Você está na página 1de 12

www.raycapsurgeprotection.

com
Installation Instructions:
DC12-48-60-0-25E
INSTALL INSTRUCTIONS DC12-48-60-0-25E
www.raycapsurgeprotection.com
Raycap All rights reserved
(320-0666) Rev.B
Page 1 of 10
INSTALL INSTRUCTIONS DC12-48-60-0-25E
Contents
1 Copyright 2
1.1 Disclaimer 2
1.2 Warnings 2
2 Introduction 3
3 OVP Package Contents 3
3.1 Prerequisites 3
3.2 Tools 3
4 Port Defnitions / OVP Defnitions 4
5 Installing 2" Conduit 5
6 Installing Alarm Cable / Confguring alarm daisy chain 5
7 Installing Ground Cable 7
8 Installing DC Trunk Cables 8
(-48V power supply)
(-48V to tower / roof)
DC12-48-60-0-25E INSTALL INSTRUCTIONS
www.raycapsurgeprotection.com
Raycap All rights reserved
(320-0666) Rev.B
Page 2 of 10
1.0 Copyright
Raycap, Inc. 2013 - All Rights Reserved
1.1 Disclaimer
The information in this document is subject to change without notice and describes only the
product defned in the introduction of this documentation. This documentation is intended for the
use of Raycap customers only for the purposes of the agreement under which the document is
submitted, and no part may be used, reproduced, modifed or transmitted in any form or means
without the prior written permission of Raycap. The documentation has been prepared to be used
by professional and properly trained personnel, and the customer assumes full responsibility when
using it. Raycap welcomes customer comments as part of the process of continuous development
and improvement of the documentation.
Raycap has made all reasonable efforts to ensure that the instructions contained in this document
are adequate and free of material errors and omissions. Raycap will, if deemed necessary explain
issues which may not be covered by this document.
The contents of this document are subject to revision without notice due to continued progress in
methodology, design and manufacturing. Raycap shall have no liability for any error damage of any
kind resulting from the use of this document.
1.2 Warnings
Please read this manual prior to use to become familiar with the products numerous features and
operating procedures. To maintain the maximum degree of safety, follow the sequences as outlined.

Before using the product, read all instructions and cautionary markings on the product and on any
equipment connected to the product.
CAUTION Unless otherwise noted, product usage that is not recommended or sold by the product
manufacturer can result in risk of fre, electric shock, or injury to persons.
CAUTION Do not operate the product if it has been damaged in any way. Return damaged
products to their manufacturer for repair or replacement.
CAUTION Do not disassemble the product as incorrect reassembling can risk electrical shock
or fre.
WARNING Disconnect or disable the DC power source to the product prior to beginning its
installation. Ensure that the DC power source to the product remains de-energized until the
completion of the installation and after all connections have been verifed to be correctly confgured.
For conditions other than those described above, please contact a Raycap Account Representative
at (208) 777-1166, (800) 890-2569 or www.raycapsurgeprotection.com
Thank you for choosing quality products from Raycap.
www.raycapsurgeprotection.com
Raycap All rights reserved
(320-0666) Rev.B
Page 3 of 10
INSTALL INSTRUCTIONS DC12-48-60-0-25E
2.0 Introduction
In a split Radio Base Station (RBS) architecture the typical RBS consists of a Base Band Unit
(BBU) and Remote Radio Heads (RRH) connected by cabling. Power to the RRH is provided
through copper cables traveling from the base station to the top of the tower or roof top. This
creates a conductive path, making the active equipment at the top and the base of the site
vulnerable to damage by direct lightning strikes. Protection systems installed in front of both
the BBU and the RRH must be able to withstand direct lightning currents in order to protect
the sensitive equipment. Raycaps RRH solutions featuring Strikesorb SPD technology
signifcantly enhance the reliability & availability of the RRH site by providing superior
electrical protection at the RRH and BBU, and also enable fexible fber optic and power cable
management solutions.
3.0 OVP Package Contents
1 each
OVP Enclosure
4 each
Fitting, 2" PVC Terminal Adapter Male
2 each
Ground lugs (#6 AWG with inspection port)
3.1 Prerequisites
This Document describes how to install the DC12-48-60-0-25E on-site.
Installers of Raycaps RRH surge protective and fber/power management solutions must be
industry professionals who have attended training on the proper installation of the equipment
by Raycap and/or the mobile operator. Installers are required to read this installation guide
thoroughly prior to installation of the Raycap RRH protection equipment.
3.2 Tools
#1 Flat blade screwdriver
#1 Philips screw driver
7/16" Nut Driver (for ground lug)
Jewelers fat blade screwdriver (for alarm install)
DC12-48-60-0-25E INSTALL INSTRUCTIONS
www.raycapsurgeprotection.com
Raycap All rights reserved
(320-0666) Rev.B
Page 4 of 10
Alarm Connectors
12 to 22 AWG
Ground Bar use
14 to 1/0 AWG
Double lug ground #6 AWG
Can be rotated vertically or
horizontally
Compression Lug
2 -14 AWG
2 conduit Ground
0.2 - 0.39 wire
Procedure
Port Defnitions
4.1 See illustration to identify
Base Port
Assembly Defnitions
Note:
Optional glands and inserts
are included in hardware kit
shipped with the
DC12-48-60-0-25E.
OVP Defnitions
4.2
2" Conduit 2" Conduit
Ground Ground
www.raycapsurgeprotection.com
Raycap All rights reserved
(320-0666) Rev.B
Page 5 of 10
INSTALL INSTRUCTIONS DC12-48-60-0-25E
Procedure
Installing conduit
5.1 Open cover loosening the two screws
on the front of unit.
5.2 Install 2" conduit into the conduit
ports on bottom of unit as needed.
Installing alarm cable
6.1 Connect wires according to
your established color guide.
Connect alarm wires to
alarm lugs.
DC12-48-60-0-25E INSTALL INSTRUCTIONS
www.raycapsurgeprotection.com
Raycap All rights reserved
(320-0666) Rev.B
Page 6 of 10
Procedure
Alarm Daisy Chain
6.2
6.3 Alarm installation complete.
If less than 12 modules are powered,
disconnect termination loop of Daisy
Chain and install into alarm wire
assembly at the last powered module.
Position of termination loop for
6 module connection
Typical alarm Daisy Chain
when all 12 modules are powered.
Position of termination loop
for 12 module connection
www.raycapsurgeprotection.com
Raycap All rights reserved
(320-0666) Rev.B
Page 7 of 10
INSTALL INSTRUCTIONS DC12-48-60-0-25E
Procedure
Installing ground cable
7.1 Feed ground cable through
ground port and connect to
ground lug.

7.2 Ground installation complete.
DC12-48-60-0-25E INSTALL INSTRUCTIONS
www.raycapsurgeprotection.com
Raycap All rights reserved
(320-0666) Rev.B
Page 8 of 10
Procedure
Installing DC trunk cable
(-48V power supply)
8.1 Feed DC trunk cable
through conduit port hole.
Connect wires according to
AT&T color guide.
Installing DC Jumpers
(-48V to tower/roof)
8.2 Feed DC trunk cable
through conduit port hole.
Connect wires according to
AT&T color guide.
www.raycapsurgeprotection.com
Raycap All rights reserved
(320-0666) Rev.B
Page 9 of 10
INSTALL INSTRUCTIONS DC12-48-60-0-25E
8.3 Lock cover tightening the two
screws on the front of unit.
8.4 Installation complete.
www.raycapsurgeprotection.com
Raycap All rights reserved
(320-0666) Rev.B
DC12-48-60-0-25E INSTALL INSTRUCTIONS

Você também pode gostar