Você está na página 1de 16

Project : PROPOSED ONE UNIT COMMUNAL FAUCET (STAND POST)

Location :
Scope of Work :
NON-ENGINEERING BASIC ITEMS
SUPERVISION
ENGINEERING BASIC ITEMS
I. LAYOUTING & EXCAVATION WORKS
II. FORMS & SCAFFOLDING WORKS
III. CONCRETING WORKS
IV. REBAR WORKS
V. MASONRY WORKS
VI. PLUMBING WORKS
VII. STEELWORKS
Cost of Project :
Qty. Unit Unit Cost Amount Total Cost
NON-ENGINEERING BASIC ITEMS
SUPERVISION
1 - Engineering Assistant 8 days 524.00 4,192.00 4,192.00
TOTAL DIRECT COST 4,192.00
OVERHEAD EXPENSES 210.00
PHYSICAL CONTINGENCIES 168.00
MISCELLANEOUS EXPENSES 42.00 420.00
TOTAL COST OF SUPERVISION 4,612.00
ENGINEERING BASIC ITEMS
I. LAYOUTING & EXCAVATION WORKS
A. Materials:
4 pcs. - 2" x 4" x 10' Coco Lumber 27 bd.ft. 21.00 567.00
1 pcs. - 2" x 3" x 10' Coco Lumber 5 bd.ft. 21.00 105.00
#100 Nylon Chord 1 roll 110.00 110.00
4" C.W. Nail 1 kg. 51.00 51.00 833.00
B. Labor:
1 - Carpenter 1 day 366.00 366.00
2 - Laborers 1 day 341.00 682.00 1,048.00
TOTAL DIRECT COST 1,881.00
OVERHEAD EXPENSES 94.00
PHYSICAL CONTINGENCIES 75.00
MISCELLANEOUS EXPENSES 19.00 188.00
TOTAL COST OF ITEM I 2,069.00
II. FORMS & SCAFFOLDING WORKS
A. Materials:
3 pcs. - 2" x 2" x 6' Coco Lumber 6 bd.ft. 21.00 126.00
7 pcs. - 2" x 2" x 8' Coco Lumber 19 bd.ft. 21.00 399.00
6 pcs. - 2" x 4" x 6' Coco Lumber 24 bd.ft. 21.00 504.00
12mm thk. X 1.20m x 2.40m Ordinary Plywood 1 sht. 750.00 750.00
2" C.W. Nail 1 kg. 54.00 54.00
4" C.W. Nail 2 kgs. 51.00 102.00 1,935.00
B. Labor:
1 - Carpenter 2 days 366.00 732.00 732.00
TOTAL DIRECT COST 2,667.00
OVERHEAD EXPENSES 133.00
PHYSICAL CONTINGENCIES 107.00
MISCELLANEOUS EXPENSES 27.00 267.00
TOTAL COST OF ITEM II 2,934.00
III. CONCRETING WORKS
A. Materials:
Portland Cement 16 bags 235.00 3,760.00
Washed Sand 1 cu.m. 1,000.00 1,000.00
Gravel (G-3/4) 2 cu.m. 1,000.00 2,000.00 6,760.00
Republic of the Philippines
ZAMBOANGA CITY WATER DISTRICT
Pilar Street, Zamboanga City
40,501.00 Php
BILL OF MATERIALS & COST ESTIMATES
Item Description
Page 1 of 16 Price Database as of September, 2012
B. Labor:
1 - Mason/Steelman 2 days 366.00 732.00
1 - Carpenter 2 days 366.00 732.00
1 - Plumber 2 days 366.00 732.00
2 - Laborers 2 days 341.00 1,364.00 3,560.00
TOTAL DIRECT COST 10,320.00
OVERHEAD EXPENSES 1,032.00
PHYSICAL CONTINGENCIES 413.00
MISCELLANEOUS EXPENSES 103.00 1,548.00
TOTAL COST OF ITEM III 11,868.00
IV. REBAR WORKS
A. Materials:
10mm x 6.00m DRSB 13 pcs. 165.00 2,145.00
Page 2 of 16 Price Database as of September, 2012
Hacksaw Blade 3 pcs. 53.00 159.00
#16 G.I. Tie-wire 4 kgs. 65.00 260.00 2,564.00
B. Labor:
1 - Mason/Steelman 1 day 366.00 366.00 366.00
TOTAL DIRECT COST 2,930.00
OVERHEAD EXPENSES 293.00
PHYSICAL CONTINGENCIES 117.00
MISCELLANEOUS EXPENSES 29.00 439.00
TOTAL COST OF ITEM IV 3,369.00
V. MASONRY WORKS
A. Materials:
100mm Gravel 1 cu.m. 795.00 795.00
Washed Sand 0.20 cu.m. 1,000.00 200.00 995.00
B. Labor:
1 - Mason/Steelman 1 day 366.00 366.00
1 - Laborer 1 day 341.00 341.00 707.00
TOTAL DIRECT COST 1,702.00
OVERHEAD EXPENSES 170.00
PHYSICAL CONTINGENCIES 68.00
