0.0840 oh
pekerja
55,000.00
4,620.00
0.1250 oh
tukang kayu
70,000.00
8,750.00
0.0130 oh
kepala tukang
75,000.00
975.00
0.0040 oh
mandor
75,000.00
14,645.00
134,645.00
nok paten
6.0000 bh
20,000.00
120,000.00
0.0840 oh
pekerja
55,000.00
4,620.00
0.1250 oh
tukang kayu
70,000.00
8,750.00
0.0130 oh
kepala tukang
75,000.00
975.00
0.0040 oh
mandor
75,000.00
300.00
120,000.00
14,645.00
134,645.00
6.0000 bh
20,000.00
120,000.00
0.1000 oh
pekerja
55,000.00
5,500.00
0.1500 oh
tukang kayu
70,000.00
10,500.00
0.0130 oh
kepala tukang
75,000.00
975.00
0.0040 oh
mandor
75,000.00
JUMLAH
H. 6.6.29
134,645.00
300.00
120,000.00
JUMLAH
H. 6.6.28
14,645.00
JUMLAH
H. 6.6.27
300.00
120,000.00
300.00
120,000.00
17,275.00
137,275.00
6.0000 bh
20,000.00
120,000.00
0.1000 oh
pekerja
55,000.00
5,500.00
0.1500 oh
tukang kayu
70,000.00
10,500.00
0.0130 oh
kepala tukang
75,000.00
975.00
0.0040 oh
mandor
75,000.00
JUMLAH
300.00
120,000.00
17,275.00
137,275.00
H. 6.6.30
genteng beton
3,500.00
38,500.00
0.0300 kg
15,583.33
467.50
0.2000 oh
pekerja
55,000.00
11,000.00
0.1000 oh
tukang kayu
70,000.00
7,000.00
0.0100 oh
kepala tukang
75,000.00
750.00
0.0100 oh
mandor
75,000.00
JUMLAH
H. 6.6.31
6.9000 lbr
genteng aspal
2,500.00
17,250.00
0.3500 lbr
80,000.00
28,000.00
0.0300 kg
15,583.33
467.50
0.5000 bh
Plastic aerator
1,200.00
600.00
0.2000 oh
pekerja
55,000.00
11,000.00
0.3000 oh
tukang kayu
70,000.00
21,000.00
0.0030 oh
kepala tukang
75,000.00
225.00
0.0100 oh
mandor
75,000.00
750.00
46,317.50
32,975.00
1.4200 lbr
genteng metal
40,000.00
56,800.00
0.2000 kg
28,500.00
5,700.00
0.2000 oh
pekerja
55,000.00
11,000.00
0.1000 oh
tukang kayu
70,000.00
7,000.00
0.0100 oh
kepala tukang
75,000.00
750.00
0.0010 oh
mandor
75,000.00
79,292.50
75.00
62,500.00
18,825.00
81,325.00
genteng sirap
1,500.00
90,000.00
0.2000 kg
15,583.33
3,116.67
0.1660 oh
pekerja
55,000.00
9,130.00
0.2500 oh
tukang kayu
70,000.00
17,500.00
0.0250 oh
kepala tukang
75,000.00
1,875.00
0.0080 oh
mandor
75,000.00
JUMLAH
H. 6.6.34
58,467.50
JUMLAH
H. 6.6.33
19,500.00
JUMLAH
H. 6.6.32
750.00
38,967.50
600.00
93,116.67
29,105.00
122,221.67
5,000.00
0.0500 kg
Paku pancing
30,250.00
1,512.50
1,300.00
14,040.00
0.0320 m3
Pasir pasang
278,750.00
8,920.00
1.0000 kg
Semen warna
9,833.33
9,833.33
0.4000 oh
pekerja
55,000.00
22,000.00
0.2000 oh
tukang kayu
70,000.00
14,000.00
0.0200 oh
kepala tukang
75,000.00
1,500.00
0.0200 oh
mandor
75,000.00
10.8000 kg
JUMLAH
17,500.00
1,500.00
51,805.83
39,000.00
90,805.83
H. 6.6.35
genteng aspal
2,500.00
5,000.00
0.0500 kg
paku seng
24,666.67
1,233.33
0.0035 m3
2,200,000.00
7,700.00
0.1250 oh
pekerja
55,000.00
6,875.00
0.2500 oh
tukang kayu
70,000.00
17,500.00
0.0250 oh
kepala tukang
75,000.00
1,875.00
0.0060 oh
mandor
75,000.00
JUMLAH
H. 6.6.36
1.1000 bh
0.0500 kg
15,583.33
779.17
0.2500 oh
pekerja
55,000.00
13,750.00
0.1500 oh
tukang kayu
70,000.00
10,500.00
0.0150 oh
kepala tukang
75,000.00
1,125.00
0.0130 oh
mandor
75,000.00
975.00
779.17
26,350.00
0.4000 lbr
seng plat
45,833.33
18,333.33
0.1100 kg
paku seng
24,666.67
2,713.33
0.0040 oh
2,300,000.00
9,200.00
0.1250 oh
pekerja
55,000.00
6,875.00
0.2500 oh
tukang kayu
70,000.00
17,500.00
0.0250 oh
kepala tukang
75,000.00
1,875.00
0.0060 oh
mandor
75,000.00
27,129.17
450.00
30,246.67
26,700.00
56,946.67
39,125.00
27,387.50
0.0200 kg
paku seng
24,666.67
493.33
0.1200 oh
pekerja
55,000.00
6,600.00
0.0600 oh
tukang kayu
70,000.00
4,200.00
0.0060 oh
kepala tukang
75,000.00
450.00
0.0060 oh
mandor
75,000.00
JUMLAH
H. 6.6.39
40,633.33
JUMLAH
H. 6.6.38
26,700.00
JUMLAH
H. 6.6.37
450.00
13,933.33
450.00
27,880.83
11,700.00
39,580.83
seng plat
45,833.33
50,416.67
0.0500 kg
paku seng
24,666.67
1,233.33
0.1500 oh
pekerja
55,000.00
8,250.00
0.2500 oh
tukang kayu
70,000.00
17,500.00
0.0150 oh
kepala tukang
75,000.00
1,125.00
0.0130 oh
mandor
75,000.00
JUMLAH
975.00
51,650.00
27,850.00
79,500.00
H. 6.6.40
0.0200 kg
24,666.67
493.33
0.1500 oh
pekerja
55,000.00
8,250.00
0.7500 oh
tukang kayu
70,000.00
52,500.00
0.0080 oh
kepala tukang
75,000.00
600.00
0.0060 oh
mandor
75,000.00
JUMLAH
H. 6.6.41
61,800.00
62,293.33
0.0400 kg
24,666.67
986.67
0.1000 oh
pekerja
55,000.00
5,500.00
1.0000 oh
tukang kayu
70,000.00
70,000.00
0.0100 oh
kepala tukang
75,000.00
750.00
0.0100 oh
mandor
75,000.00
JUMLAH
H. 6.6.42
450.00
493.33
750.00
986.67
77,000.00
77,986.67
450,000.00
0.1500 oh
pekerja
55,000.00
8,250.00
0.0500 oh
tukang kayu
70,000.00
3,500.00
0.0050 oh
kepala tukang
75,000.00
375.00
0.0080 oh
mandor
75,000.00
JUMLAH
472,500.00
600.00
472,500.00
12,725.00
485,225.00
I. PEKERJAAN PLAFOND
I. 6.6.1
29,400.00
32,340.00
0.0100 kg
paku plywood
23,750.00
237.50
0.0300 oh
pekerja
55,000.00
1,650.00
0.0700 oh
tukang kayu
70,000.00
4,900.00
0.0070 oh
kepala tukang
75,000.00
525.00
0.0015 oh
mandor
75,000.00
JUMLAH
I. 6.6.2
112.50
32,577.50
7,187.50
39,765.00
29,400.00
32,340.00
0.0100 kg
paku plywood
23,750.00
237.50
0.0300 oh
pekerja
55,000.00
1,650.00
0.0700 oh
tukang kayu
70,000.00
4,900.00
0.0070 oh
kepala tukang
75,000.00
525.00
0.0015 oh
mandor
75,000.00
JUMLAH
112.50
32,577.50
7,187.50
39,765.00
I. 6.6.3
75,000.00
82,500.00
0.0100 kg
paku plywood
23,750.00
237.50
0.0300 oh
pekerja
55,000.00
1,650.00
0.0700 oh
tukang kayu
70,000.00
4,900.00
0.0070 oh
kepala tukang
75,000.00
525.00
0.0015 oh
mandor
75,000.00
JUMLAH
I. 6.6.4
1.1000 lbr
75,000.00
82,500.00
0.0100 kg
paku plywood
23,750.00
237.50
0.0300 oh
pekerja
55,000.00
1,650.00
0.0700 oh
tukang kayu
70,000.00
4,900.00
0.0070 oh
kepala tukang
75,000.00
525.00
0.0015 oh
mandor
75,000.00
112.50
82,737.50
7,187.50
akustik ukuran 30 x 30 cm
0.0500 kg
paku plywood
23,750.00
89,925.00
0.0600 oh
pekerja
55,000.00
3,300.00
0.1200 oh
tukang kayu
70,000.00
8,400.00
0.1200 oh
kepala tukang
75,000.00
9,000.00
0.0030 oh
mandor
75,000.00
JUMLAH
1,187.50
225.00
1,187.50
20,925.00
22,112.50
akustik ukuran 30 x 60 cm
0.0500 kg
paku plywood
23,750.00
0.0600 oh
pekerja
55,000.00
3,300.00
0.1000 oh
tukang kayu
70,000.00
7,000.00
0.0100 oh
kepala tukang
75,000.00
750.00
0.0030 oh
mandor
75,000.00
JUMLAH
I. 6.6.7
89,925.00
I. 6.6.6
7,187.50
JUMLAH
I. 6.6.5
112.50
82,737.50
1,187.50
225.00
1,187.50
11,275.00
12,462.50
0.0500 kg
paku plywood
23,750.00
0.0600 oh
pekerja
55,000.00
3,300.00
0.1000 oh
tukang kayu
70,000.00
7,000.00
0.0100 oh
kepala tukang
75,000.00
750.00
0.0030 oh
mandor
75,000.00
JUMLAH
1,187.50
225.00
1,187.50
11,275.00
12,462.50
I. 6.6.8
Plywood 4mm
55,000.00
19,800.00
0.0300 kg
paku plywood
23,750.00
712.50
0.0700 oh
pekerja
55,000.00
3,850.00
0.1000 oh
tukang kayu
70,000.00
7,000.00
0.0100 oh
kepala tukang
75,000.00
750.00
0.0035 oh
mandor
75,000.00
JUMLAH
I. 6.6.9
0.3600 lbr
Plywood 6mm
124,583.33
44,850.00
0.0300 kg
paku plywood
23,750.00
712.50
0.0700 oh
pekerja
55,000.00
3,850.00
0.1000 oh
tukang kayu
70,000.00
7,000.00
0.0100 oh
kepala tukang
75,000.00
750.00
0.0035 oh
mandor
75,000.00
262.50
45,562.50
11,862.50
0.3750 lbr
Plywood 2mm
44,375.00
16,640.63
0.0300 kg
paku plywood
23,750.00
712.50
0.0700 oh
pekerja
55,000.00
3,850.00
0.1000 oh
tukang kayu
70,000.00
7,000.00
0.0100 oh
kepala tukang
75,000.00
750.00
0.0035 oh
mandor
75,000.00
57,425.00
262.50
17,353.13
11,862.50
29,215.63
Plywood 6mm
80,000.00
30,000.00
0.0300 kg
paku plywood
23,750.00
712.50
0.0700 oh
pekerja
55,000.00
3,850.00
0.1000 oh
tukang kayu
70,000.00
7,000.00
0.0100 oh
kepala tukang
75,000.00
750.00
0.0035 oh
mandor
75,000.00
JUMLAH
I. 6.6.12
32,375.00
JUMLAH
I. 6.6.11
11,862.50
JUMLAH
I. 6.6.10
262.50
20,512.50
262.50
30,712.50
11,862.50
42,575.00
Teakwood 4 mm
99,300.00
35,748.00
0.0300 kg
paku plywood
23,750.00
712.50
0.0700 oh
pekerja
55,000.00
3,850.00
0.1000 oh
tukang kayu
70,000.00
7,000.00
0.0100 oh
kepala tukang
75,000.00
750.00
0.0035 oh
mandor
75,000.00
JUMLAH
262.50
36,460.50
11,862.50
48,323.00
I. 6.6.13
Teakwood 4 mm
120,200.00
45,075.00
0.0300 kg
paku plywood
23,750.00
712.50
0.0700 oh
pekerja
55,000.00
3,850.00
0.1000 oh
tukang kayu
70,000.00
7,000.00
0.0100 oh
kepala tukang
75,000.00
750.00
0.0035 oh
mandor
75,000.00
JUMLAH
I. 6.6.14
0.0240 lbr
7,000,000.00
0.0100 Kg
paku biasa
15,583.33
155.83
0.0500 kg
paku sekrup
20,000.00
1,000.00
0.2000 oh
pekerja
55,000.00
11,000.00
0.2000 oh
tukang kayu
70,000.00
14,000.00
0.0600 oh
kepala tukang
75,000.00
4,500.00
0.0100 oh
mandor
75,000.00
168,000.00
750.00
169,155.83
30,250.00
0.0240 lbr
2,300,000.00
0.0100 Kg
paku biasa
15,583.33
155.83
0.0500 kg
paku sekrup
20,000.00
1,000.00
0.2000 oh
pekerja
55,000.00
11,000.00
0.2000 oh
tukang kayu
70,000.00
14,000.00
0.0600 oh
kepala tukang
75,000.00
4,500.00
0.0100 oh
mandor
75,000.00
199,405.83
55,200.00
750.00
56,355.83
30,250.00
86,605.83
6,000,000.00
0.0100 Kg
paku biasa
15,583.33
155.83
0.0500 kg
paku sekrup
20,000.00
1,000.00
0.2000 oh
pekerja
55,000.00
11,000.00
0.2000 oh
tukang kayu
70,000.00
14,000.00
0.0600 oh
kepala tukang
75,000.00
4,500.00
0.0100 oh
mandor
75,000.00
JUMLAH
I. 6.6.17
57,650.00
JUMLAH
I. 6.6.16
11,862.50
JUMLAH
I. 6.6.15
262.50
45,787.50
144,000.00
750.00
145,155.83
30,250.00
175,405.83
0.0300 Kg
paku biasa
15,583.33
0.6000 oh
pekerja
55,000.00
33,000.00
0.1000 oh
tukang kayu
70,000.00
7,000.00
0.0100 oh
kepala tukang
75,000.00
750.00
0.0030 oh
mandor
75,000.00
JUMLAH
467.50
225.00
467.50
40,975.00
41,442.50
I. 6.6.18
Profil alumunium T
0.1500 kg
1.0000 bh
1.5000 lbr
0.1500 oh
pekerja
55,000.00
8,250.00
0.5000 oh
tukang kayu
70,000.00
35,000.00
0.0500 oh
kepala tukang
75,000.00
3,750.00
0.0075 oh
mandor
75,000.00
JUMLAH
I. 6.6.19
I. 6.6.20
I. 6.6.22
562.50
-
47,562.50
47,562.50
10,300.00
11,330.00
0.0100 Kg
paku biasa
15,583.33
155.83
0.0500 oh
pekerja
55,000.00
2,750.00
0.0500 oh
tukang kayu
70,000.00
3,500.00
0.0050 oh
kepala tukang
75,000.00
375.00
0.0030 oh
mandor
75,000.00
225.00
JUMLAH
11,485.83
26,400.00
6,850.00
18,335.83
kayu meranti
2,200,000.00
0.0600 Kg
paku biasa
15,583.33
935.00
1.1000 lbr
75,000.00
82,500.00
0.1800 oh
pekerja
55,000.00
9,900.00
0.3200 oh
tukang kayu
70,000.00
22,400.00
0.0320 oh
kepala tukang
75,000.00
2,400.00
0.0090 oh
mandor
75,000.00
JUMLAH
I. 6.6.21
675.00
109,835.00
35,375.00
145,210.00
kayu meranti
2,300,000.00
0.0600 kg
paku biasa
15,583.33
52,900.00
935.00
0.3900 lbr
55,000.00
21,450.00
0.2700 oh
pekerja
55,000.00
14,850.00
0.4000 oh
tukang kayu
70,000.00
28,000.00
0.0400 oh
kepala tukang
75,000.00
3,000.00
0.0135 oh
mandor
75,000.00
1,012.50
JUMLAH
75,285.00
46,862.50
122,147.50
kayu meranti
2,300,000.00
52,900.00
0.0600 kg
paku biasa
15,583.33
935.00
5.8000 bh
akustik 30 x 60 cm
0.2600 oh
pekerja
55,000.00
14,300.00
0.4000 oh
tukang kayu
70,000.00
28,000.00
0.0400 oh
kepala tukang
75,000.00
3,000.00
0.0130 oh
mandor
75,000.00
JUMLAH
975.00
53,835.00
46,275.00
100,110.00
I. 6.6.23
2,200,000.00
59,400.00
0.0600 kg
paku
15,583.33
935.00
akustik 30 x30 cm
0.3100 oh
pekerja
55,000.00
17,050.00
0.4700 oh
tukang kayu
70,000.00
32,900.00
0.0470 oh
kepala tukang
75,000.00
3,525.00
0.0155 oh
mandor
75,000.00
11.5000 bh
JUMLAH
I. 6.6.24
1,162.50
60,335.00
54,637.50
114,972.50
65,000.00
23,660.00
0.1100 kg
paku sekrup
20,000.00
2,200.00
0.1000 oh
pekerja
55,000.00
5,500.00
0.0500 oh
tukang kayu
70,000.00
3,500.00
0.0050 oh
kepala tukang
75,000.00
375.00
0.0050 oh
mandor
75,000.00
JUMLAH
375.00
25,860.00
9,750.00
35,610.00
J. PEKERJAAN SANITAIR
J. 6.6.1
1,575,000.00
1,575,000.00
6.0000 %
94,500.00
94,500.00
3.3000 oh
pekerja
55,000.00
181,500.00
1.1000 oh
tukang kayu
70,000.00
77,000.00
0.0010 oh
kepala tukang
75,000.00
75.00
0.1600 oh
mandor
75,000.00
12,000.00
JUMLAH
J. 6.6.2
270,575.00
1,940,075.00
132,083.33
132,083.33
6.0000 kg
semen portland
1,300.00
7,800.00
0.0100 m3
pasir pasang
278,750.00
2,787.50
1.0000 oh
pekerja
55,000.00
55,000.00
1.5000 oh
tukang kayu
70,000.00
105,000.00
1.5000 oh
kepala tukang
75,000.00
112,500.00
0.1600 oh
mandor
75,000.00
JUMLAH
J. 6.6.3
1,669,500.00
12,000.00
142,670.83
284,500.00
427,170.83
98,333.33
98,333.33
7.0000 bh
Bata Merah
800.00
5,600.00
6.0000 Kg
semen portland
1,300.00
7,800.00
0.0100 m3
pasir pasang
278,750.00
2,787.50
1.0000 oh
Pekerja
55,000.00
55,000.00
1.5000 oh
Tukang Batu
70,000.00
105,000.00
0.3000 oh
kepala tukang
75,000.00
22,500.00
0.1100 oh
mandor
75,000.00
JUMLAH
8,250.00
114,520.83
190,750.00
305,270.83
Hal : 467
J. 6.6.4
MEMASANG 1 BH URINOIR
1.0000 bh
urinoir
1,865,500.00
1,865,500.00
Perlengkapan
559,650.00
559,650.00
6.0000 Kg
Semen Portland
1,300.00
7,800.00
0.0100 m3
Pasir Pasang
278,750.00
2,787.50
1.0000 oh
pekerja
55,000.00
55,000.00
1.0000 oh
Tukang Batu
70,000.00
70,000.00
0.1000 oh
kepala tukang
75,000.00
7,500.00
0.1000 oh
mandor
75,000.00
30.0000 %
J. 6.6.5
MEMASANG 1 BH WASTAFEL
1.0000 bh
1,865,500.00
1,865,500.00
Perlengkapan
559,650.00
559,650.00
6.0000 Kg
Semen Portland
1,300.00
7,800.00
0.0100 m3
pasir pasang
278,750.00
2,787.50
1.2000 oh
pekerja
55,000.00
66,000.00
1.4500 oh
Tukang Batu
70,000.00
101,500.00
0.1500 oh
kepala tukang
75,000.00
11,250.00
0.1000 oh
mandor
75,000.00
Bak Teraso
185,000.00
185,000.00
6.0000 Kg
semen portland
1,300.00
7,800.00
0.0100 m3
pasir pasang
278,750.00
2,787.50
2.1000 oh
pekerja
55,000.00
115,500.00
0.7500 oh
Tukang Batu
70,000.00
52,500.00
0.0700 oh
kepala tukang
75,000.00
5,250.00
0.1100 oh
mandor
75,000.00
2,621,987.50
8,250.00
195,587.50
181,500.00
377,087.50
Bak Fiberglass
160,000.00
160,000.00
Perlengkapan
28,800.00
28,800.00
1.8000 oh
pekerja
55,000.00
99,000.00
2.7000 oh
Tukang Batu
70,000.00
189,000.00
0.5400 oh
kepala tukang
75,000.00
40,500.00
0.1100 oh
mandor
75,000.00
JUMLAH
0.012
186,250.00
1.0000 bh
18.0000 %
2.4000
7,500.00
2,435,737.50
JUMLAH
J. 6.6.8
2,575,737.50
JUMLAH
J. 6.6.7
140,000.00
Wastafel
12.0000 %
J. 6.6.6
7,500.00
2,435,737.50
8,250.00
188,800.00
336,750.00
525,550.00
batu bata
800.00
320.00
semen portland
1,300.00
156,000.00
pasir pasang
278,750.00
83,625.00
Porselen ( 11x11)cm
2,500.00
900,000.00
6.0000 kg
Semen nat
12,000.00
72,000.00
6.0000 oh
pekerja
55,000.00
330,000.00
3.0000 oh
tukang batu
70,000.00
210,000.00
0.3000 oh
kepala tukang
75,000.00
22,500.00
0.3000 oh
mandor
75,000.00
120.0000 kg
0.3000 m3
360.0000 Bh
JUMLAH
22,500.00
1,211,945.00
585,000.00
1,796,945.00
J. 6.6.9
Badkip
6.0000 %
Perlengkapan
pekerja
55,000.00
0.0750 oh
Tukang Batu
70,000.00
5,250.00
0.7500 oh
kepala tukang
75,000.00
56,250.00
0.2500 oh
mandor
75,000.00
oh
JUMLAH
J. 6.6.9
Badkip
6.0000 %
Perlengkapan
pekerja
55,000.00
0.0750 oh
Tukang Batu
70,000.00
5,250.00
0.7500 oh
kepala tukang
75,000.00
56,250.00
0.2500 oh
mandor
75,000.00
80,250.00
oh
18,750.00
-
80,250.00
80,250.00
Badkip
6.0000 %
Perlengkapan
pekerja
55,000.00
0.0750 oh
Tukang Batu
70,000.00
5,250.00
0.7500 oh
kepala tukang
75,000.00
56,250.00
0.2500 oh
mandor
75,000.00
oh
JUMLAH
18,750.00
-
80,250.00
80,250.00
1,132,125.00
Besi Beton
10,000.00
1,800,000.00
8.0000 m3
kayu cetakan
1,750,000.00
14,000,000.00
5.0000 m2
Ubin Porselen
70,000.00
350,000.00
Perlengkapan
7,000.00
70,000.00
3.5000 oh
pekerja
55,000.00
192,500.00
4.5000 oh
Tukang Batu
70,000.00
315,000.00
0.9000 oh
kepala tukang
75,000.00
67,500.00
0.9000 oh
mandor
75,000.00
180.0000 kg
10.0000 %
JUMLAH
J. 6.6.11
80,250.00
1.0000 bh
JUMLAH
J. 6.6.10
18,750.00
-
J. 6.6.9
1,018,912.50
67,500.00
17,238,912.50
642,500.00
17,881,412.50
Bak Fiberglass
450,000.00
450,000.00
Perlengkapan
54,000.00
54,000.00
3.0000 oh
pekerja
55,000.00
165,000.00
4.5000 oh
Tukang Batu
70,000.00
315,000.00
0.9000 oh
kepala tukang
75,000.00
67,500.00
0.9000 oh
mandor
75,000.00
12.0000 %
JUMLAH
67,500.00
504,000.00
615,000.00
1,119,000.00
J. 6.6.12
MEMASANG 1M' PIPA PENYALUR AIR LIMBAH JENIS PIPA TANAH, DIA.15 CM
1.6000 bh
Pipa tanah
0.6800 kg
Semen Portland
1,300.00
884.00
0.0130 m3
pasir pasang
278,750.00
3,623.75
0.0110 m3
pasir urug
51,900.00
570.90
0.0600 oh
pekerja
55,000.00
3,300.00
0.0300 oh
Tukang Batu
70,000.00
2,100.00
0.0030 oh
kepala tukang
75,000.00
225.00
0.0025 oh
mandor
75,000.00
JUMLAH
J. 6.6.13
1.6000 bh
Pipa tanah
0.8700 kg
Semen Portland
1,300.00
1,131.00
10,891.15
0.0140 m3
pasir pasang
278,750.00
3,902.50
0.0140 m3
pasir urug
51,900.00
726.60
0.0800 oh
pekerja
55,000.00
4,400.00
0.0400 oh
Tukang Batu
70,000.00
2,800.00
0.0040 oh
kepala tukang
75,000.00
300.00
0.0070 oh
mandor
75,000.00
525.00
5,760.10
8,025.00
13,785.10
pipa beton
0.0270 m3
Batu bata
3.9200 kg
Semen Portland
1,300.00
5,096.00
0.0560 m3
pasir pasang
278,750.00
15,610.00
0.0240 m3
pasir urug
51,900.00
1,245.60
0.1400 oh
pekerja
55,000.00
7,700.00
0.0700 oh
Tukang Batu
70,000.00
4,900.00
0.0070 oh
kepala tukang
75,000.00
525.00
0.0070 oh
mandor
75,000.00
800.00
JUMLAH
J. 6.6.15
5,812.50
MEMASANG 1M' PIPA PENYALUR AIR LIMBAH JENIS PIPA TANAH, DIA.20 CM
JUMLAH
J. 6.6.14
187.50
5,078.65
21.60
525.00
21,973.20
13,650.00
35,623.20
pipa beton
0.5500 m3
Batu bata
10.3000 kg
800.00
440.00
Semen Portland
1,300.00
13,390.00
0.0610 m3
pasir pasang
278,750.00
17,003.75
0.0690 m3
pasir urug
51,900.00
3,581.10
0.3800 oh
pekerja
55,000.00
20,900.00
0.1900 oh
Tukang Batu
70,000.00
13,300.00
0.0190 oh
kepala tukang
75,000.00
1,425.00
0.0190 oh
mandor
75,000.00
JUMLAH
1,425.00
34,414.85
37,050.00
71,464.85
J. 6.6.16
MEMASANG 1BH BAK KONTROL PAS. BATU BATA UKURAN (30X30)CM TINGGI 35 CM
0.1450 bh
Batu bata
800.00
116.00
Semen Portland
1,300.00
57,200.00
0.0700 kg
pasir pasang
278,750.00
19,512.50
0.0700 m3
Batu kerikil
263,000.00
18,410.00
1.6000 kg
Besi Beton
10,000.00
16,000.00
0.0600 m3
Pasir Beton
250,000.00
15,000.00
3.2000 oh
pekerja
55,000.00
176,000.00
1.0150 oh
Tukang Batu
70,000.00
71,050.00
0.0015 oh
kepala tukang
75,000.00
112.50
0.0160 oh
mandor
75,000.00
1,200.00
44.0000 m3
JUMLAH
J. 6.6.17
0.2500 bh
800.00
200.00
Semen Portland
1,300.00
100,100.00
0.1300 kg
pasir pasang
278,750.00
36,237.50
0.0200 m3
Batu kerikil
263,000.00
5,260.00
2.6000 kg
Besi Beton
10,000.00
26,000.00
0.0900 m3
Pasir Beton
250,000.00
22,500.00
1.4200 oh
pekerja
55,000.00
78,100.00
0.4730 oh
Tukang Batu
70,000.00
26,015.00
0.0470 oh
kepala tukang
75,000.00
2,820.00
0.0710 oh
mandor
75,000.00
JUMLAH
374,601.00
4,260.00
190,297.50
111,195.00
301,492.50
MEMASANG 1BH BAK KONTROL PAS. BATU BATA UKURAN (60 x 60)CM TINGGI 65 CM
0.3710 bh
Batu bata
800.00
296.80
Semen Portland
1,300.00
148,200.00
0.1840 kg
pasir pasang
278,750.00
51,290.00
0.0330 m3
Batu koral
263,000.00
8,679.00
4.8500 kg
Besi Beton
10,000.00
48,500.00
0.1200 m3
Pasir Beton
250,000.00
30,000.00
2.1600 oh
pekerja
55,000.00
118,800.00
0.7200 oh
Tukang Batu
70,000.00
50,400.00
0.0720 oh
kepala tukang
75,000.00
5,400.00
0.1080 oh
mandor
75,000.00
8,100.00
0.1000 oh
Tukang gali
55,000.00
114.0000 m3
JUMLAH
J. 6.6.19
263,362.50
Batu bata
77.0000 m3
J. 6.6.18
111,238.50
MEMASANG 1BH BAK KONTROL PAS. BATU BATA UKURAN (45X45)CM TINGGI 50 CM
5,500.00
286,965.80
188,200.00
475,165.80
Pipa galvanis
52,100.00
62,520.00
Perlengkapan
18,235.00
18,235.00
0.0540 oh
pekerja
55,000.00
2,970.00
0.0900 oh
Tukang Batu
70,000.00
6,300.00
0.0090 oh
kepala tukang
75,000.00
675.00
0.0270 oh
mandor
75,000.00
2,025.00
35.0000 %
JUMLAH
80,755.00
11,970.00
92,725.00
J. 6.6.20
Pipa galvanis
52,100.00
62,520.00
Perlengkapan
3,937.50
3,937.50
0.0540 oh
pekerja
55,000.00
2,970.00
0.0900 oh
Tukang Batu
70,000.00
6,300.00
0.0090 oh
kepala tukang
75,000.00
675.00
0.0270 oh
mandor
75,000.00
2,025.00
35.0000 %
JUMLAH
J. 6.6.21
1.2000 m'
52,100.00
62,520.00
Perlengkapan
18,235.00
18,235.00
0.0540 oh
pekerja
55,000.00
2,970.00
0.0900 oh
Tukang Batu
70,000.00
6,300.00
0.0090 oh
kepala tukang
75,000.00
675.00
0.0270 oh
mandor
75,000.00
2,025.00
JUMLAH
1.2000 m'
80,755.00
11,970.00
Pipa galvanis
103,100.00
123,720.00
Perlengkapan
7,875.00
7,875.00
0.1080 oh
pekerja
55,000.00
5,940.00
0.1800 oh
Tukang Batu
70,000.00
12,600.00
0.0180 oh
kepala tukang
75,000.00
1,350.00
0.0054 oh
mandor
75,000.00
JUMLAH
92,725.00
405.00
131,595.00
20,295.00
151,890.00
Pipa galvanis
182,150.00
218,580.00
Perlengkapan
63,752.50
63,752.50
0.1080 oh
pekerja
55,000.00
5,940.00
0.1800 oh
Tukang Batu
70,000.00
12,600.00
0.0180 oh
kepala tukang
75,000.00
1,350.00
0.0054 oh
mandor
75,000.00
35.0000 %
JUMLAH
J. 6.6.24
160,852.50
J. 6.6.23
9,540.00
Pipa galvanis
35.0000 %
J. 6.6.22
151,312.50
405.00
282,332.50
16,164.00
298,496.50
Pipa galvanis
259,300.00
311,160.00
Perlengkapan
90,755.00
90,755.00
0.1350 oh
pekerja
55,000.00
7,425.00
0.2250 oh
Tukang Batu
70,000.00
15,750.00
0.0225 oh
kepala tukang
75,000.00
1,687.50
0.0068 oh
mandor
75,000.00
35.0000 %
JUMLAH
510.00
401,915.00
25,372.50
427,287.50
J. 6.6.25
Pipa PVC
19,416.67
23,300.00
Perlengkapan
6,795.83
6,795.83
0.0360 oh
pekerja
55,000.00
1,980.00
0.0600 oh
Tukang Batu
70,000.00
4,200.00
0.0060 oh
kepala tukang
75,000.00
450.00
0.0018 oh
mandor
75,000.00
35.0000 %
JUMLAH
J. 6.6.26
1.2000 m'
Pipa PVC
5,208.33
6,250.00
Perlengkapan
1,822.92
1,822.92
0.0360 oh
pekerja
55,000.00
1,980.00
0.0600 oh
Tukang Batu
70,000.00
4,200.00
0.0060 oh
kepala tukang
75,000.00
450.00
0.0018 oh
mandor
75,000.00
JUMLAH
1.2000 m'
135.00
8,072.92
6,765.00
Pipa PVC
6,520.83
7,825.00
Perlengkapan
2,282.29
2,282.29
0.0360 oh
pekerja
55,000.00
1,980.00
0.0600 oh
Tukang Batu
70,000.00
4,200.00
0.0060 oh
kepala tukang
75,000.00
450.00
0.0018 oh
mandor
75,000.00
JUMLAH
14,837.92
135.00
10,107.29
6,765.00
16,872.29
Pipa PVC
12,458.33
14,950.00
Perlengkapan
4,360.42
4,360.42
0.0360 oh
pekerja
55,000.00
1,980.00
0.0600 oh
Tukang Batu
70,000.00
4,200.00
0.0060 oh
kepala tukang
75,000.00
450.00
0.0018 oh
mandor
75,000.00
35.0000 %
JUMLAH
J. 6.6.29
36,860.83
J. 6.6.28
6,765.00
J. 6.6.27
135.00
30,095.83
135.00
19,310.42
6,765.00
26,075.42
Pipa PVC
25,775.00
30,930.00
Perlengkapan
9,021.25
9,021.25
0.0360 oh
pekerja
55,000.00
1,980.00
0.0600 oh
Tukang Batu
70,000.00
4,200.00
0.0060 oh
kepala tukang
75,000.00
450.00
0.0018 oh
mandor
75,000.00
35.0000 %
JUMLAH
135.00
39,951.25
6,765.00
46,716.25
J. 6.6.30
Pipa PVC
12,458.33
14,950.00
Perlengkapan
4,360.42
4,360.42
0.0360 oh
pekerja
55,000.00
1,980.00
0.0600 oh
Tukang Batu
70,000.00
4,200.00
0.0060 oh
kepala tukang
75,000.00
450.00
0.0018 oh
mandor
75,000.00
35.0000 %
JUMLAH
J. 6.6.31
1.2000 m'
Pipa PVC
38,500.00
46,200.00
Perlengkapan
13,475.00
13,475.00
0.0810 oh
pekerja
55,000.00
4,455.00
0.1350 oh
Tukang Batu
70,000.00
9,450.00
0.0135 oh
kepala tukang
75,000.00
1,012.50
0.0041 oh
mandor
75,000.00
JUMLAH
1.2000 m'
307.50
59,675.00
15,225.00
Pipa PVC
37,708.33
45,250.00
Perlengkapan
13,197.92
13,197.92
0.0810 oh
pekerja
55,000.00
4,455.00
0.1350 oh
Tukang Batu
70,000.00
9,450.00
0.0135 oh
kepala tukang
75,000.00
1,012.50
0.0041 oh
mandor
75,000.00
JUMLAH
74,900.00
307.50
58,447.92
15,225.00
73,672.92
442,916.67
442,916.67
1.0000 set
35,000.00
35,000.00
0.0300 oh
pekerja
55,000.00
1,650.00
0.3000 oh
Tukang Batu
70,000.00
21,000.00
0.0300 oh
kepala tukang
75,000.00
2,250.00
0.0015 oh
mandor
75,000.00
JUMLAH
J. 6.6.34
26,075.42
J. 6.6.33
6,765.00
