HO Control BSC 63

INTRODOUCTION

Rural cells selected having drops due to DL level. Work Order summary:
Parameter HODLLEVTHS HOULLEVTHS PWRCONTROLDL MSTXPWRMAX Current Value
15 15 1

Proposed Value
18 18 0
29,29,29,29

30,30,30,30

Total cells: 15 Implementation date: 21 Feb 2013. Time: 20:00 (static).

CSSR

HOSR

Total Drops

RLT Drops

Drops Due to Handover Failures

CDR

Total Traffic

UL RQ(5~7) %

DL RQ(5~7)%

Summary

Improvement in all Major KPIs has been observed.


Significant reduction has been observed in number of drops. Traffic Trend is under observation.