REPORT AS ON 10/07/2014 ` IN LAC

NO. DATE
1 CONSTRUCTION OF 15 KM
BITUMINOUS ROAD FROM
DHANJHAR MORE TO
KARAPARA (BANSIDIHA),
RANIBANDH, BANKURA
ADDITIONAL EXECUTIVE
OFFICER, BANKURA ZILLA
PARISHAD
114/PM(F)/P
/1B-
143/2012
16-05-2013 499.18268 374.59134 70% 272.23827 WORK IN PROGRESS
2 CONSTRUCTION OF R.C.C. BOX
BRIDGE ON ARKOSHA RIVER
NEAR LAXMISOLE VILLAGE,
CHHATNA, BANKURA
ADDITIONAL EXECUTIVE
OFFICER, BANKURA ZILLA
PARISHAD
117/PM(F)/P
/1B-13/2012
16-05-2013 51.91000 51.91000 90% 16.68464 WORK IN PROGRESS
3 BORING OF TWO DEEP TUBE-
WELL (`3.27600 EACH) AT
LOHAGARH MOUZA AND BALI
DUMDUMI MOUZA,
CHHATNA, BANKURA
ADDITIONAL EXECUTIVE
OFFICER, BANKURA ZILLA
PARISHAD
44/PM(F)/P/
1B-163/2013
20-01-2014 6.55200 6.55200
4 SCHEMES UNDER ZILLA
PARISHAD-PUAD MEGA
SCHEME:
AGRICULTURE MACHINERY
HUB FOR CULTIVATION
THROUGH FARM
MECHANIZATION SUPPORT
AND TRAINING FOR
CULTIVATORS/ FARMERS: 1
TRACTOR WITH HYDRAULIC
TROLLEY, 1 TRACTOR WITH
HAL, 1 TRACTOR WITH
ZYLOVATOR, 5 POWER TILLER,
BANKURA
ADDITIONAL EXECUTIVE
OFFICER, BANKURA ZILLA
PARISHAD
119/PM(F)/P
/1B-25/2014
03-03-2014 33.00000 33.00000
EXECUTING AGENCY WITH
CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
BILL PAID
FROM PUP
DISTRICT: BANKURA
DETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2013-14
PHYSICAL
PROGRESS
NAME OF THE SCHEME RELEASED
AMOUNT
FROM PUP
UC RECEIVED REMARKS SANCTIONED
AMOUNT
EXPECTED
DATE OF
COMPLETION
SL.
NO.
REPORT AS ON 10/07/2014 ` IN LAC
NO. DATE
EXECUTING AGENCY WITH
CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
BILL PAID
FROM PUP
DISTRICT: BANKURA
DETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2013-14
PHYSICAL
PROGRESS
NAME OF THE SCHEME RELEASED
AMOUNT
FROM PUP
UC RECEIVED REMARKS SANCTIONED
AMOUNT
EXPECTED
DATE OF
COMPLETION
SL.
NO.
5 SCHEMES UNDER ZILLA
PARISHAD-PUAD MEGA
SCHEME:
INSTALLATION OF RLI FROM
CANAL AT VEDUERA MOUZA,
SUPUR ANCHAL, KHATRA,
BANKURA
ADDITIONAL EXECUTIVE
OFFICER, BANKURA ZILLA
PARISHAD
119/PM(F)/P
/1B-25/2014
03-03-2014 50.00000 50.00000
6 SCHEMES UNDER ZILLA
PARISHAD-PUAD MEGA
SCHEME:
RE-EXCAVATION OF MEJIA JHIL
AT MOUZA TARAPUR, MEJIA,
BANKURA
ADDITIONAL EXECUTIVE
OFFICER, BANKURA ZILLA
PARISHAD
119/PM(F)/P
/1B-25/2014
03-03-2014 50.00000 50.00000
7 SINKING OF 332 DEEP TUBE-
WELLS (`1.44272 EACH) FOR
PROVIDING DRINKING WATER
IN DIFF. BLOCKS WITHIN
KHATRA SUB-DIVISION,
BANKURA
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
113/PM(F)/P
/1B-49/2013
& 74
16-05-2013 478.98304 63.09512 70% 63.09512 WORK IN PROGRESS,
245 COMPLETE
8 RE-EXCAVATION OF
TANTIKANTA BARABUNDH
WITH GUARDWALL, KHATRA,
BANKURA
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
118/PM(F)/P
/1B-21/2012
16-05-2013 12.37325 100% 0.00000 COMPLETE
9 CONSTRUCTION OF CHECK
DAM OVER DHARAMPUR
MARADI JORE, KHATRA,
BANKURA
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
118/PM(F)/P
/1B-21/2012
16-05-2013 9.26139 6.68601 100% 6.68601 COMPLETE
10 CONSTRUCTION OF
BITUMINOUS ROAD FROM
LOHAMERIA TO PANTRI (1 KM
TO 6 KM), RAIPUR, BANKURA
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
119/PM(F)/P
/1B-24/2012
16-05-2013 56.59242 55.01622 100% 55.01622 COMPLETE
REPORT AS ON 10/07/2014 ` IN LAC
NO. DATE
EXECUTING AGENCY WITH
CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
BILL PAID
FROM PUP
DISTRICT: BANKURA
DETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2013-14
PHYSICAL
PROGRESS
NAME OF THE SCHEME RELEASED
AMOUNT
FROM PUP
UC RECEIVED REMARKS SANCTIONED
AMOUNT
EXPECTED
DATE OF
COMPLETION
SL.
NO.
11 CONSTRUCTION OF
BITUMINOUS ROAD FROM
SALBONI TO SUSUNIA (0 KM
TO 3 KM), RAIPUR, BANKURA
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
120/PM(F)/P
/1B-25/2012
16-05-2013 37.28448 30.25720 100% 30.25720 COMPLETE
12 CONSTRUCTION OF GROUND
FLOOR & 1ST FLOOR OF SOIL
TESTING CENTRE AT DALPUR
SREE SREE GYANANANDA
SARASWATI ASHRAM,
BANKURA
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
121/PM(F)/P
/1B-48/2013
16-05-2013 31.11718 18.47618 95% 18.47618 WORK IN PROGRESS
13 CONSTRUCTION OF
APPROACH ROAD FROM
KHATRA-RANIBANDH MAIN
ROAD TO NEWLY
CONSTRUCTED ITI BUILDING,
KHATRA, BANKURA
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
142/PM(F)/P
/1B-62/2013
14-08-2013 22.90051 21.73302 100% 21.73302 COMPLETE
14 REPAIRING OF ROAD FROM
HIRBANDH TO MOSHIARA VIA
AMJHURI VILLAGE, HIRBANDH,
BANKURA
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
174/PM(F)/P
/1B-
104/2013 &
189
09-10-2013 &
07-11-2013
27.83292 27.61950 100% 27.61950 COMPLETE
15 ESTABLISHMENT OF MOTHER
BLOCK OF MAJOR AND MINOR
FRUITS FOR SOCIO-ECONOMIC
UPLIFTMENT IN
PASCHIMANCHAL
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
179/PM(F)/P
/1B-68/2013
10-10-2013 1.91300 1.08740 75% 1.08740 WORK IN PROGRESS
REPORT AS ON 10/07/2014 ` IN LAC
NO. DATE
EXECUTING AGENCY WITH
CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
BILL PAID
FROM PUP
DISTRICT: BANKURA
DETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2013-14
PHYSICAL
PROGRESS
NAME OF THE SCHEME RELEASED
AMOUNT
FROM PUP
UC RECEIVED REMARKS SANCTIONED
AMOUNT
EXPECTED
DATE OF
COMPLETION
SL.
NO.
16 CONSTRUCTION OF CONCRETE
ROAD AND PUCCA DRAIN
FROM SYNDICATE BANK TO
THE END 'A' ZONE OF
SRINAGAR, BANKURA-I,
BANKURA
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
78/PM(F)/P/
1B-04/2014
17-02-2014 26.04877 15% WORK IN PROGRESS
17 CONSTRUCTION OF 50
ANGANWADI CENTRES UNDER
4 BLOCKS CLUBBING WITH
MGNREGS, ONDA, CHHATNA,
BARJORA, BANKURA-I BLOCK,
BANKURA
DISTRICT MAGISTRATE,
BANKURA
154/PM(F)/P
/1B-91/2013
09-09-2013 200.58850 200.58850 AMOUNT SUB-
ALLOTED TO E.O. OF
DIFF. P.S. ON 12-11-
2013
18 CONSTRUCTION OF 131
ANGANWADI CENTRES EACH
@ `6.89600 LAC, BANKURA
DISTRICT MAGISTRATE,
BANKURA
160/PM(F)/P
/1B-91/2013
23-09-2013 903.37600 903.37600
19 IMPLEMENTATION OF
DIFFERENT PROJECT @ `50
LAC EACH BLOCK IN 16
BLOCKS, BANKURA
DISTRICT MAGISTRATE,
BANKURA
151/PM(F)/P
/1B-82/2013
30-08-2013 800.00000 399.98555 30% 294.74295 WORK IN PROGRESS
20 RENOVATION OF CANAL IN
THE FORM OF RESECTIONING
& LINING IN BETWEEN CH.
0.00 AND CH. 32.00 AND CH.
153.00 & CH. 178.00 OF DY
NO. 8 OF BISHNUPUR BRANCH
CANAL FOR RESTORATION OF
DISTRESSED IRRIGATION
POTENTIAL,
TALDANGRA,BANKURA
EXECUTIVE ENGINEER,
BANKURA IRRIGATION
DIVISION
103/PM(F)/P
/1B-67/2012
12-04-2013 24.80000 24.80000 30-11-2013 0.00000
REPORT AS ON 10/07/2014 ` IN LAC
NO. DATE
EXECUTING AGENCY WITH
CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
BILL PAID
FROM PUP
DISTRICT: BANKURA
DETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2013-14
PHYSICAL
PROGRESS
NAME OF THE SCHEME RELEASED
AMOUNT
FROM PUP
UC RECEIVED REMARKS SANCTIONED
AMOUNT
EXPECTED
DATE OF
COMPLETION
SL.
NO.
21 RENOVATION OF CANAL IN
THE FORM OF RESECTIONING
& LINING IN BETWEEN CH.
426.00 & CH. 445.00 OF DY
NO. 4 OF BISHNUPUR BRANCH
CANAL FOR RESTORATION OF
DISTRESSED IRRIGATION
POTENTIAL, ONDA, BANKURA
EXECUTIVE ENGINEER,
BANKURA IRRIGATION
DIVISION
103/PM(F)/P
/1B-67/2012
12-04-2013 23.12000 23.12000 30-11-2013 0.00000
22 RENOVATION OF CANAL IN
THE FORM OF RESECTIONING
& LINING IN BETWEEN CH.