J. 6.6.32
135.00
19,310.42
112.50
230,000.00
25,012.50
255,012.50
293,000.00
293,000.00
1.0000 set
35,000.00
35,000.00
Semen Portland
1,300.00
26,000.00
0.0500 m3
Pasir
278,750.00
13,937.50
0.0500 oh
Pekerja
55,000.00
2,750.00
0.5000 oh
Tukang Batu
70,000.00
35,000.00
0.0500 oh
kepala tukang
75,000.00
3,750.00
0.0025 oh
mandor
75,000.00
20.0000 Kg
JUMLAH
187.50
367,937.50
41,687.50
409,625.00
J. 6.6.35
Kran Air
25,000.00
25,000.00
0.0250 Bh
Seal Tape
4,000.00
100.00
0.0100 oh
pekerja
55,000.00
550.00
0.1000 oh
Tukang Batu
70,000.00
7,000.00
0.0100 oh
kepala tukang
75,000.00
750.00
0.0050 oh
mandor
75,000.00
JUMLAH
J. 6.6.36
375.00
25,100.00
8,675.00
33,775.00
Floor drain
35,000.00
0.0100 oh
pekerja
55,000.00
550.00
0.1000 oh
Tukang Batu
70,000.00
7,000.00
0.0100 oh
kepala tukang
75,000.00
750.00
0.0050 oh
mandor
75,000.00
JUMLAH
35,000.00
375.00
35,000.00
8,675.00
43,675.00
Besi Profil WF
0.0800 Kg
Meni Besi
20,333.33
0.0060 oh
Tukang Besi
70,000.00
420.00
0.0600 oh
Pekerja
55,000.00
3,300.00
0.0060 oh
kepala tukang
75,000.00
450.00
0.0003 oh
mandor
75,000.00
JUMLAH
K. 6.6.2
22.50
1,626.67
4,192.50
5,819.17
0.0060 oh
70,000.00
420.00
0.0600 oh
Pekerja
55,000.00
3,300.00
0.0060 oh
kepala tukang
75,000.00
450.00
0.0003 oh
mandor
75,000.00
JUMLAH
K. 6.6.3
1,626.67
22.50
-
4,192.50
4,192.50
Jendela Besi
1.0500 oh
70,000.00
73,500.00
1.0500 oh
Pekerja
55,000.00
57,750.00
0.1050 oh
kepala tukang
75,000.00
7,875.00
0.0053 oh
mandor
75,000.00
JUMLAH
393.75
-
139,518.75
139,518.75
K. 6.6.4
1.2000 oh
70,000.00
84,000.00
1.0220 oh
Pekerja
55,000.00
56,210.00
0.1200 oh
kepala tukang
75,000.00
9,000.00
0.0060 oh
mandor
75,000.00
JUMLAH
K. 6.6.5
1.0000 m2
1.2000 oh
70,000.00
84,000.00
1.2000 oh
Pekerja
55,000.00
66,000.00
0.1200 oh
kepala tukang
75,000.00
9,000.00
0.0060 oh
mandor
75,000.00
159,450.00
1.1000 m2
Pintu Lipat
0.0060 oh
70,000.00
159,450.00
420.00
0.0600 oh
Pekerja
55,000.00
3,300.00
0.0060 oh
kepala tukang
75,000.00
450.00
0.0003 oh
mandor
75,000.00
22.50
-
4,192.50
4,192.50
Sunscreen Allumunium
0.8000 oh
70,000.00
56,000.00
0.0800 oh
Pekerja
55,000.00
4,400.00
0.0800 oh
kepala tukang
75,000.00
6,000.00
0.0040 oh
mandor
75,000.00
300.00
-
66,700.00
66,700.00
Roll Door
1.5000 oh
70,000.00
105,000.00
1.0500 oh
Pekerja
55,000.00
57,750.00
0.1050 oh
kepala tukang
75,000.00
7,875.00
0.0052 oh
mandor
75,000.00
JUMLAH
K. 6.6.9
450.00
-
JUMLAH
K. 6.6.8
149,660.00
JUMLAH
K. 6.6.7
149,660.00
JUMLAH
K. 6.6.6
450.00
-
390.00
-
171,015.00
171,015.00
Pintu Allumunium
1.0500 oh
70,000.00
73,500.00
1.0500 oh
Pekerja
55,000.00
57,750.00
0.1050 oh
kepala tukang
75,000.00
7,875.00
0.0052 oh
mandor
75,000.00
JUMLAH
390.00
-
139,515.00
139,515.00
K. 6.6.10
Venetions Blinds
0.3500 oh
Tukang kayu
70,000.00
24,500.00
0.3500 oh
Pekerja
55,000.00
19,250.00
0.0350 oh
kepala tukang
75,000.00
2,625.00
0.0018 oh
mandor
75,000.00
JUMLAH
K. 6.6.11
1.0000 m2
Vertikals blinds
0.3500 oh
Tukang Kayu
70,000.00
24,500.00
0.3500 oh
Pekerja
55,000.00
19,250.00
0.0350 oh
kepala tukang
75,000.00
2,625.00
0.0018 oh
mandor
75,000.00
46,506.25
Besi Strip 2 x 3
31,800.00
70,000.00
84,000.00
1.2000 oh
Pekerja
55,000.00
66,000.00
0.0120 oh
kepala tukang
75,000.00
900.00
0.0006 oh
mandor
75,000.00
46,506.25
365,700.00
45.00
365,700.00
150,945.00
516,645.00
kawat harmonika
28,350.00
0.0200 kg
15,583.33
311.67
0.0018 m3
papan ky meranti
2,300,000.00
4,140.00
0.1000 oh
pekerja
55,000.00
5,500.00
0.1000 oh
tukang kayu
70,000.00
7,000.00
0.0100 oh
kepala tukang
75,000.00
750.00
0.0005 oh
mandor
75,000.00
JUMLAH
31,185.00
37.50
43,624.13
10,630.00
54,254.13
kawat nyamuk
25,000.00
0.0200 kg
15,583.33
311.67
0.0018 m3
papan ky meranti
2,300,000.00
4,140.00
0.1000 oh
pekerja
55,000.00
5,500.00
0.1000 oh
tukang kayu
70,000.00
7,000.00
0.0100 oh
kepala tukang
75,000.00
750.00
0.0005 oh
mandor
75,000.00
JUMLAH
K. 6.6.15
131.25
-
1.2000 oh
JUMLAH
K. 6.6.14
46,506.25
K. 6.6.13
46,506.25
JUMLAH
K. 6.6.12
131.25
-
27,500.00
37.50
31,951.67
13,287.50
45,239.17
kawat kassa
7,750.00
0.0200 kg
15,583.33
311.67
0.0018 m3
2,300,000.00
4,140.00
0.1000 oh
pekerja
55,000.00
5,500.00
0.1000 oh
tukang kayu
70,000.00
7,000.00
0.0100 oh
kepala tukang
75,000.00
750.00
0.0005 oh
mandor
75,000.00
JUMLAH
8,525.00
37.50
12,976.67
13,287.50
26,264.17
K. 6.6.16
kawat Burung
107,300.00
0.0200 kg
15,583.33
311.67
0.0018 m3
6,000,000.00
10,800.00
0.1000 oh
pekerja
55,000.00
5,500.00
0.1000 oh
tukang kayu
70,000.00
7,000.00
0.0100 oh
kepala tukang
75,000.00
750.00
0.0005 oh
mandor
75,000.00
JUMLAH
K. 6.6.17
Jendela Nako
326,700.00
359,370.00
0.0200 kg
15,583.33
311.67
0.0250 m3
Besi Strip
31,800.00
795.00
0.2000 oh
pekerja
55,000.00
11,000.00
0.2000 oh
tukang kayu
70,000.00
14,000.00
0.0200 oh
kepala tukang
75,000.00
1,500.00
0.0010 oh
mandor
75,000.00
142,429.17
75.00
360,476.67
26,575.00
387,051.67
45,833.33
0.0150 kg
15,583.33
233.75
0.0096 m3
5,400,000.00
51,840.00
0.2500 kg
37,666.67
9,416.67
0.1500 oh
pekerja
55,000.00
8,250.00
0.4000 oh
tukang kayu
70,000.00
28,000.00
0.0250 oh
kepala tukang
75,000.00
1,875.00
0.0013 oh
mandor
75,000.00
22,916.67
93.75
84,407.08
38,218.75
122,625.83
45,833.33
0.0150 kg
15,583.33
233.75
0.0190 m3
5,400,000.00
102,600.00
0.3000 kg
37,666.67
11,300.00
0.0400 oh
pekerja
55,000.00
2,200.00
0.4000 oh
tukang kayu
70,000.00
28,000.00
0.0250 oh
kepala tukang
75,000.00
1,875.00
0.0013 oh
mandor
75,000.00
JUMLAH
K. 6.6.20
13,287.50
1.1000 m2
JUMLAH
K. 6.6.19
37.50
129,141.67
JUMLAH
K. 6.6.18
118,030.00
22,916.67
93.75
137,050.42
32,168.75
169,219.17
45,833.33
0.1000 kg
15,583.33
1,558.33
0.0190 m3
5,400,000.00
102,600.00
0.5000 kg
besi Strip
31,800.00
15,900.00
0.1500 oh
pekerja
55,000.00
8,250.00
0.2500 oh
tukang kayu
70,000.00
17,500.00
0.0250 oh
kepala tukang
75,000.00
1,875.00
0.0013 oh
mandor
75,000.00
JUMLAH
13,750.00
93.75
133,808.33
27,718.75
161,527.08
K. 6.6.21
45,833.33
0.0150 kg
15,583.33
233.75
0.0190 m3
5,400,000.00
102,600.00
0.3000 kg
besi Strip
31,800.00
9,540.00
0.0400 oh
pekerja
55,000.00
2,200.00
0.4000 oh
tukang kayu
70,000.00
28,000.00
0.0250 oh
kepala tukang
75,000.00
1,875.00
0.0013 oh
mandor
75,000.00
JUMLAH
22,916.67
93.75
135,290.42
32,168.75
167,459.17
0.0600 oh
Pekerja
55,000.00
3,300.00
0.6000 oh
Tukang Kayu
70,000.00
42,000.00
0.0600 oh
kepala tukang
75,000.00
4,500.00
0.0030 oh
mandor
75,000.00
JUMLAH
L. 6.6.2
1.0000 Bh
0.0100 oh
Pekerja
55,000.00
550.00
0.0500 oh
Tukang Kayu
70,000.00
3,500.00
0.0100 oh
kepala tukang
75,000.00
750.00
0.0050 oh
mandor
75,000.00
50,025.00
375.00
-
5,175.00
5,175.00
0.0050 oh
Pekerja
55,000.00
275.00
0.5000 oh
Tukang Kayu
70,000.00
35,000.00
0.0050 oh
kepala tukang
75,000.00
375.00
0.0025 oh
mandor
75,000.00
187.50
-
35,837.50
35,837.50
Kunci Silinder
0.0050 oh
Pekerja
55,000.00
275.00
0.5000 oh
Tukang Kayu
70,000.00
35,000.00
0.0050 oh
kepala tukang
75,000.00
375.00
0.0003 oh
mandor
75,000.00
JUMLAH
L. 6.6.5
50,025.00
JUMLAH
L. 6.6.4
225.00
-
JUMLAH
L. 6.6.3
18.75
-
35,668.75
28,040.00
Engsel Pintu
27,527.78
0.0150 oh
Pekerja
55,000.00
825.00
0.1500 oh
Tukang Kayu
70,000.00
10,500.00
0.0150 oh
kepala tukang
75,000.00
1,125.00
0.0008 oh
mandor
75,000.00
JUMLAH
27,527.78
56.25
27,527.78
12,506.25
40,034.03
L. 6.6.6
Engsel Jendela
15,416.67
0.0100 oh
Pekerja
55,000.00
550.00
0.1000 oh
Tukang Kayu
70,000.00
7,000.00
0.0100 oh
kepala tukang
75,000.00
750.00
0.0005 oh
mandor
75,000.00
JUMLAH
L. 6.6.7
Engsel angin
0.0200 oh
Pekerja
55,000.00
1,100.00
0.2000 oh
Tukang Kayu
70,000.00
14,000.00
0.0200 oh
kepala tukang
75,000.00
1,500.00
0.0100 oh
mandor
75,000.00
750.00
-
17,350.00
17,350.00
Spring Knip
0.0150 oh
Pekerja
55,000.00
825.00
0.1500 oh
Tukang Kayu
70,000.00
10,500.00
0.0150 oh
kepala tukang
75,000.00
1,125.00
0.0008 oh
mandor
75,000.00
56.25
-
12,506.25
12,506.25
Kait angin
12,000.00
0.0150 oh
Pekerja
55,000.00
825.00
0.1500 oh
Tukang Kayu
70,000.00
10,500.00
0.0150 oh
kepala tukang
75,000.00
1,125.00
0.0008 oh
mandor
75,000.00
12,000.00
56.25
12,000.00
12,506.25
24,506.25
Door Closer
0.0500 oh
Pekerja
55,000.00
2,750.00
0.5000 oh
Tukang Kayu
70,000.00
35,000.00
0.0500 oh
kepala tukang
75,000.00
3,750.00
0.0025 oh
mandor
75,000.00
JUMLAH
L. 6.6.11
23,754.17
JUMLAH
L. 6.6.10
8,337.50
1.0000 Bh
JUMLAH
L. 6.6.9
37.50
15,416.67
JUMLAH
L. 6.6.8
15,416.67
187.50
-
41,687.50
41,687.50
Kunci selot
0.0200 oh
Pekerja
55,000.00
1,100.00
0.2000 oh
Tukang Kayu
70,000.00
14,000.00
0.0200 oh
kepala tukang
75,000.00
1,500.00
0.0010 oh
mandor
75,000.00
JUMLAH
75.00
-
16,675.00
16,675.00
L. 6.6.12
Door Holder
0.0500 oh
Pekerja
55,000.00
2,750.00
0.5000 oh
Tukang Kayu
70,000.00
35,000.00
0.0500 oh
kepala tukang
75,000.00
3,750.00
0.0025 oh
mandor
75,000.00
JUMLAH
L. 6.6.13
1.0000 Bh
Door Stop
0.0100 oh
Pekerja
55,000.00
550.00
0.1000 oh
Tukang Kayu
70,000.00
7,000.00
0.0100 oh
kepala tukang
75,000.00
750.00
0.0005 oh
mandor
75,000.00
8,337.50
1.0000 Bh
0.0600 oh
Pekerja
55,000.00
8,337.50
3,300.00
0.6000 oh
Tukang Kayu
70,000.00
42,000.00
0.0600 oh
kepala tukang
75,000.00
4,500.00
0.0030 oh
mandor
75,000.00
225.00
-
50,025.00
50,025.00
Kunci Lemari
25,000.00
0.0250 oh
Pekerja
55,000.00
1,375.00
0.2500 oh
Tukang Kayu
70,000.00
17,500.00
0.0250 oh
kepala tukang
75,000.00
1,875.00
0.0013 oh
mandor
75,000.00
25,000.00
93.75
25,000.00
20,843.75
45,843.75
kaca
84,700.00
0.0150 oh
Pekerja
55,000.00
825.00
0.1500 oh
Tukang Kayu
70,000.00
10,500.00
0.0150 oh
kepala tukang
75,000.00
1,125.00
0.0008 oh
mandor
75,000.00
JUMLAH
L. 6.6.17
37.50
-
JUMLAH
L. 6.6.16
41,687.50
JUMLAH
L. 6.6.15
41,687.50
JUMLAH
L. 6.6.14
187.50
-
93,170.00
56.25
93,170.00
12,506.25
105,676.25
Kaca
102,300.00
0.0150 oh
Pekerja
55,000.00
825.00
0.1500 oh
Tukang Kayu
70,000.00
10,500.00
0.0150 oh
kepala tukang
75,000.00
1,125.00
0.0008 oh
mandor
75,000.00
JUMLAH
112,530.00
56.25
112,530.00
12,506.25
125,036.25
L. 6.6.18
16,000.00
1.1000 m2
Kaca
127,000.00
0.0165 oh
Pekerja
55,000.00
907.50
0.1650 oh
Tukang Kayu
70,000.00
11,550.00
0.0165 oh
kepala tukang
75,000.00
1,237.50
0.0008 oh
mandor
75,000.00
JUMLAH
L. 6.6.19
kaca gelap
127,000.00
139,700.00
0.0500 kg
Sealent
35,000.00
1,750.00
0.0250 oh
Pekerja
55,000.00
1,375.00
0.2500 oh
Tukang Kayu
70,000.00
17,500.00
0.0250 oh
kepala tukang
75,000.00
1,875.00
0.0013 oh
mandor
75,000.00
93.75
141,450.00
20,843.75
1.1000 m2
Kaca cermin
114,000.00
0.0150 oh
Pekerja
55,000.00
825.00
0.1500 oh
Tukang Kayu
70,000.00
10,500.00
0.0150 oh
kepala tukang
75,000.00
1,125.00
0.0008 oh
mandor
75,000.00
162,293.75
125,400.00
56.25
125,400.00
12,506.25
137,906.25
Kaca cermin
114,000.00
0.0150 oh
Pekerja
55,000.00
825.00
0.1500 oh
Tukang Kayu
70,000.00
10,500.00
0.0150 oh
kepala tukang
75,000.00
1,125.00
0.0008 oh
mandor
75,000.00
125,400.00
56.25
125,400.00
12,506.25
137,906.25
Kaca cermin
152,000.00
0.0165 oh
Pekerja
55,000.00
907.50
0.1650 oh
Tukang Kayu
70,000.00
11,550.00
0.0165 oh
kepala tukang
75,000.00
1,237.50
0.0008 oh
mandor
75,000.00
JUMLAH
L. 6.6.23
153,451.25
JUMLAH
L. 6.6.22
13,751.25
1.1000 m2
JUMLAH
L. 6.6.21
56.25
139,700.00
JUMLAH
L. 6.6.20
139,700.00
152,000.00
60.00
152,000.00
13,755.00
165,755.00
Kaca Wireglass
0.0150 oh
Pekerja
55,000.00
825.00
0.1500 oh
Tukang Kayu
70,000.00
10,500.00
0.0150 oh
kepala tukang
75,000.00
1,125.00
0.0008 oh
mandor
75,000.00
JUMLAH
56.25
-
12,506.25
12,506.25
L. 6.6.24
Kaca Patri
400,000.00
0.0150 oh
Pekerja
55,000.00
825.00
0.1500 oh
Tukang Kayu
70,000.00
10,500.00
0.0150 oh
kepala tukang
75,000.00
1,125.00
0.0008 oh
mandor
75,000.00
JUMLAH
440,000.00
56.25
440,000.00
12,506.25
452,506.25
Ubin abu-abu 40 x 40 cm
7,466.06
49,500.00
9.8000 kg
Semen portland
1,300.00
12,740.00
0.0215 m3
Pasir pasang
278,750.00
5,993.13
0.2500 oh
pekerja
55,000.00
13,750.00
0.1200 oh
tukang batu
70,000.00
8,400.00
0.0120 oh
kepala tukang
75,000.00
900.00
0.0125 oh
mandor
75,000.00
JUMLAH
M.6.6.2
0.09
0.09
23,987.50
92,220.63
Ubin abu-abu 30 x 30 cm
3,454.09
41,000.00
10.0000 kg
semen portland
1,300.00
13,000.00
0.0215 m3
pasir pasang
278,750.00
5,993.13
0.2600 oh
pekerja
55,000.00
14,300.00
0.1250 oh
tukang batu
70,000.00
8,750.00
0.0125 oh
kepala tukang
75,000.00
937.50
0.0130 oh
mandor
75,000.00
JUMLAH
M.6.6.3
937.50
68,233.13
975.00
59,993.13
24,962.50
84,955.63
Ubin abu-abu 20 x 20 cm
1,660.38
44,000.00
10.4000 kg
semen portland
1,300.00
13,520.00
0.0135 m3
pasir pasang
278,750.00
3,763.13
0.2700 oh
pekerja
55,000.00
14,850.00
0.1300 oh
tukang batu
70,000.00
9,100.00
0.0130 oh
kepala tukang
75,000.00
975.00
0.0135 oh
mandor
75,000.00
1,012.50
JUMLAH
61,283.13
25,937.50
87,220.63
M.6.6.4
0.09
Ubin Warna 40 x 40 cm
7,466.06
49,500.00
8.1600 kg
semen portland
1,300.00
10,608.00
0.0230 m3
pasir pasang
278,750.00
6,411.25
0.9000 kg
Semen warna
1,947.92
1,753.13
0.2500 oh
pekerja
55,000.00
13,750.00
0.1200 oh
tukang batu
70,000.00
8,400.00
0.0120 oh
kepala tukang
75,000.00
900.00
0.0125 oh
mandor
75,000.00
JUMLAH
M.6.6.5
0.09
0.09
11.8700 Bh
Ubin Warna 30 x 30 cm
3,117.10
37,000.00
8.3600 kg
semen portland
1,300.00
10,868.00
0.0230 m3
pasir pasang
278,750.00
6,411.25
0.9000 kg
Semen warna
1,947.92
1,753.13
0.2500 oh
pekerja
55,000.00
13,750.00
0.1200 oh
tukang batu
70,000.00
8,400.00
0.0120 oh
kepala tukang
75,000.00
900.00
0.0125 oh
mandor
75,000.00
0.09
92,259.88
937.50
56,032.38
23,987.50
80,019.88
Ubin Warna 20 x 20 cm
1,660.38
44,000.00
8.7600 kg
semen portland
1,300.00
11,388.00
0.0230 m3
pasir pasang
278,750.00
6,411.25
0.9000 kg
Semen warna
1,947.92
1,753.13
0.2700 oh
pekerja
55,000.00
14,850.00
0.1300 oh
tukang batu
70,000.00
9,100.00
0.0130 oh
kepala tukang
75,000.00
975.00
0.0135 oh
mandor
75,000.00
1,012.50
JUMLAH
M.6.6.7
23,987.50
JUMLAH
M.6.6.6
937.50
68,272.38
63,552.38
25,937.50
89,489.88
Ubin teraso 40 x 40 cm
10,000.00
62,500.00
8.8000 kg
semen portland
1,300.00
11,440.00
0.0215 m3
pasir pasang
278,750.00
5,993.13
0.9000 kg
Semen warna
1,947.92
1,753.13
0.2500 oh
pekerja
55,000.00
13,750.00
0.1200 oh
tukang batu
70,000.00
8,400.00
0.0120 oh
kepala tukang
75,000.00
900.00
0.0125 oh
mandor
75,000.00
JUMLAH
937.50
81,686.25
23,987.50
105,673.75
M.6.6.8
0.09
Ubin teraso 30 x 30 cm
6,000.00
71,220.00
10.0000 kg
semen portland
1,300.00
13,000.00
0.0215 m3
pasir pasang
278,750.00
5,993.13
1.5400 kg
Semen warna
1,947.92
2,999.79
0.2600 oh
pekerja
55,000.00
14,300.00
0.1250 oh
tukang batu
70,000.00
8,750.00
0.0125 oh
kepala tukang
75,000.00
937.50
0.0130 oh
mandor
75,000.00
JUMLAH
M.6.6.9
0.09
0.09
6.9300 Bh
Ubin granito 40 x 40 cm
15,000.00
103,950.00
9.8000 kg
semen portland
1,300.00
12,740.00
0.0215 m3
pasir pasang
278,750.00
5,993.13
1.3000 kg
Semen warna
1,947.92
2,532.29
0.2500 oh
pekerja
55,000.00
13,750.00
0.1200 oh
tukang batu
70,000.00
8,400.00
0.0120 oh
kepala tukang
75,000.00
900.00
0.0125 oh
mandor
75,000.00
0.09
118,175.42
937.50
125,215.42
23,987.50
149,202.92
Ubin granito 30 x 30 cm
9,000.00
106,830.00
10.0000 kg
semen portland
1,300.00
13,000.00
0.0215 m3
pasir pasang
278,750.00
5,993.13
1.5000 kg
Semen warna
1,947.92
2,921.88
0.2600 oh
pekerja
55,000.00
14,300.00
0.1250 oh
tukang batu
70,000.00
8,750.00
0.0125 oh
kepala tukang
75,000.00
937.50
0.0130 oh
mandor
75,000.00
JUMLAH
M.6.6.11
24,962.50
JUMLAH
M.6.6.10
975.00
93,212.92
975.00
128,745.00
24,962.50
153,707.50
8.8000 kg
semen portland
1,300.00
11,440.00
0.0215 m3
pasir pasang
278,750.00
5,993.13
1.3000 kg
Semen warna
1,947.92
2,532.29
0.2500 oh
pekerja
55,000.00
13,750.00
0.1200 oh
tukang batu
70,000.00
8,400.00
0.0120 oh
kepala tukang
75,000.00
900.00
0.0125 oh
mandor
75,000.00
JUMLAH
937.50
19,965.42
23,987.50
43,952.92
M.6.6.12
0.09
10.0000 kg
semen portland
1,300.00
13,000.00
0.0215 m3
pasir pasang
278,750.00
5,993.13
1.1250 kg
Semen warna
1,947.92
2,191.41
0.2500 oh
pekerja
55,000.00
13,750.00
0.1200 oh
tukang batu
70,000.00
8,400.00
0.0120 oh
kepala tukang
75,000.00
900.00
0.0125 oh
mandor
75,000.00
JUMLAH
M.6.6.13
0.09
0.09
5.6000 Bh
8.1900 kg
semen portland
1,300.00
10,647.00
0.09
45,172.03
0.0450 m3
pasir pasang
278,750.00
12,543.75
1.0000 kg
Semen warna
1,947.92
1,947.92
0.2500 oh
pekerja
55,000.00
13,750.00
0.1200 oh
tukang batu
70,000.00
8,400.00
0.0120 oh
kepala tukang
75,000.00
900.00
0.0125 oh
mandor
75,000.00
937.50
25,138.67
23,987.50
49,126.17
8.8000 kg
semen portland
1,300.00
11,440.00
0.0215 m3
pasir pasang
278,750.00
5,993.13
1.3000 kg
Semen warna
1,947.92
2,532.29
0.6720 oh
pekerja
55,000.00
36,960.00
0.2240 oh
tukang batu
70,000.00
15,680.00
0.0220 oh
kepala tukang
75,000.00
1,650.00
0.0340 oh
mandor
75,000.00
JUMLAH
M.6.6.15
23,987.50
JUMLAH
M.6.6.14
937.50
21,184.53
2,550.00
19,965.42
56,840.00
76,805.42
10.0000 kg
semen portland
1,300.00
13,000.00
0.0250 m3
pasir pasang
278,750.00
6,968.75
1.5000 kg
Semen warna
1,947.92
2,921.88
0.7000 oh
pekerja
55,000.00
38,500.00
0.3400 oh
tukang batu
70,000.00
23,800.00
0.0340 oh
kepala tukang
75,000.00
2,550.00
0.0350 oh
mandor
75,000.00
JUMLAH
2,625.00
22,890.63
67,475.00
90,365.63
M.6.6.16
0.09
Plint Ubin 15 x 20 cm
1,660.38
8,800.00
1.5600 kg
semen portland
1,300.00
2,028.00
0.0040 m3
pasir pasang
278,750.00
1,115.00
0.0600 oh
pekerja
55,000.00
3,300.00
0.0300 oh
tukang batu
70,000.00
2,100.00
0.0030 oh
kepala tukang
75,000.00
225.00
0.0030 oh
mandor
75,000.00
JUMLAH
M.6.6.17
0.09
0.09
3.5300 Bh
Plint Ubin 10 x 30 cm
1,151.36
4,064.31
1.5600 kg
semen portland
1,300.00
2,028.00
0.0030 m3
pasir pasang
278,750.00
836.25
0.0600 oh
pekerja
55,000.00
3,300.00
0.0300 oh
tukang batu
70,000.00
2,100.00
0.0030 oh
kepala tukang
75,000.00
225.00
0.0030 oh
mandor
75,000.00
0.09
0.09
225.00
6,928.56
5,850.00
2.6500 Bh
Plint Ubin 10 x 40 cm
1,866.52
4,946.27
1.5600 kg
semen portland
1,300.00
2,028.00
0.0030 m3
pasir pasang
278,750.00
836.25
0.0600 oh
pekerja
55,000.00
3,300.00
0.0300 oh
tukang batu
70,000.00
2,100.00
0.0030 oh
kepala tukang
75,000.00
225.00
0.0030 oh
mandor
75,000.00
12,778.56
225.00
7,810.52
5,850.00
13,660.52
830.19
4,400.00
1.2000 kg
semen portland
1,300.00
1,560.00
0.0030 m3
pasir pasang
278,750.00
836.25
0.1900 kg
Semen warna
9,833.33
1,868.33
0.0600 oh
pekerja
70,000.00
4,200.00
0.0300 oh
tukang batu
70,000.00
2,100.00
0.0030 oh
kepala tukang
75,000.00
225.00
0.0030 oh
mandor
75,000.00
JUMLAH
M.6.6.20
17,793.00
JUMLAH
M.6.6.19
5,850.00
JUMLAH
M.6.6.18
225.00
11,943.00
225.00
8,664.58
6,750.00
15,414.58
1,039.03
3,459.98
1.6500 kg
semen portland
1,300.00
2,145.00
0.0032 m3
pasir pasang
278,750.00
892.00
0.1000 kg
Semen warna
9,833.33
983.33
0.0600 oh
pekerja
55,000.00
3,300.00
0.0300 oh
tukang batu
70,000.00
2,100.00
0.0030 oh
kepala tukang
75,000.00
225.00
0.0030 oh
mandor
75,000.00
JUMLAH
225.00
7,480.32
5,850.00
13,330.32
M.6.6.21
0.09
1,866.52
4,946.27
1.2000 kg
semen portland
1,300.00
1,560.00
0.0030 m3
pasir pasang
278,750.00
836.25
0.1000 kg
Semen warna
9,833.33
983.33
0.0800 oh
pekerja
55,000.00
4,400.00
0.0400 oh
tukang batu
70,000.00
2,800.00
0.0040 oh
kepala tukang
75,000.00
300.00
0.0040 oh
mandor
75,000.00
JUMLAH
M.6.6.22
0.09
0.09
3.5300 Bh
2,000.00
7,060.00
1.5600 kg
semen portland
1,300.00
2,028.00
0.0030 m3
pasir pasang
278,750.00
836.25
0.1900 kg
Semen warna
9,833.33
1,868.33
0.0800 oh
pekerja
55,000.00
4,400.00
0.0400 oh
tukang batu
70,000.00
2,800.00
0.0040 oh
kepala tukang
75,000.00
300.00
0.0040 oh
mandor
75,000.00
0.09
16,125.85
300.00
11,792.58
7,800.00
19,592.58
2,500.00
6,625.00
1.2000 kg
semen portland
1,300.00
1,560.00
0.0030 m3
pasir pasang
278,750.00
836.25
1.0000 kg
Semen warna
9,833.33
9,833.33
0.0800 oh
pekerja
55,000.00
4,400.00
0.0400 oh
tukang batu
70,000.00
2,800.00
0.0040 oh
kepala tukang
75,000.00
300.00
0.0040 oh
mandor
75,000.00
JUMLAH
M.6.6.24
7,800.00
JUMLAH
M.6.6.23
300.00
8,325.85
300.00
18,854.58
7,800.00
26,654.58
3,750.00
9,937.50
1.2000 kg
semen portland
1,300.00
1,560.00
0.0030 m3
pasir pasang
278,750.00
836.25
1.0000 kg
Semen warna
9,833.33
9,833.33
0.0600 oh
pekerja
55,000.00
3,300.00
0.0300 oh
tukang batu
70,000.00
2,100.00
0.0030 oh
kepala tukang
75,000.00
225.00
0.0030 oh
mandor
75,000.00
JUMLAH
225.00
22,167.08
5,850.00
28,017.08
M.6.6.25
0.09
3,000.00
9,990.00
1.6500 kg
semen portland
1,300.00
2,145.00
0.0032 m3
pasir pasang
278,750.00
892.00
0.1000 kg
Semen warna
9,833.33
983.33
0.9000 oh
pekerja
55,000.00
49,500.00
0.0900 oh
tukang batu
70,000.00
6,300.00
0.0090 oh
kepala tukang
75,000.00
675.00
0.0045 oh
mandor
75,000.00
JUMLAH
M.6.6.26
0.09
0.09
2.5000 Bh
1.6500 kg
semen portland
1,300.00
2,145.00
0.0032 m3
pasir pasang
278,750.00
892.00
0.1000 kg
Semen warna
9,833.33
983.33
0.9000 oh
pekerja
55,000.00
49,500.00
0.0900 oh
tukang batu
70,000.00
6,300.00
0.0090 oh
kepala tukang
75,000.00
675.00
0.0045 oh
mandor
75,000.00
0.09
70,822.83
337.50
4,020.33
56,812.50
60,832.83
1.6500 kg
semen portland
1,300.00
2,145.00
0.0032 m3
pasir pasang
278,750.00
892.00
0.1000 kg
Semen warna
9,833.33
983.33
0.9000 oh
pekerja
55,000.00
49,500.00
0.0900 oh
tukang batu
70,000.00
6,300.00
0.0090 oh
kepala tukang
75,000.00
675.00
0.0045 oh
mandor
75,000.00
JUMLAH
M.6.6.28
56,812.50
JUMLAH
M.6.6.27
337.50
14,010.33
337.50
4,020.33
56,812.50
60,832.83
1.6500 kg
semen portland
1,300.00
2,145.00
0.0032 m3
pasir pasang
278,750.00
892.00
0.1000 kg
Semen warna
9,833.33
983.33
0.9000 oh
pekerja
55,000.00
49,500.00
0.0900 oh
tukang batu
70,000.00
6,300.00
0.0090 oh
kepala tukang
75,000.00
675.00
0.0045 oh
mandor
75,000.00
JUMLAH
337.50
4,020.33
56,812.50
60,832.83
M.6.6.29
0.09
1.6500 kg
semen portland
1,300.00
2,145.00
0.0032 m3
pasir pasang
278,750.00
892.00
0.1000 kg
Semen warna
9,833.33
983.33
0.9000 oh
pekerja
55,000.00
49,500.00
0.0900 oh
tukang batu
70,000.00
6,300.00
0.0090 oh
kepala tukang
75,000.00
675.00
0.0045 oh
mandor
75,000.00
JUMLAH
M.6.6.30
0.09
0.09
3.3000 Bh
1.6500 kg
semen portland
1,300.00
2,145.00
0.0032 m3
pasir pasang
278,750.00
892.00
0.1000 kg
Semen warna
9,833.33
983.33
0.9000 oh
pekerja
55,000.00
49,500.00
0.0900 oh
tukang batu
70,000.00
6,300.00
0.0090 oh
kepala tukang
75,000.00
675.00
0.0045 oh
mandor
75,000.00
0.09
0.09
337.50
4,020.33
56,812.50
0.0036 m3
0.9000 oh
pekerja
55,000.00
60,832.83
49,500.00
0.0900 oh
tukang batu
70,000.00
6,300.00
0.0090 oh
kepala tukang
75,000.00
675.00
0.0045 oh
mandor
75,000.00
337.50
-
56,812.50
56,812.50
0.9000 oh
pekerja
55,000.00
49,500.00
0.0900 oh
tukang batu
70,000.00
6,300.00
0.0090 oh
kepala tukang
75,000.00
675.00
0.0045 oh
mandor
75,000.00
JUMLAH
M.6.6.33
59,190.11
JUMLAH
M.6.6.32
56,812.50
JUMLAH
M.6.6.31
337.50
2,377.61
337.50
-
56,812.50
56,812.50
0.0400 m2
pasir pasang
278,750.00
0.2700 oh
pekerja
55,000.00
14,850.00
0.1500 oh
tukang batu
70,000.00
10,500.00
0.0150 oh
kepala tukang
75,000.00
1,125.00
0.0135 oh
mandor
75,000.00
14.1400 kg
JUMLAH
11,150.00
1,012.50
11,150.00
27,487.50
38,637.50
M.6.6.34
0.09
1,200.00
60,000.00
11.3800 kg
semen portland
1,300.00
14,794.00
0.0420 m2
pasir pasang
278,750.00
11,707.50
1.5000 kg
Semen warna
9,833.33
