EPC 60 Retrofit
Automation development
EPC60
MACE
EPC50
1965
1974
1979
1985
1999
2008
www.alfalaval.com
EPC 60 Retrofit
Reason to upgrade
MACE, IPC 231 and EPC 30: Not possible to get parts anymore EPC 41/400: The electrical components on the EPC print card is difficult to get hold of. In many cases we must special order parts.
www.alfalaval.com
EPC 60 Retrofit
Reason to upgrade
EPC 60 is using the latest technology Easy and logical human interface Supporting remote monitoring with Modbus TPC Easy fault finding and replacement with separate I/Os Built in P&I temperature controller Possible to utilize future upgrades
www.alfalaval.com
EPC 60 Retrofit
Replacing opportunities
Capable of replacing:
IPC 231 EPC 30 EPC 41 EPC 400
Compatible with:
MAPX MOPX WHPX MMPX LOPX FOPX MFPX
www.alfalaval.com
EPC 60 Retrofit
Automation development
EPC 400/41 Control cabinet Starter Air block
Power cabinet
Vibration switch
PS 41
PS 42
0 1 2 3 4
6
bar
4 0 ,6 0 ,4 2 0 ,2 0 0
bar MPa
8 0 ,8 1 1 ,2 1 2 1 0
Water transducer
2 3 4 56
1 0
8
0 1
www.alfalaval.com
EPC 60 Retrofit
Automation development
Water block kit Transformer kit Control cabinet kit
Air block Transformer kit
Starter
16
We need to protect the new EPC We need to protect the new EPC 60 against cut-off voltage peaks 60 against cut-off voltage peaks To cover the customers need We have two different cabinets generated in the coils on the generated in the coils on the regarding supply voltage to the available; one for conventional water block. We mount these water block. We mount these system we have two different separators: WHPX, MOPX, MMPX protectors on the exiting coils. protectors on the exiting coils. transformer kits available. This isone for ALCAP; FOPX, LOPX and Water block for the EPC operation and valve/ and MFPX. The cabinets are the SRV operation. same but the program is Temperature sensor Transducer kit PT 100 different.
15
Power
Since the EPC 60 uses 4-20mA signals to communicate with the We MT board we need to change to need to change the old pressure switches into a pressure the new MT 60 board. sensor working on a 4-20mA MT 60 signal to be able to communicate with the EPC 60.
2 3 4 56 1 0 8
1 0
8 0,8 1 1,2 12 10
www.alfalaval.com
EPC 60 Retrofit
Selection process
Alfa Laval
Slide 10
www.alfalaval.com
EPC 60 Retrofit
Preparation process
Done by the crew or Alfa Laval service engineer Check that all the parts has arrived Prepare the installation Install new cables if necessary Mount new cabinets (Heater, transformer) Wright down all parameters from the old cabinet
Alfa Laval Slide 11
www.alfalaval.com
EPC 60 Retrofit
Installation
Done by the crew or Alfa Laval service engineer Install tall the new parts Mount new cabinets (Heater, transformer) Install new cables if necessary Connect all the cables
Alfa Laval
Slide 12
www.alfalaval.com
EPC 60 Retrofit
Commissioning
Done by Alfa Laval Service engineer Control of the installation Programming of the new EPC 60 Function test Start up