0.00 AND CH. 50.00 OF MINOR
D OF DY-2 OF BISHNUPUR
BRANCH CANAL INCLUDING
RENOVATION OF PIPE FALL
STRUCTURE AT CH. 11.20 &
CROSS DRAINAGE WORK AT
CH. 15.35 FOR RESTORATION
OF DISTRESSED IRRIGATION
POTENTIAL UNDER BANKURA
IRRIGATION DIVISION, ONDA,
BANKURA
EXECUTIVE ENGINEER,
BANKURA IRRIGATION
DIVISION
89/PM(F)/P/
1B-67/2012
20-02-2014 19.99683 19.99683
REPORT AS ON 10/07/2014 ` IN LAC
NO. DATE
EXECUTING AGENCY WITH
CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
BILL PAID
FROM PUP
DISTRICT: BANKURA
DETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2013-14
PHYSICAL
PROGRESS
NAME OF THE SCHEME RELEASED
AMOUNT
FROM PUP
UC RECEIVED REMARKS SANCTIONED
AMOUNT
EXPECTED
DATE OF
COMPLETION
SL.
NO.
23 IMPROVEMENT OF CANAL IN
THE FORM OF RESECTIONING
& LINING OF BERAI MAIN
CANAL INCLUDING
RENOVATION OF IRRIGATION
STRUCTURES IN BETWEEN CH.
276.70 & CH. 311.50 UNDER
BANKURA IRRIGATION
DIVISION, ONDA, BANKURA
EXECUTIVE ENGINEER,
BANKURA IRRIGATION
DIVISION
89/PM(F)/P/
1B-67/2012
20-02-2014 22.49873 22.49873
24 INCOME GENERATIVE
COMMERCIAL HORTICULTURE
IN SMALL PLOT (5 KATTA) FOR
CULTIVATION OF EARLY
SUMMER VEGETABLE
SURROUNDED BY QUICK
GROWING LIME; RAIPUR,
RANIBUNDH, SARENGA,
SIMLAPAL (250 BENEFICIARIES
IN EACH BLOCK, COST OF
GROWING VEGETABLE CROPS
PER BENEFICIARY FOR 5 KATTA
IS RS. 4,321/-), BANKURA
MANAGING DIRECTOR, WEST
BENGAL STATE FOOD
PROCESSING &
HORTICULTURE
DEVELOPMENT CORPORATION
LIMITED
13/PM(F)/P/
1B-117/2013
07-01-2014 43.21000 43.21000 100% 43.21000 COMPLETE
3432.54170 2203.62895 223.97065 850.84651 TOTAL:
` IN LAC
NO. DATE
1 SCHEMES UNDER ZILLA
PARISHAD-PUAD MEGA
SCHEME:
IMPROVEMENT OF ROAD
FROM MULUK ADARSHA PALLI
TO SIAN HOSPITAL, BOLPUR-
SRINIKETAN, BIRBHUM
ADDITIONAL EXECUTIVE
OFFICER, BIRBHUM ZILLA
PARISHAD
120/PM(F)/P
/1B-28/2014
03-03-2014 22.50000 22.50000
2 SCHEMES UNDER ZILLA
PARISHAD-PUAD MEGA
SCHEME:
REPAIRING OF ROAD FROM
KASHIMBAZAR TO N.H.-2(B),
BOLPUR-SRINIKETAN,
BIRBHUM
ADDITIONAL EXECUTIVE
OFFICER, BIRBHUM ZILLA
PARISHAD
120/PM(F)/P
/1B-28/2014
03-03-2014 20.00000 20.00000
3 SCHEMES UNDER ZILLA
PARISHAD-PUAD MEGA
SCHEME:
IMPROVEMENT OF ROAD
FROM DHOLKATA TO
HABRAPAHARI PHASE-1, MD.
BAZAR, BIRBHUM
ADDITIONAL EXECUTIVE
OFFICER, BIRBHUM ZILLA
PARISHAD
120/PM(F)/P
/1B-28/2014
03-03-2014 15.00000 15.00000
4 SCHEMES UNDER ZILLA
PARISHAD-PUAD MEGA
SCHEME:
REPAIRING AND
MAINTENANCE OF CAUSEWAY
AT GOLTE, ILLAMBAZAR,
BIRBHUM
ADDITIONAL EXECUTIVE
OFFICER, BIRBHUM ZILLA
PARISHAD
120/PM(F)/P
/1B-28/2014
03-03-2014 22.50000 22.50000
SANCTIONED
AMOUNT
RELEASED
AMOUNT
FROM PUP
BILL PAID
FROM PUP
DISTRICT: BIRBHUM
DETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2013-14
SL.
NO.
NAME OF THE SCHEME EXECUTING AGENCY WITH
CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
EXPECTED
DATE OF
COMPLETION
UC RECEIVED REMARKS PHYSICAL
PROGRESS
` IN LAC
NO. DATE
SANCTIONED
AMOUNT
RELEASED
AMOUNT
FROM PUP
BILL PAID
FROM PUP
DISTRICT: BIRBHUM
DETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2013-14
SL.
NO.
NAME OF THE SCHEME EXECUTING AGENCY WITH
CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
EXPECTED
DATE OF
COMPLETION
UC RECEIVED REMARKS PHYSICAL
PROGRESS
5 SCHEMES UNDER ZILLA
PARISHAD-PUAD MEGA
SCHEME:
MAINTENANCE AND
UPGRADATION OF SURI-
AMJORA ROAD, SURI,
BIRBHUM
ADDITIONAL EXECUTIVE
OFFICER, BIRBHUM ZILLA
PARISHAD
120/PM(F)/P
/1B-28/2014
03-03-2014 22.50000 22.50000
6 SCHEMES UNDER ZILLA
PARISHAD-PUAD MEGA
SCHEME:
IMPROVEMENT OF ROAD
FROM KASTHOGORA TO
DHARAMPUR, RAMPURHAT-I,
BIRBHUM
ADDITIONAL EXECUTIVE
OFFICER, BIRBHUM ZILLA
PARISHAD
120/PM(F)/P
/1B-28/2014
03-03-2014 22.50000 22.50000
7 REPAIR & RENOVATION OF
SURI AREA OFFICE OF PUP
SITUATED AT GOLBARI, SURI,
BIRBHUM
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
198/PM(F)/P
/1B-
127/2013
25-11-2013 2.99546 2.88624 100% 2.88624 COMPLETE
8 IMPROVEMENT OF ROAD
FROM SIMULTALA PITCH
ROAD (PARUI GOYALPARA
ROAD) VIA BANDHANBAGRAM
HIGH SCHOOL AT KASBA G.P.,
BOLPUR-SRINIKETAN,
BIRBHUM
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
18/PM(F)/P/
1B-155/2013
07-01-2014 11.89758 WORK ORDER
ISSUED, SUBMITTED
TO PUA DEPTT. FOR
ADDITIONAL
SANCTION
` IN LAC
NO. DATE
SANCTIONED
AMOUNT
RELEASED
AMOUNT
FROM PUP
BILL PAID
FROM PUP
DISTRICT: BIRBHUM
DETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2013-14
SL.
NO.
NAME OF THE SCHEME EXECUTING AGENCY WITH
CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
EXPECTED
DATE OF
COMPLETION
UC RECEIVED REMARKS PHYSICAL
PROGRESS
9 IMPROVEMENT OF ROAD
FROM ASHADULLAPUR
ADIBASIPARA
(GHOSHALDANGA BRIDGE TO
SATTORE PRIMARY HEALTH
CENTRE) VIA SRICHANDRAPUR
AT KASBA G.P., BOLPUR-
SRINIKETAN, BIRBHUM
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
18/PM(F)/P/
1B-155/2013
07-01-2014 19.28353 WORK ORDER
ISSUED, SUBMITTED
TO PUA DEPTT. FOR
ADDITIONAL
SANCTION
10 IMPROVEMENT OF ROAD
FROM GHOSHALDANGA
BRIDGE TO BISHNUBATI
ADIBASIPARA AT KASBA G.P.,
BOLPUR-SRINIKETAN,
BIRBHUM
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
18/PM(F)/P/
1B-155/2013
07-01-2014 11.89758 WORK ORDER
ISSUED, SUBMITTED
TO PUA DEPTT. FOR
ADDITIONAL
SANCTION
11 CONSTRUCTION OF
APPROACH ROAD OF WEIR
BRIDGE OVER KANDAR AT
GHOSHALDANGA AT
ASHADULLAPUR AT SATTORE
G.P., BOLPUR-SRINIKETAN,
BIRBHUM
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
18/PM(F)/P/
1B-155/2013
07-01-2014 4.23950 WORK ORDER
ISSUED, SUBMITTED
TO PUA DEPTT. FOR
ADDITIONAL
SANCTION
12 IMPROVEMENT OF ROAD
FROM DEBAGRAM
MAGHIPARA TO SALON
VILLAGE OF DEBAGRAM
MAGHIPARA BHERAMARI
ROAD AT SATTORE G.P.,
BOLPUR-SRINIKETAN,
BIRBHUM
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
18/PM(F)/P/
1B-155/2013
07-01-2014 20.70158 WORK ORDER
ISSUED, SUBMITTED
TO PUA DEPTT. FOR
ADDITIONAL
SANCTION
` IN LAC
NO. DATE
SANCTIONED
AMOUNT
RELEASED
AMOUNT
FROM PUP
BILL PAID
FROM PUP
DISTRICT: BIRBHUM
DETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2013-14
SL.
NO.