14,750.00
0.6200 oh
pekerja
55,000.00
34,100.00
0.3500 oh
tukang batu
70,000.00
24,500.00
0.0350 oh
kepala tukang
75,000.00
2,625.00
0.0300 oh
mandor
75,000.00
0.09
M.6.6.35
0.09
JUMLAH
100.0000 bh
750.00
75,000.00
semen portland
1,300.00
14,794.00
0.0420 m2
pasir pasang
278,750.00
11,707.50
2.0000 kg
Semen warna
9,833.33
19,666.67
0.6200 oh
pekerja
55,000.00
34,100.00
0.3500 oh
tukang batu
70,000.00
24,500.00
0.0350 oh
kepala tukang
75,000.00
2,625.00
0.0300 oh
mandor
75,000.00
0.09
0.09
JUMLAH
100.0000 m2
0.09
2,250.00
121,168.17
63,475.00
600.00
60,000.00
semen portland
1,300.00
14,794.00
0.0420 m2
pasir pasang
278,750.00
11,707.50
1.5000 kg
Semen warna
9,833.33
14,750.00
0.6200 oh
pekerja
55,000.00
34,100.00
0.3500 oh
tukang batu
70,000.00
24,500.00
0.0350 oh
kepala tukang
75,000.00
2,625.00
0.0300 oh
mandor
75,000.00
0.09
0.09
164,726.50
184,643.17
M.6.6.37
63,475.00
M.6.6.36
2,250.00
101,251.50
JUMLAH
2,250.00
101,251.50
63,475.00
164,726.50
1,200.00
6,000.00
1.6500 kg
semen portland
1,300.00
2,145.00
0.0032 m2
pasir pasang
278,750.00
892.00
0.1000 kg
Semen warna
9,833.33
983.33
0.0900 oh
pekerja
55,000.00
4,950.00
0.0900 oh
tukang batu
70,000.00
6,300.00
0.0090 oh
kepala tukang
75,000.00
675.00
0.0045 oh
mandor
75,000.00
JUMLAH
337.50
10,020.33
12,262.50
22,282.83
M.6.6.38
0.09
750.00
3,750.00
1.6500 kg
semen portland
1,300.00
2,145.00
0.0032 m2
pasir pasang
278,750.00
892.00
0.1200 kg
Semen warna
9,833.33
1,180.00
0.0900 oh
pekerja
55,000.00
4,950.00
0.0900 oh
tukang batu
70,000.00
6,300.00
0.0090 oh
kepala tukang
75,000.00
675.00
0.0045 oh
mandor
75,000.00
0.09
M.6.6.39
0.09
JUMLAH
0.09
5.0000 m2
600.00
3,000.00
0.8500 kg
semen portland
1,300.00
1,105.00
0.0022 m2
pasir pasang
278,750.00
613.25
0.0800 kg
Semen warna
9,833.33
786.67
0.0900 oh
pekerja
55,000.00
4,950.00
0.0900 oh
tukang batu
70,000.00
6,300.00
0.0090 oh
kepala tukang
75,000.00
675.00
0.0045 oh
mandor
75,000.00
JUMLAH
0.09
10.0000 m2
0.09
337.50
5,504.92
12,262.50
Interval cove ( 5 x 5 x 20 ) cm
1.4150 kg
semen portland
1,300.00
1,839.50
0.0390 m2
pasir pasang
278,750.00
10,871.25
1.2000 kg
Semen warna
9,833.33
11,800.00
0.7500 oh
pekerja
55,000.00
41,250.00
0.4500 oh
tukang batu
70,000.00
31,500.00
0.0450 oh
kepala tukang
75,000.00
3,375.00
0.0375 oh
mandor
75,000.00
17,767.42
JUMLAH
2,812.50
24,510.75
78,937.50
103,448.25
0.0800 kg
Lem vinyl
0.0800 oh
pekerja
55,000.00
4,400.00
0.0800 oh
tukang batu
70,000.00
5,600.00
0.0080 oh
kepala tukang
75,000.00
600.00
0.0040 oh
mandor
75,000.00
0.09
M.6.6.42
20,229.50
0.09
M.6.6.41
12,262.50
0.09
M.6.6.40
337.50
7,967.00
JUMLAH
300.00
-
10,900.00
10,900.00
700.00
35,000.00
11.3000 kg
semen portland
1,300.00
14,690.00
0.0420 m2
pasir pasang
278,750.00
11,707.50
1.5000 kg
Semen warna
9,833.33
14,750.00
0.6200 oh
pekerja
55,000.00
34,100.00
0.3500 oh
tukang batu
70,000.00
24,500.00
0.0350 oh
kepala tukang
75,000.00
2,625.00
0.0300 oh
mandor
75,000.00
JUMLAH
2,250.00
76,147.50
63,475.00
139,622.50
M.6.6.43
0.09
Ubin keramik 15 x 15 cm
850.00
37,400.00
11.3800 kg
semen portland
1,300.00
14,794.00
0.0420 m2
pasir pasang
278,750.00
11,707.50
1.5000 kg
Semen warna
9,833.33
14,750.00
0.6200 oh
pekerja
55,000.00
34,100.00
0.3500 oh
tukang batu
70,000.00
24,500.00
0.0350 oh
kepala tukang
75,000.00
2,625.00
0.0300 oh
mandor
75,000.00
0.09
M.6.6.44
0.09
JUMLAH
0.09
25.0000 Bh
Ubin keramik 20 x 20 cm
2,600.00
65,000.00
11.3800 kg
semen portland
1,300.00
14,794.00
0.0420 m2
pasir pasang
278,750.00
11,707.50
1.5000 kg
Semen warna
9,833.33
14,750.00
0.6200 oh
pekerja
55,000.00
34,100.00
0.3500 oh
tukang batu
70,000.00
24,500.00
0.0350 oh
kepala tukang
75,000.00
2,625.00
0.0300 oh
mandor
75,000.00
JUMLAH
0.09
0.09
142,126.50
2,250.00
106,251.50
63,475.00
169,726.50
Ubin keramik 25 x 25 cm
2,750.00
44,000.00
11.3800 kg
semen portland
1,300.00
14,794.00
0.0420 m2
pasir pasang
278,750.00
11,707.50
1.5000 kg
Semen warna
9,833.33
14,750.00
0.6200 oh
pekerja
55,000.00
34,100.00
0.3500 oh
tukang batu
70,000.00
24,500.00
0.0350 oh
kepala tukang
75,000.00
2,625.00
0.0300 oh
mandor
75,000.00
0.09
M.6.6.46
63,475.00
0.09
M.6.6.45
2,250.00
78,651.50
JUMLAH
2,250.00
85,251.50
63,475.00
148,726.50
Ubin keramik 15 x 20 cm
2,102.00
73,570.00
11.3800 kg
semen portland
1,300.00
14,794.00
0.0420 m2
pasir pasang
278,750.00
11,707.50
1.5000 kg
Semen warna
9,833.33
14,750.00
0.6200 oh
pekerja
55,000.00
34,100.00
0.3500 oh
tukang batu
70,000.00
24,500.00
0.0350 oh
kepala tukang
75,000.00
2,625.00
0.0300 oh
mandor
75,000.00
JUMLAH
2,250.00
114,821.50
63,475.00
178,296.50
M.6.6.47
0.09
Ubin keramik 30 x 30 cm
3,757.58
41,750.84
11.3800 kg
semen portland
1,300.00
14,794.00
0.0420 m2
pasir pasang
278,750.00
11,707.50
1.5000 kg
Semen warna
9,833.33
14,750.00
0.6200 oh
pekerja
55,000.00
34,100.00
0.3500 oh
tukang batu
70,000.00
24,500.00
0.0350 oh
kepala tukang
75,000.00
2,625.00
0.0300 oh
mandor
75,000.00
0.09
M.6.6.48
0.09
JUMLAH
0.09
11.1111 Bh
4,522.73
50,252.53
11.3800 kg
semen portland
1,300.00
14,794.00
0.0420 m2
pasir pasang
278,750.00
11,707.50
1.5000 kg
Semen warna
9,833.33
14,750.00
0.6200 oh
pekerja
55,000.00
34,100.00
0.3500 oh
tukang batu
70,000.00
24,500.00
0.0350 oh
kepala tukang
75,000.00
2,625.00
0.0300 oh
mandor
75,000.00
JUMLAH
0.09
0.09
146,477.34
2,250.00
91,504.03
63,475.00
154,979.03
Ubin keramik 10 x 33 cm
11.3800 kg
semen portland
1,300.00
14,794.00
0.0420 m2
pasir pasang
278,750.00
11,707.50
1.5000 kg
Semen warna
9,833.33
14,750.00
0.6200 oh
pekerja
55,000.00
34,100.00
0.3500 oh
tukang batu
70,000.00
24,500.00
0.0350 oh
kepala tukang
75,000.00
2,625.00
0.0300 oh
mandor
75,000.00
0.09
M.6.6.50
63,475.00
0.09
M.6.6.49
2,250.00
83,002.34
JUMLAH
2,250.00
41,251.50
63,475.00
104,726.50
Mosaik 30 x 30 cm
14.1500 kg
semen portland
1,300.00
18,395.00
0.0390 m2
pasir pasang
278,750.00
10,871.25
2.0000 kg
Semen warna
9,833.33
19,666.67
0.6200 oh
pekerja
55,000.00
34,100.00
0.3500 oh
tukang batu
70,000.00
24,500.00
0.0350 oh
kepala tukang
75,000.00
2,625.00
0.0300 oh
mandor
75,000.00
JUMLAH
2,250.00
48,932.92
63,475.00
112,407.92
M.6.6.51
0.09
Marmer
495,000.00
520,740.00
semen portland
1,300.00
18,395.00
0.0390 m2
pasir pasang
278,750.00
10,871.25
2.0000 kg
Semen warna
9,833.33
19,666.67
0.6200 oh
pekerja
55,000.00
34,100.00
0.3500 oh
tukang batu
70,000.00
24,500.00
0.0350 oh
kepala tukang
75,000.00
2,625.00
0.0300 oh
mandor
75,000.00
14.1500 kg
0.09
M.6.6.52
0.09
JUMLAH
0.09
1.0500 Bh
0.3500 kg
Lem Vinyl
0.1700 oh
pekerja
55,000.00
9,350.00
0.1700 oh
tukang batu
70,000.00
11,900.00
0.0170 oh
kepala tukang
75,000.00
1,275.00
0.0085 oh
mandor
75,000.00
0.09
0.09
0.09
637.50
-
23,162.50
23,162.50
0.3500 kg
Lem Vinyl
0.1700 oh
pekerja
55,000.00
9,350.00
0.1700 oh
tukang batu
70,000.00
11,900.00
0.0170 oh
kepala tukang
75,000.00
1,275.00
0.0085 oh
mandor
75,000.00
JUMLAH
637.50
-
23,162.50
23,162.50
0.1200 oh
pekerja
55,000.00
6,600.00
0.1200 oh
tukang batu
70,000.00
8,400.00
0.0120 oh
kepala tukang
75,000.00
900.00
0.0060 oh
mandor
75,000.00
0.09
M.6.6.55
633,147.92
JUMLAH
0.09
M.6.6.54
63,475.00
0.09
M.6.6.53
2,250.00
569,672.92
JUMLAH
450.00
-
16,350.00
16,350.00
Carpet
0.3500 kg
Lem Vinyl
0.1700 oh
pekerja
55,000.00
9,350.00
0.1700 oh
tukang batu
70,000.00
11,900.00
0.0170 oh
kepala tukang
75,000.00
1,275.00
0.0085 oh
mandor
75,000.00
JUMLAH
637.50
-
23,162.50
23,162.50
M.6.6.56
0.09
Parquet jati
0.3500 kg
Lem Vinyl
0.1700 oh
pekerja
55,000.00
9,350.00
0.1700 oh
tukang batu
70,000.00
11,900.00
0.0170 oh
kepala tukang
75,000.00
1,275.00
0.0085 oh
mandor
75,000.00
0.09
M.6.6.57
0.09
JUMLAH
0.09
0.09
0.09
0.09
23,162.50
Gymfloor
0.6000 kg
Lem Vinyl
0.6500 oh
pekerja
55,000.00
35,750.00
0.3500 oh
tukang batu
70,000.00
24,500.00
0.0350 oh
kepala tukang
75,000.00
2,625.00
0.0325 oh
mandor
75,000.00
18,530.00
JUMLAH
2,437.50
-
65,312.50
65,312.50
porselin 11 x 11 cm
9.3000 kg
Semen abu-abu
1,300.00
12,090.00
0.0180 m3
pasir pasang
278,750.00
5,017.50
1.5000 Kg
Semen warna
9,833.33
14,750.00
0.6200 oh
pekerja
55,000.00
34,100.00
0.5000 oh
tukang batu
70,000.00
35,000.00
0.0500 oh
kepala tukang
75,000.00
3,750.00
0.0300 oh
mandor
75,000.00
JUMLAH
2,250.00
31,857.50
75,100.00
106,957.50
porselin 11 x 11 cm warna
9.3000 Kg
Semen abu-abu
1,300.00
12,090.00
0.0180 m3
pasir pasang
278,750.00
5,017.50
1.5000 kg
Semen warna
9,833.33
14,750.00
0.6200 oh
pekerja
55,000.00
34,100.00
0.5000 oh
tukang batu
70,000.00
35,000.00
0.0500 oh
kepala tukang
75,000.00
3,750.00
0.0300 oh
mandor
75,000.00
0.09
M.6.6.60
637.50
-
1.0500 Bh
0.09
M.6.6.59
1 M2 PASANG GYMFLOOR
0.09
M.6.6.58
JUMLAH
2,250.00
31,857.50
75,100.00
106,957.50
porselin 15 x 15 cm putih
2,300.00
103,500.00
9.3000 Kg
Semen abu-abu
1,300.00
12,090.00
0.0180 m3
pasir pasang
278,750.00
5,017.50
1.5000 kg
Semen warna
9,833.33
14,750.00
0.6000 oh
pekerja
55,000.00
33,000.00
0.4500 oh
tukang batu
70,000.00
31,500.00
0.0450 oh
kepala tukang
75,000.00
3,375.00
0.0300 oh
mandor
75,000.00
JUMLAH
2,250.00
118,390.21
56,250.00
174,640.21
M.6.6.61
0.09
porselin 15 x 15 cm putih
2,800.00
126,000.00
9.3000 Kg
Semen abu-abu
1,300.00
12,090.00
0.0180 m3
pasir pasang
278,750.00
5,017.50
1.5000 kg
Semen warna
9,833.33
14,750.00
0.6000 oh
pekerja
55,000.00
33,000.00
0.4500 oh
tukang batu
70,000.00
31,500.00
0.0450 oh
kepala tukang
75,000.00
3,375.00
0.0300 oh
mandor
75,000.00
0.09
M.6.6.62
0.09
JUMLAH
0.09
50.0000 Bh
2,500.00
125,000.00
9.3000 Kg
Semen abu-abu
1,300.00
12,090.00
0.0180 m3
pasir pasang
278,750.00
5,017.50
1.5000 kg
Semen warna
9,833.33
14,750.00
0.6000 oh
pekerja
55,000.00
33,000.00
0.4500 oh
tukang batu
70,000.00
31,500.00
0.0450 oh
kepala tukang
75,000.00
3,375.00
0.0300 oh
mandor
75,000.00
JUMLAH
0.09
0.09
227,982.50
2,250.00
156,857.50
70,125.00
226,982.50
3,000.00
75,000.00
9.3000 Kg
Semen abu-abu
1,300.00
12,090.00
0.1800 m3
pasir pasang
278,750.00
50,175.00
1.5000 kg
Semen warna
9,833.33
14,750.00
0.6000 oh
pekerja
55,000.00
33,000.00
0.4500 oh
tukang batu
70,000.00
31,500.00
0.0450 oh
kepala tukang
75,000.00
3,375.00
0.0300 oh
mandor
75,000.00
0.09
M.6.6.64
70,125.00
0.09
M.6.6.63
2,250.00
157,857.50
JUMLAH
2,250.00
152,015.00
70,125.00
222,140.00
Keramik artistik 10 x 20 cm
1,000.00
100,000.00
9.3000 Kg
Semen abu-abu
1,300.00
12,090.00
0.0180 m3
pasir pasang
278,750.00
5,017.50
1.5000 kg
Semen warna
9,833.33
14,750.00
0.6000 oh
pekerja
55,000.00
33,000.00
0.4500 oh
tukang batu
70,000.00
31,500.00
0.0450 oh
kepala tukang
75,000.00
3,375.00
0.0300 oh
mandor
75,000.00
JUMLAH
2,250.00
131,857.50
70,125.00
201,982.50
M.6.6.65
0.09
Keramik artistik 5 x 20 cm
500.00
50,000.00
9.3000 Kg
Semen abu-abu
1,300.00
12,090.00
0.0180 m3
pasir pasang
278,750.00
5,017.50
1.5000 kg
Semen warna
9,833.33
14,750.00
0.6000 oh
pekerja
55,000.00
33,000.00
0.4500 oh
tukang batu
70,000.00
31,500.00
0.0450 oh
kepala tukang
75,000.00
3,375.00
0.0300 oh
mandor
75,000.00
0.09
M.6.6.66
0.09
JUMLAH
0.09
50.0000 Bh
Keramik 10 x 20 cm
1,027.78
51,388.89
9.3000 Kg
Semen abu-abu
1,300.00
12,090.00
0.0180 m3
pasir pasang
278,750.00
5,017.50
1.5000 kg
Semen warna
9,833.33
14,750.00
0.6000 oh
pekerja
55,000.00
33,000.00
0.4500 oh
tukang batu
70,000.00
31,500.00
0.0450 oh
kepala tukang
75,000.00
3,375.00
0.0300 oh
mandor
75,000.00
JUMLAH
0.09
0.09
151,982.50
2,250.00
83,246.39
70,125.00
153,371.39
Keramik 15 x 15 cm
850.00
38,250.00
9.3000 Kg
Semen abu-abu
1,300.00
12,090.00
0.0180 m3
pasir pasang
278,750.00
5,017.50
1.5000 kg
Semen warna
9,833.33
14,750.00
0.6000 oh
pekerja
55,000.00
33,000.00
0.4500 oh
tukang batu
70,000.00
31,500.00
0.0450 oh
kepala tukang
75,000.00
3,375.00
0.0300 oh
mandor
75,000.00
0.09
M.6.6.68
70,125.00
0.09
M.6.6.67
2,250.00
81,857.50
JUMLAH
2,250.00
70,107.50
70,125.00
140,232.50
Keramik 20 x 20 cm
1,112.96
27,824.07
9.3000 Kg
Semen abu-abu
1,300.00
12,090.00
0.0180 m3
pasir pasang
278,750.00
5,017.50
1.5000 kg
Semen warna
9,833.33
14,750.00
0.6000 oh
pekerja
55,000.00
33,000.00
0.4500 oh
tukang batu
70,000.00
31,500.00
0.0450 oh
kepala tukang
75,000.00
3,375.00
0.0300 oh
mandor
75,000.00
JUMLAH
2,250.00
59,681.57
70,125.00
129,806.57
M.6.6.69
0.09
Keramik 10 x 20 cm
1,027.78
51,388.89
9.3000 Kg
Semen abu-abu
1,300.00
12,090.00
0.0180 m3
pasir pasang
278,750.00
5,017.50
1.5000 kg
Semen warna
9,833.33
14,750.00
0.6000 oh
pekerja
55,000.00
33,000.00
0.1250 oh
tukang batu
70,000.00
8,750.00
0.0125 oh
kepala tukang
75,000.00
937.50
0.0300 oh
mandor
75,000.00
2,250.00
0.09
M.6.6.70
0.09
JUMLAH
1.0200 m2
marmer
2.0000 Kg
25,000.00
50,000.00
16,172.00
12.4400 Kg
0.09
Semen abu-abu
1,300.00
pasir pasang
278,750.00
6,968.75
1.5000 kg
Semen warna
9,833.33
14,750.00
0.7200 oh
pekerja
55,000.00
39,600.00
0.6500 oh
tukang batu
70,000.00
45,500.00
0.0650 oh
kepala tukang
75,000.00
4,875.00
0.0350 oh
mandor
75,000.00
JUMLAH
0.09
0.09
92,600.00
770.00
46,200.00
12.4400 Kg
Semen abu-abu
1,300.00
16,172.00
0.0250 m3
pasir pasang
278,750.00
6,968.75
0.6500 oh
pekerja
9,833.33
6,391.67
0.5000 oh
tukang batu
55,000.00
27,500.00
0.0500 oh
kepala tukang
75,000.00
3,750.00
0.0300 oh
mandor
75,000.00
JUMLAH
180,490.75
2,250.00
69,340.75
39,891.67
109,232.42
770.00
61,600.00
12.4400 Kg
Semen abu-abu
1,300.00
16,172.00
0.0250 m3
pasir pasang
278,750.00
6,968.75
0.6200 oh
pekerja
55,000.00
34,100.00
0.3500 oh
tukang batu
70,000.00
24,500.00
0.0350 oh
kepala tukang
75,000.00
2,625.00
0.0350 oh
mandor
75,000.00
JUMLAH
2,625.00
84,740.75
63,850.00
148,590.75
Batu paros
Semen abu-abu
1,500.00
17,625.00
0.0350 m3
pasir pasang
278,750.00
9,756.25
0.6200 oh
pekerja
55,000.00
34,100.00
0.3500 oh
tukang batu
70,000.00
24,500.00
0.0350 oh
kepala tukang
75,000.00
2,625.00
0.0300 oh
mandor
75,000.00
11.7500 Kg
0.09
2,625.00
87,890.75
60.0000 Bh
0.09
M.6.6.73
128,183.89
0.09
M.6.6.72
44,937.50
0.0250 m3
0.09
M.6.6.71
83,246.39
JUMLAH
2,250.00
27,381.25
63,475.00
90,856.25
M.6.6.74
0.09
Semen abu-abu
1,300.00
15,275.00
0.0350 m3
pasir pasang
278,750.00
9,756.25
0.6200 oh
pekerja
55,000.00
34,100.00
0.3500 oh
tukang batu
70,000.00
24,500.00
0.0350 oh
kepala tukang
75,000.00
2,625.00
0.0300 oh
mandor
75,000.00
11.7500 Kg
0.09
M.6.6.75
0.09
JUMLAH
0.09
11.0500 m2
0.09
Vinyl karet 30 x 30 cm KL I
Lem Vinyl
0.1500 oh
pekerja
55,000.00
8,250.00
0.1500 oh
tukang batu
70,000.00
10,500.00
0.0150 oh
kepala tukang
75,000.00
1,125.00
0.0075 oh
mandor
75,000.00
0.09
0.09
88,506.25
JUMLAH
562.50
-
20,437.50
20,437.50
Vinyl karet 30 x 30 cm KL II
0.3500 Kg
Lem Vinyl
0.1500 oh
pekerja
55,000.00
8,250.00
0.1500 oh
tukang batu
70,000.00
10,500.00
0.0150 oh
kepala tukang
75,000.00
1,125.00
0.0075 oh
mandor
75,000.00
JUMLAH
562.50
-
20,437.50
20,437.50
Vinyl asbes 30 x 30 cm
0.3500 Kg
Lem Vinyl
0.1500 oh
pekerja
55,000.00
8,250.00
0.1500 oh
tukang batu
70,000.00
10,500.00
0.0150 oh
kepala tukang
75,000.00
1,125.00
0.0075 oh
mandor
75,000.00
0.09
M.6.6.78
63,475.00
0.3500 Kg
0.09
M.6.6.77
2,250.00
25,031.25
0.09
M.6.6.76
JUMLAH
562.50
-
20,437.50
20,437.50
0.3500 Kg
Lem Vinyl
0.1500 oh
pekerja
55,000.00
8,250.00
0.1500 oh
tukang batu
70,000.00
10,500.00
0.0150 oh
kepala tukang
75,000.00
1,125.00
0.0075 oh
mandor
75,000.00
JUMLAH
562.50
-
20,437.50
20,437.50
M.6.6.79
0.09
0.2500 Kg
Lem
0.7500 oh
pekerja
55,000.00
41,250.00
0.1700 oh
tukang batu
70,000.00
11,900.00
0.0170 oh
kepala tukang
75,000.00
1,275.00
0.0085 oh
mandor
75,000.00
0.09
M.6.6.80
0.09
JUMLAH
0.09
0.09
637.50
-
55,062.50
3.0000 Kg
0.1200 oh
pekerja
55,000.00
6,600.00
0.1200 oh
tukang batu
70,000.00
8,400.00
0.0120 oh
kepala tukang
75,000.00
900.00
0.0060 oh
mandor
75,000.00
55,062.50
JUMLAH
450.00
-
16,350.00
16,350.00
Mastercron "S"
0.1200 oh
pekerja
55,000.00
6,600.00
0.1200 oh
tukang batu
70,000.00
8,400.00
0.0120 oh
kepala tukang
75,000.00
900.00
0.0060 oh
mandor
75,000.00
0.09
M.6.6.82
0.09
M.6.6.81
JUMLAH
450.00
-
16,350.00
16,350.00
1 M2 PLINT KAYU 2 X 10 CM
0.0024 m3
7,000,000.00
0.0500 Kg
20,000.00
1,000.00
0.1200 oh
pekerja
55,000.00
6,600.00
0.1200 oh
tukang batu
70,000.00
8,400.00
0.0120 oh
kepala tukang
75,000.00
900.00
0.0060 oh
mandor
75,000.00
0.09
JUMLAH
16,800.00
450.00
16,800.00
17,350.00
34,150.00
Soda Api
0.1500 oh
pekerja
55,000.00
8,250.00
0.0750 oh
tukang cat
70,000.00
5,250.00
0.0075 oh
kepala tukang
75,000.00
562.50
0.0025 oh
mandor
75,000.00
JUMLAH
N. 6.6.2
187.50
-
14,250.00
14,250.00
Sabun
10,500.00
0.1500 oh
pekerja
55,000.00
8,250.00
0.0750 oh
tukang cat
70,000.00
5,250.00
0.0075 oh
kepala tukang
75,000.00
562.50
0.0025 oh
mandor
75,000.00
JUMLAH
525.00
187.50
525.00
14,250.00
14,775.00
N. 6.6.3
Sabun
10,500.00
0.1500 oh
pekerja
55,000.00
8,250.00
0.0750 oh
tukang cat
70,000.00
5,250.00
0.0075 oh
kepala tukang
75,000.00
562.50
0.0025 oh
mandor
75,000.00
JUMLAH
N. 6.6.4
187.50
525.00
14,250.00
14,775.00
Sabun
10,500.00
0.1500 oh
pekerja
55,000.00
8,250.00
0.0750 oh
tukang cat
70,000.00
5,250.00
0.0075 oh
kepala tukang
75,000.00
562.50
0.0025 oh
mandor
75,000.00
JUMLAH
N. 6.6.5
525.00
525.00
187.50
525.00
14,250.00
14,775.00
Pasir silika
10.0000 Ltr
BBM, solar
6,950.00
69,500.00
425,197.11
425,197.11
1.0000 Hr
1.6000 oh
pekerja
55,000.00
88,000.00
1.6000 oh
tukang cat
70,000.00
112,000.00
0.8000 oh
kepala tukang
75,000.00
60,000.00
0.5000 oh
mandor
75,000.00
JUMLAH
N. 6.6.6
792,197.11
792,197.11
Dempul jadi
21,666.67
1,733.33
0.0200 kg
Minyak cat
12,500.00
250.00
0.0100 kg
Batu apung
15,125.00
151.25
0.0400 oh
pekerja
55,000.00
2,200.00
0.0400 oh
tukang cat
70,000.00
2,800.00
0.0040 oh
kepala tukang
75,000.00
300.00
0.0025 oh
mandor
75,000.00
JUMLAH
N. 6.6.7
37,500.00
-
187.50
2,134.58
5,487.50
7,622.08
plamir
18,500.00
2,775.00
0.1700 kg
cat dasar
20,333.33
3,456.67
0.1700 kg
cat penutup/kilap
36,750.00
6,247.50
0.0700 oh
pekerja
55,000.00
3,850.00
0.0750 oh
tukang cat
70,000.00
5,250.00
0.0075 oh
kepala tukang
75,000.00
562.50
0.0025 oh
mandor
75,000.00
JUMLAH
187.50
12,479.17
9,850.00
22,329.17
N. 6.6.8
cat meni
20,333.33
4,066.67
0.1200 kg
Plamir
20,000.00
2,400.00
0.1700 kg
cat dasar
20,000.00
3,400.00
0.2600 kg
36,750.00
9,555.00
0.0700 oh
pekerja
55,000.00
3,850.00
0.0090 oh
tukang cat
70,000.00
630.00
0.0060 oh
kepala tukang
75,000.00
450.00
0.0025 oh
mandor
75,000.00
JUMLAH
N. 6.6.9
187.50
19,421.67
5,117.50
24,539.17
cat meni
20,333.33
4,066.67
0.1500 kg
plamir
20,000.00
3,000.00
0.1700 kg
cat dasar
20,000.00
3,400.00
0.3500 oh
36,750.00
12,862.50
0.0700 oh
pekerja
55,000.00
3,850.00
0.1050 oh
tukang cat
70,000.00
7,350.00
0.0040 oh
kepala tukang
75,000.00
300.00
0.0025 oh
mandor
75,000.00
JUMLAH
N. 6.6.10
0.3600 ltr
oli bekas
37,300.00
0.0400 oh
pekerja
55,000.00
2,200.00
0.0630 oh
tukang cat
70,000.00
4,410.00
0.0630 oh
kepala tukang
75,000.00
4,725.00
0.0025 oh
mandor
75,000.00
35,016.67
13,428.00
187.50
13,428.00
11,522.50
24,950.50
plitur
35,583.33
5,337.50
0.3720 ltr
plitur jadi
35,583.33
13,237.00
2.0000 lbr
ampelas
2,875.00
5,750.00
pekerja
0.0600 oh
tukang cat
70,000.00
4,200.00
0.0160 oh
kepala tukang
75,000.00
1,200.00
0.0025 oh
mandor
75,000.00
oh
JUMLAH
N. 6.6.12
11,687.50
JUMLAH
N. 6.6.11
187.50
23,329.17
187.50
24,324.50
5,587.50
29,912.00
5,000.00
1,750.00
0.1000 oh
pekerja
45,000.00
4,500.00
oh
tukang cat
oh
kepala tukang
mandor
0.0060 oh
60,000.00
JUMLAH
360.00
6,250.00
360.00
6,610.00
N. 6.6.13
Vernis
10,000.00
1,500.00
0.0500 Kg
Dempul
21,666.67
1,083.33
0.1000 Ltr
ampelas
2,875.00
287.50
0.0100 bh
Kuas
7,500.00
75.00
0.1600 oh
pekerja
55,000.00
8,800.00
0.1600 oh
tukang cat
70,000.00
11,200.00
0.0160 oh
kepala tukang
75,000.00
1,200.00
0.0025 oh
mandor
75,000.00
JUMLAH
N. 6.6.14
187.50
2,945.83
21,387.50
24,333.33
plamir
20,000.00
0.1000 kg
cat dasar
8,600.00
860.00
0.2600 kg
cat penutup
8,600.00
2,236.00
0.0200 oh
pekerja
55,000.00
1,100.00
0.0630 oh
tukang cat
70,000.00
4,410.00
0.0063 oh
kepala tukang
75,000.00
472.50
0.0025 oh
mandor
75,000.00
JUMLAH
N. 6.6.15
2,000.00
187.50
5,096.00
6,170.00
11,266.00
cat dasar
20,000.00
2,400.00
0.1800 kg
cat penutup 2 x
8,600.00
1,548.00
0.0280 oh
pekerja
8,600.00
240.80
0.0420 oh
tukang cat
70,000.00
2,940.00
0.0042 oh
kepala tukang
75,000.00
315.00
0.0025 oh
mandor
75,000.00
JUMLAH
N. 6.6.16
3,683.30
7,631.30
Kalkarium
0.0280 oh
pekerja
55,000.00
1,540.00
0.0420 oh
tukang cat
70,000.00
2,940.00
0.0042 oh
kepala tukang
75,000.00
315.00
0.0025 oh
mandor
75,000.00
JUMLAH
N. 6.6.17
187.50
3,948.00
187.50
-
4,982.50
4,982.50
Ampelas
2,875.00
0.2500 Ikat
Alang-alang
500.00
125.00
0.0020 m3
Perancah kayu
2,300,000.00
4,600.00
0.1500 kg
kapur sirih
10,000.00
1,500.00
0.1500 oh
pekerja
55,000.00
8,250.00
0.0010 oh
tukang cat
70,000.00
70.00
0.0001 oh
kepala tukang
75,000.00
7.50
0.0025 oh
mandor
75,000.00
187.50
JUMLAH
287.50
6,512.50
8,515.00
15,027.50
N. 6.6.18
Perancah kayu
2,300,000.00
4,600.00
0.3000 kg
kapur sirih
10,000.00
3,000.00
0.0400 oh
pekerja
55,000.00
2,200.00
0.0050 oh
tukang cat
70,000.00
350.00
0.0005 oh
kepala tukang
75,000.00
37.50
0.0025 oh
Mandor
75,000.00
187.50
JUMLAH
N. 6.6.19
7,600.00
1.2000 lbr
Wall paper
0.2000 kg
Perekat
10,000.00
2,000.00
0.0200 oh
pekerja
55,000.00
1,100.00
0.2000 oh
tukang cat
70,000.00
14,000.00
0.0020 oh
kepala tukang
75,000.00
150.00
0.0025 oh
Mandor
75,000.00
JUMLAH
N. 6.6.20
187.50
2,000.00
15,437.50
0.1000 kg
meni besi
20,333.33
2,033.33
0.0100 Ikat
Kuas
9,666.67
96.67
0.0200 oh
pekerja
55,000.00
1,100.00
0.2000 oh
tukang cat
70,000.00
14,000.00
0.0200 oh
kepala tukang
75,000.00
1,500.00
0.0100 oh
Mandor
75,000.00
17,437.50
750.00
2,130.00
17,350.00
19,480.00
meni besi
20,333.33
0.0100 Ikat
Kuas
9,666.67
96.67
0.0020 m3
Perancah kayu
2,300,000.00
4,600.00
0.2500 oh
pekerja
55,000.00
13,750.00
0.2250 oh
tukang cat
70,000.00
15,750.00
0.0225 oh
kepala tukang
75,000.00
1,687.50
0.0075 oh
Mandor
75,000.00
JUMLAH
N. 6.6.22
10,375.00
JUMLAH
N. 6.6.21
2,775.00
2,033.33
562.50
6,730.00
31,750.00
38,480.00
0.1000 kg
0.0400 kg
Alumunium C
0.0400 kg
Alumunium C
0.0100 Ltr
Pengencer
0.0020 m3
Perancah kayu
2,300,000.00
0.0060 oh
pekerja
55,000.00
0.0060 oh
tukang cat
70,000.00
420.00
0.0225 oh
kepala tukang
75,000.00
1,687.50
0.0075 oh
Mandor
4,600.00
330.00
75,000.00
JUMLAH
562.50
4,600.00
3,000.00
7,600.00
N. 6.6.23
cat
0.0060 oh
pekerja
55,000.00
330.00
0.0600 oh
tukang cat
70,000.00
4,200.00
0.0120 oh
kepala tukang
75,000.00
900.00
0.0060 oh
Mandor
75,000.00
JUMLAH
N. 6.6.24
450.00
-
5,880.00
5,880.00
Cat dasar
0.1700 kg
cat antara
0.0800 kg
cat penutup
0.5000 oh
pekerja
55,000.00
27,500.00
0.8000 oh
tukang cat
70,000.00
56,000.00
0.3000 oh
kepala tukang
75,000.00
22,500.00
0.2000 oh
Mandor
75,000.00
JUMLAH
N. 6.6.25
15,000.00
-
121,000.00
121,000.00
cat dasar
0.4000 oh
pekerja
55,000.00
22,000.00
0.7000 oh
tukang cat
70,000.00
49,000.00
0.2000 oh
kepala tukang
75,000.00
15,000.00
0.2000 oh
Mandor
75,000.00
JUMLAH
15,000.00
-
101,000.00
101,000.00
65,000.00 Semen
1,300.00
2600
HARGA
INDEK
SATUAN
URAIAN
HARGA SATUAN ( Rp )
BAHAN
UPAH
( Rp )
( Rp )
JUMLAH HARGA ( Rp )