MISCELLANEOUS EXPENSES 17.00 255.00
TOTAL COST OF ITEM V 1,957.00
VI. PLUMBING WORKS
A. Materials:
12mm. x 63mm. Brass Tail Piece 2 pcs. 66.00 132.00
12mm. x 90
o
ANSI B16.3 Class 150 Std. G.I. Elbow 5 pcs. 17.00 85.00
12mm. Brass Safety Valve, w/ Lock Head (Key Type) 1 pc. 253.00 253.00
12mm. Brass Ball Valve, w/ Lock Wing 1 pc. 219.00 219.00
19mm. x 12mm. ANSI B16.3 Class 150 Std. G.I. Reducer 1 pc. 11.00 11.00
19mm. Brass Single Adaptor, Pack Joint/Clamp Type 1 pc. 250.00 250.00
12mm. ANSI B16.3 Class 150 Std. G.I. Coupling 3 pcs. 9.00 27.00
12mm. x 12mm. ANSI B16.3 Class 150 Std. G.I. Tee 1 pc. 15.00 15.00
12mm. Brass Faucet Hose Bibb 2 pcs. 138.00 276.00
12mm. x 75mm. ASTM A53-90A G.I. Nipple (Standard BSP Thread, Both Ends) 2 pcs. 33.00 66.00
12mm. x 50mm. ASTM A53-90A G.I. Nipple (Standard BSP Thread, Both Ends) 2 pcs. 22.00 44.00
12mm. x 250mm. ASTM A53-90A G.I. Nipple (Standard BSP Thread, Both Ends) 1 pc. 110.00 110.00
12mm. x 200mm. ASTM A53-90A G.I. Nipple (Standard BSP Thread, Both Ends) 1 pc. 88.00 88.00
12mm. x 1.00m. ASTM A53-90A G.I. Nipple (Standard BSP Thread, Both Ends) 1 pc. 440.00 440.00
12mm. Water Meter 1 pc. 1,720.00 1,720.00
25mm x 10.00m Teflon Tape 4 pcs. 28.00 112.00
100mm x 100mm Stainless Steel C-Cover Floor Drain 1 pc. 189.00 189.00
50mm. x 60.00m P.E. Pipe Tubing, SDR-11 20 mtrs. 126.00 2,520.00 6,557.00
B. Labor:
1 - Plumber 1 day 366.00 366.00 366.00
TOTAL DIRECT COST 6,923.00
OVERHEAD EXPENSES 346.00
PHYSICAL CONTINGENCIES 277.00
MISCELLANEOUS EXPENSES 69.00 692.00
TOTAL COST OF ITEM VI 7,615.00
VII. STEELWORKS
A. Materials:
6mm. thk x 50mm. x 50mm. x 6.00m Angle Bar 1 pc. 1233.00 1,233.00
6mm. thk x 25mm. x 6.00m Flat Bar 1 pc. 748.00 748.00
6011 Welding Rod 10 pcs. 5.00 50.00 2,031.00
B. Labor:
1 - Welder 1 day 366.00 366.00 366.00
C. Equipment Rental
1 - Unit Welding Machine 1 day 3,128.00 3,128.00 3,128.00
TOTAL DIRECT COST 5,525.00
OVERHEAD EXPENSES 276.00
PHYSICAL CONTINGENCIES 221.00
MISCELLANEOUS EXPENSES 55.00 552.00
TOTAL COST OF ITEM VII 6,077.00
Page 3 of 16 Price Database as of September, 2012
NON-ENGINEERING BASIC ITEMS
SUPERVISION
ENGINEERING BASIC ITEMS
I. LAYOUTING & EXCAVATION WORKS
II. FORMS & SCAFFOLDING WORKS
III. CONCRETING WORKS
IV. REBAR WORKS
V. MASONRY WORKS
VI. PLUMBING WORKS
VII. STEELWORKS
PROJECT COST
Prepared by: Checked & Reviewed by: Approved by:
FELIXBERTO R. CAARE, JR. MARIE CLAIRE C. BONGO MARLI ACOSTA-DE FIESTA
Reseacher/Analyst A (J.O.) Principal Engineer C
Planning & Development Section Planning & Development Section
Recommending Project Implementation: Approved for Project Implementation:
ARNULFO A. ALFONSO LEONARDO REY D. VASQUEZ
Department Manager General Manager
Maintenance Department
S U M M A R Y
4,612.00 Php
2,069.00 Php
2,934.00 Php
11,868.00 Php
3,369.00 Php
1,957.00 Php
7,615.00 Php
Officer-In-Charge
Planning & Design Division
40,501.00 Php
6,077.00 Php
Page 4 of 16 Price Database as of September, 2012
PROJECT : PROPOSED ONE UNIT COMMUNAL FAUCET (STAND POST)
Location :
Project Cost :
Project Duration : Eight (8) Calendar Days