NAME OF THE SCHEME EXECUTING AGENCY WITH
CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
EXPECTED
DATE OF
COMPLETION
UC RECEIVED REMARKS PHYSICAL
PROGRESS
13 IMPROVEMENT OF ROAD
FROM SALON VILLAGE TO
BHERAMARI SCHOOL OF
DEBAGRAM MAGHIPARA
BHERAMARI ROAD AT
SATTORE G.P., BOLPUR-
SRINIKETAN, BIRBHUM
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
18/PM(F)/P/
1B-155/2013
07-01-2014 16.59200 WORK ORDER
ISSUED, SUBMITTED
TO PUA DEPTT. FOR
ADDITIONAL
SANCTION
14 IMPLEMENTATION OF
DIFFERENT PROJECT @ `50
LAC EACH BLOCK IN 10
BLOCKS, BIRBHUM
DISTRICT MAGISTRATE,
BIRBHUM
151/PM(F)/P
/1B-82/2013
30-08-2013 500.00000 249.92835 50% 185.38892 WORK IN PROGRESS
15 CONSTRUCTION OF 119
ANGANWADI CENTRES EACH
@ `6.89600 LAC IN 10 BLOCKS,
BIRBHUM
DISTRICT MAGISTRATE,
BIRBHUM
188/PM(F)/P
/1B-97/2013
07-11-2013 820.62400 820.62400 20% 62.70500 SUB-ALLOTTED TO
E.O. OF P.S. ON 06-
12-2013, U.C. BY
MD. BAZAR
16 CONSTRUCTION OF MINI
BARRAGE OVER KANA AJOY
(6TH & 7TH INST.),
UPARKHARA MOUZA, BOLPUR-
SRINIKETAN, BIRBHUM
FUND: DISTRICT MAGISTRATE,
BIRBHUM; E.A.: EXECUTIVE
ENGINEER, MAYURAKSHI
SOUTH CANALS DIVISION,
IRRIGATION & WATERWAYS
DIRECTORATE, SANTINIKETAN
126/PM(F)/P
/1B-
89/2008(PT.-
I) & 29
23-05-2013 &
08-01-2014
160.91000 160.91000 75% 31-10-2013 109.39000 CIVIL PART
COMPLETE
17 IMPROVEMENT &
STRENGTHENING OF BOLPUR
ILLAMBAZAR ROAD FROM
1.0 KMP TO 9.40 KMP
EXCLUDING 3.0 KMP TO 5.20
KMP UNDER BOLPUR SUB-
DIVISION, BIRBHUM
EXECUTIVE ENGINEER, P.W.D.,
BIRBHUM DIVISION, 03462-
255261, 9830149949,
pwdbirbhum@gmail.com
158/PM(F)/P
/1B-
133/2011
17-09-2013 137.30196 137.30196 95% 31-08-2013 46.46058 WORK IN PROGRESS
1831.44319 1493.76431 2.88624 406.83074 TOTAL:
` IN LAC
NO. DATE
1 DRINKING WATER
ARRANGEMENT IN DIFFERENT
BLOCKS WITHIN JURISDICTION
OF PUP AREA, BURDWAN
ADDITIONAL EXECUTIVE
OFFICER, BURDWAN ZILLA
PARISHAD
88/PM(F)/P/
1B-20/2014
20-02-2014 251.64000 251.64000
2 CONSTRUCTION OF 200
ANGANWADI CENTRES EACH
@ `6.89600 LAC IN 10 BLOCKS,
BURDWAN
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
150/PM(F)/P
/1B-73/2013
30-08-2013 1,379.20000 657.03125 35% 657.03125 WORK IN PROGRESS
3 IMPLEMENTATION OF
DIFFERENT PROJECT @ `50
LAC EACH BLOCK IN 10
BLOCKS, BURDWAN
DISTRICT MAGISTRATE,
BURDWAN
151/PM(F)/P
/1B-82/2013
30-08-2013 500.00000 498.74322 50% 249.37161 WORK IN PROGRESS
4 RESTORATION OF CANAL BED
AND SLOPES INCLUDING
LINING WORKS WITH PCC
FROM CH. 472.00 TO CH.
488.00 UNDER BURDWAN
IRRIGATION SUB-DIVISION NO.-
III, KANKSA, BURDWAN
DISTRICT MAGISTRATE,
BURDWAN
47/PM(F)/P/
1B-258/2012
21-01-2014 22.44526 22.44526 22.44526 COMPLETE
5 RESTORATION OF CANAL BED
AND SLOPES INCLUDING
LINING WORKS WITH PCC
FROM CH. 488.00 TO CH.
506.00 UNDER BURDWAN
IRRIGATION SUB-DIVISION NO.-
III, KANKSA & AUSGRAM-II,
BURDWAN
DISTRICT MAGISTRATE,
BURDWAN
47/PM(F)/P/
1B-258/2012
21-01-2014 22.28023 22.28023 22.28023 COMPLETE
SANCTIONED
AMOUNT
RELEASED
AMOUNT
FROM PUP
BILL PAID
FROM PUP
DISTRICT: BURDWAN
DETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2013-14
SL.
NO.
NAME OF THE SCHEME EXECUTING AGENCY WITH
CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
EXPECTED
DATE OF
COMPLETION
UC RECEIVED REMARKS PHYSICAL
PROGRESS
` IN LAC
NO. DATE
SANCTIONED
AMOUNT
RELEASED
AMOUNT
FROM PUP
BILL PAID
FROM PUP
DISTRICT: BURDWAN
DETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2013-14
SL.
NO.
NAME OF THE SCHEME EXECUTING AGENCY WITH
CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
EXPECTED
DATE OF
COMPLETION
UC RECEIVED REMARKS PHYSICAL
PROGRESS
6 RESTORATION OF CANAL BED
AND SLOPES INCLUDING
LINING WORKS WITH PCC
FROM CH. 528.00 TO CH.
544.00 UNDER BURDWAN
IRRIGATION SUB-DIVISION NO.-
III, AUSGRAM-II, BURDWAN
DISTRICT MAGISTRATE,
BURDWAN
47/PM(F)/P/
1B-258/2012
21-01-2014 22.34318 22.34318 22.34318 COMPLETE
2197.90867 817.45189 657.03125 973.47153 TOTAL:
` IN LAC
NO. DATE
1 CONSTRUCTION OF VILLAGE
ROADS AND BOULDER/
MORRUM OR CONCRETE/
SMALL CULVERT, FOOT
BRIDGE, MINOR IRRIGATION
FACILITY, DRINKING WATER
SOURCE ETC. DIFFERENT PUP
BLOCKS, PASCHIM MEDINIPUR
ADDITIONAL EXECUTIVE
OFFICER, PASCHIM
MEDINIPUR ZILLA PARISHAD
64/PM(F)/P/
1B-08/2014
31-01-2014 503.00270 503.00270 50% 301.80162 WORK IN PROGRESS
2 IMPROVEMENT OF ROAD
FROM CHERABONI TO
BANDRABONI, BINPUR-I,
PASCHIM MEDINIPUR
BLOCK DEVELOPMENT
OFFICER, BINPUR-I BLOCK
108/PM(F)/P
/1B-40/2013
19-04-2013 4.44122 NIT ISSUED ON 10-
10-2013
3 IMPROVEMENT OF ROAD
FROM TENTULDANGA TO
NAHAR KHAL, BINPUR-I,
PASCHIM MEDINIPUR
BLOCK DEVELOPMENT
OFFICER, BINPUR-I BLOCK
108/PM(F)/P
/1B-40/2013
19-04-2013 12.79257 NIT ISSUED ON 10-
10-2013
4 CONSTRUCTION OF SLAB
CULVERT AT PASCHIM
CHAMAR BANDH, NAYAGRAM,
PASCHIM MEDINIPUR
BLOCK DEVELOPMENT
OFFICER, NAYAGRAM BLOCK
177/PM(F)/P
/1B-90/2013
10-10-2013 4.46171 0.12870 4.19632 100% 4.19632 COMPLETE
5 RENOVATION OF DAMP
BANDH, GARHBETA-III,
PASCHIM MEDINIPUR
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
106/PM(F)/P
/1B-42/2013
19-04-2013 19.27379 95% WORK IN PROGRESS
6 CONSTRUCTION OF 2
CLASSROOMS AT BHULAVEDA
JANAKALYAN HIGH SCHOOL
(HS), BINPUR-II, PASCHIM
MEDINIPUR
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
107/PM(F)/P
/1B-41/2013
19-04-2013 12.82295 11.14291 100% 11.14291 COMPLETE
SANCTIONED
AMOUNT
RELEASED
AMOUNT
FROM PUP
BILL PAID
FROM PUP
DISTRICT: PASCHIM MEDINIPUR
DETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2013-14
SL.
NO.
NAME OF THE SCHEME EXECUTING AGENCY WITH
CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
EXPECTED
DATE OF
COMPLETION
UC RECEIVED REMARKS PHYSICAL
PROGRESS
` IN LAC
NO. DATE
SANCTIONED
AMOUNT
RELEASED
AMOUNT
FROM PUP
BILL PAID
FROM PUP
DISTRICT: PASCHIM MEDINIPUR
DETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2013-14
SL.
NO.
NAME OF THE SCHEME EXECUTING AGENCY WITH
CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
EXPECTED
DATE OF
COMPLETION
UC RECEIVED REMARKS PHYSICAL
PROGRESS
7 SINKING OF 263 INDIAN MARK-
II TUBE-WELLS (`1.44871 LAC
EACH) FOR PROVIDING
DRINKING WATER IN 5 BLOCKS
(JAMBONI, GOPIBALLAVPUR-II,
SANKRAIL, JHARGRAM,
BINPUR-II), PASCHIM
MEDINIPUR
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
128/PM(F)/P
/1B-
112/2012 &
104
23-05-2013 &
05-05-2014
381.01073 75.17531 50% 75.17531 WORK IN PROGRESS,
148 COMPLETE
8 CONSTRUCTION OF CHECK
DAM OVER NAHAR KHAL AT
TENTULDANGA, BINPUR-I,
PASCHIM MEDINIPUR
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
132/PM(F)/P
/1B-53/2013
23-05-2013 28.09204 11.89156 50% 11.89156 WORK IN PROGRESS
9 CONSTRUCTION OF CHECK
DAM OVER NAHAR KHAL AT
JOULBHANGA, BINPUR-I,
PASCHIM MEDINIPUR
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
132/PM(F)/P
/1B-53/2013
23-05-2013 18.25182 10.66923 70% 10.66923 WORK IN PROGRESS
10 DISMENTLING OF BRIDGE &
DIVERSION OF ROAD OVER
HATITOLA TO JOSHPUR ROAD
(NAHAR KHAL), JHARGRAM,
PASCHIM MEDINIPUR
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
133/PM(F)/P
/1B-54/2013
23-05-2013 3.80927 3.80927 100% 3.80927 COMPLETE
` IN LAC
NO. DATE
SANCTIONED
AMOUNT
RELEASED
AMOUNT
FROM PUP
BILL PAID
FROM PUP
DISTRICT: PASCHIM MEDINIPUR
DETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2013-14
SL.
NO.
NAME OF THE SCHEME EXECUTING AGENCY WITH
CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
EXPECTED
DATE OF
COMPLETION
UC RECEIVED REMARKS PHYSICAL
PROGRESS
11 PREPARATION OF DPR
ALONGWITH OTHER WORK
FOR CONSTRUCTION OF
BRIDGE AT PAPATPUR NADI
GHAT VIZ. SOIL TESTING (`1
LAC), SURVEY WORK (`0.5
LAC), PREPARATION OF DPR
(`8 LAC) & OTHER MISC.
WORK (`0.5 LAC), BINPUR-I,
PASCHIM MEDINIPUR
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
135/PM(F)/P
/1B-55/2013
24-05-2013 10.00000 EOI ISSUED
12 CONSTRUCTION OF
APPROACH ROAD WITH CROSS
DRAINAGE WORK TO
RAMGARH POLYTECHNIC,
BINPUR-I, PASCHIM
MEDINIPUR
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
141/PM(F)/P
/1B-61/2013
& 50
31-07-2013 &
21-01-2014
78.11984 72.67030 100% 72.67030 COMPLETE
13 CONSTRUCTION OF ACCESS
ROAD VIA SALBONI COLLEGE
TO SALBONI STADIUM FROM
BHADUTALA LALGARH BLACK
TOP ROAD (600MM) WITH
CROSS DRAINAGE STRUCTURE
(1000MM DIA DOUBLE HUME
PIPE) & GUARD WALL (30
MTR) ALONG POND TO
PROTECT THE ACCESS ROAD,
SALBONI, PASCHIM
MEDINIPUR
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
141/PM(F)/P
/1B-61/2013
& 155 & 118
31-07-2013 &
11-09-2013 &
03-03-2014
50.67236 50.66634 100% 50.66634 COMPLETE
` IN LAC
NO. DATE
SANCTIONED
AMOUNT
RELEASED
AMOUNT
FROM PUP
BILL PAID
FROM PUP
DISTRICT: PASCHIM MEDINIPUR
DETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2013-14
SL.