A. PEKERJAAN PERSIAPAN
A. 6.6.1
9,500.00
11,875.00
2.5000 kg
Semen portland
1,298.00
3,245.00
0.0050 m3
Pasir beton
250,000.00
1,250.00
0.0090 m3
Koral beton
263,000.00
2,367.00
0.0720 m3
Kayu 5/7
1,800,000.00
129,600.00
0.0600 kg
15,583.33
935.00
0.4000 lt
Residu
20,333.33
8,133.33
0.2000 oh
Tukang kayu
70,000.00
14,000.00
0.4000 oh
Pekerja
55,000.00
22,000.00
0.0200 oh
Kepala tukang
75,000.00
1,500.00
0.0200 oh
Mandor
75,000.00
JUMLAH
A. 6.6.2
39,000.00
196,405.33
9,500.00
2.5000 kg
Semen portland
1,298.00
3,245.00
1.2000 Lbr
39,125.00
46,950.00
0.0050 m3
Pasir Beton
250,000.00
1,250.00
0.0090 m3
Koral beton
263,000.00
2,367.00
0.0720 kg
Kayu 5/7
1,800,000.00
129,600.00
0.0600 kg
15,583.33
935.00
0.4500 Kg
Meni besi
20,333.33
9,150.00
0.2000 oh
Tukang kayu
70,000.00
14,000.00
0.4000 oh
Pekerja
55,000.00
22,000.00
0.0200 oh
Kepala tukang
75,000.00
1,500.00
0.0200 oh
Mandor
75,000.00
JUMLAH
A. 6.6.3
1,500.00
157,405.33
11,875.00
1,500.00
205,372.00
39,000.00
244,372.00
9,500.00
2.5000 kg
Semen portland
1,300.00
3,250.00
Kawat Duri
79,166.67
1,979,166.67
0.0050 m3
Pasir Beton
250,000.00
1,250.00
0.0090 m3
Koral beton
263,000.00
2,367.00
0.0720 kg
15,583.33
1,122.00
0.2000 oh
Tukang kayu
70,000.00
14,000.00
0.3000 oh
Pekerja
55,000.00
16,500.00
0.0200 oh
Kepala tukang
75,000.00
1,500.00
0.0200 oh
Mandor
75,000.00
25.0000 kg
JUMLAH
11,875.00
1,500.00
1,999,030.67
33,500.00
2,032,530.67
Hal : 404
A. 6.6.4
1,750,000.00
0.0200 kg
15,583.33
311.67
0.0070 m3
2,300,000.00
16,100.00
0.1000 oh
tukang kayu
70,000.00
7,000.00
0.1000 oh
pekerja
55,000.00
5,500.00
0.0100 oh
kepala tukang
75,000.00
750.00
0.0050 oh
mandor
75,000.00
JUMLAH
A. 6.6.5
375.00
37,411.67
13,625.00
51,036.67
9,500.00
11,875.00
0.1800 kg
Kayu
1,750,000.00
315,000.00
0.8500 m3
Kayu Biasa
1,800,000.00
1,530,000.00
1.1000 m3
Besi Strip
31,800.00
34,980.00
Semen portland
1,300.00
45,500.00
0.1500 kg
Pasir Pasang
278,750.00
41,812.50
0.1000 m3
Pasir Beton
250,000.00
25,000.00
0.1500 m3
Koral beton
263,000.00
39,450.00
Bata merah
800.00
24,000.00
0.2500 Lbr
Seng Plat
45,833.33
11,458.33
2.0000 Bh
Jendela Nako
326,700.00
653,400.00
0.0800 m2
Kaca Polos
102,300.00
8,184.00
0.0150 Bh
Kunci Tanam
0.0600 Lbr
Plywood 4 mm
55,000.00
70,000.00
70,000.00
70,000.00
55,000.00
110,000.00
22,500.00
35.0000 kg
30.0000 Bh
2.0000 oh
1.0000 oh
2.0000 oh
tukang kayu
Tukang Batu
pekerja
0.3000 oh
Kepala tukang
75,000.00
0.0500 oh
Mandor
75,000.00
JUMLAH
A. 6.6.6
21,000.00
3,300.00
140,000.00
3,750.00
2,743,959.83
346,250.00
3,090,209.83
9,500.00
16,150.00
0.2100 kg
Kayu
1,750,000.00
367,500.00
0.3000 kg
15,583.33
4,675.00
10.5000 kg
Semen portland
1,300.00
13,650.00
0.0300 m3
Pasir Beton
250,000.00
7,500.00
0.0500 m3
Koral beton
263,000.00
13,150.00
1.5000 Lbr
Seng gelombang
39,125.00
58,687.50
2.0000 oh
Tukang kayu
70,000.00
140,000.00
1.0000 oh
Pekerja
55,000.00
55,000.00
0.2000 oh
Kepala tukang
75,000.00
15,000.00
0.0500 oh
Mandor
75,000.00
JUMLAH
3,750.00
481,312.50
213,750.00
695,062.50
A. 6.6.7
9,500.00
28,500.00
0.2760 kg
Kayu
1,750,000.00
483,000.00
0.7000 kg
15,583.33
10,908.33
1.5000 Lbr
39,125.00
58,687.50
1.5000 oh
Tukang kayu
70,000.00
105,000.00
1.0000 oh
Pekerja
55,000.00
55,000.00
0.1500 oh
Kepala tukang
75,000.00
11,250.00
0.0500 oh
Mandor
75,000.00
JUMLAH
A. 6.6.8
0.1000 oh
pekerja
55,000.00
0.0500 oh
mandor
75,000.00
5,500.00
3,750.00
-
9,250.00
1.2500 btg
9,500.00
11,875.00
0.1860 kg
Kayu
1,750,000.00
325,500.00
0.3000 Kg
15,583.33
4,675.00
Semen portland
1,300.00
23,400.00
0.0300 m3
Pasir Beton
250,000.00
7,500.00
0.0500 m3
Koral beton
263,000.00
13,150.00
1.5000 Lbr
39,125.00
58,687.50
1.3500 Lbr
Plywood 4 mm
55,000.00
74,250.00
2.0000 oh
Tukang kayu
70,000.00
140,000.00
1.0000 oh
Pekerja
55,000.00
55,000.00
0.2000 oh
Kepala tukang
75,000.00
15,000.00
0.0500 oh
Mandor
75,000.00
JUMLAH
9,250.00
3,750.00
519,037.50
213,750.00
732,787.50
Kayu Terentang
1,750,000.00
0.0800 kg
15,583.33
1,246.67
1.0000 btg
kaso 5/7
25,000.00
25,000.00
0.3000 oh
Tukang kayu
70,000.00
0.0015 oh
Mandor
75,000.00
JUMLAH
A. 6.6.11
756,095.83
18.0000 kg
A. 6.6.10
175,000.00
JUMLAH
A. 6.6.9
3,750.00
581,095.83
63,000.00
21,000.00
112.50
89,246.67
21,112.50
110,359.17
10,000.00
10,000.00
0.2500 kg
Tali Ijuk
25,000.00
6,250.00
0.0170 oh
Tukang kayu
70,000.00
1,190.00
0.2500 oh
Pekerja
55,000.00
13,750.00
0.0020 oh
Kepala tukang
75,000.00
150.00
0.0130 oh
Mandor
75,000.00
JUMLAH
975.00
16,250.00
16,065.00
29,335.00
A. 6.6.12
215,400.00
32,310.00
0.0900 m3
263,000.00
23,670.00
0.0100 m3
Pasir pasang
278,750.00
2,787.50
1.0000 oh
pekerja
55,000.00
0.0500 oh
mandor
75,000.00
JUMLAH
A. 6.6.13
0.3330 oh
pekerja
Mandor
55,000.00
75,000.00
JUMLAH
0.3330 oh
117,517.50
366,685.00
24,975.00
-
pekerja
Mandor
55,000.00
75,000.00
JUMLAH
391,660.00
391,660.00
366,685.00
24,975.00
-
391,660.00
391,660.00
107,300.00
0.0420 oh
Pekerja
55,000.00
0.0040 oh
Kepala tukang
75,000.00
300.00
0.0420 oh
Tukang
70,000.00
2,940.00
0.0020 oh
Mandor
46,568.20
2,310.00
75,000.00
JUMLAH
A. 6.6.16
58,750.00
A. 6.6.15
3,750.00
58,767.50
A. 6.6.14
55,000.00
150.00
46,568.20
5,700.00
52,268.20
0.5250 btg
0.0740 m3
Pasir Beton
250,000.00
18,500.00
0.1460 m3
Koral
263,000.00
38,398.00
1,300.00
58,500.00
0.1250 oh
Tukang batu
70,000.00
0.0120 oh
Kepala tukang
75,000.00
900.00
0.3750 oh
pekerja
55,000.00
20,625.00
0.0190 oh
mandor
45.0000 kg
8,750.00
75,000.00
JUMLAH
1,425.00
115,398.00
31,700.00
147,098.00
B. PEKERJAAN TANAH
B. 6.6.1
pekerja
55,000.00
oh
tukang gali
70,000.00
oh
kepala tukang
75,000.00
mandor
75,000.00
0.0400 oh
JUMLAH
22,000.00
3,000.00
25,000.00
25,000.00
B. 6.6.2
pekerja
55,000.00
oh
tukang gali
70,000.00
oh
kepala tukang
75,000.00
mandor
75,000.00
0.0520 oh
JUMLAH
B. 6.6.3
pekerja
55,000.00
oh
tukang gali
70,000.00
oh
kepala tukang
75,000.00
mandor
75,000.00
0.0730 oh
JUMLAH
pekerja
55,000.00
oh
tukang gali
70,000.00
oh
kepala tukang
75,000.00
mandor
75,000.00
0.0620 oh
JUMLAH
pekerja
55,000.00
oh
tukang gali
70,000.00
oh
kepala tukang
75,000.00
mandor
75,000.00
0.1250 oh
JUMLAH
pekerja
55,000.00
oh
tukang gali
70,000.00
oh
kepala tukang
75,000.00
mandor
75,000.00
0.0830 oh
JUMLAH
40,425.00
5,475.00
45,900.00
45,900.00
34,375.00
4,650.00
39,025.00
39,025.00
68,750.00
9,375.00
78,125.00
78,125.00
45,265.00
6,225.00
51,490.00
51,490.00
pekerja
55,000.00
oh
tukang gali
70,000.00
oh
kepala tukang
75,000.00
mandor
75,000.00
375.00
0.0050 oh
JUMLAH
B. 6.6.8
32,830.00
B. 6.6.7
32,830.00
B. 6.6.6
3,900.00
B. 6.6.5
B. 6.6.4
28,930.00
2,750.00
-
3,125.00
3,125.00
pekerja
55,000.00
oh
tukang gali
70,000.00
oh
kepala tukang
75,000.00
mandor
75,000.00
0.0500 oh
JUMLAH
28,380.00
3,750.00
32,130.00
32,130.00
B. 6.6.9
1 M3 URUGAN KEMBALI
0.1920 oh
pekerja
55,000.00
oh
tukang gali
70,000.00
oh
kepala tukang
75,000.00
mandor
75,000.00
0.0190 oh
10,560.00
1,425.00
JUMLAH
B. 6.6.10
11,985.00
0.5000 oh
pekerja
55,000.00
oh
tukang gali
70,000.00
oh
kepala tukang
75,000.00
mandor
75,000.00
0.0500 oh
27,500.00
3,750.00
JUMLAH
B. 6.6.11
31,250.00
1.2000 M3
Tanah urug
51,900.00
0.2500 oh
pekerja
55,000.00
0.0250 oh
mandor
75,000.00
1,875.00
1.0000 oh
Ls biaya pemadatan
31,250.00
31,250.00
13,750.00
62,280.00
46,875.00
1.2000 M3
pasir urug
51,900.00
0.3000 oh
pekerja
55,000.00
0.0100 oh
mandor
75,000.00
750.00
1.0000 oh
Ls biaya pemadatan
31,250.00
31,250.00
109,155.00
62,280.00
16,500.00
62,280.00
48,500.00
110,780.00
pasir urug
0.1090 M3
kapur padam
51,900.00
0.7630 M3
tanah liat
0.8330 oh
pekerja
55,000.00
45,815.00
0.4160 oh
tukang batu
70,000.00
29,120.00
0.0400 oh
kepala tukang
75,000.00
3,000.00
0.0830 oh
mandor
75,000.00
JUMLAH
B. 6.6.13
62,280.00
1 M3 URUGAN PASIR
JUMLAH
B. 6.6.12
31,250.00
1 M3 URUGAN TANAH
JUMLAH
B. 6.6.11.a
11,985.00
PEMADATAN TANAH
17,127.00
6,225.00
17,127.00
84,160.00
133,602.12
kapur padam
1.0000 M3
tanah liat
0.8330 oh
pekerja
55,000.00
45,815.00
0.4160 oh
tukang batu
70,000.00
29,120.00
0.0410 oh
kepala tukang
75,000.00
3,075.00
0.0810 oh
mandor
75,000.00
JUMLAH
6,075.00
-
84,085.00
84,085.00
B. 6.6.14
ijuk
0.1500 oh
pekerja
55,000.00
oh
tukang gali
70,000.00
oh
kepala tukang
75,000.00
mandor
75,000.00
0.0150 oh
JUMLAH
B. 6.6.15
1,125.00
-
9,375.00
9,375.00
1 M3 URUGAN SIRTU
1.2000 M3
Sirtu
274,800.00
0.2500 oh
pekerja
55,000.00
oh
tukang gali
70,000.00
oh
kepala tukang
75,000.00
mandor
75,000.00
0.0250 oh
JUMLAH
B. 6.6.16
8,250.00
329,760.00
13,750.00
1,875.00
329,760.00
15,625.00
345,385.00
batu belah
215,400.00
0.0300 m3
kerikil /Koral
263,000.00
7,890.00
0.0500 m3
pasir
250,000.00
12,500.00
1.0000 oh
pekerja
55,000.00
oh
tukang gali
70,000.00
oh
kepala tukang
75,000.00
mandor
75,000.00
0.1000 oh
JUMLAH
59,235.00
55,000.00
7,500.00
79,625.00
62,500.00
142,125.00
C. PEKERJAAN PONDASI
C.6.6.1
215,400.00
236,940.00
semen porland
1,300.00
509,600.00
0.3140 m3
pasir pasang
250,000.00
78,500.00
1.5000 oh
pekerja
55,000.00
82,500.00
0.6000 oh
tukang batu
70,000.00
42,000.00
0.0600 oh
kepala tukang
75,000.00
4,500.00
0.0750 oh
mandor
75,000.00
392.0000 kg
JUMLAH
C.6.6.2
5,625.00
825,040.00
134,625.00
959,665.00
215,400.00
236,940.00
semen porland
1,300.00
347,100.00
0.4270 m3
pasir pasang
250,000.00
106,750.00
1.5000 oh
pekerja
55,000.00
82,500.00
0.6000 oh
tukang batu
70,000.00
42,000.00
0.0600 oh
kepala tukang
75,000.00
4,500.00
0.0750 oh
mandor
75,000.00
267.0000 kg
JUMLAH
5,625.00
690,790.00
134,625.00
825,415.00
C.6.6.3
215,400.00
236,940.00
semen porland
1,300.00
509,600.00
0.3140 m3
pasir pasang
250,000.00
78,500.00
1.5000 oh
pekerja
55,000.00
82,500.00
0.6000 oh
tukang batu
70,000.00
42,000.00
0.0600 oh
kepala tukang
75,000.00
4,500.00
0.0750 oh
mandor
75,000.00
392.0000 kg
JUMLAH
C.6.6.4
134,625.00
1.1000 m3
215,400.00
236,940.00
semen porland
1,300.00
262,600.00
0.4850 m3
pasir pasang
250,000.00
121,250.00
1.5000 oh
pekerja
55,000.00
82,500.00
0.6000 oh
tukang batu
70,000.00
42,000.00
0.0600 oh
kepala tukang
75,000.00
4,500.00
0.0750 oh
mandor
75,000.00
JUMLAH
5,625.00
620,790.00
134,625.00
1.1000 m3
215,400.00
236,940.00
semen porland
1,300.00
211,900.00
0.5200 m3
250,000.00
130,000.00
1.5000 oh
pekerja
55,000.00
82,500.00
3.6
0.6000 oh
tukang batu
70,000.00
42,000.00
0.36
0.0600 oh
kepala tukang
75,000.00
4,500.00
0.45
0.0750 oh
mandor
75,000.00
JUMLAH
1.1000 m3
134,625.00
215,400.00
236,940.00
semen porland
1,300.00
211,900.00
0.5200 m3
64,500.00
33,540.00
1.5000 oh
pekerja
55,000.00
82,500.00
0.6000 oh
tukang batu
70,000.00
42,000.00
0.0600 oh
kepala tukang
75,000.00
4,500.00
0.0750 oh
mandor
75,000.00
JUMLAH
713,465.00
5,625.00
482,380.00
134,625.00
617,005.00
225,000.00
247,500.00
semen porland
1,300.00
211,900.00
0.5200 m3
225,000.00
117,000.00
1.5000 oh
pekerja
55,000.00
82,500.00
0.6000 oh
tukang batu
70,000.00
42,000.00
0.0600 oh
kepala tukang
75,000.00
4,500.00
0.0750 oh
mandor
75,000.00
163.0000 kg
JUMLAH
C.6.6.6
5,625.00
578,840.00
C.6.6.5.b
755,415.00
C.6.6.5.a
959,665.00
C.6.6.5
5,625.00
825,040.00
5,625.00
576,400.00
215,400.00
236,940.00
semen porland
1,300.00
176,800.00
pasir pasang
250,000.00
136,000.00
134,625.00
711,025.00
1.5000 oh
pekerja
55,000.00
82,500.00
0.6000 oh
tukang batu
70,000.00
42,000.00
0.0600 oh
kepala tukang
75,000.00
4,500.00
0.0750 oh
mandor
75,000.00
JUMLAH
C.6.6.7
5,625.00
549,740.00
134,625.00
684,365.00
215,400.00
236,940.00
semen porland
1,300.00
152,100.00
0.5610 m3
pasir pasang
250,000.00
140,250.00
1.5000 oh
pekerja
55,000.00
82,500.00
0.6000 oh
tukang batu
70,000.00
42,000.00
0.0600 oh
kepala tukang
75,000.00
4,500.00
0.0750 oh
mandor
75,000.00
117.0000 kg
JUMLAH
5,625.00
529,290.00
134,625.00
663,915.00
C.6.6.8
215,400.00
236,940.00
semen porland
1,300.00
118,300.00
0.5610 m3
pasir pasang
250,000.00
140,250.00
1.5000 oh
pekerja
55,000.00
82,500.00
0.6000 oh
tukang batu
70,000.00
42,000.00
0.0600 oh
kepala tukang
75,000.00
4,500.00
0.0750 oh
mandor
75,000.00
91.0000 kg
JUMLAH
C.6.6.9
1.1000 m3
215,400.00
236,940.00
0.2290 kg
kapur pasang
1,300.00
297.70
0.2290 m3
semen merah
1,600.00
366.40
0.5440 oh
pasir pasang
250,000.00
136,000.00
1.5000 oh
pekerja
55,000.00
82,500.00
0.6000 oh
tukang batu
70,000.00
42,000.00
0.0600 oh
kepala tukang
75,000.00
4,500.00
0.0750 oh
mandor
75,000.00
630,115.00
5,625.00
373,299.60
108,600.00
481,899.60
215,400.00
236,940.00
0.1700 kg
kapur pasang
1,300.00
221.00
0.1700 m3
semen merah
1,600.00
272.00
0.3400 oh
pasir pasang
250,000.00
85,000.00
1.5000 oh
pekerja
55,000.00
82,500.00
0.6000 oh
tukang batu
70,000.00
42,000.00
0.0600 oh
kepala tukang
75,000.00
4,500.00
0.0750 oh
mandor
75,000.00
JUMLAH
C.6.6.11
134,625.00
JUMLAH
C.6.6.10
5,625.00
495,490.00
5,625.00
322,433.00
134,625.00
457,058.00
215,400.00
236,940.00
semen portland
1,300.00
202,800.00
0.0320 m3
kapur pasang
5,000.00
160.00
0.5480 oh
pasir pasang
250,000.00
137,000.00
1.5000 oh
pekerja
55,000.00
82,500.00
0.6000 oh
tukang batu
70,000.00
42,000.00
0.0600 oh
kepala tukang
75,000.00
4,500.00
0.0750 oh
mandor
75,000.00
156.0000 kg
JUMLAH
5,625.00
576,900.00
134,625.00
711,525.00
C.6.6.12
215,400.00
236,940.00
semen portland
1,300.00
79,300.00
0.1470 m3
kapur pasang
5,000.00
735.00
0.4920 oh
pasir pasang
250,000.00
123,000.00
1.5000 oh
pekerja
55,000.00
82,500.00
0.6000 oh
tukang batu
70,000.00
42,000.00
0.0600 oh
kepala tukang
75,000.00
4,500.00
0.0750 oh
mandor
75,000.00
61.0000 kg
JUMLAH
C.6.6.13
1.1000 m3
215,400.00
236,940.00
semen portland
1,300.00
53,300.00
0.1310 m3
kapur pasang
5,000.00
655.00
0.5230 oh
pasir pasang
250,000.00
130,750.00
1.5000 oh
pekerja
55,000.00
82,500.00
0.6000 oh
tukang batu
70,000.00
42,000.00
0.0600 oh
kepala tukang
75,000.00
4,500.00
0.0750 oh
mandor
75,000.00
JUMLAH
574,600.00
5,625.00
421,645.00
134,625.00
556,270.00
batu gunung
215,400.00
258,480.00
0.3000 m3
pasir urug
51,900.00
15,570.00
0.7800 oh
pekerja
55,000.00
42,900.00
0.3900 oh
tukang batu
70,000.00
27,300.00
0.0390 oh
kepala tukang
75,000.00
2,925.00
0.0390 oh
mandor
75,000.00
JUMLAH
C. 6.6.15
134,625.00
C. 6.6.14
5,625.00
439,975.00
2,925.00
274,050.00
76,050.00
350,100.00
besi beton
10,000.00
750,000.00
semen portland
1,300.00
262,600.00
0.3200 m3
pasir beton
250,000.00
80,000.00
0.4900 m3
koral beton
263,000.00
128,870.00
0.8000 kg
kawat beton
20,000.00
16,000.00
3.0000 oh
pekerja
55,000.00
165,000.00
0.8500 oh
tukang batu
70,000.00
59,500.00
0.0850 oh
kepala tukang
75,000.00
6,375.00
0.1500 oh
mandor
75,000.00
11,250.00
202.0000 kg
JUMLAH
1,237,470.00
242,125.00
1,479,595.00
C. 6.6.16
215,400.00
96,930.00
semen portland
1,300.00
364,000.00
0.4500 m3
pasir beton
250,000.00
112,500.00
0.6700 m3
koral beton
263,000.00
176,210.00
2.3800 oh
pekerja
55,000.00
130,900.00
0.3000 oh
tukang batu
70,000.00
21,000.00
0.0300 oh
kepala tukang
75,000.00
2,250.00
0.0800 oh
mandor
75,000.00
280.0000 kg
JUMLAH
C. 6.6.17
160,150.00
909,790.00
51,900.00
986.10
0.0940 m3
pasir beton
250,000.00
23,500.00
0.1500 m3
39,450.00
koral beton
263,000.00
60.5000 kg
semen portland
1,300.00
78,650.00
45.0000 kg
besi beton
11,750.00
528,750.00
0.9000 kg
kawat beton
20,000.00
18,000.00
0.0320 m3
1,750,000.00
56,000.00
0.1200 kg
paku
15,583.33
1,870.00
0.0900 lt
minyak bekisting
13,500.00
1,215.00
0.2400 kg
plamur tembok
18,500.00
4,440.00
1.0000 oh
pekerja
55,000.00
55,000.00
0.6700 oh
tukang batu
70,000.00
46,900.00
0.0670 oh
kepala tukang
75,000.00
5,025.00
0.0500 oh
mandor
75,000.00
JUMLAH
C. 6.6.18
6,000.00
749,640.00
3,750.00
752,861.10
110,675.00
863,536.10
51,900.00
830.40
0.0800 m3
pasir beton
250,000.00
20,000.00
0.1250 m3
32,875.00
koral beton
263,000.00
49.0000 kg
semen portland
1,300.00
63,700.00
34.5000 kg
besi beton
11,750.00
405,375.00
0.7000 kg
kawat beton
10,000.00
7,000.00
0.0270 m3
1,750,000.00
47,250.00
0.1200 kg
paku
15,583.33
1,870.00
0.0900 lt
minyak bekisting
13,500.00
1,215.00
0.2000 kg
plamur tembok
18,500.00
3,700.00
0.8000 oh
pekerja
55,000.00
44,000.00
0.5000 oh
tukang batu
70,000.00
35,000.00
0.0500 oh
kepala tukang
75,000.00
3,750.00
0.0400 oh
mandor
75,000.00
JUMLAH
3,000.00
583,815.40
85,750.00
669,565.40
D. PEKERJAAN DINDING
D.6.6.1
62.5
bata merah
800.00
96,000.00
semen portland
1,300.00
83,239.00
0.0590 m3
pasir pasang
250,000.00
14,750.00
0.6500 oh
pekerja
55,000.00
35,750.00
0.2000 oh
tukang batu
70,000.00
14,000.00
0.0200 oh
kepala tukang
75,000.00
1,500.00
0.0300 oh
mandor
75,000.00
64.0300 kg
JUMLAH
D.6.6.2
bata merah
800.00
96,000.00
semen portland
1,300.00
56,550.00
0.0800 m3
pasir pasang
250,000.00
20,000.00
0.6500 oh
pekerja
55,000.00
35,750.00
0.2000 oh
tukang batu
70,000.00
14,000.00
0.0200 oh
kepala tukang
75,000.00
1,500.00
0.0300 oh
mandor
75,000.00
43.5000 kg
JUMLAH
2,250.00
172,550.00
53,500.00
bata merah
800.00
96,000.00
semen portland
1,300.00
42,835.00
0.0910 m3
pasir pasang
250,000.00
22,750.00
0.6500 oh
pekerja
55,000.00
35,750.00
0.2000 oh
tukang batu
70,000.00
14,000.00
0.0200 oh
kepala tukang
75,000.00
1,500.00
0.0300 oh
mandor
75,000.00
32.9500 kg
JUMLAH
226,050.00
2,250.00
161,585.00
53,500.00
215,085.00
bata merah
800.00
96,000.00
semen portland
1,300.00
34,515.00
0.0930 m3
pasir pasang
250,000.00
23,250.00
0.6500 oh
pekerja
55,000.00
35,750.00
0.2000 oh
tukang batu
70,000.00
14,000.00
0.0200 oh
kepala tukang
75,000.00
1,500.00
0.0300 oh
mandor
75,000.00
26.5500 kg
JUMLAH
D.6.6.5
247,489.00
D.6.6.4
53,500.00
D.6.6.3
2,250.00
193,989.00
2,250.00
153,765.00
53,500.00
207,265.00
bata merah
800.00
96,000.00
semen portland
1,300.00
28,860.00
0.1020 m3
pasir pasang
250,000.00
25,500.00
0.6500 oh
pekerja
55,000.00
35,750.00
0.2000 oh
tukang batu
70,000.00
14,000.00
0.0200 oh
kepala tukang
75,000.00
1,500.00
0.0300 oh
mandor
75,000.00
22.2000 kg
JUMLAH
2,250.00
150,360.00
53,500.00
203,860.00
D.6.6.6
bata merah
800.00
96,000.00
semen portland
1,300.00
28,860.00
0.1020 m3
pasir pasang
250,000.00
25,500.00
0.6500 oh
pekerja
55,000.00
35,750.00
0.2000 oh
tukang batu
70,000.00
14,000.00
0.0200 oh
kepala tukang
75,000.00
1,500.00
0.0300 oh
mandor
75,000.00
22.2000 kg
JUMLAH
D.6.6.7
800.00
96,000.00
semen portland
1,300.00
13,104.00
0.0925 m3
pasir pasang
250,000.00
23,125.00
0.0275 m3
kapur pasang
5,000.00
137.50
0.6500 oh
pekerja
55,000.00
35,750.00
0.2000 oh
tukang batu
70,000.00
14,000.00
0.0200 oh
kepala tukang
75,000.00
1,500.00
0.0300 oh
mandor
75,000.00
2,250.00
132,366.50
53,500.00
185,866.50
bata merah
800.00
48,000.00
27.8000 kg
semen portland
1,300.00
36,140.00
0.0280 m3
pasir pasang
250,000.00
7,000.00
0.3200 oh
pekerja
55,000.00
17,600.00
0.1000 oh
tukang batu
70,000.00
7,000.00
0.0100 oh
kepala tukang
75,000.00
750.00
0.0150 oh
mandor
75,000.00
1,125.00
JUMLAH
91,140.00
26,475.00
117,615.00
bata merah 8 x 8 x 15 cm
800.00
48,000.00
18.9500 kg
semen porland
1,300.00
24,635.00
0.0380 m3
pasir pasang
250,000.00
9,500.00
0.3200 oh
pekerja
55,000.00
17,600.00
0.1000 oh
tukang batu
70,000.00
7,000.00
0.0100 oh
kepala tukang
75,000.00
750.00
0.0150 oh
mandor
75,000.00
1,125.00
JUMLAH
D. 6.6.10
203,860.00
JUMLAH
D. 6.6.9
53,500.00
bata merah
10.0800 kg
D.6.6.8
2,250.00
150,360.00
82,135.00
26,475.00
108,610.00
bata merah 8 x 8 x 15 cm
800.00
48,000.00
14.3700 kg
semen porland
1,300.00
18,681.00
0.0400 m3
pasir pasang
250,000.00
10,000.00
0.3200 oh
pekerja
55,000.00
17,600.00
0.1000 oh
tukang batu
70,000.00
