PREDIMENSIONAMIENTO PABELLON B

1.0 PREDIMENSIONAMIENTO DE LOSAS:

2.0 PREDIMENSIONAMIENTO DE VIGAS:


VIGA PRINCIPAL:
0,70

0,35

VIGA SECUNDARIA:

0,55

3.0 PREDIMENSIONAMIENTO DE COLUMNAS:


COLUMNA C-2
[

] ( )

0,25

] ( )

)
6,10

CHEQUEO COLUMNA C-2


CARGA MUERTA CM

Longitud Viga = 5.125 + (6.10 0.35) = 10.875 m.

5,125
2,563

Losa de 0.25 m. = 350 kg/m2 = 0.35 Ton/m2.


Losa = (5.125 - 0.35) * (6.10 - 0.35) * (0.35 Ton/m2) = 9.60 Ton
Piso Terminado = (5.125 m * 6.10 m) * 0.10 Ton/m2 = 3.12 Ton
Muros = (4.59 m * 1.65 m * 0.14 m) * 1.9 Ton/m3 = 2.01 Ton

2,563

Total Carga Muerta: CM = 6.40 + 9.60 + 3.12 + 2.01 = 21 .13 Ton


CARGA VIVA
S/C Aulas = 250 kg/m2 = 0.25 Ton/m2
S/C Corredores = 400 kg/m2 = 0.40 Ton/m2
S/C Azotea = 100 kg/m2 = 0.10 Ton/m2

3,91

2,19

5,125

1N = (3.91 m * 5.125 m) * (0.25 Ton/m) + (2.19 m * 5.125 m) * (0.40 Ton/m) = 9.51 Ton
2N = (3.91 m * 5.125 m) * (0.25 Ton/m) + (2.19 m * 5.125 m) * (0.40 Ton/m) = 9.51 Ton
3N = (3.91 m * 5.125 m) * (0.25 Ton/m) + (2.19 m * 5.125 m) * (0.40 Ton/m) = 9.51 Ton
4N = (5.125 m * 6.10 m) * (0.10 Ton/m)

= 3.13 Ton
Total Carga Muerta

Peso de Columna
1N = (0.53 m * 0.53 m * 2.60 m) * (2.4 Ton/m) = 1.76 Ton
2N = (0.53 m * 0.53 m * 2.50 m) * (2.4 Ton/m) = 1.69 Ton
3N = (0.53 m * 0.53 m * 2.50 m) * (2.4 Ton/m) = 1.69 Ton
4N = (0.53 m * 0.53 m * 2.50 m) * (2.4 Ton/m) = 1.69 Ton
Peso Columna

= 6.83 Ton

= 31.63 Ton

PG = CM + CV
PG = (4 * 21.23 Ton) + 6.83 Ton + 31.63 Ton
CM

CV

PG = 133.38 Ton
P = 1.25 * (133.38 Ton) = 166.725 Ton
0,56

BA = 0.56 m

0,56

COLUMNA C-4

] ( )

] ( )
4,23

5,125

0,38

AB = 0.38 cm

0,38

CHEQUEO COLUMNA C-4


CARGA MUERTA CM

Longitud Viga = 4.23 + (5.125 0.35) = 9.005 m.

Losa = (5.125 - 0.35) * (4.23 - 0.35) * (0.35 Ton/m2) = 6.48 Ton

Piso Terminado = (5.125 m * 4.23 m) * 0.10 Ton/m2 = 2.17 Ton


Muros = (2.48 m * 1.65 m * 0.14 m) * 1.9 Ton/m3 =1.09 Ton
Muros = (1.53 m * 2.50 m * 0.24 m) * 1.9 Ton/m3 =1.70 Ton
Total Carga Muerta: CM = 13.68 Ton

2.04

2,19

1,24

0,60 0,19 0,60

1,24

2,56

1N = (2.04 m * 5.125 m) * (0.25 Ton/m) + (2.19 m * 5.125 m) * (0.40 Ton/m) = 7.10 Ton
2N = (2.04 m * 5.125 m) * (0.25 Ton/m) + (2.19 m * 5.125 m) * (0.40 Ton/m) = 7.10 Ton
3N = (2.04 m * 5.125 m) * (0.25 Ton/m) + (2.19 m * 5.125 m) * (0.40 Ton/m) = 7.10 Ton
4N = (5.125 m * 2.04 m) * (0.25 Ton/m)

= 2.62 Ton
Total Carga Muerta

Peso de Columna
1N = (0.38 m * 0.38 m * 2.60 m) * (2.4 Ton/m) = 0.90 Ton
2N = (0.38 m * 0.38 m * 2.50 m) * (2.4 Ton/m) = 0.87 Ton
3N = (0.38 m * 0.38 m * 2.50 m) * (2.4 Ton/m) = 0.87 Ton
4N = (0.38 m * 0.38 m * 2.50 m) * (2.4 Ton/m) = 0.87 Ton
Peso Columna

PG = CM + CV

= 3.51 Ton

= 23.92 Ton

PG = (4 * 13.68 Ton) + 3.51 Ton + 23.92 Ton


CM

CV

PG = 82.14 Ton
P = 1.10 * (82.14 Ton) = 90.354 Ton

0,41

0,41

BA = 0.41 m

COLUMNA C-4

] ( )

] ( )
2,13

2,67

0,28

AB = 0.28 cm

0,28

CHEQUEO COLUMNA C-4


CARGA MUERTA CM

Longitud Viga = 2.13 + (2.67 0.35) = 4.45 m.

