DATA DATE:
PRIORITY
AREA
M10-M11 Switchbox
9 july 2013 10 july 2013 11 july 2013 Handover &Acces to Qatary Force Area from gate 10 FENCING APPROVED SELECTION ok BUDGET ok
Al Matar C Al Matar B Al Matar D Al Matar E Ring Station Ring Station Ring Station Ring Station
17 June 2013 6/18/2013 6/19/2013 approved OK N/A N/A N/A N/A N/A 17 June 2013 18 June 2013 19 June 2013 approved OK N/A N/A N/A N/A N/A Substation &cables relocation 9 july 2013 10 july 2013 9 july 2013 10 july 2013
MLPA
M40/M104 Switchbox
10/12/2013 to schedule
Al Khubaib Station
posponed posponed posponed posponed posponed posponed posponed posponed posponed posponed postponed postponed postponed postponed postponed postponed postponed postponed postponed postponed postponed postponed postponed postponed postponed postponed postponed postponed postponed postponed postponed postponed postponed postponed postponed postponed postponed postponed postponed postponed postponed
Remarks
INSPECTION DATE
AREA
HSE PLAN
Comments RLS/JV SCOPE DESIGN
on progress
approved ok ok SELECTION ok BUDGET ok on progress on progress all cables and utilities to relocated on progress on progress DIA-CAA to coordinate DIA/QR DIA wall QR on approval process submitted Cost submitted on progress 0% on progress on progress submitted CAA DIA MOI approval DIA Ashgal MOE approval APPROVED cost N/A site survey on progress on progress
on progress
approved FENCING approved SELECTION ok BUDGET ok on progress on progress Substation &cables relocation on progress on progress DIA-CAA to coordinate DIA/QR DIA wall QR on approval process submitted Cost submitted on progress Al Matar E Ring Station Substation &cables relocation on progress on progress DIA-CAA to coordinate DIA/QR DIA wall QR on approval process submitted Cost submitted on progress 0% 10 july 2013
on progress
Optic Fiber to remove FENCING N/A N/A N/A on progress on progress
on progress
ok to schedule to schedule to schedule to schedule to schedule to schedule
WALL
SUBCONTRACT
Method Statment % PROGRESS SCOPE Trial pit Site Survey Permit Karhama MOE/MOI/Ashgal/DIA Army Force Access/Work permit Design approval SUBCONTRACTOR
on progress 15%
DI 1200 conduit & 11kv cable 700m +20m suspension wall PWDI 150 capping Completed
on progress OK/DIA-CAA DIA ok OK/DIA-CAA submitted Cost submitted
Letter to Q petrolium
to schedule
to schedule
Completed
on progress Scheme & permit Karhama Karhama Karhama/Ashgal submitted Cost submitted on progress 0% approved approved ok N/A
Completed
on progress Scheme & permit Karhama/Ashgal Karhama/Ashgal Karhama/Ashgal submitted Cost submitted on progress 0% approved on progress DVE on progress
N/A N/A JV SURVEY JV /CDD JV/CDD ON PROGRESS ON PROGRESS N/A 0% N/A N/A N/A on progress Ashgal MOE CDD approval N/A N/A site survey on progress N/A
to schedule to schedule to schedule to schedule to schedule to schedule to schedule to schedule to schedule to schedule to schedule to schedule to schedule
UTILITIES
Method Statment % PROGRESS Geophysical Design approval Method Statment/Construction Demolition/ grading starting
on progress 10% on progress on progress DVE on progress DIA Ashgal MOE approval APPROVED cost N/A
DEWATERING
APPROVED
to schedule
to schedule
to schedule to schedule to schedule to schedule to schedule to schedule to schedule to schedule to schedule to schedule to schedule to schedule to schedule to schedule to schedule to schedule
to schedule to schedule to schedule to schedule to schedule to schedule to schedule to schedule to schedule to schedule to schedule to schedule to schedule to schedule to schedule to schedule
on progress on progress
5%
on progress
0%
approved
0%
approved on progress on progress approved ASHGAL /MOE Dust control APPROVED N/A on progress
0%
on process on progress submitted CAA DIA MOI approval CAA DIA MOI approval APPROVED N/A on progress
N/A
N/A Camp & plan to Submit on progress N/A MOI CDD approval N/A N/A N/A N/A on progress/Site acces& exit APPROVED
DIA wall QR approved approved down to -6 DVE submitted CAA DIA MOI approval APPROVED N/A approved N/A N/A APPROVED N/A APPROVED
on progress
approved FENCING approved SELECTION ok BUDGET ok on progress on progress on progress APPROVED
EXCAVATION
others
SUBCONTRACTOR
APPROVED
5%
on progress/Site acces& exit APPROVED
10%
on progress/Site acces& exit APPROVED
0%
on progress APPROVED
0%
on progress APPROVED
TRAFFIC
Method Statement
% PROGRESS
5%
0%
0%
0%
0%
0%
to schedule
postponed
to schedule
TOTAL PROGRESS %
40%
OK IDENTIFIED CRITICAL