7,000.00
0.0100 oh
kepala tukang
75,000.00
750.00
0.0150 oh
mandor
75,000.00
1,125.00
JUMLAH
76,681.00
26,475.00
103,156.00
D. 6.6.11
bata merah 8 x 8 x 15 cm
800.00
48,000.00
11.5000 kg
semen porland
1,300.00
14,950.00
0.0430 m3
pasir pasang
250,000.00
10,750.00
0.3200 oh
pekerja
55,000.00
17,600.00
0.1000 oh
tukang batu
70,000.00
7,000.00
0.0100 oh
kepala tukang
75,000.00
750.00
0.0150 oh
mandor
75,000.00
1,125.00
JUMLAH
73,700.00
26,475.00
100,175.00
D. 6.6.11.a 1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA, 1 pc ; 4 ps (pasir Putih Lokal)
60.0000 bh
bata merah 8 x 8 x 15 cm
800.00
48,000.00
11.5000 kg
semen porland
1,300.00
14,950.00
0.0430 m3
64,500.00
2,773.50
0.3200 oh
pekerja
55,000.00
17,600.00
0.1000 oh
tukang batu
70,000.00
7,000.00
0.0100 oh
kepala tukang
75,000.00
750.00
0.0150 oh
mandor
75,000.00
1,125.00
JUMLAH
65,723.50
26,475.00
92,198.50
D. 6.6.11.b 1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA, 1 pc ; 4 ps (pasir Putih Sepaku)
60.0000 bh
bata merah 8 x 8 x 15 cm
800.00
48,000.00
11.5000 kg
semen porland
1,300.00
14,950.00
0.0430 m3
225,000.00
9,675.00
0.3200 oh
pekerja
55,000.00
17,600.00
0.1000 oh
tukang batu
70,000.00
7,000.00
0.0100 oh
kepala tukang
75,000.00
750.00
0.0150 oh
mandor
75,000.00
1,125.00
JUMLAH
D. 6.6.12
bata merah 8 x 8 x 15 cm
800.00
48,000.00
9.6800 kg
semen porland
1,300.00
12,584.00
0.0450 m3
pasir pasang
250,000.00
11,250.00
0.3200 oh
pekerja
55,000.00
17,600.00
0.1000 oh
tukang batu
70,000.00
7,000.00
0.0100 oh
kepala tukang
75,000.00
750.00
0.0150 oh
mandor
75,000.00
1,125.00
JUMLAH
99,100.00
71,834.00
26,475.00
98,309.00
bata merah 8 x 8 x 15 cm
800.00
48,000.00
8.3200 kg
semen porland
1,300.00
10,816.00
0.0490 m3
pasir pasang
250,000.00
12,250.00
0.3200 oh
pekerja
55,000.00
17,600.00
0.1000 oh
tukang batu
70,000.00
7,000.00
0.0100 oh
kepala tukang
75,000.00
750.00
0.0150 oh
mandor
75,000.00
1,125.00
JUMLAH
D. 6.6.14
26,475.00
D. 6.6.13
72,625.00
71,066.00
bata merah 8 x 8 x 15 cm
800.00
48,000.00
26,475.00
97,541.00
6.5000 kg
semen porland
1,300.00
8,450.00
0.0500 m3
pasir pasang
250,000.00
12,500.00
0.3200 oh
pekerja
55,000.00
17,600.00
0.1000 oh
tukang batu
70,000.00
7,000.00
0.0100 oh
kepala tukang
75,000.00
750.00
0.0150 oh
mandor
75,000.00
1,125.00
JUMLAH
68,950.00
26,475.00
95,425.00
D. 6.6.15
bata merah 8 x 8 x 15 cm
800.00
4.5000 kg
semen porland
1,300.00
5,850.00
0.0500 m3
pasir pasang
250,000.00
12,500.00
0.0150 m3
kapur padam
5,000.00
75.00
0.3200 oh
pekerja
55,000.00
17,600.00
0.1000 oh
tukang batu
70,000.00
7,000.00
0.0100 oh
kepala tukang
75,000.00
750.00
0.0150 oh
mandor
75,000.00
1,125.00
JUMLAH
D. 6.6.16
26,550.00
bata merah
800.00
0.0180 kg
1,300.00
23.40
0.0180 m3
pasir pasang
250,000.00
4,500.00
0.0180 m3
kapur padam
5,000.00
90.00
0.3200 oh
pekerja
55,000.00
17,600.00
0.1000 oh
tukang batu
70,000.00
7,000.00
0.0100 oh
kepala tukang
75,000.00
750.00
0.0150 oh
mandor
75,000.00
1,125.00
JUMLAH
92,900.00
48,000.00
52,613.40
26,475.00
79,088.40
bata merah
800.00
0.0140 kg
1,300.00
18.20
0.0280 m3
pasir pasang
250,000.00
7,000.00
0.0140 m3
kapur padam
5,000.00
70.00
0.3200 oh
pekerja
55,000.00
17,600.00
0.1000 oh
tukang batu
70,000.00
7,000.00
0.0100 oh
kepala tukang
75,000.00
750.00
0.0150 oh
mandor
75,000.00
1,125.00
JUMLAH
D. 6.6.18
66,350.00
D. 6.6.17
48,000.00
48,000.00
55,088.20
26,475.00
81,563.20
Hollow block
800.00
10,000.00
13.5000 kg
semen portland
1,300.00
17,550.00
0.0480 m3
pasir pasang
250,000.00
12,000.00
1.9500 m3
10,000.00
19,500.00
0.3500 oh
pekerja
55,000.00
19,250.00
0.1500 oh
tukang batu
70,000.00
10,500.00
0.0150 oh
kepala tukang
75,000.00
1,125.00
0.0170 oh
mandor
75,000.00
JUMLAH
1,275.00
59,050.00
32,150.00
91,200.00
D. 6.6.19
Hollow block
13,375.00
167,187.50
10.4500 kg
semen portland
1,300.00
13,585.00
0.0380 m3
pasir pasang
250,000.00
9,500.00
1.9500 m3
10,000.00
19,500.00
0.3200 oh
pekerja
55,000.00
17,600.00
0.1200 oh
tukang batu
70,000.00
8,400.00
0.0120 oh
kepala tukang
75,000.00
900.00
0.0150 oh
mandor
75,000.00
1,125.00
JUMLAH
D. 6.6.20
28,025.00
237,797.50
Hollow block
13,375.00
167,187.50
7.5000 kg
semen portland
1,300.00
9,750.00
0.0270 m3
pasir pasang
250,000.00
6,750.00
1.9500 m3
10,000.00
19,500.00
0.3200 oh
pekerja
55,000.00
17,600.00
0.1000 oh
tukang batu
70,000.00
7,000.00
0.0100 oh
kepala tukang
75,000.00
750.00
0.0150 oh
mandor
75,000.00
1,125.00
JUMLAH
D. 6.6.21
209,772.50
203,187.50
26,475.00
229,662.50
concrete block
13,375.00
167,187.50
14.0500 kg
semen portland
1,300.00
18,265.00
0.0040 m3
pasir beton
250,000.00
1,000.00
0.0420 m3
pasir pasang
64,500.00
2,709.00
3.8700 kg
10,000.00
38,700.00
0.0060 kg
15,583.33
93.50
0.0010 kg
kayu terentang
55,000.00
55.00
0.0300 kg
kawat beton
20,000.00
600.00
0.0050 kg
koral beton
263,000.00
1,315.00
0.3700 oh
pekerja
55,000.00
20,350.00
0.1570 oh
tukang batu
70,000.00
10,990.00
0.0070 oh
tukang besi
70,000.00
490.00
0.0164 oh
kepala tukang
75,000.00
1,230.00
0.0185 oh
mandor
75,000.00
JUMLAH
1,387.50
229,925.00
34,447.50
264,372.50
D. 6.6.22
concrete block
13,375.00
167,187.50
10.4600 kg
semen portland
1,300.00
13,598.00
0.0300 m3
pasir beton
250,000.00
7,500.00
0.0320 m3
pasir pasang
64,500.00
2,064.00
0.8700 kg
10,000.00
8,700.00
0.0040 kg
15,583.33
62.33
0.0010 kg
kayu terentang
55,000.00
55.00
0.0200 kg
kawat beton
20,000.00
400.00
0.0040 kg
koral beton
263,000.00
1,052.00
0.3400 oh
pekerja
55,000.00
18,700.00
0.1300 oh
tukang batu
70,000.00
9,100.00
0.0070 oh
tukang besi
70,000.00
490.00
0.0137 oh
kepala tukang
75,000.00
1,027.50
0.0170 oh
mandor
75,000.00
JUMLAH
D. 6.6.23
30,592.50
231,211.33
concrete block
13,375.00
167,187.50
7.2000 kg
semen portland
1,300.00
9,360.00
0.0020 m3
pasir beton
250,000.00
500.00
0.0210 m3
pasir pasang
64,500.00
1,354.50
2.5400 kg
10,000.00
25,400.00
0.0030 kg
15,583.33
46.75
0.0010 kg
kayu terentang
55,000.00
55.00
0.0150 kg
kawat beton
20,000.00
300.00
0.0030 kg
koral beton
263,000.00
789.00
0.3400 oh
pekerja
55,000.00
18,700.00
0.1070 oh
tukang batu
70,000.00
7,490.00
0.0070 oh
tukang besi
70,000.00
490.00
0.0114 oh
kepala tukang
75,000.00
855.00
0.0170 oh
mandor
75,000.00
1,275.00
JUMLAH
D. 6.6.24
1,275.00
200,618.83
204,992.75
28,810.00
233,802.75
bondbeam 40x20x20 cm
5.1000 kg
semen portland
1,300.00
6,630.00
0.0800 m3
pasir beton
250,000.00
20,000.00
1.5000 kg
10,000.00
15,000.00
0.1500 m3
koral beton
263,000.00
39,450.00
0.1000 oh
pekerja
55,000.00
5,500.00
0.0300 oh
tukang batu
70,000.00
2,100.00
0.0300 oh
tukang besi
70,000.00
2,100.00
0.0060 oh
kepala tukang
75,000.00
450.00
mandor
75,000.00
0.005 oh
JUMLAH
375.00
81,080.00
10,525.00
91,605.00
D. 6.6.25
0.04
26.0000 bh
roster / terawang
6,000.00
156,000.00
25
12.8000 kg
semen porland
1,300.00
16,640.00
0.0350 m3
pasir pasang
250,000.00
8,750.00
0.3000 oh
pekerja
55,000.00
16,500.00
0.1000 oh
tukang batu
70,000.00
7,000.00
0.0150 oh
kepala tukang
75,000.00
1,125.00
0.0150 oh
mandor
75,000.00
JUMLAH
D. 6.6.26
1,125.00
181,390.00
25,750.00
0.04
80.0000 bh
bata berongga
800.00
25
23.6500 kg
semen porland
1,300.00
30,745.00
0.5700 m3
pasir pasang
250,000.00
142,500.00
0.3200 oh
pekerja
55,000.00
17,600.00
0.1500 oh
tukang batu
70,000.00
10,500.00
0.0150 oh
kepala tukang
75,000.00
1,125.00
0.0150 oh
mandor
75,000.00
JUMLAH
D. 6.6.27
64,000.00
1,125.00
237,245.00
30,350.00
267,595.00
0.04
1.5000 m2
bilik bambu
2,500.00
3,750.00
25
0.0140 m3
kayu
1,750,000.00
24,500.00
0.0120 kg
paku
15,583.33
187.00
0.0030 m3
1,750,000.00
5,250.00
0.1000 oh
pekerja
55,000.00
5,500.00
0.0500 oh
tukang batu
70,000.00
3,500.00
0.0050 oh
kepala tukang
75,000.00
375.00
0.0020 oh
mandor
75,000.00
150.00
33,687.00
D. 6.6.28
207,140.00
9,525.00
43,212.00
2,200,000.00
42,900.00
0.0070 m3
2,300,000.00
16,100.00
0.1000 kg
15,583.33
1,558.33
1.0000 lbr
plywood 4 mm
55,000.00
55,000.00
0.2000 oh
pekerja
55,000.00
11,000.00
0.6000 oh
tukang kayu
70,000.00
42,000.00
0.0600 oh
kepala tukang
75,000.00
4,500.00
0.0100 oh
mandor
75,000.00
JUMLAH
750.00
115,558.33
58,250.00
173,808.33
E. PEKERJAAN PLESTERAN
E. 6.6.1
semen portland
1,300.00
16,796.00
0.0130 m3
pasir pasang
250,000.00
3,250.00
0.2000 oh
pekerja
55,000.00
11,000.00
0.1500 oh
tukang batu
70,000.00
10,500.00
0.0150 oh
kepala tukang
75,000.00
1,125.00
0.0100 oh
mandor
75,000.00
750.00
20,046.00
E. 6.6.2
8.5200 kg
semen portland
1,300.00
11,076.00
0.0170 m3
pasir pasang
250,000.00
4,250.00
0.2000 oh
pekerja
55,000.00
11,000.00
0.1500 oh
tukang batu
70,000.00
10,500.00
0.0150 oh
kepala tukang
75,000.00
1,125.00
0.0100 oh
mandor
75,000.00
semen portland
1,300.00
8,424.00
0.0190 m3
pasir pasang
250,000.00
4,750.00
0.2000 oh
pekerja
55,000.00
11,000.00
0.1500 oh
tukang batu
70,000.00
10,500.00
0.0150 oh
kepala tukang
75,000.00
1,125.00
0.0100 oh
mandor
75,000.00
750.00
13,174.00
23,375.00
5.2000 kg
semen portland
1,300.00
6,760.00
0.0200 m3
pasir pasang
250,000.00
5,000.00
0.2000 oh
pekerja
55,000.00
11,000.00
0.1500 oh
tukang batu
70,000.00
10,500.00
0.0150 oh
kepala tukang
75,000.00
1,125.00
0.0100 oh
mandor
75,000.00
36,549.00
750.00
11,760.00
23,375.00
35,135.00
semen portland
1,300.00
6,760.00
0.0200 m3
64,500.00
1,290.00
0.2000 oh
pekerja
55,000.00
11,000.00
0.1500 oh
tukang batu
70,000.00
10,500.00
0.0150 oh
kepala tukang
75,000.00
1,125.00
0.0100 oh
mandor
75,000.00
750.00
8,050.00
23,375.00
31,425.00
semen portland
1,300.00
6,760.00
0.0200 m3
225,000.00
4,500.00
0.2000 oh
pekerja
55,000.00
11,000.00
0.1500 oh
tukang batu
70,000.00
10,500.00
0.0150 oh
kepala tukang
75,000.00
1,125.00
0.0100 oh
mandor
75,000.00
JUMLAH
E. 6.6.5
38,701.00
JUMLAH
E. 6.6.4.b
23,375.00
6.4800 kg
JUMLAH
E. 6.6.4.a
750.00
15,326.00
JUMLAH
E. 6.6.4
43,421.00
JUMLAH
E. 6.6.3
23,375.00
750.00
11,260.00
23,375.00
34,635.00
4.3200 kg
semen portland
1,300.00
5,616.00
0.0220 m3
64,500.00
1,419.00
0.2000 oh
pekerja
55,000.00
11,000.00
0.1500 oh
tukang batu
70,000.00
10,500.00
0.0150 oh
kepala tukang
75,000.00
1,125.00
0.0100 oh
mandor
75,000.00
JUMLAH
750.00
7,035.00
23,375.00
30,410.00
E. 6.6.6
semen portland
1,300.00
4,784.00
0.0230 m3
64,500.00
1,483.50
0.2000 oh
pekerja
55,000.00
11,000.00
0.1500 oh
tukang batu
70,000.00
10,500.00
0.0150 oh
kepala tukang
75,000.00
1,125.00
0.0100 oh
mandor
75,000.00
JUMLAH
E. 6.6.7
2.8800 kg
semen portland
1,300.00
3,744.00
0.0240 m3
pasir pasang
250,000.00
6,000.00
0.2000 oh
pekerja
55,000.00
11,000.00
0.1500 oh
tukang batu
70,000.00
10,500.00
0.0150 oh
kepala tukang
75,000.00
1,125.00
0.0100 oh
mandor
75,000.00
23,375.00
33,119.00
semen portland
1,300.00
0.0030 m3
Kapur padam
5,000.00
15.00
0.0130 m3
pasir pasang
250,000.00
3,250.00
0.2000 oh
pekerja
55,000.00
11,000.00
0.1500 oh
tukang batu
70,000.00
10,500.00
0.0150 oh
kepala tukang
75,000.00
1,125.00
0.0100 oh
mandor
75,000.00
7,488.00
750.00
10,753.00
23,375.00
34,128.00
semen portland
1,300.00
0.0060 m3
Kapur padam
5,000.00
30.00
0.0140 m3
pasir pasang
250,000.00
3,500.00
0.2000 oh
pekerja
55,000.00
11,000.00
0.1500 oh
tukang batu
70,000.00
10,500.00
0.0150 oh
kepala tukang
75,000.00
1,125.00
0.0100 oh
mandor
75,000.00
JUMLAH
E. 6.6.10
29,642.50
750.00
9,744.00
JUMLAH
E. 6.6.9
23,375.00
JUMLAH
E. 6.6.8
750.00
6,267.50
2,392.00
750.00
5,922.00
23,375.00
29,297.00
semen portland
1,300.00
0.0050 m3
Kapur padam
5,000.00
25.00
0.0190 m3
pasir pasang
250,000.00
4,750.00
0.2000 oh
pekerja
55,000.00
11,000.00
0.1500 oh
tukang batu
70,000.00
10,500.00
0.0150 oh
kepala tukang
75,000.00
1,125.00
0.0100 oh
mandor
75,000.00
JUMLAH
3,900.00
750.00
8,675.00
23,375.00
32,050.00
E. 6.6.11
semen merah
1,300.00
0.0090 m3
Kapur padam
5,000.00
45.00
0.0090 m3
pasir pasang
250,000.00
2,250.00
0.2000 oh
pekerja
55,000.00
11,000.00
0.1500 oh
tukang batu
70,000.00
10,500.00
0.0150 oh
kepala tukang
75,000.00
1,125.00
0.0100 oh
mandor
75,000.00
JUMLAH
E. 6.6.12
semen merah
1,300.00
9.10
0.0070 m3
Kapur padam
5,000.00
35.00
0.0150 m3
pasir pasang
250,000.00
3,750.00
0.2000 oh
pekerja
55,000.00
11,000.00
0.1500 oh
tukang batu
70,000.00
10,500.00
0.0150 oh
kepala tukang
75,000.00
1,125.00
0.0100 oh
mandor
75,000.00
25,681.70
750.00
3,794.10
23,375.00
27,169.10
1,300.00
18,564.00
0.0230 m3
pasir pasang
250,000.00
5,750.00
0.2500 oh
pekerja
55,000.00
13,750.00
0.2000 oh
tukang batu
70,000.00
14,000.00
0.0200 oh
kepala tukang
75,000.00
1,500.00
0.0125 oh
mandor
75,000.00
JUMLAH
937.50
24,314.00
30,187.50
54,501.50
semen portland
1,300.00
14,040.00
0.0260 m3
pasir pasang
250,000.00
6,500.00
0.2500 oh
pekerja
55,000.00
13,750.00
0.2000 oh
tukang batu
70,000.00
14,000.00
0.0200 oh
kepala tukang
75,000.00
1,500.00
0.0125 oh
mandor
75,000.00
JUMLAH
E. 6.6.15
23,375.00
0.0070 kg
14.2800 kg
E. 6.6.14
750.00
2,306.70
JUMLAH
E. 6.6.13
11.70
937.50
20,540.00
30,187.50
50,727.50
semen portland
1,300.00
11,284.00
0.0280 m3
pasir pasang
250,000.00
7,000.00
0.2500 oh
pekerja
55,000.00
13,750.00
0.2000 oh
tukang batu
70,000.00
14,000.00
0.0200 oh
kepala tukang
75,000.00
1,500.00
0.0125 oh
mandor
75,000.00
JUMLAH
937.50
18,284.00
30,187.50
48,471.50
E. 6.6.16
semen portland
1,300.00
9,477.00
0.0280 m3
pasir pasang
250,000.00
7,000.00
0.2500 oh
pekerja
55,000.00
13,750.00
0.2000 oh
tukang batu
70,000.00
14,000.00
0.0200 oh
kepala tukang
75,000.00
1,500.00
0.0125 oh
mandor
75,000.00
JUMLAH
E. 6.6.17
6.2400 kg
semen portland
1,300.00
8,112.00
0.0300 m3
250,000.00
7,500.00
0.2500 oh
pekerja
55,000.00
13,750.00
0.2000 oh
tukang batu
70,000.00
14,000.00
0.0200 oh
kepala tukang
75,000.00
1,500.00
0.0125 oh
mandor
75,000.00
937.50
15,612.00
30,187.50
0.0090 kg
semen merah
1,300.00
0.0090 m3
Kapur padam
5,000.00
45.00
0.0180 m3
pasir pasang
250,000.00
4,500.00
0.2500 oh
pekerja
55,000.00
13,750.00
0.2000 oh
tukang batu
70,000.00
14,000.00
0.0200 oh
kepala tukang
75,000.00
1,500.00
0.0125 oh
mandor
75,000.00
45,799.50
11.70
937.50
4,556.70
30,187.50
34,744.20
semen portland
1,300.00
20,150.00
0.0130 m3
pasir pasang
250,000.00
3,250.00
0.3000 oh
pekerja
55,000.00
16,500.00
0.2000 oh
tukang batu
70,000.00
14,000.00
0.0200 oh
kepala tukang
75,000.00
1,500.00
0.0130 oh
mandor
75,000.00
JUMLAH
E. 6.6.20
46,664.50
JUMLAH
E. 6.6.19
30,187.50
JUMLAH
E. 6.6.18
937.50
16,477.00
975.00
23,400.00
32,975.00
56,375.00
semen portland
1,300.00
15,275.00
0.0350 m3
pasir pasang
250,000.00
8,750.00
0.3000 oh
pekerja
55,000.00
16,500.00
0.2000 oh
tukang batu
70,000.00
14,000.00
0.0200 oh
kepala tukang
75,000.00
1,500.00
0.0130 oh
mandor
75,000.00
JUMLAH
975.00
24,025.00
32,975.00
57,000.00
E. 6.6.21
semen portland
1,300.00
12,324.00
0.0380 m3
pasir pasang
250,000.00
9,500.00
0.3000 oh
pekerja
55,000.00
16,500.00
0.2000 oh
tukang batu
70,000.00
14,000.00
0.0200 oh
kepala tukang
75,000.00
1,500.00
0.0130 oh
mandor
75,000.00
JUMLAH
E. 6.6.22
7.9400 kg
semen portland
1,300.00
10,322.00
0.0390 m3
pasir pasang
250,000.00
9,750.00
0.3000 oh
pekerja
55,000.00
16,500.00
0.2000 oh
tukang batu
70,000.00
14,000.00
0.0200 oh
kepala tukang
75,000.00
1,500.00
0.0130 oh
mandor
75,000.00
975.00
20,072.00
32,975.00
semen portland
1,300.00
24,245.00
0.0350 m3
pasir pasang
250,000.00
8,750.00
0.3200 oh
pekerja
55,000.00
17,600.00
0.2500 oh
tukang batu
70,000.00
17,500.00
0.0250 oh
kepala tukang
75,000.00
1,875.00
0.0150 oh
mandor
75,000.00
JUMLAH
53,047.00
1,125.00
32,995.00
38,100.00
71,095.00
semen portland
1,300.00
18,395.00
0.0390 m3
pasir pasang
250,000.00
9,750.00
0.3200 oh
pekerja
55,000.00
17,600.00
0.2500 oh
tukang batu
70,000.00
17,500.00
0.0250 oh
kepala tukang
75,000.00
1,875.00
0.0150 oh
mandor
75,000.00
1,125.00
28,145.00
E. 6.6.25
54,799.00
E. 6.6.24
32,975.00
JUMLAH
E. 6.6.23
975.00
21,824.00
38,100.00
66,245.00
semen portland
1,300.00
14,794.00
0.0420 m3
pasir pasang
250,000.00
10,500.00
0.3200 oh
pekerja
55,000.00
17,600.00
0.2500 oh
tukang batu
70,000.00
17,500.00
0.0250 oh
kepala tukang
75,000.00
1,875.00
0.0150 oh
mandor
75,000.00
JUMLAH
1,125.00
25,294.00
38,100.00
63,394.00
E. 6.6.26
semen portland
1,300.00
10,647.00
0.0450 m3
pasir pasang
250,000.00
11,250.00
0.3200 oh
pekerja
55,000.00
17,600.00
0.2500 oh
tukang batu
70,000.00
17,500.00
0.0250 oh
kepala tukang
75,000.00
1,875.00
0.0150 oh
mandor
75,000.00
JUMLAH
E. 6.6.27
7.0700 kg
semen portland
1,300.00
9,191.00
0.0210 m3
pasir pasang
250,000.00
5,250.00
0.1500 oh
pekerja
55,000.00
8,250.00
0.0700 oh
tukang batu
70,000.00
4,900.00
0.0070 oh
kepala tukang
75,000.00
525.00
0.0080 oh
mandor
75,000.00
14,275.00
28,716.00
semen portland
1,300.00
7,371.00
0.0230 m3
pasir pasang
250,000.00
5,750.00
0.1500 oh
pekerja
55,000.00
8,250.00
0.0700 oh
tukang batu
70,000.00
4,900.00
0.0070 oh
kepala tukang
75,000.00
525.00
0.0080 oh
mandor
75,000.00
600.00
13,121.00
14,275.00
27,396.00
semen portland
1,300.00
12,090.00
0.0180 m3
pasir pasang
250,000.00
4,500.00
0.0260 oh
pekerja
55,000.00
1,430.00
0.2000 oh
tukang batu
70,000.00
14,000.00
0.0200 oh
kepala tukang
75,000.00
1,500.00
0.0130 oh
mandor
75,000.00
JUMLAH
E. 6.6.30
59,997.00
600.00
14,441.00
JUMLAH
E. 6.6.29
38,100.00
JUMLAH
E. 6.6.28
1,125.00
21,897.00
975.00
16,590.00
17,905.00
34,495.00
semen portland
1,300.00
9,191.00
0.0210 m3
pasir pasang
250,000.00
5,250.00
0.0260 oh
pekerja
55,000.00
1,430.00
0.2000 oh
tukang batu
70,000.00
14,000.00
0.0200 oh
kepala tukang
75,000.00
1,500.00
0.0130 oh
mandor
75,000.00
JUMLAH
975.00
14,441.00
17,905.00
32,346.00
E. 6.6.31
semen portland
1,300.00
650.00
0.0020 m3
pasir pasang
250,000.00
500.00
0.0570 oh
pekerja
55,000.00
3,135.00
0.0380 oh
tukang batu
70,000.00
2,660.00
0.0380 oh
kepala tukang
75,000.00
2,850.00
0.0020 oh
mandor
75,000.00
JUMLAH
E. 6.6.32
0.1440 kg
Pc Warna
9,833.33
1,416.00
Batu Granito
15,000.00
225,000.00
0.0500 oh
pekerja
55,000.00
2,750.00
0.0200 oh
tukang batu
70,000.00
1,400.00
0.0020 oh
kepala tukang
75,000.00
150.00
0.0050 oh
mandor
75,000.00
JUMLAH
0.4400 kg
Pc Warna
375.00
226,416.00
4,675.00
9,833.33
4,326.67
Batu teraso
15,000.00
172,500.00
0.4500 oh
pekerja
55,000.00
24,750.00
0.2000 oh
tukang batu
70,000.00
14,000.00
0.0200 oh
kepala tukang
75,000.00
1,500.00
0.0250 oh
mandor
75,000.00
JUMLAH
231,091.00
1,875.00
176,826.67
42,125.00
218,951.67
semen portland
0.0160 m3
pasir pasang
1,300.00
5,616.00
250,000.00
0.2500 oh
pekerja
55,000.00
4,000.00
13,750.00
0.1000 oh
tukang batu
70,000.00
7,000.00
0.0100 oh
kepala tukang
75,000.00
750.00
0.0150 oh
mandor
75,000.00
1,125.00
JUMLAH
E. 6.6.35
9,945.00
E. 6.6.34
8,795.00
E. 6.6.33
150.00
1,150.00
9,616.00
22,625.00
32,241.00
semen portland
0.0160 m3
pasir pasang
1,300.00
5,616.00
250,000.00
0.0150 oh
pekerja
55,000.00
4,000.00
825.00
0.0700 oh
tukang batu
70,000.00
4,900.00
0.0070 oh
kepala tukang
75,000.00
525.00
0.0080 oh
mandor
75,000.00
JUMLAH
600.00
9,616.00
6,850.00
16,466.00
E. 6.6.36
semen portland
1,300.00
650.00
2.9000 kg
Batacote
1,800.00
5,220.00
0.0060 m3
pasir pasang
250,000.00
1,500.00
0.3000 oh
pekerja
55,000.00
16,500.00
0.2000 oh
tukang batu
70,000.00
14,000.00
0.0200 oh
kepala tukang
75,000.00
1,500.00
0.0150 oh
mandor
75,000.00
JUMLAH
1,125.00
7,370.00
33,125.00
40,495.00
F. PEKERJAAN KAYU
F.6.6.1
5,000,000.00
6.0000 oh
pekerja
55,000.00
330,000.00
tukang kayu
70,000.00
1,400,000.00
2.0000 oh
kepala tukang
75,000.00
150,000.00
0.3000 oh
mandor
75,000.00
20.0000 oh
JUMLAH
F.6.6.2
5,500,000.00