Losa = (2.67 - 0.35) * (2.13 - 0.35) * (0.35 Ton/m2) = 1.45 Ton

Piso Terminado = (2.67 m * 2.13 m) * 0.10 Ton/m2 = 0.57 Ton


Muros = (2.39 m * 1.65 m * 0.14 m) * 1.9 Ton/m3 =1.04 Ton
Muros = (1.85 m * 2.50 m * 0.24 m) * 1.9 Ton/m3 =2.11 Ton
Total Carga Muerta: CM = 7.79 Ton

2,13

2,67

1N = (2.67 m * 2.13 m) * (0.25 Ton/m) = 1.43 Ton


2N = (2.67 m * 2.13 m) * (0.25 Ton/m) = 1.43 Ton
3N = (2.67 m * 2.13 m) * (0.25 Ton/m) = 1.43 Ton
4N = (2.67 m * 2.13 m) * (0.10 Ton/m) = 0.57 Ton
Total Carga Muerta

= 4.86 Ton

Peso de Columna
1N = (0.28 m * 0.28 m * 2.60 m) * (2.4 Ton/m) = 0.49 Ton
2N = (0.28 m * 0.28 m * 2.50 m) * (2.4 Ton/m) = 0.47 Ton
3N = (0.28 m * 0.28 m * 2.50 m) * (2.4 Ton/m) = 0.47 Ton
4N = (0.28 m * 0.28 m * 2.50 m) * (2.4 Ton/m) = 0.47 Ton
Peso Columna

PG = CM + CV

= 1.90 Ton

PG = (4 * 7.79 Ton) + 1.90 Ton + 4.86 Ton


CM

CV

PG = 37.92 Ton
P = 1.50 * (37.92 Ton) = 56.88 Ton

0,37

BA = 0.37 m

0,37

METRADO DE CARGAS EJE 4


Peso Viga = (0.35 m * 0.70 m) * (2.4 Ton/m3) = 2.03 Ton/m
Peso Losa = (5.125 m) * (0.35 Ton/m3) = 1.79 Ton/m
Piso Terminado = (5.125 m) * (0.10 Ton/m3) = 0.51 Ton/m
Sobre Carga
Aulas = 5.125 m * 0.25 Ton/m

= 1.28 Ton/m

Tabiqueria Movil = 5.125 m * 0.10 Ton/m

= 0.51 Ton/m

Total

= 1.79 Ton/m

Pasillo = 5.125 m * 0.40 Ton/m

= 2.05 Ton/m

S/C = 0.51 Ton/m


S/C = 0.51 Ton/m
Losa = 1.79 Ton/m
Viga = 2.03 Ton/m

S/C =
S/C =
Losa =
Viga =

2.05 Ton/m
0.51 Ton/m
1.79 Ton/m
2.03 Ton/m

S/C = 1.79 Ton/m


S/C = 0.51 Ton/m
Losa = 1.79 Ton/m
Viga = 2.03 Ton/m

S/C =
S/C =
Losa =
Viga =

2.05 Ton/m
0.51 Ton/m
1.79 Ton/m
2.03 Ton/m

S/C = 1.79 Ton/m


S/C = 0.51 Ton/m
Losa = 1.79 Ton/m
Viga = 2.03 Ton/m

S/C =
S/C =
Losa =
Viga =

2.05 Ton/m
0.51 Ton/m
1.79 Ton/m
2.03 Ton/m

S/C = 1.79 Ton/m


S/C = 0.51 Ton/m
Losa = 1.79 Ton/m
Viga = 2.03 Ton/m

CORTANTE BASAL

1,825 1,825

1,375
3,20
1,825

1,375
3,20
1,825

1,355
3,25
1,825

PRIMER NIVEL
Losa = (30.75 m * 10.00 m) * 0.35 Ton/m

= 107.63 Ton

V Secundaria = 2(30.75 m * 0.70 m * 0.35 m) * 2.4 Ton/m2 = 15.00 Ton


V Principal = 7 * (10.00 m * 0.70 m * 0.35 m) * 2.4 Ton/m2 = 17.15 Ton
Piso terminado = (30.75 m * 10.00 m) * 0.10 Ton/m2
Total

