ID TaskName DurationStart Finish ResourceNames Predece

1 PipingFineTuningWorks 21days 26/5/14 23/6/14


2 Piping Arrangement - Pontoon (STBD - FWD)
4days 26/5/14 29/5/14 Yuliyan
3 Piping Arrangement - Pontoon (STBD - Center)
2days 26/5/14 27/5/14 Glenn
4 Piping Arrangement - Pontoon (STBD - AFT)
4days 26/5/14 29/5/14 Joemar
5 Piping Arrangement - Pontoon (PORT - FWD)
4days 26/5/14 29/5/14 Ronald
6 Piping Arrangement - Pontoon (PORT - Center)
2days 28/5/14 29/5/14 Glenn 3
7 Piping Arrangement - Pontoon (PORT - AFT)
2days 30/5/14 2/6/14 Glenn 6
8 Piping Arrangement - Column (PORT - AFT)
5days 3/6/14 9/6/14 Glenn 7
9 Piping Arrangement - Column (STBD- AFT)
5days 30/5/14 5/6/14 Joemar 4
10 Piping Arrangement - Column (PORT- FWD)
5days 30/5/14 5/6/14 Ronald 5
11 Piping Arrangement - Column (STBD - FWD)
5days 30/5/14 5/6/14 Yuliyan 2
12 Piping Arrangement - Double Bottom (STBD - FWD)
2days 6/6/14 9/6/14 Yuliyan 11
13 Piping Arrangement - Double Bottom (STBD - AFT)
2days 6/6/14 9/6/14 Joemar 9
14 Piping Arrangement - Double Bottom (PORT - FWD)
2days 6/6/14 9/6/14 Ronald 10
15 Piping Arrangement - Double Bottom (PORT - AFT)
2days 10/6/14 11/6/14 Glenn 8
18 Piping Arrangement - L/U-PORT- P-Tank Room No.1 &
L/U-PORT P-Tank Room No.2
1day 26/5/14 26/5/14 Fransisco
19 Piping Arrangement - STBD Mud Pump Room
1day 12/6/14 12/6/14 Glenn 15
21 Piping Arrangement - PA Client/Operator Store (STBD & POR
1day 10/6/14 10/6/14 Joemar 13
23 Piping Arrangement - Mooring Winch VFD Switchboard
Room, Electrical Workshop & Mechanical Workshop
1day 10/6/14 10/6/14 Ronald 14
24 Piping Arrangement - L/U-STBD P-Tank Room No.1 &
L/U-STBD P-Tank Room No.2
2days 27/5/14 28/5/14 Fransisco 18
25 Piping Arrangement -SWBD Room No.1 & Spare & Store No.
1day 11/6/14 11/6/14 Ronald 23
26 Piping Arrangement -SWBD Room No.2 & Spare & Store No.
1day 12/6/14 12/6/14 Ronald 25
27 Piping Arrangement - Spare & Store No.1 & Lobby
1day 13/6/14 13/6/14 Ronald 26
28 Piping Arrangement - Mud Mixing Room, Mud Hopper Room
& Mud Pit Room (STBD side)
1.5
days
13/6/14 16/6/14 Glenn,Joemar 19
29 Piping Arrangement - Mud Mixing Room, Mud Hopper Room
& Mud Pit Room (PORT side)
1.5
days
16/6/14 17/6/14 Glenn,Joemar 28
32 Piping Arrangement - PF Mooring Winch Room No.1
2days 16/6/14 17/6/14 Ronald 27
33 Piping Arrangement - SF Mooring Winch Room No.1
2days 10/6/14 11/6/14 Yuliyan 12
34 Piping Arrangement - SA Mooring Winch Room No.2
2days 18/6/14 19/6/14 Joemar 29
35 Piping Arrangement - PA Mooring Winch Room No.2
2days 18/6/14 19/6/14 Glenn 29
36 Piping Arrangement - Engine Room
1day 12/6/14 12/6/14 Yuliyan 33
39 Piping Arrangement - Emergency Generator Room
1day 13/6/14 13/6/14 Yuliyan 36
40 Piping Arrangement - Drilling Equipment Store No.1 & No.2
2days 29/5/14 30/5/14 Fransisco 24
41 Piping Arrangement - Sack Storage Room No.1 & No.3
1day 2/6/14 2/6/14 Fransisco 40
42 Piping Arrangement - Sack Storage Room No.2 & No.4
1day 3/6/14 3/6/14 Fransisco 41
44 Piping Arrangement - Loading Stations (PORT & STBD)
1day 4/6/14 4/6/14 Fransisco 42
52 Piping Arrangement - Rig Air Compressor Room No.1 & No.2
2days 20/6/14 23/6/14 Glenn 35
Yuliyan
Glenn
Joemar
Ronald
Glenn
Glenn
Glenn
Joemar
Ronald
Yuliyan
Yuliyan
Joemar
Ronald
Glenn
Fransisco
Glenn
Joemar
Ronald
Fransisco
Ronald
Ronald
Ronald
Glenn,Joemar
Glenn,Joemar
Ronald
Yuliyan
Joemar
Glenn
Yuliyan
Yuliyan
Fransisco
Fransisco
Fransisco
Fransisco
Glenn
W F S T T S M W F S T T S M W F S T
4 25May'14 1Jun'14 8Jun'14 15Jun'14 22Jun'14
Task
Split
Milestone
Summary
ProjectSummary
ExternalTasks
ExternalMilestone
InactiveTask
InactiveMilestone
InactiveSummary
ManualTask
Durationonly
ManualSummaryRollup
ManualSummary
Startonly
Finishonly
Deadline
Progress
Page1
Project:PipingFineTuningPlan
Date:19/5/14