6.0000 oh
pekerja
55,000.00
330,000.00
tukang kayu
70,000.00
1,260,000.00
2.0000 oh
kepala tukang
75,000.00
150,000.00
0.3000 oh
mandor
75,000.00
7,402,500.00
6,600,000.00
22,500.00
6,600,000.00
1,762,500.00
8,362,500.00
5,000,000.00
6.0000 oh
pekerja
55,000.00
330,000.00
tukang kayu
70,000.00
1,260,000.00
2.0000 oh
kepala tukang
75,000.00
150,000.00
0.3000 oh
mandor
75,000.00
18.0000 oh
JUMLAH
6,000,000.00
22,500.00
6,000,000.00
1,762,500.00
7,762,500.00
2,200,000.00
6.0000 oh
pekerja
55,000.00
330,000.00
tukang kayu
70,000.00
1,260,000.00
2.0000 oh
kepala tukang
75,000.00
150,000.00
0.3000 oh
mandor
75,000.00
18.0000 oh
JUMLAH
F.6.6.5
1,902,500.00
1.2000 m3
JUMLAH
F.6.6.4
22,500.00
5,500,000.00
18.0000 oh
F.6.6.3
5,500,000.00
2,640,000.00
22,500.00
2,640,000.00
1,762,500.00
4,402,500.00
6,000,000.00
216,000.00
0.0500 kg
15,583.33
779.17
0.3500 oh
pekerja
55,000.00
19,250.00
1.0500 oh
tukang kayu
70,000.00
73,500.00
0.1050 oh
kepala tukang
75,000.00
7,875.00
0.0180 oh
mandor
75,000.00
JUMLAH
1,350.00
216,779.17
101,975.00
318,754.17
F.6.6.6
5,400,000.00
194,400.00
0.0500 kg
Paku ulin
19,125.00
956.25
0.3500 oh
pekerja
55,000.00
19,250.00
1.0500 oh
tukang kayu
70,000.00
73,500.00
0.1050 oh
kepala tukang
75,000.00
7,875.00
0.0180 oh
mandor
75,000.00
JUMLAH
F.6.6.7
0.0400 m3
7,000,000.00
1.0000 oh
pekerja
55,000.00
55,000.00
2.5000 oh
tukang kayu
70,000.00
175,000.00
0.2500 oh
kepala tukang
75,000.00
18,750.00
0.0500 oh
mandor
75,000.00
3,750.00
280,000.00
252,500.00
6,000,000.00
1.0000 oh
pekerja
55,000.00
55,000.00
2.5000 oh
tukang kayu
70,000.00
175,000.00
0.2500 oh
kepala tukang
75,000.00
18,750.00
0.0500 oh
mandor
75,000.00
532,500.00
240,000.00
3,750.00
240,000.00
252,500.00
492,500.00
7,000,000.00
0.8000 oh
pekerja
55,000.00
44,000.00
2.0000 oh
tukang kayu
70,000.00
140,000.00
0.2000 oh
kepala tukang
75,000.00
15,000.00
0.0400 oh
mandor
75,000.00
245,000.00
3,000.00
245,000.00
202,000.00
447,000.00
6,000,000.00
0.8000 oh
pekerja
55,000.00
44,000.00
2.0000 oh
tukang kayu
70,000.00
140,000.00
0.2000 oh
kepala tukang
75,000.00
15,000.00
0.0400 oh
mandor
75,000.00
JUMLAH
F.6.6.11
280,000.00
0.0400 m3
JUMLAH
F.6.6.10
297,331.25
JUMLAH
F.6.6.9
101,975.00
JUMLAH
F.6.6.8
1,350.00
195,356.25
210,000.00
3,000.00
210,000.00
202,000.00
412,000.00
5,400,000.00
0.8000 oh
pekerja
55,000.00
44,000.00
2.0000 oh
tukang kayu
70,000.00
140,000.00
0.2000 oh
kepala tukang
75,000.00
15,000.00
0.0400 oh
mandor
75,000.00
JUMLAH
189,000.00
3,000.00
189,000.00
202,000.00
391,000.00
F.6.6.12
7,000,000.00
1.0000 oh
pekerja
55,000.00
55,000.00
3.0000 oh
tukang kayu
70,000.00
210,000.00
0.3000 oh
kepala tukang
75,000.00
22,500.00
0.3000 oh
mandor
75,000.00
JUMLAH
F.6.6.13
6,000,000.00
1.0000 oh
pekerja
55,000.00
55,000.00
3.0000 oh
tukang kayu
70,000.00
210,000.00
0.3000 oh
kepala tukang
75,000.00
22,500.00
0.3000 oh
mandor
75,000.00
758,000.00
384,000.00
22,500.00
384,000.00
310,000.00
694,000.00
7,000,000.00
0.0300 Kg
15,583.33
467.50
0.3000 ltr
lem kayu
14,166.67
4,250.00
1.0000 lbr
55,000.00
55,000.00
0.6000 oh
pekerja
55,000.00
33,000.00
2.0000 oh
tukang kayu
70,000.00
140,000.00
0.2000 oh
kepala tukang
75,000.00
15,000.00
0.0300 oh
mandor
75,000.00
137,200.00
2,250.00
196,917.50
190,250.00
387,167.50
6,000,000.00
0.0300 Kg
15,583.33
467.50
0.3000 ltr
lem kayu
14,166.67
4,250.00
1.0000 lbr
55,000.00
55,000.00
0.6000 oh
pekerja
55,000.00
33,000.00
2.0000 oh
tukang kayu
70,000.00
140,000.00
0.2000 oh
kepala tukang
75,000.00
15,000.00
0.0300 oh
mandor
75,000.00
JUMLAH
F.6.6.16
310,000.00
0.0640 m3
JUMLAH
F.6.6.15
22,500.00
448,000.00
JUMLAH
F.6.6.14
448,000.00
117,600.00
2,250.00
177,317.50
190,250.00
367,567.50
7,000,000.00
420,000.00
0.1500 Kg
15,583.33
2,337.50
0.5000 oh
pekerja
55,000.00
27,500.00
2.0000 oh
tukang kayu
70,000.00
140,000.00
0.2000 oh
kepala tukang
75,000.00
15,000.00
0.0250 oh
mandor
75,000.00
JUMLAH
1,875.00
422,337.50
184,375.00
606,712.50
F.6.6.17
6,000,000.00
360,000.00
0.1500 Kg
15,583.33
2,337.50
0.5000 oh
pekerja
55,000.00
27,500.00
2.0000 oh
tukang kayu
70,000.00
140,000.00
0.2000 oh
kepala tukang
75,000.00
15,000.00
0.0250 oh
mandor
75,000.00
JUMLAH
F.6.6.18
0.0196 m3
5,400,000.00
0.0300 Kg
paku ulin
19,125.00
573.75
0.3000 ltr
lem kayu
14,166.67
4,250.00
1.0000 lbr
55,000.00
55,000.00
0.6000 oh
pekerja
55,000.00
33,000.00
2.0000 oh
tukang kayu
70,000.00
140,000.00
0.2000 oh
kepala tukang
75,000.00
15,000.00
0.0300 oh
mandor
75,000.00
546,712.50
105,840.00
2,250.00
165,663.75
190,250.00
355,913.75
7,000,000.00
137,200.00
0.3000 Kg
19,125.00
5,737.50
0.3000 ltr
lem kayu
14,166.67
4,250.00
1.0000 lbr
teakwood 4 mm
55,000.00
55,000.00
0.6000 oh
pekerja
55,000.00
33,000.00
2.0000 oh
tukang kayu
70,000.00
140,000.00
0.2000 oh
kepala tukang
75,000.00
15,000.00
0.0300 oh
mandor
75,000.00
JUMLAH
F.6.6.20
184,375.00
JUMLAH
F.6.6.19
1,875.00
362,337.50
2,250.00
202,187.50
190,250.00
392,437.50
6,000,000.00
0.0300 Kg
19,125.00
573.75
0.3000 ltr
lem kayu
14,166.67
4,250.00
1.0000 lbr
teakwood 4 mm
55,000.00
55,000.00
0.6000 oh
pekerja
55,000.00
33,000.00
2.0000 oh
tukang kayu
70,000.00
140,000.00
0.2000 oh
kepala tukang
75,000.00
15,000.00
0.0300 oh
mandor
75,000.00
JUMLAH
117,600.00
2,250.00
177,423.75
190,250.00
367,673.75
F.6.6.21
7,000,000.00
0.0300 Kg
15,583.33
467.50
0.8000 ltr
lem kayu
14,166.67
11,333.33
1.0000 lbr
55,000.00
55,000.00
0.5000 lbr
Formika
75,000.00
37,500.00
0.8000 oh
pekerja
55,000.00
44,000.00
2.0000 oh
tukang kayu
70,000.00
140,000.00
0.2500 oh
kepala tukang
75,000.00
18,750.00
0.0400 oh
mandor
75,000.00
JUMLAH
F.6.6.22
205,750.00
0.0196 m3
6,000,000.00
0.0300 Kg
15,583.33
467.50
0.8000 ltr
lem kayu
14,166.67
11,333.33
1.0000 lbr
55,000.00
55,000.00
0.5000 lbr
Formika
75,000.00
37,500.00
0.8000 oh
pekerja
55,000.00
44,000.00
2.0000 oh
tukang kayu
70,000.00
140,000.00
0.2500 oh
kepala tukang
75,000.00
18,750.00
0.0400 oh
mandor
447,250.83
117,600.00
75,000.00
3,000.00
221,900.83
205,750.00
427,650.83
7,000,000.00
0.0300 Kg
15,583.33
467.50
0.8000 ltr
lem kayu
14,166.67
11,333.33
0.5000 lbr
120,200.00
60,100.00
0.5000 lbr
75,000.00
37,500.00
0.8000 oh
pekerja
55,000.00
44,000.00
2.0000 oh
tukang kayu
70,000.00
140,000.00
0.2500 oh
kepala tukang
75,000.00
18,750.00
0.0400 oh
mandor
75,000.00
JUMLAH
F.6.6.24
3,000.00
241,500.83
JUMLAH
F.6.6.23
137,200.00
137,200.00
3,000.00
246,600.83
205,750.00
452,350.83
6,000,000.00
0.0300 Kg
15,583.33
467.50
0.8000 ltr
lem kayu
14,166.67
11,333.33
0.5000 lbr
120,200.00
60,100.00
0.5000 ltr
vernis
35,000.00
17,500.00
0.5000 lbr
75,000.00
37,500.00
0.8000 oh
pekerja
55,000.00
44,000.00
2.0000 oh
tukang kayu
70,000.00
140,000.00
0.2500 oh
kepala tukang
75,000.00
18,750.00
0.0400 oh
mandor
75,000.00
JUMLAH
117,600.00
3,000.00
244,500.83
205,750.00
450,250.83
F.6.6.25
7,000,000.00
0.0300 Kg
15,583.33
467.50
1.2000 ltr
lem kayu
14,166.67
17,000.00
1.0000 lbr
55,000.00
55,000.00
1.0000 lbr
75,000.00
75,000.00
1.0000 oh
pekerja
55,000.00
55,000.00
2.6000 oh
tukang kayu
70,000.00
182,000.00
0.2600 oh
kepala tukang
75,000.00
19,500.00
0.0500 oh
mandor
75,000.00
JUMLAH
F.6.6.26
260,250.00
0.0196 m3
6,000,000.00
0.0300 Kg
15,583.33
467.50
1.2000 ltr
lem kayu
14,166.67
17,000.00
1.0000 lbr
55,000.00
55,000.00
1.0000 lbr
75,000.00
75,000.00
1.0000 oh
pekerja
55,000.00
55,000.00
2.6000 oh
tukang kayu
70,000.00
182,000.00
0.2600 oh
kepala tukang
75,000.00
19,500.00
0.0500 oh
mandor
544,917.50
117,600.00
75,000.00
3,750.00
265,067.50
260,250.00
525,317.50
5,000,000.00
5,500,000.00
besi strip
31,800.00
477,000.00
0.8000 Kg
15,583.33
12,466.67
4.0000 oh
pekerja
55,000.00
220,000.00
tukang kayu
70,000.00
840,000.00
1.2000 oh
kepala tukang
75,000.00
90,000.00
0.2000 oh
mandor
75,000.00
15.0000 Kg
12.0000 oh
JUMLAH
F.6.6.28
3,750.00
284,667.50
JUMLAH
F.6.6.27
137,200.00
15,000.00
5,989,466.67
1,165,000.00
7,154,466.67
5,500,000.00
6,050,000.00
besi strip
31,800.00
477,000.00
0.8000 Kg
15,583.33
12,466.67
4.0000 oh
pekerja
55,000.00
220,000.00
tukang kayu
70,000.00
840,000.00
1.2000 oh
kepala tukang
75,000.00
90,000.00
0.2000 oh
mandor
75,000.00
15.0000 Kg
12.0000 oh
JUMLAH
15,000.00
6,539,466.67
1,165,000.00
7,704,466.67
F.6.6.29
5,000,000.00
5,500,000.00
15.0000 Kg
1.1000 m3
besi strip
31,800.00
477,000.00
0.8000 Kg
Paku ulin
15,583.33
12,466.67
4.0000 oh
pekerja
55,000.00
220,000.00
tukang kayu
70,000.00
840,000.00
1.2000 oh
kepala tukang
75,000.00
90,000.00
0.2000 oh
mandor
75,000.00
12.0000 oh
JUMLAH
F.6.6.30
1.1000 m3
2,200,000.00
2,420,000.00
besi strip
31,800.00
477,000.00
0.8000 Kg
15,583.33
12,466.67
4.0000 oh
pekerja
55,000.00
220,000.00
tukang kayu
70,000.00
840,000.00
1.2000 oh
kepala tukang
75,000.00
90,000.00
0.2000 oh
mandor
75,000.00
12.0000 oh
JUMLAH
15,000.00
2,909,466.67
1,165,000.00
0.0120 m3
5,500,000.00
66,000.00
0.1500 Kg
15,583.33
2,337.50
0.1000 oh
pekerja
55,000.00
5,500.00
0.1000 oh
tukang kayu
70,000.00
7,000.00
0.0100 oh
kepala tukang
75,000.00
750.00
0.0050 oh
mandor
75,000.00
4,074,466.67
375.00
68,337.50
13,625.00
81,962.50
5,000,000.00
60,000.00
0.1500 Kg
Paku ulin
19,125.00
2,868.75
0.1000 oh
pekerja
55,000.00
5,500.00
0.1000 oh
tukang kayu
70,000.00
7,000.00
0.0100 oh
kepala tukang
75,000.00
750.00
0.0050 oh
mandor
75,000.00
JUMLAH
F.6.6.33
7,154,466.67
JUMLAH
F.6.6.32
1,165,000.00
F.6.6.31
15,000.00
5,989,466.67
375.00
62,868.75
13,625.00
76,493.75
5,000,000.00
70,000.00
0.1500 Kg
15,583.33
2,337.50
0.1000 oh
pekerja
55,000.00
5,500.00
0.1000 oh
tukang kayu
70,000.00
7,000.00
0.0100 oh
kepala tukang
75,000.00
750.00
0.0050 oh
mandor
75,000.00
JUMLAH
375.00
72,337.50
13,625.00
85,962.50
F.6.6.34
5,500,000.00
77,000.00
0.1500 Kg
15,583.33
2,337.50
0.1000 oh
pekerja
55,000.00
5,500.00
0.1000 oh
tukang kayu
70,000.00
7,000.00
0.0100 oh
kepala tukang
75,000.00
750.00
0.0050 oh
mandor
75,000.00
JUMLAH
F.6.6.35
0.0140 m3
5,500,000.00
77,000.00
0.1500 Kg
15,583.33
2,337.50
0.1000 oh
pekerja
55,000.00
5,500.00
0.1000 oh
tukang kayu
70,000.00
7,000.00
0.0100 oh
kepala tukang
75,000.00
750.00
0.0050 oh
mandor
75,000.00
375.00
79,337.50
13,625.00
0.1650 m3
5,500,000.00
907,500.00
0.2000 Kg
15,583.33
3,116.67
0.1200 oh
pekerja
55,000.00
6,600.00
0.1200 oh
tukang kayu
70,000.00
8,400.00
0.0120 oh
kepala tukang
75,000.00
900.00
0.0060 oh
mandor
75,000.00
92,962.50
450.00
910,616.67
16,350.00
926,966.67
5,500,000.00
907,500.00
0.2000 Kg
Paku ulin
19,125.00
3,825.00
0.1200 oh
pekerja
55,000.00
6,600.00
0.1200 oh
tukang kayu
70,000.00
8,400.00
0.0120 oh
kepala tukang
75,000.00
900.00
0.0060 oh
mandor
75,000.00
JUMLAH
F.6.6.38
92,962.50
JUMLAH
F.6.6.37
13,625.00
JUMLAH
F.6.6.36
375.00
79,337.50
450.00
911,325.00
16,350.00
927,675.00
5,000,000.00
60,000.00
0.1000 Kg
15,583.33
1,558.33
0.1500 oh
pekerja
55,000.00
8,250.00
0.2500 oh
tukang kayu
70,000.00
17,500.00
0.0250 oh
kepala tukang
75,000.00
1,875.00
0.0750 oh
mandor
75,000.00
JUMLAH
5,625.00
61,558.33
33,250.00
94,808.33
F.6.6.39
5,500,000.00
66,000.00
0.1000 Kg
15,583.33
1,558.33
0.1500 oh
pekerja
55,000.00
8,250.00
0.2500 oh
tukang kayu
70,000.00
17,500.00
0.0250 oh
kepala tukang
75,000.00
1,875.00
0.0750 oh
mandor
75,000.00
JUMLAH
F.6.6.40
0.0120 m3
5,000,000.00
60,000.00
0.1000 Kg
Paku ulin
19,125.00
1,912.50
0.1500 oh
pekerja
55,000.00
8,250.00
0.2500 oh
tukang kayu
70,000.00
17,500.00
0.0250 oh
kepala tukang
75,000.00
1,875.00
0.0750 oh
mandor
75,000.00
5,625.00
61,912.50
33,250.00
0.0230 m3
5,000,000.00
115,000.00
0.1500 Kg
15,583.33
2,337.50
0.2000 oh
pekerja
55,000.00
11,000.00
0.3000 oh
tukang kayu
70,000.00
21,000.00
0.0300 oh
kepala tukang
75,000.00
2,250.00
0.0100 oh
mandor
75,000.00
95,162.50
750.00
116,773.75
27,900.00
144,673.75
5,500,000.00
126,500.00
0.1500 Kg
15,583.33
2,337.50
0.2000 oh
pekerja
55,000.00
11,000.00
0.3000 oh
tukang kayu
70,000.00
21,000.00
0.0300 oh
kepala tukang
75,000.00
2,250.00
0.0100 oh
mandor
75,000.00
JUMLAH
F.6.6.43
100,808.33
JUMLAH
F.6.6.42
33,250.00
JUMLAH
F.6.6.41
5,625.00
67,558.33
750.00
128,837.50
35,000.00
74,237.90
2,200,000.00
50,600.00
0.1500 Kg
15,583.33
2,337.50
0.2000 oh
pekerja
55,000.00
11,000.00
0.3000 oh
tukang kayu
70,000.00
21,000.00
0.0300 oh
kepala tukang
75,000.00
2,250.00
0.0100 oh
mandor
75,000.00
JUMLAH
750.00
52,937.50
35,000.00
87,937.50
F.6.6.44
5,000,000.00
135,000.00
0.2000 Kg
15,583.33
3,116.67
0.2500 oh
pekerja
55,000.00
13,750.00
0.3500 oh
tukang kayu
70,000.00
24,500.00
0.0350 oh
kepala tukang
75,000.00
2,625.00
0.0125 oh
mandor
75,000.00
JUMLAH
F.6.6.45
0.0270 m3
5,500,000.00
148,500.00
0.2000 Kg
15,583.33
3,116.67
0.2500 oh
pekerja
55,000.00
13,750.00
0.3500 oh
tukang kayu
70,000.00
24,500.00
0.0350 oh
kepala tukang
75,000.00
2,625.00
0.0125 oh
mandor
75,000.00
937.50
151,616.67
41,812.50
0.0270 m3
2,200,000.00
59,400.00
0.2000 Kg
15,583.33
3,116.67
0.2500 oh
pekerja
55,000.00
13,750.00
0.3500 oh
tukang kayu
70,000.00
24,500.00
0.0350 oh
kepala tukang
75,000.00
2,625.00
0.0125 oh
mandor
75,000.00
193,429.17
937.50
62,516.67
41,812.50
104,329.17
7,000,000.00
50,400.00
0.0500 Kg
15,583.33
779.17
0.1000 oh
pekerja
55,000.00
5,500.00
0.2000 oh
tukang kayu
70,000.00
14,000.00
0.0250 oh
kepala tukang
75,000.00
1,875.00
0.0050 oh
mandor
75,000.00
JUMLAH
F.6.6.48
179,929.17
JUMLAH
F.6.6.47
41,812.50
JUMLAH
F.6.6.46
937.50
138,116.67
375.00
51,179.17
21,750.00
72,929.17
6,000,000.00
43,200.00
0.0500 Kg
15,583.33
779.17
0.1000 oh
pekerja
55,000.00
5,500.00
0.2000 oh
tukang kayu
70,000.00
14,000.00
0.0250 oh
kepala tukang
75,000.00
1,875.00
0.0050 oh
mandor
75,000.00
JUMLAH
375.00
43,979.17
21,750.00
65,729.17
F.6.6.49
7,000,000.00
77,000.00
0.0500 Kg
15,583.33
779.17
0.1100 oh
pekerja
55,000.00
6,050.00
0.2200 oh
tukang kayu
70,000.00
15,400.00
0.0220 oh
kepala tukang
75,000.00
1,650.00
0.0050 oh
mandor
75,000.00
JUMLAH
F.6.6.50
0.0110 m3
2,137,571.94
23,513.29
0.0500 Kg
15,583.33
779.17
0.1100 oh
pekerja
55,000.00
6,050.00
0.2200 oh
tukang kayu
70,000.00
15,400.00
0.0220 oh
kepala tukang
75,000.00
1,650.00
0.0050 oh
mandor
75,000.00
375.00
24,292.46
23,475.00
0.0145 m3
6,000,000.00
87,000.00
0.0600 Kg
15,583.33
935.00
0.1500 oh
pekerja
55,000.00
8,250.00
0.2500 oh
tukang kayu
70,000.00
17,500.00
0.0250 oh
kepala tukang
75,000.00
1,875.00
0.0750 oh
mandor
75,000.00
47,767.46
5,625.00
87,935.00
33,250.00
121,185.00
6,000,000.00
51,600.00
0.0600 Kg
15,583.33
935.00
0.1000 oh
pekerja
55,000.00
5,500.00
0.1000 oh
tukang kayu
70,000.00
7,000.00
0.0100 oh
kepala tukang
75,000.00
750.00
0.0500 oh
mandor
75,000.00
3,750.00
@
F. 6.6.53.
101,254.17
JUMLAH
F.6.6.52
23,475.00
JUMLAH
F.6.6.51
375.00
77,779.17
JUMLAH
52,535.00
17,000.00
69,535.00
5,400,000.00
46,440.00
0.0600 kg
15,583.33
935.00
0.1000 oh
pekerja
55,000.00
5,500.00
0.1000 oh
tukang kayu
70,000.00
7,000.00
0.0100 oh
kepala tukang
75,000.00
750.00
0.0500 oh
mandor
75,000.00
3,750.00
JUMLAH
47,375.00
17,000.00
64,375.00
F. 6.6.54
5,500,000.00
107,250.00
0.0070 m3
6,000,000.00
42,000.00
0.1000 kg
15,583.33
1,558.33
0.1500 oh
pekerja
55,000.00
8,250.00
0.4500 oh
tukang kayu
70,000.00
31,500.00
0.0450 oh
kepala tukang
75,000.00
3,375.00
0.0750 oh
mandor
75,000.00
JUMLAH
F. 6.6.55
0.0195 m3
5,000,000.00
97,500.00
0.0070 m3
6,000,000.00
42,000.00
0.1000 kg
15,583.33
1,558.33
0.1500 oh
pekerja
55,000.00
8,250.00
0.4500 oh
tukang kayu
70,000.00
31,500.00
0.0450 oh
kepala tukang
75,000.00
3,375.00
0.0750 oh
mandor
75,000.00
199,558.33
5,625.00
141,058.33
48,750.00
189,808.33
5,500,000.00
107,250.00
0.0070 m3
6,000,000.00
42,000.00
0.1000 kg
15,583.33
1,558.33
0.1500 oh
pekerja
55,000.00
8,250.00
0.4500 oh
tukang kayu
70,000.00
31,500.00
0.0450 oh
kepala tukang
75,000.00
3,375.00
0.0750 oh
mandor
75,000.00
JUMLAH
F. 6.6.57
48,750.00
JUMLAH
F. 6.6.56
5,625.00
150,808.33
5,625.00
150,808.33
48,750.00
199,558.33
5,500,000.00
107,250.00
0.0070 m3
6,000,000.00
42,000.00
0.1000 lt
15,583.33
1,558.33
0.5600 lbr
lem kayu
14,166.67
7,933.33
1.0000 kg
55,000.00
55,000.00
0.2000 oh
pekerja
55,000.00
11,000.00
0.6000 oh
tukang kayu
70,000.00
42,000.00
0.0600 oh
kepala tukang
75,000.00
4,500.00
0.0100 oh
mandor
75,000.00
JUMLAH
750.00
213,741.67
58,250.00
271,991.67
F. 6.6.58
5,000,000.00
35,000.00
0.1000 kg
15,583.33
1,558.33
0.1500 kg
20,000.00
3,000.00
0.6000 oh
pekerja
55,000.00
33,000.00
1.8000 oh
tukang kayu
70,000.00
126,000.00
0.1800 oh
kepala tukang
75,000.00
13,500.00
0.0300 oh
mandor
75,000.00
JUMLAH
F. 6.6.59
174,750.00
214,308.33
plywood 4 mm
55,000.00
22,000.00
0.0500 kg
15,583.33
779.17
0.0250 oh
pekerja
55,000.00
1,375.00
0.0750 oh
tukang kayu
70,000.00
5,250.00
0.0075 oh
kepala tukang
75,000.00
562.50
0.0013 oh
mandor
75,000.00
JUMLAH
F. 6.6.60
2,250.00
39,558.33
97.50
22,779.17
7,285.00
30,064.17
kayu profil
10,300.00
0.0210 oh
pekerja
55,000.00
1,155.00
0.0210 oh
tukang kayu
70,000.00
1,470.00
0.0210 oh
kepala tukang
75,000.00
1,575.00
0.0010 oh
mandor
75,000.00
JUMLAH
10,815.00
75.00
10,815.00
4,275.00
15,090.00
65,000.00
1298
0.4 vol.bekisting/m'
0.03 vol.beton/m'
33.33333333 panjang beton/m3
13.33333333
13.333
Dia ( mm )
Berat kg/m'
12.00
0.89
Panjang
1.05
Batang
4.00
Jumlah (kg)
3.74
10.00
0.62
0.60
7.67
6.00
0.22
TOTAL KG
6.59
0.03
33.333333
219.67
207,600.00
436,620.00
PANJANG PONDASI
78.41 M
LA
0.3
LB
0.7
H
LUAS
VOLUME
BATU GUNUNG
SEMEN
PASIR PUTIH
0.7
0.35
27.4435 M3
27.44 M3
5.49 RET
3,567,655.00
4,473.29 KG
89.47 SAK
4,473,290.50
14.27 M3
2.85 RET
TUKANG
713,531.00
4,704,600.00
13,459,076.50
2,100,000.00
: Cipta Karya
TAHUN ANGGARAN
: 2011
NO
URAIAN
SAT
HARGA DASAR
RATA-RATA
4 = 6+5
HARGA
BANGUNAN
JAYA
HARGA
SOTEK
KECAMATAN PENAJAM
UPAH KERJA
1 Pekerja ( Buruh semi terlatih )
Hari
55,000.00
55,000
55,000
2 Tukang Batu
Hari
70,000.00
70,000
70,000
3 Tukang Kayu
Hari
70,000.00
70,000
70,000
4 Tukang Besi
Hari
70,000.00
70,000
70,000
5 Tukang Cat
Hari
70,000.00
70,000
70,000
6 Kepala Tukang
Hari
75,000.00
75,000
75,000
7 Mandor
Hari
75,000.00
75,000
75,000
8 Sopir
Hari
60,000.00
60,000
60,000
9 Pembantu Sopir
Hari
45,000.00
45,000
45,000
Roll
605,000.00
605,000
605,000
11 Ampelas
Lbr
2,875.00
3,000
3,000
Lbr
27,333.33
27,000
28,000
Bh
6,750.00
6,750
6,750
Lbr
85,000.00
85,000
85,000
Lbr
32,000.00
32,000
32,000
Lbr
Lbr
Lbr
75,000
75,000
Lbr
Lbr
35,208.33
37,500
35,000
21 Atap Sirap
Ikat
69,500.00
69,500
69,500
22 Atap Tilux
Bh
29,200.00
29,200
29,200
M2
75,000.00
75,000
75,000
M2
58,100.00
58,100
58,100
Lbr
56,400.00
56,400
56,400
Kg
47,140.12
42,500
45,000
Bh
207,727.27
200,000
170,000
Bh
255,000.00
250,000
250,000
Bh
235,833.33
225,000
230,000
Bh
442,916.67
425,000
450,000
31 Bak Kontrol 50 x 50 x 40 cm
Bh
121,000.00
121,000
121,000
Harga Bahan
71,666.67
-
Bh
293,000.00
293,000
293,000
M3
5,500,000.00
6,000,000
6,000,000
M3
5,000,000.00
5,500,000
5,000,000
M3
2,200,000.00
2,200,000
2,300,000
36 Batako
Bh
1,800.00
1,800
1,800
37 Batu alam
M2
188,300.00
188,300
188,300
38 Batu Bata
Bh
800.00
700
850
39 Batu apung
Kg
850.00
850
850
40 Batu Gunung
M3
215,400.00
215,400
215,400
M3
225,000.00
42 Baut
Kg
22,000.00
22,000
22,000
43 Bensin
Lt
5,300.00
5,300
5,300
Kg
10,000.00
10,000
10,000
Kg
11,750.00
11,750
11,750
Kg
16,300.00
16,300
16,300
47 Besi strip
Kg
31,800.00
31,800
31,800
Unit
97,000.00
97,000
97,000
Unit
156,800.00
156,800
156,800
50 Breaker
Bh
25,000.00