NO.
NAME OF THE SCHEME EXECUTING AGENCY WITH
CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
EXPECTED
DATE OF
COMPLETION
UC RECEIVED REMARKS PHYSICAL
PROGRESS
14 1 NO. CROSS DRAINAGE
STRUCTURE BY 1000MM DIA
DOUBLE HUME PIPE ON
ACCESS ROAD TO
GOPIBALLAVPUR MODEL
SCHOOL AND ANOTHER
CROSSING DRAINAGE WITH
600 MM DIA HUME PIPE ON
ACCESS ROAD TO
GOPIBALLAVPUR MODEL
SCHOOL, PASCHIM
MEDINIPUR
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
141/PM(F)/P
/1B-61/2013
& 155
31-07-2013 &
11-09-2013
2.39746 2.34680 100% 2.34680 COMPLETE
15 CONSTRUCTION OF
APPROACH ROAD TO GIRLS'
HOSTEL OF LALGARH GIRLS'
HIGH SCHOOL, PASCHIM
MEDINIPUR
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
141/PM(F)/P
/1B-61/2013
31-07-2013 3.62914 3.52095 100% 3.52095 COMPLETE
16 CONSTRUCTION OF
APPROACH ROAD TO
KRISHNABANDH INTEGRATED
SCHOOL, PASCHIM
MEDINIPUR
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
141/PM(F)/P
/1B-61/2013
31-07-2013 17.92681 17.26235 100% 17.26235 COMPLETE
17 CONSTRUCTION OF 2 NOS.
CROSS DRAINAGE WITH 900
MM DIA SINGLE BARREL
HUME PIPE CULVERT ON
ACCESS ROAD TO MIRGA
INTEGRATED SCHOOL,
SALBONI, PASCHIM
MEDINIPUR
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
141/PM(F)/P
/1B-61/2013
& 155
31-07-2013 &
11-09-2013
2.70494 2.29095 100% 2.29095 COMPLETE
` IN LAC
NO. DATE
SANCTIONED
AMOUNT
RELEASED
AMOUNT
FROM PUP
BILL PAID
FROM PUP
DISTRICT: PASCHIM MEDINIPUR
DETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2013-14
SL.
NO.
NAME OF THE SCHEME EXECUTING AGENCY WITH
CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
EXPECTED
DATE OF
COMPLETION
UC RECEIVED REMARKS PHYSICAL
PROGRESS
18 CONSTRUCTION OF
APPROACH ROAD TO
NAYAGRAM COLLEGE,
PASCHIM MEDINIPUR
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
141/PM(F)/P
/1B-61/2013
31-07-2013 78.93719 78.82938 100% 78.82938 COMPLETE
19 CONSTRUCTION OF
APPROACH ROAD TO ITI AT
SALBONI, PASCHIM
MEDINIPUR
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
141/PM(F)/P
/1B-61/2013
31-07-2013 7.68883 7.40097 100% 7.40097 COMPLETE
20 REPAIRING OF BITUMEN ROAD
FROM BINPUR TO PAPATPUR
NODIGHAT AND BOXI VIA
HARDA AND MURGIMORE
(ADDITIONAL AMOUNT),
BINPUR-I, PASCHIM
MEDINIPUR
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
152/PM(F)/P
/1B-
141/2012
06-09-2013 102.88258 40.14117 85% 40.14117 WORK ORDER
ISSUED IN 3 PARTS;
WORK IN PROGRESS,
2 PART COMPLETE
21 CONSTRUCTION OF OFFICE
BUILDING (1ST FLOOR) FOR
PASCHIM MEDINIPUR AREA-
OFFICE OF PUP AT
COLLECTORATE COMPOUND,
MEDINIPUR SADAR, PASCHIM
MEDINIPUR
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
153/PM(F)/P
/1B-67/2013
09-09-2013 41.98943 14.71570 75% 14.71570 WORK IN PROGRESS
22 RE-EXCAVATION OF RAJ
BUNDH AT LALGARH, BINPUR-
I, PASCHIM MEDINIPUR
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
161/PM(F)/P
/1B-
101/2013 &
103
23-09-2013 &
05-05-2014
102.51219 76.19344 80% 76.19344 WORK IN PROGRESS
23 CONSTRUCTION OF BRIDGE
OVER NAHAR KHAL, BINPUR-I,
PASCHIM MEDINIPUR
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
162/PM(F)/P
/1B-
100/2013
23-09-2013 127.39645 25.46514 25% 25.46514 WORK IN PROGRESS
` IN LAC
NO. DATE
SANCTIONED
AMOUNT
RELEASED
AMOUNT
FROM PUP
BILL PAID
FROM PUP
DISTRICT: PASCHIM MEDINIPUR
DETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2013-14
SL.
NO.
NAME OF THE SCHEME EXECUTING AGENCY WITH
CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
EXPECTED
DATE OF
COMPLETION
UC RECEIVED REMARKS PHYSICAL
PROGRESS
24 CONSTRUCTION OF
CLASSROOM, LIBRARY AND
GIRLS' COMMON ROOM AT
GOLAR SUSHILA VIDYAPITH,
KESHPUR, PASCHIM
MEDINIPUR
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
167/PM(F)/P
/1B-
102/2013
25-09-2013 22.98739 16.57349 70% 16.57349 WORK IN PROGRESS
25 CONSTRUCTION OF CONCRETE
ROAD FROM HOTEL PRAYAG
TO END OF SANJOY BOXI
HOUSE, GARHBETA-III,
PASCHIM MEDINIPUR
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
213/PM(F)/P
/1B-
111/2013
19-12-2013 6.79559 6.54782 100% 6.54782 COMPLETE
26 CONSTRUCTION OF CONCRETE
ROAD FROM HOTEL PRAYAG
TO GOPAL KHAMRI SAW MILL,
GARHBETA-III, PASCHIM
MEDINIPUR
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
213/PM(F)/P
/1B-
111/2013
19-12-2013 6.79559 10% WORK IN PROGRESS
27 CONSTRUCTION OF
BOUNDARY WALL AND GATE
AT KIABONI SHREE SARADA
ASHRAM, GARHBETA-III,
PASCHIM MEDINIPUR
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
213/PM(F)/P
/1B-
111/2013
19-12-2013 4.18037 WORK IN PROGRESS
28 CONSTRUCTION OF
BOUNDARY WALL AND MAIN
GATE AT KENDIJAMBONI
NORTH KABARSTHAN (WEST
SIDE), GARHBETA-III, PASCHIM
MEDINIPUR
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
213/PM(F)/P
/1B-
111/2013
19-12-2013 7.83480 10% WORK IN PROGRESS
` IN LAC
NO. DATE
SANCTIONED
AMOUNT
RELEASED
AMOUNT
FROM PUP
BILL PAID
FROM PUP
DISTRICT: PASCHIM MEDINIPUR
DETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2013-14
SL.
NO.
NAME OF THE SCHEME EXECUTING AGENCY WITH
CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
EXPECTED
DATE OF
COMPLETION
UC RECEIVED REMARKS PHYSICAL
PROGRESS
29 CONSTRUCTION OF
BOUNDARY WALL AND MAIN
GATE AT KENDIJAMBONI
NORTH KABARSTHAN (NORTH
& HALF PORTION OF EAST
SIDE), GARHBETA-III, PASCHIM
MEDINIPUR
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
213/PM(F)/P
/1B-
111/2013
19-12-2013 7.81731 10% WORK IN PROGRESS
30 CONSTRUCTION OF
BOUNDARY WALL AND MAIN
GATE AT KENDIJAMBONI
NORTH KABARSTHAN (SOUTH
& HALF PORTION OF EAST
SIDE), GARHBETA-III, PASCHIM
MEDINIPUR
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
213/PM(F)/P
/1B-
111/2013
19-12-2013 7.44975 10% WORK IN PROGRESS
31 CONSTRUCTION OF
ADDITIONAL SCHOOL
BUILDING IN GROUND FLOOR
OF SERE BHALIBANDH JR.
HIGH SCHOOL, SALBONI,
PASCHIM MEDINIPUR
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
213/PM(F)/P
/1B-
111/2013
19-12-2013 20.69437 10% WORK IN PROGRESS
32 CONSTRUCTION OF 4 NOS.
CLASSROOMS WITH
STAIRCASE AND VERANDAH OF
DHOLKATA PUKURIA
PRANABANANDA
VIDYAMANDIR, PUKURIA,
JHARGRAM, PASCHIM
MEDINIPUR
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
02/PM(F)/P/
1B-146/2013
02-01-2014 23.61376 5% WORK IN PROGRESS
` IN LAC
NO. DATE
SANCTIONED
AMOUNT
RELEASED
AMOUNT
FROM PUP
BILL PAID
FROM PUP
DISTRICT: PASCHIM MEDINIPUR
DETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2013-14
SL.
NO.
NAME OF THE SCHEME EXECUTING AGENCY WITH
CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
EXPECTED
DATE OF
COMPLETION
UC RECEIVED REMARKS PHYSICAL
PROGRESS
33 CONSTRUCTION OF PIPE
CAUSEWAY ON BAITAL KHAL,
GARHBETA-II, PASCHIM
MEDINIPUR
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
04/PM(F)/P/
1B-04/2012
03-01-2014 44.38266 28.90132 35% 28.90132 WORK IN PROGRESS
34 CONSTRUCTION OF GROUND
FLOOR SCHOOL BUILDING OF
BALARAMPUR ABHAY
ASHRAM NAITALIM VIDYAPITH
(H.S.), ARASENI MOUZA, P.O. -
BALARAMPUR, P.S. -
KHARAGPUR, PASCHIM
MEDINIPUR
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
20/PM(F)/P/
1B-161/2013
07-01-2014 28.82273 WORK ORDER
ISSUED
35 CONSTRUCTION OF CONCRETE
ROAD OF BARPAT GRAMIN
ROAD IN PATINA GRAMIN
PANCHAYAT, NAYAGRAM,
PASCHIM MEDINIPUR
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
21/PM(F)/P/
1B-162/2013
07-01-2014 17.00299 16.50087 100% 16.50087 THIS PHASE
COMPLETE, WORK
AS PER REVISED
ESTIMATE YET TO BE
TAKEN UP
36 CONSTRUCTION OF SCHOOL
BUILDING AND GROUND
FLOOR OF PROPOSED NEW
BUILDING OF BHADUTALA
VIVEKANANDA HIGH SCHOOL,
SALBONI, PASCHIM
MEDINIPUR
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
28/PM(F)/P/
1B-110/2013
08-01-2014 42.79000 5% WORK IN PROGRESS
` IN LAC
NO. DATE
SANCTIONED
AMOUNT
RELEASED
AMOUNT
FROM PUP
BILL PAID
FROM PUP
DISTRICT: PASCHIM MEDINIPUR
DETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2013-14
SL.
