Você está na página 1de 1

DOHA METRO - RLS/JV KEY DATES & INTERFACE PRIORITY ACTIONS LIST STATUS

DATA DATE:

PRIORITY

AREA

M10-M11 Switchbox
9 july 2013 10 july 2013 11 july 2013 Handover &Acces to Qatary Force Area from gate 10 FENCING APPROVED SELECTION ok BUDGET ok

Al Matar C Al Matar B Al Matar D Al Matar E Ring Station Ring Station Ring Station Ring Station
17 June 2013 6/18/2013 6/19/2013 approved OK N/A N/A N/A N/A N/A 17 June 2013 18 June 2013 19 June 2013 approved OK N/A N/A N/A N/A N/A Substation &cables relocation 9 july 2013 10 july 2013 9 july 2013 10 july 2013

MLPA

M40/M104 Switchbox
10/12/2013 to schedule

Al Khubaib Station
posponed posponed posponed posponed posponed posponed posponed posponed posponed posponed postponed postponed postponed postponed postponed postponed postponed postponed postponed postponed postponed postponed postponed postponed postponed postponed postponed postponed postponed postponed postponed postponed postponed postponed postponed postponed postponed postponed postponed postponed postponed

NDIA Terminal Station


to schedule to schedule to schedule to schedule to schedule to schedule to schedule to schedule to schedule to schedule

Remarks

INSPECTION DATE

27 June 2013 29 June 2013

AREA

QR HAND OVER DATE

HSE PLAN
Comments RLS/JV SCOPE DESIGN

on progress
approved ok ok SELECTION ok BUDGET ok on progress on progress all cables and utilities to relocated on progress on progress DIA-CAA to coordinate DIA/QR DIA wall QR on approval process submitted Cost submitted on progress 0% on progress on progress submitted CAA DIA MOI approval DIA Ashgal MOE approval APPROVED cost N/A site survey on progress on progress

on progress
approved FENCING approved SELECTION ok BUDGET ok on progress on progress Substation &cables relocation on progress on progress DIA-CAA to coordinate DIA/QR DIA wall QR on approval process submitted Cost submitted on progress Al Matar E Ring Station Substation &cables relocation on progress on progress DIA-CAA to coordinate DIA/QR DIA wall QR on approval process submitted Cost submitted on progress 0% 10 july 2013

on progress
Optic Fiber to remove FENCING N/A N/A N/A on progress on progress

on progress
ok to schedule to schedule to schedule to schedule to schedule to schedule

WALL

SUBCONTRACT

Method Statment % PROGRESS SCOPE Trial pit Site Survey Permit Karhama MOE/MOI/Ashgal/DIA Army Force Access/Work permit Design approval SUBCONTRACTOR

on progress 15%

DI 1200 conduit & 11kv cable 700m +20m suspension wall PWDI 150 capping Completed
on progress OK/DIA-CAA DIA ok OK/DIA-CAA submitted Cost submitted

Letter to Q petrolium

to schedule

to schedule

Completed
on progress Scheme & permit Karhama Karhama Karhama/Ashgal submitted Cost submitted on progress 0% approved approved ok N/A

Completed
on progress Scheme & permit Karhama/Ashgal Karhama/Ashgal Karhama/Ashgal submitted Cost submitted on progress 0% approved on progress DVE on progress

N/A N/A JV SURVEY JV /CDD JV/CDD ON PROGRESS ON PROGRESS N/A 0% N/A N/A N/A on progress Ashgal MOE CDD approval N/A N/A site survey on progress N/A

to schedule to schedule DIA-CAA to coordinate DIA-CAA to coordinate to schedule


ON PROGRESS ON PROGRESS

to schedule to schedule to schedule to schedule to schedule to schedule to schedule to schedule to schedule to schedule to schedule to schedule to schedule

UTILITIES

Method Statment % PROGRESS Geophysical Design approval Method Statment/Construction Demolition/ grading starting

on progress 10% on progress on progress DVE on progress DIA Ashgal MOE approval APPROVED cost N/A

to schedule to schedule to schedule to schedule to schedule to schedule

DEWATERING

Permit Karhama MOE/MOI/Ashgal/DI A -Army Force


SUBCONTRACTOR

APPROVED

Ashgal MOE approval

to schedule

to schedule

APPROVED cost N/A ok on review

APPROVED cost N/A site survey on progress on progress

to schedule to schedule to schedule to schedule to schedule to schedule to schedule to schedule to schedule to schedule to schedule to schedule to schedule to schedule to schedule to schedule

to schedule to schedule to schedule to schedule to schedule to schedule to schedule to schedule to schedule to schedule to schedule to schedule to schedule to schedule to schedule to schedule

Site Survey Method Statment % PROGRESS Geophysical+MS Design approval


Method Statment/Construction

on progress on progress

5%
on progress

0%
approved

0%
approved on progress on progress approved ASHGAL /MOE Dust control APPROVED N/A on progress

0%
on process on progress submitted CAA DIA MOI approval CAA DIA MOI approval APPROVED N/A on progress

N/A
N/A Camp & plan to Submit on progress N/A MOI CDD approval N/A N/A N/A N/A on progress/Site acces& exit APPROVED

DIA wall QR approved approved down to -6 DVE submitted CAA DIA MOI approval APPROVED N/A approved N/A N/A APPROVED N/A APPROVED

on progress
approved FENCING approved SELECTION ok BUDGET ok on progress on progress on progress APPROVED

EXCAVATION

Demolition/ grading starting

others
SUBCONTRACTOR

Method Statment % PROGRESS Design approval

APPROVED

5%
on progress/Site acces& exit APPROVED

10%
on progress/Site acces& exit APPROVED

0%
on progress APPROVED

0%
on progress APPROVED

TRAFFIC

Method Statement

% PROGRESS

5%

0%

0%

0%

0%

0%

to schedule

postponed

to schedule

TOTAL PROGRESS %

40%

OK IDENTIFIED CRITICAL

Você também pode gostar