25,000
25,000
Bh
506,500.00
506,500
506,500
Bh
626,000.00
626,000
626,000
Kg
8,600.00
8,000
8,000
Kg
85,000.00
85,000
85,000
58 Cat besi
Kg
37,666.67
35,000
40,000
Kg
20,000.00
20,000
20,000
Kg
36,750.00
35,000
35,000
Kg
20,333.33
20,000
15,000
Bh
132,083.33
15,000
160,000
Bh
750,000.00
750,000
750,000
Bh
98,333.33
100,000
100,000
Unit
1,575,000.00
1,500,000
1,500,000
Bh
374,800.00
374,800
374,800
Bh
314,600.00
314,600
314,600
Bh
454,000.00
454,000
454,000
69 Daun Ventilasi
Bh
78,650.00
78,650
78,650
Kg
35,200.00
35,200
35,200
71 Dempul kayu
Kg
21,666.67
20,000
20,000
72 Dempul Politur
Kg
49,583.33
50,000
50,000
Bh
15,416.67
13,500
12,500
Bh
27,527.78
27,500
30,000
75 Espagnolet
Bh
26,700.00
26,700
26,700
76 Floor Drain
Bh
35,000.00
35,000
35,000
Lbr
104,300.00
104,300
104,300
78 Genteng keramik
Bh
7,500.00
7,500
7,500
79 Glass block
Bh
23,125.00
22,500
23,000
80 Grendel Jendela
Bh
10,000.00
8,000
7,000
81 Grendel Pintu
Bh
16,375.00
12,500
10,000
Bh
125,000.00
125,000
125,000
83 Gypsum board, t = 9 mm
Lbr
65,000.00
65,000
65,000
84 Hak Angin
Bh
10,041.67
10,000
10,000
Bh
10,375.00
10,000
10,000
86 Handle Pintu
Bh
147,500.00
150,000
150,000
87 Jalusi Atap
Bh
565,700.00
565,700
565,700
M'
40,000.00
40,000
40,000
Rol
250,833.33
260,000
250,000
Set
326,700.00
326,700
326,700
92 Kaca polos 2 mm
M2
72,600.00
72,600
72,600
93 Kaca polos 3 mm
M2
84,700.00
84,700
84,700
94 Kaca polos 5 mm
M2
102,300.00
102,300
102,300
95 Kaca Rayben 5 mm
M2
127,000.00
127,000
127,000
96 Kanopi Atap
Bh
546,000.00
546,000
546,000
Kg
20,000.00
20,000
20,000
98 Kawat Bronjong
Kg
107,300.00
107,300
107,300
Rol
79,166.67
75,000
80,000
99 Kawat Duri
m2
28,350.00
28,350
28,350
m2
25,000.00
25,000
25,000
m2
7,750.00
8,000
8,000
M3
1,800,000.00
1,800,000
1,800,000
Btg
11,200.00
11,200
11,200
105 Keramik 10 x 20 cm
M2
46,250.00
47,000
47,000
106 Keramik 20 x 25 cm
M2
52,550.00
50,000
55,600
107 Keramik 20 x 20 cm
M2
50,083.33
50,000
50,000
M2
41,333.33
45,000
43,000
M2
49,750.00
49,000
48,000
M2
220,000.00
220,000
220,000
M'
7,833.33
7,000
8,000
M3
415,000.00
415,000
415,000
M3
350,000.00
350,000
350,000
M3
437,500.00
437,500
437,500
M3
263,000.00
263,000
263,000
Bh
26,000.00
26,000
26,000
Bh
26,500.00
26,500
26,500
Bh
9,666.67
9,000
10,000
Bh
196,666.67
200,000
165,000
Bh
137,500.00
216,000
216,000
Bh
210,000.00
300,000
30,000
Bh
Bh
150,000.00
150,000
150,000
Bh
154,000.00
154,000
154,000
Bh
6,000.00
6,000
6,000
Bh
7,416.67
7,500
7,500
Bh
5,958.33
6,000
6,000
Bh
6,500.00
6,000
6,000
Bh
6,583.33
6,000
6,000
Bh
5,750.00
5,000
5,000
Bh
9,416.67
7,000
10,000
Bh
42,666.67
42,000
42,000
Bh
83,250.00
83,250
83,250
Bh
75,000.00
75,000
75,000
Bh
91,000.00
91,000
91,000
Bh
101,800.00
101,800
101,800
Ltr
14,166.67
15,000
15,000
Bh
4,833.33
5,000
5,000
M'
27,500.00
27,500
27,500
M'
27,500.00
27,500
27,500
M'
27,500.00
27,500
27,500
M'
10,300.00
10,300
10,300
M'
6,050.00
6,050
6,050
M'
66,550.00
66,550
66,550
M'
36,000.00
36,000
36,000
Bh
3,166.67
3,000
3,000
Bh
2,333.33
2,000
2,500
Bh
4,916.67
4,000
5,000
Bh
2,458.33
2,000
2,500
Bh
11,500.00
10,000
12,000
m2
495,000.00
495,000
495,000
Ltr
20,000.00
20,000
20,000
Ltr
12,000.00
12,000
12,000
160 Multiplek 4 mm
Lbr
62,000.00
62,000
62,000
161 Multiplek 6 mm
Lbr
129,000.00
129,000
129,000
162 Multiplek 9 mm
Lbr
205,000.00
205,000
205,000
163 Multiplek 15 mm
Lbr
219,000.00
219,000
219,000
164 Multiplek 18 mm
Lbr
223,300.00
223,300
223,300
165 Multiplex 12 mm
Lbr
155,700.00
155,700
155,700
Bh
20,300.00
20,300
20,300
Bh
17,500.00
17,500
17,500
M'
36,700.00
36,700
36,700
Bh
32,700.00
32,700
32,700
170 Oker
Kg
22,500.00
22,500
22,500
Ltr
37,300.00
37,300
37,300
M'
M'
Kg
27,125.00
27,500
27,000
Bh
19,800.00
19,800
19,800
Kg
27,500.00
27,500
27,500
Kg
28,500.00
25,000
30,000
Kg
15,583.33
15,000
15,000
Kg
30,250.00
30,250
30,250
Kg
24,666.67
22,000
25,000
Kg
19,125.00
17,500
20,000
Kg
23,750.00
22,000
25,000
Kg
20,000.00
20,000
20,000
M3
6,000,000.00
6,500,000
6,500,000
M3
5,400,000.00
6,250,000
5,000,000
M3
1,750,000.00
1,750,000
1,800,000
M3
2,300,000.00
2,200,000
2,300,000
Bh
550,000.00
550,000
550,000
M'
24,200.00
24,200
24,200
Unit
513,000.00
513,000
513,000
Unit
607,400.00
607,400
607,400
M3
250,000.00
250,000
250,000
M3
330,000.00
330,000
330,000
M3
278,750.00
280,000
280,000
M3
64,500.00
64,500
64,500
M3
225,000.00
M3
51,900.00
51,900
51,900
bh
2,000.00
2,000
2,000
m2
104,350.00
104,350
104,350
unit
3,920,000.00
3,920,000
3,920,000
Bh
1,089,000.00
1,089,000
1,089,000
Bh
332,750.00
332,750
332,750
Bh
544,500.00
544,500
544,500
Bh
484,000.00
484,000
484,000
Bh
513,700.00
513,700
513,700
Bh
484,000.00
484,000
484,000
Bh
363,000.00
363,000
363,000
Bh
385,000.00
385,000
385,000
M'
52,100.00
52,100
52,100
M'
103,100.00
103,100
103,100
M'
182,150.00
182,150
182,150
M'
259,300.00
259,300
259,300
Btg
26,083.33
25,000
25,000
Btg
19,416.67
20,000
20,000
Btg
49,833.33
50,000
50,000
Btg
20,833.33
20,000
20,000
Btg
150,833.33
150,000
150,000
M'
37,400.00
37,400
37,400
M'
67,000.00
67,000
67,000
220 Pitting
Bh
9,916.67
10,000
10,000
221 Plamir
Kg
18,500.00
18,500
18,500
222 Plitur
Kg
35,583.33
42,500
42,500
Bh
5,000.00
5,000
5,000
Bh
21,800.00
21,800
21,800
225 Plywood 3 mm
Lbr
44,375.00
42,000
45,000
226 Plywood 4 mm
Lbr
55,000.00
56,000
55,000
227 Plywood 6 mm
Lbr
80,000.00
80,000
80,000
228 Plywood 9 mm
Lbr
124,583.33
125,000
125,000
229 Plywood 12 mm
Lbr
220,000.00
220,000
220,000
230 Plywood 18 mm
Lbr
250,000.00
250,000
250,000
231 Porselen 20 x 20 cm
Bh
52,000.00
52,000
52,000
232 Polycarbonat
M2
825,000.00
825,000
825,000
M'
53,500.00
53,500
53,500
Bh
15,875.00
15,000
16,500
1 Unit
Bh
33,000.00
33,000
33,000
Bh
46,000.00
46,000
46,000
Bh
36,000.00
36,000
36,000
M2
27,500.00
27,500
27,500
Bh
19,000.00
15,000
20,000
Bh
14,541.67
12,500
15,000
Unit
146,800.00
146,800
146,800
Zak
65,000.00
65,000
65,000
Kg
9,833.33
10,000
10,000
Kg
1,947.92
2,000
2,000
Lbr
39,125.00
37,000
40,000
Lbr
45,833.33
45,000
45,000
Unit
Unit
251 Sirlak
Kg
29,700.00
29,700
29,700
252 Sirtu
m3
274,800.00
274,800
274,800
253 Solar
Ltr
6,950.00
6,950
6,950
254 Spritus
Ltr
14,800.00
14,800
14,800
Bh
14,916.67
15,000
15,000
M'
16,041.67
12,500
16,250
Wt
M3
51,900.00
51,900
51,900
Unit
5,406,900.00
5,406,900
5,406,900
Unit
3,177,300.00
3,177,300
3,177,300
Bh
231,000.00
231,000
231,000
Bh
1,235,400.00
1,235,400
1,235,400
Bh
2,613,000.00
2,613,000
2,613,000
Bh
930,800.00
930,800
930,800
265 Teakwood 3 mm
Lbr
99,300.00
99,300
99,300
266 Teakwood 4 mm
Lbr
120,200.00
120,200
120,200
267 Teakwood 6 mm
Lbr
195,850.00
195,850
195,850
Kg
45,300.00
45,300
45,300
269 Terpentin
Ltr
4,750.00
4,750
4,750
Bt
2,984,700.00
2,984,700
2,984,700
Bt
1,960,000.00
1,960,000
1,960,000
Bt
Bt
3,520,000.00
2,311,000.00
3,520,000
2,311,000
3,520,000
2,311,000
274 Tinner A
Ltr
22,916.67
23,500
20,000
Ttk
169,400.00
169,400
169,400
Bh
275,000.00
275,000
275,000
Bh
440,000.00
440,000
440,000
Bh
495,000.00
495,000
495,000
279 Urinoir
Bh
1,865,500.00
1,865,500
1,865,500
Bh
2,400,000.00
2,400,000
2,400,000
m3
415,000.00
415,000
415,000
Bh
495,833.33
500,000
550,000
T. A 2010
1.
2.
3.
4
Catatan :
Harga diatas adalah harga disumber material ( disungai, dilokasi penggalian) khusus utk bahan lokal
Untuk bahan-bahan non lokal harga tersebut adalah harga toko / harga yang berlaku dipasaran
Harga sudah terrmasuk keuntungan kontraktor dan ongkos angkut
Harga belum termasuk PPn
HARGA
BANGUNAN
R2T
HARGA
CAHAYA
ABADI
AMATAN PENAJAM
HARGA
SINAR BARU
HARGA
BINTANG
BARU
HARGA
BINTANG MAS
KECAMATAN WARU
HARGA
HARAPAN
BARU
HARGA
BANGUNAN
KECAMATAN BABULU
55,000
55,000
55,000
55,000
55,000
55,000
55,000
70,000
70,000
70,000
70,000
70,000
70,000
70,000
70,000
70,000
70,000
70,000
70,000
70,000
70,000
70,000
70,000
70,000
70,000
70,000
70,000
70,000
70,000
70,000
70,000
70,000
70,000
70,000
70,000
75,000
75,000
75,000
75,000
75,000
75,000
75,000
75,000
75,000
75,000
75,000
75,000
75,000
75,000
60,000
60,000
60,000
60,000
60,000
60,000
60,000
45,000
45,000
45,000
45,000
45,000
45,000
45,000
605,000
605,000
605,000
605,000
605,000
605,000
605,000
3,000
2,500
3,500
4,000
3,000
3,000
3,000
27,000
27,000
27,000
28,000
28,000
28,000
27,000
6,750
6,750
6,750
6,750
6,750
6,750
6,750
85,000
85,000
85,000
85,000
85,000
85,000
85,000
32,000
32,000
32,000
32,000
32,000
32,000
32,000
70,000
70,000
60,000
75,000
70,000
70,000
70,000
35,000
35,000
35,000
35,000
35,000
35,000
35,000
69,500
69,500
69,500
69,500
69,500
69,500
69,500
29,200
29,200
29,200
29,200
29,200
29,200
29,200
75,000
75,000
75,000
75,000
75,000
75,000
75,000
58,100
58,100
58,100
58,100
58,100
58,100
58,100
56,400
56,400
56,400
56,400
56,400
56,400
56,400
75,100
54,200
54,200
54,200
54,200
54,200
54,200
200,000
250,000
250,000
250,000
185,000
190,000
190,000
250,000
350,000
245,000
270,000
250,000
225,000
300,000
180,000
170,000
250,000
250,000
250,000
425,000
500,000
365,000
450,000
450,000
450,000
450,000
121,000
121,000
121,000
121,000
121,000
121,000
121,000
293,000
293,000
293,000
293,000
293,000
293,000
293,000
6,000,000
6,000,000
6,000,000
6,000,000
6,000,000
6,000,000
6,000,000
5,500,000
5,500,000
5,000,000
5,500,000
5,500,000
5,000,000
5,500,000
2,300,000
2,200,000
2,300,000
2,300,000
2,200,000
2,300,000
2,300,000
1,800
1,800
1,800
1,800
1,800
1,800
1,800
188,300
188,300
188,300
188,300
188,300
188,300
188,300
850
800
800
800
800
800
800
850
850
850
850
850
850
850
215,400
215,400
215,400
215,400
215,400
215,400
215,400
22,000
22,000
22,000
22,000
22,000
22,000
22,000
5,300
5,300
5,300
5,300
5,300
5,300
5,300
10,000
10,000
10,000
10,000
10,000
10,000
10,000
11,750
11,750
11,750
11,750
11,750
11,750
11,750
16,300
16,300
16,300
16,300
16,300
16,300
16,300
31,800
31,800
31,800
31,800
31,800
31,800
31,800
97,000
97,000
97,000
97,000
97,000
97,000
97,000
156,800
156,800
156,800
156,800
156,800
156,800
156,800
25,000
25,000
25,000
25,000
25,000
25,000
25,000
506,500
506,500
506,500
506,500
506,500
506,500
506,500
626,000
626,000
626,000
626,000
626,000
626,000
626,000
8,000
7,000
13,000
11,200
8,000
8,000
8,000
85,000
85,000
85,000
85,000
85,000
85,000
85,000
30,000
38,000
38,000
40,000
38,000
38,000
38,000
20,000
20,000
20,000
20,000
20,000
20,000
20,000
35,000
38,000
38,000
40,000
35,000
35,000
35,000
20,000
20,000
15,000
20,000
22,000
25,000
20,000
150,000
15,000
160,000
150,000
160,000
150,000
150,000
750,000
750,000
750,000
750,000
750,000
750,000
750,000
95,000
100,000
100,000
95,000
100,000
100,000
95,000
1,500,000
1,800,000
1,500,000
1,500,000
1,800,000
1,500,000
1,500,000
374,800
374,800
374,800
374,800
374,800
374,800
374,800
314,600
314,600
314,600
314,600
314,600
314,600
314,600
454,000
454,000
454,000
454,000
454,000
454,000
454,000
78,650
78,650
78,650
78,650
78,650
78,650
78,650
35,200
35,200
35,200
35,200
35,200
35,200
35,200
20,000
35,000
20,000
15,000
20,000
20,000
20,000
50,000
40,000
50,000
55,000
50,000
50,000
50,000
12,500
13,500
12,500
12,500
20,000
20,000
20,000
35,000
33,000
20,000
20,000
35,000
25,000
30,833
26,700
26,700
26,700
26,700
26,700
26,700
26,700
35,000
35,000
35,000
35,000
35,000
35,000
35,000
104,300
104,300
104,300
104,300
104,300
104,300
104,300
7,500
7,500
7,500
7,500
7,500
7,500
7,500
22,000
23,000
21,000
25,000
23,000
21,000
25,000
10,000
12,000
8,000
10,000
10,000
8,000
10,000
20,000
12,000
15,000
25,000
15,000
12,000
15,000
125,000
125,000
125,000
125,000
125,000
125,000
125,000
65,000
65,000
65,000
65,000
65,000
65,000
65,000
10,000
10,000
8,500
12,000
10,000
12,000
10,000
10,000
7,500
10,000
15,000
10,000
12,000
10,000
150,000
165,000
150,000
150,000
150,000
130,000
150,000
565,700
565,700
565,700
565,700
565,700
565,700
565,700
40,000
40,000
40,000
40,000
40,000
40,000
40,000
250,000
250,000
250,000
250,000
250,000
250,000
250,000
326,700
326,700
326,700
326,700
326,700
326,700
326,700
72,600
72,600
72,600
72,600
72,600
72,600
72,600
84,700
84,700
84,700
84,700
84,700
84,700
84,700
102,300
102,300
102,300
102,300
102,300
102,300
102,300
127,000
127,000
127,000
127,000
127,000
127,000
127,000
546,000
546,000
546,000
546,000
546,000
546,000
546,000
20,000
20,000
20,000
20,000
20,000
20,000
20,000
107,300
107,300
107,300
107,300
107,300
107,300
107,300
80,000
80,000
80,000
80,000
70,000
85,000
80,000
28,350
28,350
28,350
28,350
28,350
28,350
28,350
25,000
25,000
25,000
25,000
25,000
25,000
25,000
8,000
7,000
7,000
7,000
8,000
8,000
8,000
1,800,000
1,800,000
1,800,000
1,800,000
1,800,000
1,800,000
1,800,000
11,200
11,200
11,200
11,200
11,200
11,200
11,200
45,000
47,000
47,000
47,000
47,000
40,000
47,000
55,000
55,000
50,000
50,000
50,000
52,000
55,000
50,000
55,000
50,000
50,000
48,000
48,000
50,000
45,000
38,000
41,000
50,000
49,000
45,000
50,000
50,000
50,000
55,000
48,000
50,000
49,000
220,000
220,000
220,000
220,000
220,000
220,000
220,000
8,000
8,000
6,000
8,000
8,000
8,000
8,000
26,000
26,000
26,000
26,000
26,000
26,000
26,000
26,500
26,500
26,500
26,500
26,500
26,500
26,500
7,000
12,000
10,000
10,000
8,000
10,000
10,000
250,000
165,000
200,000
180,000
200,000
200,000
200,000
300,000
160,000
216,000
300,000
30,000
300,000
415,000
350,000
437,500
263,000
216,000
300,000
300,000
30,000
300,000
150,000
150,000
150,000
150,000
150,000
150,000
150,000
154,000
154,000
154,000
154,000
154,000
154,000
154,000
6,000
6,000
6,000
6,000
6,000
6,000
6,000
7,500
7,500
6,000
8,000
7,500
7,500
7,500
6,000
7,000
4,500
6,000
6,000
6,000
6,000
6,000
7,000
5,000
6,000
7,000
7,000
7,000
6,000
8,000
5,000
6,000
7,000
7,000
7,000
5,000
3,000
5,000
4,000
7,000
7,000
7,000
10,000
10,000
10,000
6,000
10,000
10,000
10,000
42,000
43,000
43,000
42,000
43,000
43,000
43,000
83,250
83,250
83,250
83,250
83,250
83,250
83,250
75,000
75,000
75,000
75,000
75,000
75,000
75,000
91,000
91,000
91,000
91,000
91,000
91,000
91,000
101,800
101,800
101,800
101,800
101,800
101,800
101,800
15,000
15,000
12,000
16,000
12,000
15,000
15,000
5,000
5,000
4,000
5,000
4,000
5,000
5,000
27,500
27,500
27,500
27,500
27,500
27,500
27,500
27,500
27,500
27,500
27,500
27,500
27,500
27,500
27,500
27,500
27,500
27,500
27,500
27,500
27,500
10,300
10,300
10,300
10,300
10,300
10,300
10,300
6,050
6,050
6,050
6,050
6,050
6,050
6,050
66,550
66,550
66,550
66,550
66,550
66,550
66,550
36,000
36,000
36,000
36,000
36,000
36,000
36,000
3,000
3,000
3,000
4,000
4,000
3,000
3,000
2,500
2,000
2,500
3,000
2,000
2,000
2,500
5,000
4,000
5,000
5,000
5,000
5,000
5,000
2,500
2,500
2,500
2,500
2,500
2,000
2,500
12,000
10,000
12,000
12,000
12,000
10,000
12,000
495,000
495,000
495,000
495,000
495,000
495,000
495,000
20,000
20,000
20,000
20,000
20,000
20,000
20,000
12,000
12,000
12,000
12,000
12,000
12,000
12,000
62,000
62,000
62,000
62,000
62,000
62,000
62,000
129,000
129,000
129,000
129,000
129,000
129,000
129,000
205,000
205,000
205,000
205,000
205,000
205,000
205,000
219,000
219,000
219,000
219,000
219,000
219,000
219,000
223,300
223,300
223,300
223,300
223,300
223,300
223,300
155,700
155,700
155,700
155,700
155,700
155,700
155,700
20,300
20,300
20,300
20,300
20,300
20,300
20,300
17,500
17,500
17,500
17,500
17,500
17,500
17,500
36,700
36,700
36,700
36,700
36,700
36,700
36,700
32,700
32,700
32,700
32,700
32,700
32,700
32,700
22,500
22,500
22,500
22,500
22,500
22,500
22,500
37,300
37,300
37,300
37,300
37,300
37,300
37,300
27,000
24,000
27,000
25,000
28,000
28,000
28,000
19,800
19,800
19,800
19,800
19,800
19,800
19,800
27,500
27,500
27,500
27,500
27,500
27,500
27,500
30,000
25,000
27,000
30,000
28,000
27,000
30,000
16,000
16,000
14,000
17,000
15,000
15,000
16,000
30,250
30,250
30,250
30,250
30,250
30,250
30,250
25,000
24,000
25,000
25,000
25,000
25,000
25,000
20,000
18,000
18,000
18,000
18,000
20,000
20,000
25,000
20,000
20,000
25,000
22,000
26,000
25,000
20,000
20,000
20,000
20,000
20,000
20,000
20,000
6,500,000
6,500,000
6,500,000
6,500,000
6,500,000
6,500,000
6,500,000
5,000,000
6,250,000
5,000,000
5,000,000
6,250,000
5,000,000
5,000,000
1,800,000
1,750,000
1,800,000
1,800,000
1,750,000
1,800,000
1,800,000
2,300,000
2,200,000
2,300,000
2,300,000
2,200,000
2,300,000
2,300,000
550,000
550,000
550,000
550,000
550,000
550,000
550,000
24,200
24,200
24,200
24,200
24,200
24,200
24,200
513,000
513,000
513,000
513,000
513,000
513,000
513,000
607,400
607,400
607,400
607,400
607,400
607,400
607,400
250,000
250,000
250,000
250,000
225,000
225,000
225,000
330,000
330,000
330,000
330,000
330,000
330,000
330,000
280,000
280,000
280,000
280,000
255,000
255,000
255,000
64,500
64,500
64,500
64,500
64,500
64,500
64,500
51,900
51,900
51,900
51,900
51,900
51,900
51,900
2,000
2,000
2,000
2,000
2,000
2,000
2,000
104,350
104,350
104,350
104,350
104,350
104,350
104,350
3,920,000
3,920,000
3,920,000
3,920,000
3,920,000
3,920,000
3,920,000
1,089,000
1,089,000
1,089,000
1,089,000
1,089,000
1,089,000
1,089,000
332,750
332,750
332,750
332,750
332,750
332,750
332,750
544,500
544,500
544,500
544,500
544,500
544,500
544,500
484,000
484,000
484,000
484,000
484,000
484,000
484,000
513,700
513,700
513,700
513,700
513,700
513,700
513,700
484,000
484,000
484,000
484,000
484,000
484,000
484,000
363,000
363,000
363,000
363,000
363,000
363,000
363,000
385,000
385,000
385,000
385,000
385,000
385,000
385,000
52,100
52,100
52,100
52,100
52,100
52,100
52,100
103,100
103,100
103,100
103,100
103,100
103,100
103,100
182,150
182,150
182,150
182,150
182,150
182,150
182,150
259,300
259,300
259,300
259,300
259,300
259,300
259,300
25,000
30,000
25,000
30,000
25,000
28,000
25,000
20,000
16,000
20,000
20,000
15,000
22,000
20,000
50,000
50,000
50,000
55,000
45,000
48,000
50,000
20,000
25,000
20,000
25,000
20,000
20,000
20,000
150,000
150,000
150,000
160,000
150,000
150,000
150,000
37,400
37,400
37,400
37,400
37,400
37,400
37,400
67,000
67,000
67,000
67,000
67,000
67,000
67,000
10,000
9,000
10,000
10,000
10,000
10,000
10,000
18,500
18,500
18,500
18,500
18,500
18,500
18,500
55,000
38,000
38,000
38,000
42,500
5,000
5,000
5,000
5,000
5,000
5,000
5,000
21,800
21,800
21,800
21,800
21,800
21,800
21,800
45,000
43,000
42,500
45,000
45,000
45,000
45,000
55,000
55,000
54,000
55,000
55,000
55,000
55,000
80,000
80,000
75,000
85,000
80,000
80,000
80,000
125,000
125,000
125,000
120,000
125,000
125,000
125,000
220,000
220,000
220,000
220,000
220,000
220,000
220,000
250,000
250,000
250,000
250,000
250,000
250,000
250,000
52,000
52,000
52,000
52,000
52,000
52,000
52,000
825,000
825,000
825,000
825,000
825,000
825,000
825,000
53,500
53,500
53,500
53,500
53,500
53,500
53,500
16,500
15,000
15,000
18,000
16,000
16,000
16,000
33,000
33,000
33,000
33,000
33,000
33,000
33,000
46,000
46,000
46,000
46,000
46,000
46,000
46,000
36,000
36,000
36,000
36,000
36,000
36,000
36,000
27,500
27,500
27,500
27,500
27,500
27,500
27,500
20,000
15,000
20,000
18,000
20,000
20,000
20,000
15,000
15,000
12,000
15,000
15,000
15,000
15,000
146,800
146,800
146,800
146,800
146,800
146,800
146,800
65,000
65,000
65,000
65,000
65,000
65,000
65,000
10,000
10,000
10,000
8,000
10,000
10,000
10,000
2,000
1,750
1,875
1,750
2,000
2,000
2,000
40,000
40,000
40,000
37,000
38,000
37,500
40,000
45,000
45,000
45,000
55,000
45,000
45,000
45,000
29,700
29,700
29,700
29,700
29,700
29,700
29,700
6,950
6,950
6,950
6,950
6,950
6,950
6,950
14,800
14,800
14,800
14,800
14,800
14,800
14,800
15,000