NO.
NAME OF THE SCHEME EXECUTING AGENCY WITH
CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
EXPECTED
DATE OF
COMPLETION
UC RECEIVED REMARKS PHYSICAL
PROGRESS
37 CONSTRUCTION OF BUILDING
AND OTHER INFRASTRUCTURE
FOR NEWLY SET UP DUKI
JUNIOR HIGH SCHOOL,
GARHBETA-III, PASCHIM
MEDINIPUR
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
28/PM(F)/P/
1B-110/2013
08-01-2014 7.81775 20% WORK IN PROGRESS
38 CONSTRUCTION OF CONCRETE
ROAD FROM LALGARH GYAN
MANDIR TO AGAMANI
BANERJEES HOUSE VIA H/O
SUNIL SAMANTA, NIRMAL
ROY, AKHRAGORA HARI
MANDIR & DIREN ROYS
HOUSE, LALGARH GP, BINPUR-
I, PASCHIM MEDINIPUR
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
41/PM(F)/P/
1B-148/2013
17-01-2014 41.12834 WORK ORDER
ISSUED
39 CONSTRUCTION OF CONCRETE
ROAD FROM LALGARH GYAN
MANDIR TO MAHADEV ROYS
TEA SHOP VIA AIRTEL TOWER,
POST OFFICE, BIBEK
GOSWAMIS HOUSE & KISHOR
TEWARIS HOUSE, LALGARH
GP, BINPUR-I, PASCHIM
MEDINIPUR
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
41/PM(F)/P/
1B-148/2013
17-01-2014 36.96035 WORK ORDER
ISSUED
` IN LAC
NO. DATE
SANCTIONED
AMOUNT
RELEASED
AMOUNT
FROM PUP
BILL PAID
FROM PUP
DISTRICT: PASCHIM MEDINIPUR
DETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2013-14
SL.
NO.
NAME OF THE SCHEME EXECUTING AGENCY WITH
CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
EXPECTED
DATE OF
COMPLETION
UC RECEIVED REMARKS PHYSICAL
PROGRESS
40 CONSTRUCTION OF CONCRETE
ROAD FROM BHOKTAPARA
NIRANJAN DASS HOUSE TO
RAJARBANDH VIA LALGARH
GIRLS SCHOOL, U.B.I., SAROJ
GOSWAMI, PRADIP
NARAYANS HOUSE, LALGARH
GP, BINPUR-I, PASCHIM
MEDINIPUR
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
41/PM(F)/P/
1B-148/2013
17-01-2014 26.34803 WORK ORDER
ISSUED
41 CONSTRUCTION OF CONCRETE
ROAD FROM BIDYUT ROYS
HOUSE TO RAJAR BUNDH VIA
HOUSE OF BHUDEB ROY,
RAMKHAHARI ROY, RATAN
KHILARI, LALGARH GP, BINPUR-
I, PASCHIM MEDINIPUR
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
41/PM(F)/P/
1B-148/2013
17-01-2014 15.82739 WORK ORDER
ISSUED
42 CONSTRUCTION OF CONCRETE
ROAD FROM TEA SHOP OF
NARAD DAS AT LALGARH
BAZAR TO KANGSHABATI NODI
GHAT VIA BAGHAKHULHI,
LALGARH GP, BINPUR-I,
PASCHIM MEDINIPUR
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
41/PM(F)/P/
1B-148/2013
17-01-2014 25.83520 WORK ORDER
ISSUED
43 CONSTRUCTION OF CONCRETE
ROAD FROM KANKON GIRLS
SAW MILL TO RAJARBUNDH,
LALGARH GP, BINPUR-I,
PASCHIM MEDINIPUR
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
41/PM(F)/P/
1B-148/2013
17-01-2014 10.55103 WORK ORDER
ISSUED
` IN LAC
NO. DATE
SANCTIONED
AMOUNT
RELEASED
AMOUNT
FROM PUP
BILL PAID
FROM PUP
DISTRICT: PASCHIM MEDINIPUR
DETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2013-14
SL.
NO.
NAME OF THE SCHEME EXECUTING AGENCY WITH
CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
EXPECTED
DATE OF
COMPLETION
UC RECEIVED REMARKS PHYSICAL
PROGRESS
44 CONSTRUCTION OF CONCRETE
ROAD FROM PRASANTA
DUTTAS HOUSE TO
RAMKRISHNA VIDYALAYA VIA
BRAHMAN PALLY, LALGARH
GP, BINPUR-I, PASCHIM
MEDINIPUR
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
41/PM(F)/P/
1B-148/2013
17-01-2014 12.52810 WORK ORDER
ISSUED
45 CONSTRUCTION OF CONCRETE
ROAD FROM LATE
SATYANARAYAN ROYS HOUSE
TO RAJAR BUNDH, LALGARH
GP, BINPUR-I, PASCHIM
MEDINIPUR
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
41/PM(F)/P/
1B-148/2013
17-01-2014 5.34396 WORK ORDER
ISSUED
46 CONSTRUCTION OF CONCRETE
ROAD FROM TEA SHOP OF
MAHADEV ROY NEAR
BITUMEN ROAD TO CRPF
CAMP & FOREST RANGE
OFFICE VIA HOUSE OF ABDUL
SK, LALGARH GP, BINPUR-I,
PASCHIM MEDINIPUR
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
41/PM(F)/P/
1B-148/2013
17-01-2014 15.82739 WORK ORDER
ISSUED
47 IMPROVEMENT OF MORRUM
BOULDER ROAD AT DARHPARI
KHAL TO KANAI HANSDA
HOUSE VIA BARANALA,
BINPUR-I, PASCHIM
MEDINIPUR
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
54/PM(F)/P/
1B-05/2014
24-01-2014 44.58280 9.30480 50% 9.30480 WORK IN PROGRESS
48 RE-EXCAVATION OF SURER
BUNDH (1ST PART) AT
RAMGARH G.P., BINPUR-I,
PASCHIM MEDINIPUR
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
66/PM(F)/P/
1B-10/2014
& 106
31-01-2014 &
06-05-2014
198.96817 TENDER IN PROCESS
` IN LAC
NO. DATE
SANCTIONED
AMOUNT
RELEASED
AMOUNT
FROM PUP
BILL PAID
FROM PUP
DISTRICT: PASCHIM MEDINIPUR
DETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2013-14
SL.
NO.
NAME OF THE SCHEME EXECUTING AGENCY WITH
CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
EXPECTED
DATE OF
COMPLETION
UC RECEIVED REMARKS PHYSICAL
PROGRESS
49 REPAIR OF CAUSEWAY-1 AT
BORO MURGI TO
DHALBHANGA ROAD OVER
TARAPHENI RIVER, BINPUR-I,
PASCHIM MEDINIPUR
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
68/PM(F)/P/
1B-84/2013
06-02-2014 42.18033 TENDER IN PROCESS
50 REPAIR OF CAUSEWAY-2 AT
CHOTO MURGI TO
DHALBHANGA ROAD OVER
BIJALIS KHAL, BINPUR-I,
PASCHIM MEDINIPUR
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
68/PM(F)/P/
1B-84/2013
06-02-2014 3.94059 TENDER IN PROCESS
51 CONSTRUCTION OF RCC ROAD
BRIDGE AT PAPATPUR
NODIGHAT (PHASE-I), BINPUR-
I, PASCHIM MEDINIPUR
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
69/PM(F)/P/
1B-11/2014
& 110
06-02-2014 &
28-02-2014
203.82968 DPR SUBMITTED
52 CONSTRUCTION & REPAIR OF
ROAD FROM BITUMINOUS
MAIN ROAD TO CHILKIGARH
TEMPLE AT CHILKIGARH,
JAMBONI, PASCHIM
MEDINIPUR
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
74/PM(F)/P/
1B-159/13
11-02-2014 17.68090 TENDER IN PROCESS
53 CONSTRUCTION OF TWO
STORIED SCHOOL BUILDING,
BOYS TOILET BLOCK AND
LADIES TOILET BLOCK OF
KHASLA INDUMOTI HIGH
SCHOOL, SALBONI, PASCHIM
MEDINIPUR
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
75/PM(F)/P/
1B-112/2013
11-02-2014 36.64856 5% WORK IN PROGRESS
` IN LAC
NO. DATE
SANCTIONED
AMOUNT
RELEASED
AMOUNT
FROM PUP
BILL PAID
FROM PUP
DISTRICT: PASCHIM MEDINIPUR
DETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2013-14
SL.
NO.
NAME OF THE SCHEME EXECUTING AGENCY WITH
CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
EXPECTED
DATE OF
COMPLETION
UC RECEIVED REMARKS PHYSICAL
PROGRESS
54 CONSTRUCTION OF BRIDGE
OVER KELEGHAI NADI AT
BAGMARI GHAT, SANKRAIL,
PASCHIM MEDINIPUR
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
65/PM(F)/P/
1B-09/2014
31-01-2014 45.48852 TENDER INFORMAL
55 CONSTRUCTION OF BRIDGE AT
PALOIDANGA OVER GHUNIA
KHAL, SANKRAIL, PASCHIM
MEDINIPUR
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
65/PM(F)/P/
1B-09/2014
31-01-2014 49.96803 WORK ORDER
ISSUED
56 RE-EXCAVATION OF
BHUSKABURIS POND OF
NEDABAHRA G.P., JHARGRAM,
PASCHIM MEDINIPUR
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
79/PM(F)/P/
1B-06/2014
& 105
17-02-2014 &
06-05-2014
48.09887 TENDER INVITED
57 CONSTRUCTION OF CHECK
DAM OVER PACHA KHAL AT
BHANGABANDH, JHARGRAM,
PASCHIM MEDINIPUR
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
79/PM(F)/P/
1B-06/2014
17-02-2014 23.18594 TENDER INVITED
58 CONSTRUCTION OF CHECK
DAM OVER PUTRANGI KHAL
AT CHANDABILA, JHARGRAM,
PASCHIM MEDINIPUR
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
79/PM(F)/P/
1B-06/2014
17-02-2014 25.73531 TENDER INVITED
59 CONSTRUCTION OF CHECK
DAM OVER NAHAR KHAL AT
JORAKHALI, JHARGRAM,
PASCHIM MEDINIPUR
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
79/PM(F)/P/
1B-06/2014
17-02-2014 19.72363 TENDER INVITED
60 RE-EXCAVATION OF PARGANA
BUNDH AT RAGHUNATHPUR
MOUJA, BINPUR-I, PASCHIM
MEDINIPUR
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
79/PM(F)/P/
1B-06/2014
17-02-2014 66.89922 TENDER INVITED
` IN LAC
NO. DATE
SANCTIONED
AMOUNT
RELEASED
AMOUNT
FROM PUP
BILL PAID
FROM PUP
DISTRICT: PASCHIM MEDINIPUR
DETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2013-14
SL.
