DATE: June 16, 2011

TO: Dave Finney, Road Maintenance

CC: John Engel, Supervisor, Surface Water Management
Debbie Terwilleger, Director, Surface Water Management

FROM: Dave Lucas, Project Manager

SUBJECT: Release for Construction Steelhead Haven Landslide Mitigation RR49022


Steelhead Haven Landslide Mitigation, RR49022, has received all Federal, State and Local permits and
is authorized for construction.

Work at the Chatham Acres site below Ordinary High Water is subject to the fish window listed in the
Hydraulic Project Approval (HPA), July 15 through August 15.

Work at the Steelhead Haven Site, roadway removal, is not subject to the fish window and may be held
until the fall to complete. Adrienne Hulbert, Right of Way Specialist, is contacting the landowners to
obtain Temporary Construction Permits. Once I have those, I will forward them to you.

Please contact the landowners prior to construction to arrange for movement of vehicles and access to
the work site.

Ronald and Gail Thompson
30812 Steelhead Dr.
Arlington, WA 98223
(360) 435-4133


Mark J Gustafson
31310 Steelhead Dr #E
Arlington, WA 98223
Disconnected number (looking for a good one)

Please call with any questions.

Attachments: HPA (3 copies)
Corps Permit (3 copies)
Shoreline Management Permit (3 copies)
Land Disturbing Activity Approval (3 copies)
SWPPP (3 Copies)
Plan set (3 copies)