15,000
12,000
15,000
15,000
17,000
15,000
16,250
16,250
17,500
16,250
16,250
16,250
16,250
51,900
51,900
51,900
51,900
51,900
51,900
51,900
5,406,900
5,406,900
5,406,900
5,406,900
5,406,900
5,406,900
5,406,900
3,177,300
3,177,300
3,177,300
3,177,300
3,177,300
3,177,300
3,177,300
274,800
231,000
231,000
231,000
231,000
231,000
231,000
231,000
1,235,400
1,235,400
1,235,400
1,235,400
1,235,400
1,235,400
1,235,400
2,613,000
2,613,000
2,613,000
2,613,000
2,613,000
2,613,000
2,613,000
930,800
930,800
930,800
930,800
930,800
930,800
930,800
99,300
99,300
99,300
99,300
99,300
99,300
99,300
120,200
120,200
120,200
120,200
120,200
120,200
120,200
195,850
195,850
195,850
195,850
195,850
195,850
195,850
45,300
45,300
45,300
45,300
45,300
45,300
45,300
4,750
4,750
4,750
4,750
4,750
4,750
4,750
2,984,700
2,984,700
2,984,700
2,984,700
2,984,700
2,984,700
2,984,700
1,960,000
1,960,000
1,960,000
1,960,000
1,960,000
1,960,000
1,960,000
3,520,000
2,311,000
3,520,000
2,311,000
3,520,000
2,311,000
3,520,000
2,311,000
3,520,000
2,311,000
3,520,000
2,311,000
3,520,000
2,311,000
23,500
23,500
23,500
20,000
23,500
23,500
23,500
169,400
169,400
169,400
169,400
169,400
169,400
169,400
275,000
275,000
275,000
275,000
275,000
275,000
275,000
440,000
440,000
440,000
440,000
440,000
440,000
440,000
495,000
495,000
495,000
495,000
495,000
495,000
495,000
1,865,500
1,865,500
1,865,500
1,865,500
1,865,500
1,865,500
1,865,500
2,400,000
2,400,000
2,400,000
2,400,000
2,400,000
2,400,000
2,400,000
415,000
415,000
415,000
415,000
415,000
415,000
415,000
500,000
400,000
500,000
500,000
500,000
500,000
500,000
HARGA
BANGUNAN
BARU
HARGA
MITRA
BANGUNAN
HARGA BUMI
HARAPAN
INDAH
TAHUN 2010
KECAMATAN SEPAKU
55,000
55,000
55,000
55,000
70,000
70,000
70,000
70,000
70,000
70,000
70,000
70,000
70,000
70,000
70,000
70,000
70,000
70,000
70,000
70,000
75,000
75,000
75,000
75,000
75,000
75,000
75,000
75,000
60,000
60,000
60,000
60,000
45,000
45,000
45,000
45,000
605,000
605,000
605,000
605,000
2,000
2,500
2,000
2,750
27,000
27,000
27,000
28,700
6,750
6,750
6,750
6,750
85,000
85,000
85,000
40,200
32,000
32,000
32,000
19,969
75,000
75,000
75,000
9,477
8,462
35,000
35,000
35,000
31,750
69,500
69,500
69,500
69,500
29,200
29,200
29,200
29,200
75,000
75,000
75,000
44,500
58,100
58,100
58,100
58,100
56,400
56,400
56,400
56,400
19,470
33,378
25,033
75,100
175,000
225,000
207,000
236,000
175,000
250,000
250,000
250,000
229,400
450,000
450,000
450,000
427,700
121,000
121,000
121,000
121,000
293,000
293,000
293,000
293,000
6,000,000
6,000,000
6,000,000
3,169,000
5,500,000
5,000,000
5,500,000
2,665,000
2,200,000
2,300,000
2,300,000
1,723,000
1,800
1,800
1,800
1,800
188,300
188,300
188,300
188,300
800
800
800
780
850
850
850
850
215,400
215,400
215,400
200,000
225,000
225,000
225,000
225,000
22,000
22,000
22,000
4,000
5,300
5,300
5,300
5,300
10,000
10,000
10,000
10,000
11,750
11,750
11,750
11,750
16,300
16,300
16,300
16,300
31,800
31,800
31,800
31,800
97,000
97,000
97,000
97,000
156,800
156,800
156,800
156,800
25,000
25,000
25,000
25,000
506,500
506,500
506,500
506,500
626,000
626,000
626,000
626,000
8,000
8,000
8,000
8,560
85,000
85,000
85,000
67,500
39,000
39,000
39,000
39,000
20,000
20,000
20,000
20,800
45,000
35,000
35,000
34,650
22,000
25,000
20,000
18,350
175,000
150,000
150,000
146,600
750,000
750,000
750,000
750,000
100,000
100,000
95,000
211,800
1,800,000
1,500,000
1,500,000
1,370,000
374,800
374,800
374,800
374,800
314,600
314,600
314,600
314,600
454,000
454,000
454,000
454,000
78,650
78,650
78,650
78,650
35,200
35,200
35,200
35,200
30,000
20,000
20,000
20,000
50,000
50,000
50,000
37,700
18,000
15,000
15,000
23,000
25,000
24,000
25,000
27,800
26,700
26,700
26,700
26,700
35,000
35,000
35,000
31,700
104,300
104,300
104,300
104,300
7,500
7,500
7,500
7,500
25,000
22,000
25,000
30,000
12,000
12,500
12,500
9,000
20,000
20,000
20,000
16,500
125,000
125,000
125,000
37,000
65,000
65,000
65,000
48,800
8,000
10,000
10,000
9,400
10,000
10,000
10,000
8,300
125,000
150,000
150,000
109,000
565,700
565,700
565,700
565,700
40,000
40,000
40,000
40,000
250,000
250,000
250,000
230,000
326,700
326,700
326,700
326,700
72,600
72,600
72,600
72,600
84,700
84,700
84,700
84,700
102,300
102,300
102,300
102,300
127,000
127,000
127,000
127,000
546,000
546,000
546,000
546,000
20,000
20,000
20,000
19,600
107,300
107,300
107,300
107,300
80,000
80,000
80,000
74,850
28,350
28,350
28,350
28,350
25,000
25,000
25,000
24,300
8,000
8,000
8,000
8,000
1,800,000
1,800,000
1,800,000
1,452,000
11,200
11,200
11,200
11,200
47,000
47,000
47,000
49,600
48,000
55,000
55,000
55,600
50,000
50,000
50,000
55,000
50,000
45,000
45,000
49,000
48,000
50,000
50,000
55,500
220,000
220,000
220,000
220,000
9,000
8,000
8,000
8,650
415,000
350,000
437,500
263,000
26,000
26,000
26,000
26,000
26,500
26,500
26,500
26,500
10,000
10,000
10,000
8,300
200,000
200,000
200,000
161,750
216,000
110,000
216,000
300,000
30,000
300,000
255,900
132,800
150,000
150,000
150,000
154,000
154,000
154,000
154,000
154,000
6,000
6,000
6,000
6,300
7,500
7,500
7,500
8,200
6,000
6,000
6,000
7,100
7,000
7,000
7,000
9,250
7,000
7,000
7,000
6,300
7,000
7,000
7,000
5,200
10,000
10,000
10,000
10,000
43,000
43,000
43,000
42,100
83,250
83,250
83,250
83,250
75,000
75,000
75,000
74,800
91,000
91,000
91,000
91,000
101,800
101,800
101,800
101,800
13,000
15,000
12,000
15,000
5,000
5,000
5,000
6,200
27,500
27,500
27,500
27,500
27,500
27,500
27,500
27,500
27,500
27,500
27,500
27,500
10,300
10,300
10,300
10,300
6,050
6,050
6,050
6,050
66,550
66,550
66,550
66,550
36,000
36,000
36,000
36,000
3,000
3,000
3,000
34,000
2,000
2,500
2,500
2,500
6,000
5,000
5,000
5,600
3,000
2,500
2,500
5,100
12,000
12,000
12,000
12,900
495,000
495,000
495,000
495,000
20,000
20,000
20,000
20,000
12,000
12,000
12,000
12,000
62,000
62,000
62,000
62,000
129,000
129,000
129,000
129,000
205,000
205,000
205,000
205,000
219,000
219,000
219,000
219,000
223,300
223,300
223,300
223,300
155,700
155,700
155,700
155,700
20,300
20,300
20,300
20,300
17,500
17,500
17,500
17,500
36,700
36,700
36,700
36,700
32,700
32,700
32,700
32,700
22,500
22,500
22,500
22,500
37,300
37,300
37,300
37,300
28,000
28,000
28,000
27,300
19,800
19,800
19,800
19,800
27,500
27,500
27,500
27,500
30,000
30,000
30,000
29,200
16,000
16,000
16,000
16,650
30,250
30,250
30,250
30,250
25,000
25,000
25,000
26,350
20,000
20,000
20,000
19,800
25,000
25,000
25,000
23,500
20,000
20,000
20,000
11,500
6,500,000
6,500,000
6,500,000
3,992,000
6,250,000
5,000,000
5,000,000
3,600,000
1,750,000
1,800,000
1,800,000
1,500,000
2,200,000
2,300,000
2,300,000
1,786,000
550,000
550,000
550,000
550,000
24,200
24,200
24,200
24,200
513,000
513,000
513,000
513,000
607,400
607,400
607,400
607,400
275,000
275,000
275,000
250,000
330,000
330,000
330,000
330,000
300,000
300,000
300,000
280,000
61,800
225,000
225,000
225,000
225,000
51,900
51,900
51,900
51,900
2,000
2,000
2,000
3,680
104,350
104,350
104,350
104,350
3,920,000
3,920,000
3,920,000
3,920,000
1,089,000
1,089,000
1,089,000
1,089,000
332,750
332,750
332,750
332,750
544,500
544,500
544,500
544,500
484,000
484,000
484,000
484,000
513,700
513,700
513,700
513,700
484,000
484,000
484,000
484,000
363,000
363,000
363,000
363,000
385,000
385,000
385,000
385,000
52,100
52,100
52,100
52,100
103,100
103,100
103,100
103,100
182,150
182,150
182,150
182,150
259,300
259,300
259,300
259,300
25,000
25,000
25,000
24,100
20,000
20,000
20,000
20,200
50,000
50,000
50,000
48,900
20,000
20,000
20,000
19,650
150,000
150,000
150,000
112,400
37,400
37,400
37,400
37,400
67,000
67,000
67,000
67,000
10,000
10,000
10,000
6,450
18,500
18,500
18,500
18,500
42,500
43,000
45,000
42,500
5,000
5,000
5,000
3,100
21,800
21,800
21,800
21,800
45,000
45,000
45,000
44,600
55,000
55,000
55,000
56,500
80,000
80,000
80,000
79,000
125,000
125,000
125,000
116,500
220,000
220,000
220,000
220,000
250,000
250,000
250,000
231,000
52,000
52,000
52,000
52,000
825,000
825,000
825,000
825,000
53,500
53,500
53,500
53,500
16,500
15,000
15,000
16,500
33,000
33,000
33,000
33,000
46,000
46,000
46,000
46,000
36,000
36,000
36,000
36,000
27,500
27,500
27,500
27,500
20,000
20,000
20,000
16,700
15,000
15,000
15,000
12,800
146,800
146,800
146,800
146,800
65,000
65,000
65,000
63,500
10,000
10,000
10,000
13,500
2,000
2,000
2,000
19,250
40,000
40,000
40,000
40,900
45,000
45,000
45,000
53,600
695,000
1,815,000
29,700
29,700
29,700
29,700
6,950
6,950
6,950
6,950
14,800
14,800
14,800
14,800
15,000
15,000
15,000
12,500
16,250
16,250
16,250
89,100
51,900
51,900
51,900
51,900
5,406,900
5,406,900
5,406,900
5,406,900
3,177,300
3,177,300
3,177,300
3,177,300
274,800
231,000
231,000
231,000
231,000
1,235,400
1,235,400
1,235,400
1,235,400
2,613,000
2,613,000
2,613,000
2,613,000
930,800
930,800
930,800
930,800
99,300
99,300
99,300
99,300
120,200
120,200
120,200
120,200
195,850
195,850
195,850
195,850
45,300
45,300
45,300
45,300
4,750
4,750
4,750
4,750
2,984,700
2,984,700
2,984,700
2,984,700
1,960,000
1,960,000
1,960,000
1,960,000
3,520,000
2,311,000
3,520,000
2,311,000
3,520,000
2,311,000
3,520,000
2,311,000
207,600.00
23,500
23,500
23,500
23,500
169,400
169,400
169,400
169,400
275,000
275,000
275,000
275,000
440,000
440,000
440,000
440,000
495,000
495,000
495,000
495,000
1,865,500
1,865,500
1,865,500
1,865,500
2,400,000
2,400,000
2,400,000
2,400,000
415,000
415,000
415,000
415,000
500,000
500,000
500,000
439,000
4
palu
ponton
mobil
1,100,000.00
420,000.00
1,520,000.00
1,520,000.00
380,000.00
418,000.00
38,000.00
: Cipta Karya
TAHUN ANGGARAN
: 2011
NO
URAIAN
SAT
HARGA DASAR
TANPA PAJAK
BIAYA
ANGKUT
HARGA DASAR
SATUAN
KETERANGAN
4 = 6+5
UPAH KERJA
1 Pekerja ( Buruh semi terlatih )
Hari
55,000.00
55,000.00
2 Tukang Batu
Hari
70,000.00
70,000.00
3 Tukang Kayu
Hari
70,000.00
70,000.00
4 Tukang Besi
Hari
70,000.00
70,000.00
5 Tukang Cat
Hari
70,000.00
70,000.00
6 Kepala Tukang
Hari
75,000.00
75,000.00
7 Mandor
Hari
75,000.00
75,000.00
8 Sopir
Hari
60,000.00
60,000.00
9 Pembantu Sopir
Hari
45,000.00
45,000.00
Roll
605,000.00
605,000.00
2 Ampelas
Lbr
2,875.00
2,875.00
Lbr
27,333.33
27,333.33
Harga Bahan
Bh
6,750.00
6,750.00
Lbr
85,000.00
85,000.00
Lbr
35,208.33
35,208.33
7 Atap Sirap
Ikat
69,500.00
69,500.00
8 Atap Tilux
Bh
29,200.00
29,200.00
M2
75,000.00
75,000.00
M2
58,100.00
58,100.00
Lbr
56,400.00
56,400.00
Kg
47,140.12
47,140.12
Bh
207,727.27
207,727.27
Bh
255,000.00
255,000.00
Bh
235,833.33
235,833.33
isi 100 bh
NO
URAIAN
SAT
HARGA DASAR
TANPA PAJAK
BIAYA
ANGKUT
4 = 6+5
HARGA DASAR
SATUAN
KETERANGAN
Bh
442,916.67
442,916.67
17 Bak Kontrol 50 x 50 x 40 cm
Bh
121,000.00
121,000.00
Bh
293,000.00
293,000.00
M3
5,500,000.00
5,500,000.00
M3
5,000,000.00
5,000,000.00
M3
2,200,000.00
2,200,000.00
22 Batako
Bh
1,800.00
1,800.00
23 Batu alam
M2
188,300.00
188,300.00
24 Batu Bata
Bh
800.00
800.00
25 Batu apung
Kg
850.00
850.00
26 Batu Gunung
M3
215,400.00
215,400
M3
225,000.00
225,000
27 Baut
Bh
22,000.00
22,000.00
28 Bensin
Lt
5,300.00
5,300.00
Kg
10,000.00
10,000.00
10.68
Kg
11,750.00
11,750.00
7022.47191
Kg
16,300.00
16,300.00
14513.10861
32 Besi strip
Kg
31,800.00
31,800.00
Unit
97,000.00
97,000.00
Unit
156,800.00
156,800.00
35 Breaker
Bh
25,000.00
25,000.00
Bh
506,500.00
506,500.00
Bh
626,000.00
626,000.00
Kg
8,600.00
Kg
85,000.00
43 Cat besi
Kg
37,666.67
37,666.67
Kg
20,000.00
20,000.00
Kg
36,750.00
36,750.00
Kg
20,333.33
20,333.33
Bh
132,083.33
132,083.33
Bh
750,000.00
750,000.00
8,600.00
85,000.00
NO
URAIAN
SAT
HARGA DASAR
TANPA PAJAK
BIAYA
ANGKUT
4 = 6+5
Bh
HARGA DASAR
SATUAN
KETERANGAN
98,333.33
98,333.33
Unit
1,575,000.00
1,575,000.00
Bh
374,800.00
374,800.00
Bh
314,600.00
314,600.00
Bh
454,000.00
454,000.00
54 Daun Ventilasi
Bh
78,650.00
78,650.00
Kg
35,200.00
35,200.00
56 Dempul kayu
Kg
21,666.67
21,666.67
57 Dempul Politur
Kg
49,583.33
49,583.33
Bh
15,416.67
15,416.67
Bh
27,527.78
27,527.78
60 Espagnolet
Bh
26,700.00
26,700.00
61 Floor Drain
Bh
35,000.00
35,000.00
Lbr
104,300.00
104,300.00
63 Genteng keramik
Bh
7,500.00
7,500.00
64 Glass block
Bh
23,125.00
23,125.00
65 Grendel Jendela
Bh
10,000.00
10,000.00
66 Grendel Pintu
Bh
16,375.00
16,375.00
Bh
125,000.00
125,000.00
68 Gypsum board, t = 9 mm
Lbr
65,000.00
65,000.00
69 Hak Angin
Bh
10,041.67
10,041.67
Bh
10,375.00
10,375.00
71 Handle Pintu
Bh
147,500.00
147,500.00
72 Jalusi Atap
Bh
565,700.00
565,700.00
M'
40,000.00
40,000.00
Rol
250,833.33
250,833.33
Set
326,700.00
326,700.00
77 Kaca polos 2 mm
M2
72,600.00
72,600.00
78 Kaca polos 3 mm
M2
84,700.00
84,700.00
79 Kaca polos 5 mm
M2
102,300.00
102,300.00
80 Kaca Rayben 5 mm
M2
127,000.00
127,000.00
16,000.00
NO
URAIAN
SAT
HARGA DASAR
TANPA PAJAK
BIAYA
ANGKUT
4 = 6+5
81 Kanopi Atap
Bh
HARGA DASAR
SATUAN
KETERANGAN
546,000.00
Kg
20,000.00
20,000.00
Kg
107,300.00
107,300.00
84 Kawat Duri
Rol
79,166.67
79,166.67
85 Kawat Harmonika
m2
28,350.00
28,350.00
m2
25,000.00
25,000.00
m2
7,750.00
7,750.00
88 Kayu Klas 2
M3
1,800,000.00
1,800,000.00
Btg
11,200.00
11,200.00
90 Keramik 10 x 20 cm
M2
46,250.00
46,250.00
91 Keramik 20 x 25 cm
M2
52,550.00
52,550.00
92 Keramik 20 x 20 cm
M2
50,083.33
50,083.33
93 Keramik 30 x 30 cm Halus
M2
41,333.33
41,333.33
94 Keramik 30 x 30 cm Kasar
M2
49,750.00
49,750.00
M2
220,000.00
220,000.00
96 Karet Talang
M'
7,833.33
7,833.33
M3
415,000.00
415,000.00
M3
350,000.00
350,000.00
M3
437,500.00
437,500.00
M3
263,000.00
263,000.00
Bh
26,000.00
26,000.00
Bh
26,500.00
26,500.00
Bh
9,666.67
9,666.67
Bh
196,666.67
196,666.67
Bh
137,500.00
137,500.00
Bh
210,000.00
210,000.00
Bh
99 Koral (ex.Lokal)
546,000.00
Bh
150,000.00
150,000.00
NO
URAIAN
SAT
HARGA DASAR
TANPA PAJAK
BIAYA
ANGKUT
4 = 6+5
HARGA DASAR
SATUAN
KETERANGAN
Bh
154,000.00
154,000.00
Bh
6,000.00
6,000.00
Bh
7,416.67
7,416.67
Bh
5,958.33
5,958.33
Bh
6,500.00
6,500.00
Bh
6,583.33
6,583.33
Bh
5,750.00
5,750.00
Bh
9,416.67
9,416.67
Bh
42,666.67
42,666.67
Bh
83,250.00
83,250.00
Bh
75,000.00
75,000.00
Bh
91,000.00
91,000.00
Bh
101,800.00
101,800.00
Ltr
14,166.67
14,166.67
Bh
4,833.33
4,833.33
M'
27,500.00
27,500.00
M'
27,500.00
27,500.00
M'
27,500.00
27,500.00
M'
10,300.00
10,300.00
M'
6,050.00
6,050.00
M'
66,550.00
66,550.00
32,692.62
M'
36,000.00
36,000.00
5,000.00
Bh
3,166.67
3,166.67
Bh
2,333.33
2,333.33
Bh
4,916.67
4,916.67
Bh
2,458.33
2,458.33
Bh
11,500.00
11,500.00
m2
495,000.00
495,000.00
Ltr
20,000.00
20,000.00
Ltr
12,000.00
12,000.00
144 Multiplek 4 mm
Lbr
62,000.00
62,000.00
66,666.67
NO
URAIAN
SAT
HARGA DASAR
TANPA PAJAK
BIAYA
ANGKUT
4 = 6+5
HARGA DASAR
SATUAN
KETERANGAN
145 Multiplek 6 mm
Lbr
129,000.00
129,000.00
146 Multiplek 9 mm
Lbr
205,000.00
205,000.00
100,000.00
16,666.67
147 Multiplek 15 mm
Lbr
219,000.00
219,000.00
250,000.00
148 Multiplek 18 mm
Lbr
223,300.00
223,300.00
300,000.00
149 Multiplex 12 mm
Lbr
155,700.00
155,700.00
200,000.00
Bh
20,300.00
20,300.00
Bh
17,500.00
17,500.00
M'
36,700.00
36,700.00
Bh
32,700.00
32,700.00
154 Oker
Kg
22,500.00
22,500.00
Ltr
37,300.00
37,300.00
M'
M'
Kg
27,125.00
27,125.00
Bh
19,800.00
19,800.00
Kg
27,500.00
27,500.00
Kg
28,500.00
28,500.00
Kg
15,583.33
15,583.33
Kg
30,250.00
30,250.00
Kg
24,666.67
24,666.67
Kg
19,125.00
19,125.00
Kg
23,750.00
23,750.00
Kg
20,000.00
20,000.00
M3
6,000,000.00
6,000,000.00
M3
5,400,000.00
5,400,000.00
M3
1,750,000.00
1,750,000.00
M3
2,300,000.00
2,300,000.00
Bh
550,000.00
550,000.00
M'
24,200.00
24,200.00
Unit
513,000.00
513,000.00
Unit
607,400.00
607,400.00
NO
URAIAN
SAT
HARGA DASAR
TANPA PAJAK
BIAYA
ANGKUT
4 = 6+5
HARGA DASAR
SATUAN
KETERANGAN
M3
250,000.00
250,000.00
M3
330,000.00
330,000.00
M3
278,750.00
278,750.00
M3
64,500.00
64,500.00
M3
225,000.00
225,000.00
M3
51,900.00
51,900.00
bh
2,000.00
2,000.00
m2
104,350.00
104,350.00
unit
3,920,000.00
3,920,000.00
Bh
1,089,000.00
1,089,000.00
Bh
332,750.00
332,750.00
Bh
544,500.00
544,500.00
Bh
484,000.00
484,000.00
Bh
513,700.00
513,700.00
Bh
484,000.00
484,000.00
Bh
363,000.00
363,000.00
Bh
385,000.00
385,000.00
M'
52,100.00
52,100.00
M'
103,100.00
103,100.00
M'
182,150.00
182,150.00
M'
259,300.00
259,300.00
Btg
26,083.33
26,083.33
4 m' / btg
Btg
19,416.67
19,416.67
4 m' / btg
Btg
49,833.33
49,833.33
4 m' / btg
Btg
20,833.33
20,833.33
4 m' / btg
Btg
150,833.33
150,833.33
4 m' / btg
M'
37,400.00
37,400.00
M'
67,000.00
67,000.00
200 Pitting
Bh
9,916.67
9,916.67
201 Plamir
Kg
18,500.00
18,500.00
202 Plitur
Kg
35,583.33
35,583.33
NO
URAIAN
SAT
HARGA DASAR
TANPA PAJAK
BIAYA
ANGKUT
HARGA DASAR
SATUAN
KETERANGAN
4 = 6+5
Bh
5,000.00
5,000.00
Bh
21,800.00
21,800.00
205 Plywood 3 mm
Lbr
44,375.00
44,375.00
15,333.33
206 Plywood 4 mm
Lbr
55,000.00
55,000.00
61,333.33
207 Plywood 6 mm
Lbr
80,000.00
80,000.00
92,000.00
208 Plywood 9 mm
Lbr
124,583.33
124,583.33
184,000.00
209 Plywood 12 mm
Lbr
220,000.00
220,000.00
230,000.00
210 Plywood 18 mm
Lbr
250,000.00
250,000.00
276,000.00
211 Porselen 20 x 20 cm
Bh
52,000.00
52,000.00
212 Polycarbonat
M2
825,000.00
825,000.00
M'
53,500.00
53,500.00
Bh
15,875.00
15,875.00
1 Unit
Bh
33,000.00
33,000.00
Bh
46,000.00
46,000.00
Bh
36,000.00
36,000.00
M2
27,500.00
27,500.00
Bh
19,000.00
19,000.00
Bh
14,541.67
14,541.67
Unit
146,800.00
146,800.00
Zak
65,000.00
65,000.00
Kg
9,833.33
9,833.33
Kg
1,947.92
1,947.92
Lbr
39,125.00
39,125.00
Lbr
45,833.33
45,833.33
Unit
Unit
231 Sirlak
Kg
29,700.00
29,700.00
232 Sirtu
m3
274,800.00
274,800.00
233 Solar
Ltr
6,950.00
6,950.00
234 Spritus
Ltr
14,800.00
14,800.00
NO
URAIAN
SAT
HARGA DASAR
TANPA PAJAK
BIAYA
ANGKUT
4 = 6+5
HARGA DASAR
SATUAN
KETERANGAN
Bh
14,916.67
14,916.67
M'
16,041.67
16,041.67
Wt
Perbatang 4 m'
M3
51,900.00
51,900.00
Unit
5,406,900.00
5,406,900.00
Unit
3,177,300.00
3,177,300.00
Bh
231,000.00
231,000.00
Bh
1,235,400.00
1,235,400.00
Bh
2,613,000.00
2,613,000.00
Bh
930,800.00
930,800.00
245 Teakwood 3 mm
Lbr
99,300.00
99,300.00
28,333.33
246 Teakwood 4 mm
Lbr
120,200.00
120,200.00
113,333.33
247 Teakwood 6 mm
Lbr
195,850.00
195,850.00
170,000.00
Kg
45,300.00
45,300.00
249 Terpentin
Ltr
4,750.00
4,750.00
Bt
2,984,700.00
2,984,700.00
Bt
1,960,000.00
1,960,000.00
Bt
Bt
3,520,000.00
2,311,000.00
3,520,000.00
2,311,000.00
254 Tinner A
Ltr
22,916.67
22,916.67
Ttk
169,400.00
169,400.00
Bh
275,000.00
275,000.00
Bh
440,000.00
440,000.00
Bh
495,000.00
495,000.00
NO
URAIAN
259 Urinoir
SAT
3
HARGA DASAR
TANPA PAJAK
BIAYA
ANGKUT
4 = 6+5
HARGA DASAR
SATUAN
KETERANGAN
Bh
1,865,500.00
Bh
2,400,000.00
2,400,000.00
m3
415,000.00
415,000.00
Bh
495,833.33
1,865,500.00
495,833.33
T. A 2010
1.
2.
3.
4
Catatan :
Harga diatas adalah harga disumber material ( disungai, dilokasi penggalian) khusus utk bahan lokal
Untuk bahan-bahan non lokal harga tersebut adalah harga toko / harga yang berlaku dipasaran
Harga sudah terrmasuk keuntungan kontraktor dan ongkos angkut
Harga belum termasuk PPn
Rp
45,000.00
12
Rp
75,000.00
12
Rp
115,000.00
12
7.44
Rp
6,048.39
10.64
Rp
7,046.22
14.51
Rp
7,926.66
: CIPTA KARYA
: September 2008
NO
MATERIAL
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
SAT
m3
m3
m3
m3
m3
btg
m3
m3
m3
m3
m3
m3
m3
m3
m3
m3
m3
m3
JARAK ANGKUT
RATA-RATA 46 - 70
ONGKOS
ANGKUT
JUMLAH
-
5,500,000.00
5,000,000.00
2,200,000.00
215,400.00
1,230,000.00
9,500.00
415,000.00
263,000.00
6,000,000.00
5,400,000.00
1,750,000.00
2,300,000.00
250,000.00
278,750.00
64,500.00
51,900.00
274,800.00
51,900.00