NO.
NAME OF THE SCHEME EXECUTING AGENCY WITH
CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
EXPECTED
DATE OF
COMPLETION
UC RECEIVED REMARKS PHYSICAL
PROGRESS
61 EXCAVATION OF NEW POND
AT KHOSA MOUZA, NEPURA
G.P., JHARGRAM, PASCHIM
MEDINIPUR
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
80/PM(F)/P/
1B-13/2014
17-02-2014 28.49980 TENDER INVITED
62 RE-EXCAVATION OF RAJ
BUNDH AT RAMGARH,
RAMGARH G.P., BINPUR-I,
PASCHIM MEDINIPUR
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
81/PM(F)/P/
1B-22/2014
17-02-2014 199.34859
63 IMPLEMENTATION OF
DIFFERENT PROJECT @ `50
LAC EACH BLOCK IN 18
BLOCKS, PASCHIM MEDINIPUR
DISTRICT MAGISTRATE,
PASCHIM MEDINIPUR
151/PM(F)/P
/1B-82/2013
30-08-2013 900.00000 438.26543 30% 321.77288 WORK IN PROGRESS
64 INFRASTRUCTURAL
DEVELOPMENT OF SILDA
CHANDRA SEKHAR COLLEGE
EXECUTIVE ENGINEER-I, PWD,
KHARAGPUR DIVISION,
PASCHIM MEDINIPUR
34/PM(F)/P/
1B-
67/2008(PT-
IV)
13-01-2014 100.00000 100.00000
65 CONSTRUCTION OF DEEP
TUBEWELL FOR IRRIGATION
WATER AT RANABANDH,
BINPUR-I, PASCHIM
MEDINIPUR
EXECUTIVE OFFICER, BINPUR-I
PANCHAYAT SAMITY
79/PM(F)/P/
1B-06/2014
17-02-2014 8.99553 8.99553
66 CONSTRUCTION OF DEEP
TUBEWELL FOR IRRIGATION
WATER AT DHABANI, BINPUR-
I, PASCHIM MEDINIPUR
EXECUTIVE OFFICER, BINPUR-I
PANCHAYAT SAMITY
79/PM(F)/P/
1B-06/2014
17-02-2014 8.99553 8.99553
` IN LAC
NO. DATE
SANCTIONED
AMOUNT
RELEASED
AMOUNT
FROM PUP
BILL PAID
FROM PUP
DISTRICT: PASCHIM MEDINIPUR
DETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2013-14
SL.
NO.
NAME OF THE SCHEME EXECUTING AGENCY WITH
CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
EXPECTED
DATE OF
COMPLETION
UC RECEIVED REMARKS PHYSICAL
PROGRESS
67 CONSTRUCTION OF DEEP
TUBEWELL FOR IRRIGATION
WATER AT SINGPUR, BINPUR-I,
PASCHIM MEDINIPUR
EXECUTIVE OFFICER, BINPUR-I
PANCHAYAT SAMITY
79/PM(F)/P/
1B-06/2014
17-02-2014 8.99553 8.99553
68 CONSTRUCTION OF
PASSENGER SHED WITH
TOILET AT ANDHARIA BUS
STAND, BINPUR-I, PASCHIM
MEDINIPUR
EXECUTIVE OFFICER, BINPUR-I
PANCHAYAT SAMITY
79/PM(F)/P/
1B-06/2014
17-02-2014 2.96647 2.96647
69 CONSTRUCTION OF TUBEWELL
FOR DRINKING WATER AT
BHANJADIHI S.S.K., ANDHARIA
G.P., BINPUR-I, PASCHIM
MEDINIPUR
EXECUTIVE OFFICER, BINPUR-I
PANCHAYAT SAMITY
79/PM(F)/P/
1B-06/2014
17-02-2014 4.03449 4.03449
70 CONSTRUCTION OF TUBEWELL
FOR DRINKING WATER AT
KUSUMDANGA, ANDHARIA
G.P., BINPUR-I, PASCHIM
MEDINIPUR
EXECUTIVE OFFICER, BINPUR-I
PANCHAYAT SAMITY
79/PM(F)/P/
1B-06/2014
17-02-2014 4.03449 4.03449
71 CONSTRUCTION OF TUBEWELL
FOR DRINKING WATER AT
DUBRAJPUR PR. SCHOOL AT
ANDHARIA G.P., BINPUR-I,
PASCHIM MEDINIPUR
EXECUTIVE OFFICER, BINPUR-I
PANCHAYAT SAMITY
79/PM(F)/P/
1B-06/2014
17-02-2014 4.03449 4.03449
72 CONSTRUCTION OF CONCRETE
ROAD AT BHALUKHULIA MAIN
ROAD TO AAM BAGAN
VILLAGE ROAD,
GOPIBALLAVPUR-II, PASCHIM
MEDINIPUR
EXECUTIVE OFFICER,
GOPIBALLAVPUR-II
PANCHAYAT SAMITY
77/PM(F)/P/
1B-03/2014
17-02-2014 12.76862 12.76862
` IN LAC
NO. DATE
SANCTIONED
AMOUNT
RELEASED
AMOUNT
FROM PUP
BILL PAID
FROM PUP
DISTRICT: PASCHIM MEDINIPUR
DETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2013-14
SL.
NO.
NAME OF THE SCHEME EXECUTING AGENCY WITH
CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
EXPECTED
DATE OF
COMPLETION
UC RECEIVED REMARKS PHYSICAL
PROGRESS
73 CONSTRUCTION OF CONCRETE
ROAD AT MALANCHA BATTALA
TO RAJENDRA DANDAPAT'S
HOUSE ROAD,
GOPIBALLAVPUR-II, PASCHIM
MEDINIPUR
EXECUTIVE OFFICER,
GOPIBALLAVPUR-II
PANCHAYAT SAMITY
77/PM(F)/P/
1B-03/2014
17-02-2014 20.99831 20.99831
74 CONSTRUCTION OF DARKHULI
GRAMIN ROAD IN
RADHANAGAR G.P.,
JHARGRAM, PASCHIM
MEDINIPUR
EXECUTIVE OFFICER,
JHARGRAM PANCHAYAT
SAMITY
09/PM)F)/P/
1B-152/2013
03-01-2014 13.62735
75 IMPROVEMENT OF ROAD
FROM DARKHULI TO
MOHANPUR IN RADHANAGAR
G.P., JHARGRAM, PASCHIM
MEDINIPUR
EXECUTIVE OFFICER,
JHARGRAM PANCHAYAT
SAMITY
09/PM)F)/P/
1B-152/2013
03-01-2014 6.74976
76 IMPROVEMENT OF ROAD
FROM TENGIOA PITCH ROAD
TO KANYADUBA IN SAPDHARA
AND RADHANAGAR G.P.,
JHARGRAM, PASCHIM
MEDINIPUR
EXECUTIVE OFFICER,
JHARGRAM PANCHAYAT
SAMITY
09/PM)F)/P/
1B-152/2013
03-01-2014 14.97685
77 CONSTRUCTION OF MEETING
HALL AT DWARIGERIA BPHC,
GARHBETA-III, PASCHIM
MEDINIPUR
EXECUTIVE OFFICER,
GARHBETA-III PANCHAYAT
SAMITY
28/PM(F)/P/
1B-110/2013
08-01-2014 16.52647 16.52647
35.35216
` IN LAC
NO. DATE
SANCTIONED
AMOUNT
RELEASED
AMOUNT
FROM PUP
BILL PAID
FROM PUP
DISTRICT: PASCHIM MEDINIPUR
DETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2013-14
SL.
NO.
NAME OF THE SCHEME EXECUTING AGENCY WITH
CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
EXPECTED
DATE OF
COMPLETION
UC RECEIVED REMARKS PHYSICAL
PROGRESS
78 CONSTRUCTION OF SCHOOL
BUILDING AT KHAJRA SATISH
CHANDRA MEMORIAL HIGH
SCHOOL (HS), KESHIARY,
PASCHIM MEDINIPUR
HEADMASTER, KHAJRA SATISH
CHANDRA MEMORIAL HIGH
SCHOOL (HS), PO-KUSHGERIA,
DIST-PASCHIM MEDINIPUR
131/PM(F)/P
/1B-27/2013
23-05-2013 19.50000 9.75000
79 CONSTRUCTION OF HOSTEL
BUILDING AT NAYAGRAM
HIGH SCHOOL (H.S.), P.S. -
KOTWALI, PASCHIM
MEDINIPUR
SCHOOL AUTHORITY,
NAYAGRAM HIGH SCHOOL,
P.O. - NAYAGRAM-BENASULI,
P.S. - KOTWALI, PASCHIM
MEDINIPUR - 721102
206/PM(F)/P
/1B-
121/2013
10-12-2013 30.84796 15.42398
80 CONSTRUCTION OF
BOUNDARY WALL OF
GODAPIASAL MAHATMA
GANDHI MEMORIAL HIGH
SCHOOL (H.S.), SALBONI,
PASCHIM MEDINIPUR
SCHOOL AUTHORITY,
GODAPIASAL MAHATMA
GANDHI MEMORIAL HIGH
SCHOOL (H.S.), SALBONI,
PASCHIM MEDINIPUR
210/PM(F)/P
/1B-
129/2013
13-12-2013 24.92800 12.46400
81 CONSTRUCTION OF
COMMUNITY HALL AT
JHARGRAM NANIBALA BALIKA
VIDYALAYA, JHARGRAM,
PASCHIM MEDINIPUR
SCHOOL AUTHORITY,
JHARGRAM NANIBALA BALIKA
VIDYALAYA
33/PM(F)/P/
1B-17/2013
10-01-2014 17.91143 8.95571
82 CONSTRUCTION OF SCHOOL
BUILDING OF PAIKAMBI
NIGAMANANDA HIGH
SCHOOL, GOPIBALLAVPUR-II,
PASCHIM MEDINIPUR
SCHOOL AUTHORITY,
PAIKAMBI NIGAMANANDA
HIGH SCHOOL
82/PM(F)/P/
1B-21/2014
17-02-2014 28.37078 14.18539
` IN LAC
NO. DATE
SANCTIONED
AMOUNT
RELEASED
AMOUNT
FROM PUP
BILL PAID
FROM PUP
DISTRICT: PASCHIM MEDINIPUR
DETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2013-14
SL.
NO.