= 30.75 Ton
= 170.53 Ton

Sobre Carga
Aulas = (30.75 m * 10.00 m) * 0.25 Ton/m

= 76.87 Ton

Tab. Mvil = (30.75 m * 10.00 m) * 0.10 Ton/m

= 30.75 Ton

Total

= 107.621 Ton

Muros Parte Frontal


M = (19.30 m * 0.15 m * 1.65 m) * 1.90 Ton/m

= 9.07 Ton

Muros Parte Posterior


M = (26.50 m * 0.15 m * 2.05 m) * 1.90 Ton/m

= 15.48 Ton

Muros Portante
M = 4 * (3.25 m * 0.24 m * 6.50 m) * 1.90 Ton/m
Total

= 38.56 Ton
= 63.09 Ton

Columnas Primer Nivel


C = 4 * (3.25 m * (0.28 m)2 * 2.4 Ton/m

= 8.74 Ton

C = 6 * (3.25 m * (0.54 m)2 * 2.40 Ton/m

= 25.27 Ton

C = 8 * (3.25 m * (0.38 m)2 * 2.40 Ton/m

= 23.71 Ton

= 57.72 Ton

Total

Peso Primer Nivel CM

= 291.34 Ton

SEGUNDO Y TERCER NIVEL


Losa = (30.75 m * 10.00 m) * 0.35 Ton/m

= 107.63 Ton

V Secundaria = 2(30.75 m * 0.70 m * 0.35 m) * 2.4 Ton/m2 = 15.00 Ton


V Principal = 7 * (10.00 m * 0.70 m * 0.35 m) * 2.4 Ton/m2 = 17.15 Ton
Piso terminado = (30.75 m * 10.00 m) * 0.10 Ton/m2
Total
Sobre Carga

= 30.75 Ton
= 170.53 Ton

Aulas = (30.75 m * 10.00 m) * 0.25 Ton/m

= 76.87 Ton

Tab. Mvil = (30.75 m * 10.00 m) * 0.10 Ton/m

= 30.75 Ton

Total

= 107.621 Ton

Muros Parte Frontal


M = (19.30 m * 0.15 m * 1.65 m) * 1.90 Ton/m

= 9.07 Ton

Muros Parte Posterior


M = (26.50 m * 0.15 m * 2.05 m) * 1.90 Ton/m

= 15.48 Ton

Muros Portante
M = 4 * (3.20 m * 0.24 m * 6.50 m) * 1.90 Ton/m
Total

= 37.94 Ton
= 62.49 Ton

Columnas Segundo y Tercer Nivel


C = 4 * (3.20 m * (0.28 m)2 * 2.4 Ton/m

= 8.60 Ton

C = 6 * (3.20 m * (0.54 m)2 * 2.40 Ton/m

= 24.88 Ton

C = 8 * (3.20 m * (0.38 m)2 * 2.40 Ton/m

= 23.34 Ton

= 56.82 Ton

Total

Peso Segundo Nivel CM

= 289.89 Ton

Peso Tercer Nivel CM

= 289.89 Ton

CUARTO NIVEL
Losa = (30.75 m * 10.00 m) * 0.35 Ton/m

= 107.63 Ton

V Secundaria = 2(30.75 m * 0.70 m * 0.35 m) * 2.4 Ton/m2 = 15.00 Ton


V Principal = 7 * (10.00 m * 0.70 m * 0.35 m) * 2.4 Ton/m2 = 17.15 Ton
Piso terminado = (30.75 m * 10.00 m) * 0.10 Ton/m2
Total

= 30.75 Ton
= 170.53 Ton

Sobre Carga
Azotea = (30.75 m * 10.00 m) * 0.10 Ton/m
Total

= 30.75 Ton
= 30.75 Ton

Muros Portante
M = 4 * (1.83 m * 0.24 m * 6.50 m) * 1.90 Ton/m
Total

= 21.70 Ton
= 21.70 Ton

Columnas Cuarto Nivel


C = 4 * (1.83 m * (0.28 m)2 * 2.4 Ton/m

= 4.92 Ton

C = 6 * (1.83 m * (0.54 m)2 * 2.40 Ton/m

= 14.23 Ton

C = 8 * (1.83 m * (0.38 m)2 * 2.40 Ton/m

= 13.35 Ton

= 32.50 Ton

Total

Peso Cuarto Nivel CM


1er. Nivel
2do. Nivel
3er. Nivel
4to. Nivel

= 224.73 Ton
CM
291.34 Ton
289.84 Ton
289.84 Ton
224.73 Ton

CV
107.62 Ton
107.62 Ton
107.62 Ton
30.75 Ton

%
50
50
50
25

Peso
345.15
343.62
343.65
232.42
1264.87

C
Z = 0.4 (costa)

C = 2.5 (tp/t)

U = 1.5 (categora A)

C = 2.5 (0.4/0.37)

t = hn / ct

S = 1 (roca o suelo muy rigido

t = 12.78/35

R = 8 (muros aporticados)

C = 2.5

t = 0.37

niveles

p*h

4
3
2
1

232.42
343.65
343.65
345.15

12.78
9.58
6.38
3.18
Suma p*h

2970.30
3292.17
2192.46
1097.58
9552.53

p * h/
p*h
0.31
0.34
0.23
0.11
1.00

73.74
155.48
209.91
237.16
237.16

73.34
155.48
209.91
237.16

73.74

81.74

73.74

54.33

155.48

27.25

209.91

237.16

73.74

155.48

209.91

237.16

Você também pode gostar