NAME OF THE SCHEME EXECUTING AGENCY WITH
CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
EXPECTED
DATE OF
COMPLETION
UC RECEIVED REMARKS PHYSICAL
PROGRESS
83 CONSTRUCTION OF GIRLS
TOILET AND URINAL AT ANTRA
SARADAMONI BALIKA
VIDYALAYA, P.O. - ATTARKHI,
PASCHIM MEDINIPUR
SCHOOL AUTHORITY, ANTRA
SARADAMONI BALIKA
VIDYALAYA
91/PM(F)/P/
1B-17/2014
20-02-2014 5.91387 5.91387
84 CONSTRUCTION OF CYCLE
STAND AT SUBARNAREKHA
MAHAVIDYALAYA,
GOPIBALLAVPUR, PASCHIM
MEDINIPUR
TEACHER-IN-CHARGE,
SUBARNAREKHA
MAHAVIDYALAYA
83/PM(F)/P/
1B-139/2013
17-02-2014 6.68148 6.68148
85 CONSTRUCTION OF SINGLE
STORIED ADDITIONAL
CLASSROOMS OF
BAGHUASOLE JUNSOLE
NEHRU VIDYAPITH, P.S. -
BELIABERA, GOPIBALLAVPUR-
II, PASCHIM MEDINIPUR
HEADMASTER, BAGHUASOLE
JUNSOLE NEHRU VIDYAPITH
105/PM(F)/P
/1B-
145/2013
28-02-2014 15.88238 15.88238
86 WORK OF ADDITIONAL
CONSTRUCTION OF
VERANDAH, SANITATION
SYSTEM, ELECTRIFICATION
ETC. IN RESPECT OF
CLASSROOM IN MIDNAPORE
TOWN HANDICAPPED SOCIETY
AT OLD JAIL BUILDING,
COLLEGE GROUND ROAD,
MIDNAPORE TOWN WITHIN
SOCIETY TRAINING CENTRE
(VIKASH) COMPOUND,
PASCHIM MEDINIPUR
SECRETARY, MEDINIPUR
TOWN HANDICAPPED
WELFARE SOCIETY
12/PM(F)/P/
1B-232/2013
07-01-2014 9.43872 4.71936
` IN LAC
NO. DATE
SANCTIONED
AMOUNT
RELEASED
AMOUNT
FROM PUP
BILL PAID
FROM PUP
DISTRICT: PASCHIM MEDINIPUR
DETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2013-14
SL.
NO.
NAME OF THE SCHEME EXECUTING AGENCY WITH
CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
EXPECTED
DATE OF
COMPLETION
UC RECEIVED REMARKS PHYSICAL
PROGRESS
87 INCOME GENERATIVE
COMMERCIAL HORTICULTURE
IN SMALL PLOT (5 KATTA) FOR
CULTIVATION OF EARLY
SUMMER VEGETABLE
SURROUNDED BY QUICK
GROWING LIME; 11 BLOCKS
OF JUNGLE MAHAL (250
BENEFICIARIES IN EACH
BLOCK, COST OF GROWING
VEGETABLE CROPS PER
BENEFICIARY FOR 5 KATTA IS
RS. 4,321/-), PASCHIM
MEDINIPUR
MANAGING DIRECTOR, WEST
BENGAL STATE FOOD
PROCESSING &
HORTICULTURE
DEVELOPMENT CORPORATION
LIMITED
15/PM(F)/P/
1B-117/2013
07-01-2014 118.82750 118.82750 100% 118.82750 COMPLETE
4514.93582 1381.90259 586.21639 1328.61839 TOTAL:
` IN LAC
NO. DATE
1 CONSTRUCTION OF ROAD
FROM BEGUNKODAR TO
SAHARJURI (AJODHYA) VIA
BAMNI IN 4 (A,B,C,D) PARTS
FROM 0.00 KM TO 14.5 KM
UNDER "ZILLA PARISHAD-
PUAD MEGA SCHEME"
PROGRAMME
ADDITIONAL EXECUTIVE
OFFICER, PURULIA ZILLA
PARISHAD
38/PM(F)/P/
1B-157/2013
16-01-2014 500.00000 500.00000 30% 25-11-2014 99.07000 WORK IN PROGRESS
2 SINKING OF 15 DEEP TUBE-
WELLS WITH ELECTRIFICATION
(`3.31740 LAC EACH) IN
DIFFERENT SCHOOL ATTACHED
HOSTEL PREMISES, PURULIA-II,
PURULIA
BLOCK DEVELOPMENT
OFFICER, PURULIA-II BLOCK
110/PM(F)/P
/1B-
203/2012
08-05-2013 49.76100 36.32053 60% 36.32053 9 COMPLETE
3 IMPROVEMENT OF ROAD
FROM SIRKABAD HOSPITAL
MORE TO AJODHYA HILL TOP
(14.00 KM), BAGHMUNDI,
PURULIA
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
127/PM(F)/P
/1B-60/2013
& 19 & 108
23-05-2013 &
07-01-2014 &
06-05-2014
359.42844 CONTRACTOR NOT
YET MOBILIZED HIS
MANPOWER, A
NOTICE
FORWARDED TO
HIM
4 CONSTRUCTION OF SURFACE
FLOW MINOR IRRIGATION
SCHEME AT KULAI, SANTURI,
PURULIA
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
129/PM(F)/P
/1B-
240/2012
23-05-2013 35.18224 BDO FORWARDED A
MASS PETETION FOR
CHANGE OF
LOCATION
5 CONSTRUCTION OF SURFACE
FLOW MINOR IRRIGATION
SCHEME AT BARI, MANBAZAR-
II, PURULIA
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
129/PM(F)/P
/1B-
240/2012
23-05-2013 27.17421 95% WORK IN PROGRESS
SANCTIONED
AMOUNT
RELEASED
AMOUNT
FROM PUP
BILL PAID
FROM PUP
DISTRICT: PURULIA
DETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2013-14
SL.
NO.
NAME OF THE SCHEME EXECUTING AGENCY WITH
CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
EXPECTED
DATE OF
COMPLETION
UC RECEIVED REMARKS PHYSICAL
PROGRESS
` IN LAC
NO. DATE
SANCTIONED
AMOUNT
RELEASED
AMOUNT
FROM PUP
BILL PAID
FROM PUP
DISTRICT: PURULIA
DETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2013-14
SL.
NO.
NAME OF THE SCHEME EXECUTING AGENCY WITH
CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
EXPECTED
DATE OF
COMPLETION
UC RECEIVED REMARKS PHYSICAL
PROGRESS
6 CONSTRUCTION OF SURFACE
FLOW MINOR IRRIGATION
SCHEME AT K.P. RANGADI,
HURA, PURULIA
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
129/PM(F)/P
/1B-
240/2012
23-05-2013 37.26413 95% WORK IN PROGRESS
7 CONSTRUCTION OF SURFACE
FLOW MINOR IRRIGATION
SCHEME AT MAHARA,
MANBAZAR-I, PURULIA
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
129/PM(F)/P
/1B-
240/2012
23-05-2013 25.78526 12.69541 100% 12.69541 COMPLETE
8 CONSTRUCTION OF SURFACE
FLOW MINOR IRRIGATION
SCHEME AT TENTULIA,
RAGHUNATHPUR-II, PURULIA
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
129/PM(F)/P
/1B-
240/2012
23-05-2013 31.63863 95% WORK IN PROGRESS
9 CONSTRUCTION OF SURFACE
FLOW MINOR IRRIGATION
SCHEME AT AGAYA, PUNCHA,
PURULIA
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
129/PM(F)/P
/1B-
240/2012
23-05-2013 34.67832 95% WORK IN PROGRESS
10 CONSTRUCTION OF SURFACE
FLOW MINOR IRRIGATION
SCHEME AT TENTULHITY,
PARA, PURULIA
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
129/PM(F)/P
/1B-
240/2012
23-05-2013 32.48988 8.29994 95% 8.29994 WORK IN PROGRESS
11 CONSTRUCTION OF SURFACE
FLOW MINOR IRRIGATION
SCHEME AT GURDA,
BARABAZAR, PURULIA
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
129/PM(F)/P
/1B-
240/2012
23-05-2013 28.25933 95% WORK IN PROGRESS
` IN LAC
NO. DATE
SANCTIONED
AMOUNT
RELEASED
AMOUNT
FROM PUP
BILL PAID
FROM PUP
DISTRICT: PURULIA
DETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2013-14
SL.
NO.
NAME OF THE SCHEME EXECUTING AGENCY WITH
CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
EXPECTED
DATE OF
COMPLETION
UC RECEIVED REMARKS PHYSICAL
PROGRESS
12 CONSTRUCTION OF SURFACE
FLOW MINOR IRRIGATION
SCHEME AT URUSHARAM,
JHALDA-II, PURULIA
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
129/PM(F)/P
/1B-
240/2012
23-05-2013 29.34824 27.15007 100% 27.15007 COMPLETE
13 CONSTRUCTION OF SURFACE
FLOW MINOR IRRIGATION
SCHEME AT PRATAPPUR,
JOYPUR, PURULIA
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
129/PM(F)/P
/1B-
240/2012
23-05-2013 29.73171 10.10608 95% 10.10608 WORK IN PROGRESS
14 CONSTRUCTION OF
ADDITIONAL CLASSROOM OF
ARSHA COLLEGE, ARSHA,
PURULIA
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
166/PM(F)/P
/1B-
103/2013 &
107
24-09-2013 &
06-05-2014
59.12228 18.41429 55% 02-08-2014 18.41429 WORK IN PROGRESS
15 WORK OF CEMENT CONCRETE
ROAD FROM TULSI MAHATO'S
HOUSE TO CHIKRA SHIB
MANDIR, PURULIA-I, PURULIA
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
173/PM(F)/P
/1B-22/2013
09-10-2013 29.46500 80% 15-07-2014 AFTER COMPLETING
750M OUT OF 900M,
WORK STOPPED DUE
TO PUBLIC
INTERFERENCE
16 CONSTRUCTION OF 102
ANGANWADI CENTRES EACH
@ `6.89600 LAC IN DIFFERENT
BLOCKS, PURULIA
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
178/PM(F)/P
/1B-
116/2013
10-10-2013 703.39200 25.21308 10% 25.21308 WORK IN PROGRESS
17 RE-EXCAVATION OF CHAKBAD
BORO BANDH,
RAGHUNATHPUR-II, PURULIA
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
179/PM(F)/P
/1B-
115/2013
21-10-2013 22.59676 20.33877 100% 20.33877 COMPLETE
` IN LAC
NO. DATE
SANCTIONED
AMOUNT
RELEASED
AMOUNT
FROM PUP
BILL PAID
FROM PUP
DISTRICT: PURULIA
DETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2013-14
SL.
NO.
NAME OF THE SCHEME EXECUTING AGENCY WITH
CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
EXPECTED
DATE OF
COMPLETION
UC RECEIVED REMARKS PHYSICAL
PROGRESS
18 CONSTRUCTION OF GROUND
FLOOR OF SCHOOL BUILDING
AT JARGO HIGH SCHOOL,
JHALDA-I, PURULIA
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
217/PM(F)/P
/1B-39/2013
27-12-2013 24.98244 65% 07-08-2014 WORK IN PROGRESS
19 CONSTRUCTION OF
ADDITIONAL CLASSROOMS IN
NEWLY UPGRADED GHONGA
HIGH SCHOOL, PURULIA-II,
PURULIA
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
07/PM(F)/P/
1B-141/2013
03-01-2014 12.33650 85% 25-07-2014 WORK IN PROGRESS
20 CONSTRUCTION OF SCHOOL
BUILDING AT PAIRACHALI
ADIBASI JR. GIRLS HIGH
SCHOOL, MANBAZAR-I,
PURULIA
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
08/PM(F)/P/
1B-138/2013
03-01-2014 39.30432 13.40668 50% 31-08-2014 13.40668 WORK IN PROGRESS
21 CONSTRUCTION OF CONCRETE
ROAD AND GUARD WALL
FROM MAHALI PARA TO
VAGLA GARAH (HERODIH),
ARSHA, PURULIA
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
37/PM(F)/P/
1B-135/2013
16-01-2014 49.47410 75% 15-07-2014 WORK IN PROGRESS
22 CONSTRUCTION OF 81
ANGANWADI CENTRES EACH
@ `6.89600 LAC IN DIFFERENT
BLOCKS, PURULIA
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
42/PM(F)/P/
1B-116/2013
& 109
17-01-2014 &
06-05-2014
558.57600 5.34812 5% 5.34812 WORK IN PROGRESS
23 CONSTRUCTION OF ROAD
FROM GOPALPUR BUS STAND
TO BAGDA BUS STAND
(ADDITIONAL WORK),
PUNCHA, PURULIA
CHIEF EXECUTIVE OFFICER,
PASCHIMANCHAL UNNAYAN
PARSHAD
56/PM(F)/P/
1B-198/2012
28-01-2014 51.86754 100% COMPLETE
` IN LAC
NO. DATE
SANCTIONED
AMOUNT
RELEASED
AMOUNT
FROM PUP
BILL PAID
FROM PUP
DISTRICT: PURULIA
DETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2013-14
SL.
NO.
NAME OF THE SCHEME EXECUTING AGENCY WITH
CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
EXPECTED
DATE OF
COMPLETION
UC RECEIVED REMARKS PHYSICAL
PROGRESS
24 IMPLEMENTATION OF
DIFFERENT PROJECT @ `50
LAC EACH BLOCK IN 20
BLOCKS, PURULIA
DISTRICT MAGISTRATE,
PURULIA
151/PM(F)/P
/1B-82/2013
30-08-2013 1,000.00000 498.68918 50% 393.72000 SCHEMES ARE IN
PROGRESS
25 CONSTRUCTION OF
BOUNDARY WALL OF PURULIA
PALLY SEVA SANGHA
FOOTBALL GROUND, KENDA,
PUNCHA, PURULIA
EXECUTIVE OFFICER, PUNCHA
PANCHAYAT SAMITY
01/PM(F)/P/
1B-140/2013
02-01-2014 22.91735 22.91735 100% 22.91735 COMPLETE
26 CONSTRUCTION OF
ADDITIONAL CLASSROOM OF
ADABONA NAGENDRA NATH
HIGH SCHOOL (H.S.),
BARABAZAR, PURULIA
EXECUTIVE OFFICER,
BARABAZAR PANCHAYAT
SAMITY
06/PM(F)/P/
1B-136/2013
03-01-2014 16.27236 16.27236
27 CONSTRUCTION OF
BOUNDARY WALL AT
BARABAZAR BIKRAM TUDU
MEMORIAL COLLEGE, P.O.-
BARABHUM, BARABAZAR,
PURULIA
EXECUTIVE OFFICER,
BARABAZAR PANCHAYAT
SAMITY
76/PM(F)/P/
1B-143/13
14-02-2014 17.53881 17.53881 100% 17.00189 COMPLETE
28 INSTALLATION OF MINI DEEP
TUBE WELL WITH
SUBMERSIBLE PUMP AT
SARBORI BARUIPARA, SARBORI
KIRTANPARA, SARBORI MORE
NEAR BUS STAND, NIMDANGA
PRIMARY SCHOOL & RANIPUR
COLIERY HIGH SCHOOL,
SARBORI GP, NETURIA,
PURULIA
EXECUTIVE OFFICER, NETURIA
PANCHAYAT SAMITY
16/PM(F)/P/
1B-131/2013
07-01-2014 20.59305 20.59305
` IN LAC
NO. DATE
SANCTIONED
AMOUNT
RELEASED
AMOUNT
FROM PUP
BILL PAID
FROM PUP
DISTRICT: PURULIA
DETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2013-14
SL.
NO.
NAME OF THE SCHEME EXECUTING AGENCY WITH
CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
EXPECTED
DATE OF
COMPLETION
UC RECEIVED REMARKS PHYSICAL
PROGRESS
29 CONSTRUCTION OF BRIDGE
FROM SATRA TO BALIGARA,
PURULIA-I, PURULIA
EXECUTIVE OFFICER, PURULIA-
I PANCHAYAT SAMITY
84/PM(F)/P/
1B-15/2014
17-02-2014 44.76922 44.76922
30 CONSTRUCTION OF
BOUNDARY WALL, MS GRILL
GATE, MAIN ENTRANCE GATE
& COW CATCHER AT BARASINI
N.L. HIGH SCHOOL (H.S.),
PURULIA-II, PURULIA
EXECUTIVE OFFICER, PURULIA-
II PANCHAYAT SAMITY
17/PM(F)/P/
1B-156/2013
07-01-2014 12.47592 12.47592
31 CONSTRUCTION OF
BOUNDARY WALL AND MAIN
ENTRANCE GATE OF ANAI
JAMBAD P.S.D.J. HIGH
SCHOOL, PURULIA-II, PURULIA
EXECUTIVE OFFICER, PURULIA-
II PANCHAYAT SAMITY
73/PM(F)/P/
1B-142/2013
11-02-2014 7.01459 7.01459
32 EXTENSION OF HOSPITAL
BUILDING AND
CONSTRUCTION OF STAFF
QUARTERS FOR REFERRAL EYE
HOSPITAL OF NANRITAM,
PARA, PURULIA
SECRETARY, NANRITAM, FLAT
NO. 6, 28/1/2, SELIMPUR
ROAD, KOLKATA - 700031
140/PM(F)/P
/1B-09/2012
26-07-2013 56.56642 56.56642 100% 28-02-2014 56.56642 COMPLETE
33 CONSTRUCTION OF TRIBAL
HOSTEL AT YUGACHARYA
VIVEKANANDA SEVA SAMITY,
RADHAMOHANPUR, P.S.-
BORO, PURULIA
SECRETARY, YUGACHARYA
VIVEKANANDA SEVA SAMITY
90/PM(F)/P/
1B-19/2014
20-02-2014 47.97740 47.97740
` IN LAC
NO. DATE
SANCTIONED
AMOUNT
RELEASED
AMOUNT
FROM PUP
BILL PAID
FROM PUP
DISTRICT: PURULIA
DETAILS OF SCHEMES SANCTIONED BY DEPTT. OF PUA IN THE FINANCIAL YEAR 2013-14
SL.
NO.
NAME OF THE SCHEME EXECUTING AGENCY WITH
CONTACT DETAILS
PUA DEPT.'S SANCTION
ORDER
EXPECTED
DATE OF
COMPLETION
UC RECEIVED REMARKS PHYSICAL
PROGRESS
34 CULTIVATION OF 5000
KILOGRAM 'BROOD LAC' IN
1000 KUSUM TREES FOR
EMPLOYMENT OF 1000
FAMILIES IN 14 MOUZAS,
PURULIA
MANAGING DIRECTOR, WEST
BENGAL FOREST
DEVELOPMENT CORPORATION
LIMITED, 6A, RAJA SUBODH
MULLICK SQUARE (7TH
FLOOR), KOLKATA - 700013
72/PM(F)/P/
1B-12/2014
11-02-2014 40.00000 40.00000
35 INCOME GENERATIVE
COMMERCIAL HORTICULTURE
IN SMALL PLOT (5 KATTA) FOR
CULTIVATION OF EARLY
SUMMER VEGETABLE
SURROUNDED BY QUICK
GROWING LIME; 8 BLOCKS OF
JUNGLE MAHAL (250
BENEFICIARIES IN EACH
BLOCK, COST OF GROWING
VEGETABLE CROPS PER
BENEFICIARY FOR 5 KATTA IS
RS. 4,321/-), PURULIA
MANAGING DIRECTOR, WEST
BENGAL STATE FOOD
PROCESSING &
HORTICULTURE
DEVELOPMENT CORPORATION
LIMITED
14/PM(F)/P/
1B-117/2013
07-01-2014 86.42000 86.42000 100% 86.42000 COMPLETE
36 RE-EXCAVATION OF CHECK
DAM AT SUTAN TANDI,
AJODHYA HILL, BAGHMUNDI,
PURULIA
MANAGING DIRECTOR, WEST
BENGAL FOREST
DEVELOPMENT CORPORATION
LIMITED, 6A, RAJA SUBODH
MULLICK SQUARE (7TH
FLOOR), KOLKATA - 700013
115/PM(F)/P
/1B-30/2014
28-02-2014 68.35100 34.17550
37 PROPOSED BUILDING AND
OPEN STAGE FOR LAW-BIR-
BAISI AT SUTANTANDI,
AJODHYA HILL, BAGHMUNDI,
PURULIA
MANAGING DIRECTOR, WEST
BENGAL FOREST
DEVELOPMENT CORPORATION
LIMITED, 6A, RAJA SUBODH
MULLICK SQUARE (7TH
FLOOR), KOLKATA - 700013
117/PM(F)/P
/1B-31/2014
03-03-2014 24.01281 24.01281
4236.76726 1429.42261 177.29297 852.98863 TOTAL:
` IN LAC
DISTRICT SANCTIONED
AMOUNT
RELEASED AMOUNT/ BILL
PAID
AMOUNT UTILISED % OF UTILISATION W.R.T.
RELEASED AMOUNT
BANKURA 3432.54170 2427.59960 850.84651 35.05
BIRBHUM 1831.44319 1496.65055 406.83074 27.18
BURDWAN 2197.90867 1474.48314 973.47153 66.02
PASCHIM MEDINIPUR 4514.93582 1968.11898 1328.61839 67.51
PURULIA 4236.76726 1606.71558 852.98863 53.09
GRAND TOTAL 16213.59664 8973.56785 4412.75580 49.18
PASCHIMANCHAL UNNAYAN PARSHAD
FINANCIAL YEAR 2013-14
REPORT AT A GLANCE

Você também pode gostar