Manpower Requirements : 8 Manpower (1-Engineering Assistant, 2-Laborers, 1-Mason/Steelman, 1-Carpenter, & 1-Plumber)
1 2 3 4 5 6 7 8 9 10
NON-ENGINEERING BASIC ITEMS
SUPERVISION 11.51%
ENGINEERING BASIC ITEMS
I. LAYOUTING & EXCAVATION WORKS 5.16%
II. FORMS & SCAFFOLDING WORKS 7.32% # #
III. CONCRETING WORKS 29.61%
IV. REBAR WORKS 8.40% #
V. MASONRY WORKS 4.88% #
VI. PLUMBING WORKS 17.96%
VII. STEELWORKS 15.16%
TOTAL PROJECT COST 100%
CASH OUTLAY REQUIREMENT
TARGETED COMPLETION THIS PERIOD
COMMULATIVE COMPLETION TO DATE
Recommending
Prepared by: Reviewed & Checked by: Approved by: Project Implementation: Approved for Project Implementation:
FELIXBERTO R. CAARE, JR. MARIE CLAIRE C. BONGO MARLI ACOSTA - DE FIESTA ARNULFO A. ALFONSO LEONARDO REY D. VASQUEZ
Researcher/Analyst A (J.O.) Officer-In-Charge Officer-In-Charge Department Manager C General Manager
Planning & Development Section Planning & Development Section Planning & Design Division Maintenance Department
GANTT CHART
40,086.00 Php
Work Item Amounts % Perfected
1,957.00 PhP
7,200.00 PhP
6,077.00 PhP
4,612.00 PhP
2,069.00 PhP
2,934.00 PhP
11,868.00 PhP
3,369.00 PhP
40,086.00 Php
C A L E N D A R D A Y S
40,086.00
100.00%
100.00%
Republic of the Philippines
ZAMBOANGA CITY WATER DISTRICT
Pilar St., Zamboanga City
Approved for Project Implementation:
LEONARDO REY D. VASQUEZ
Republic of the Philippines
ZAMBOANGA CITY WATER DISTRICT
Pilar St., Zamboanga City
a. L: 2.20 m.
W: 1.40 m.
t: 0.10 m.
V: 0.31 cu.m.
b. L: 7.20 m.
W: 0.10 m.
t: 0.10 m.
V: 0.07 cu.m.
Vt: 0.38 cu.m.
STONE MASONRY PAD
a. L: 2.60 m.
W: 1.80 m.
t: 0.20 m.
V: 1.00 cu.m.
FAUCET PEDESTAL
a. L: 0.20 m.
W: 0.20 m.
H: 0.90 m.
V: 0.04 cu.m.
METER CONC. BOX
a. Floor
L: 0.70 m.
W: 0.70 m.
t: 0.10 m.
V: 0.05 cu.m.
b. wall
A: 0.24 sq.m.
h: 0.40 m.
V: 0.10 cu.m.
1.57 cu.m. - Total Volume of Concrete
16 - Portland Cement (bags)
1 - Washed Sand (cu.m.)
SPLASH BASIN
2 - Gravel (cu.m.)
FORMS AND SCAFFOLDINGS
a. 2" x 4" x 6' 6 pcs. 24 bd.ft.
b. 2" x 2" x 8' 7 pcs. 19 bd.ft.
c. 4" C.W.N. 1 kg.
FAUCET PEDESTAL
a. 5mm thk. X 1.20m x 2.40m. Ordinary Plywood 1 pc.
b. 2" x 2" x 6' 3 pcs.
d. 2" C.W.N. 1 kg.
e. 4" C.W.N. 1 kg.
REBAR WORKS
a. SPLASH BASIN
@ 2.20m Length
10 pcs. - 10mm x 2.20m rebars
5 pcs. - 10mm x 6.00m rebars
@ 1.40m Length
15 pcs. - 10mm x 1.40m rebars
4 pcs. - 10mm x 6.00m rebars
tie-wire
2 kgs. - #16 G.I. tie-wire
b. FAUCET PEDESTAL
@ main bars
1 pcs. - 10mm x 6.00m rebars
@ ties
1 pcs. - 10mm x 6.00m rebars
tie-wire
1 kgs. - #16 G.I. tie-wire
c. METER BOX
@ 1.50m
1 pc. - 10mm x 6.00m rebars
1 pc. - 10mm x 6.00m rebars
tie-wire
0.5 kgs. - #16 G.I. tie-wire
MASONRY WORKS
SPLASH BASIN
Concrete Pad
1.00 cu.m. - 75mm Boulders
EXCAVATION
a. Masonry Pad
Vol.: 0.94 cu.m.
b. Meter box
Vol.: 0.15 cu.m.
Volt: 1.1 cu.m.
3210
4.285714286
5.6
4.92
2.6
0.171428571
4.5
4.8
Project : PROPOSED ONE UNIT - 25mm. DIAMETER COMMUNAL FAUCET (STAND POST)
Location :
Scope of Work :
NON-ENGINEERING BASIC ITEMS
SUPERVISION
ENGINEERING BASIC ITEMS
I. LAYOUTING & EXCAVATION WORKS
II. FORMS & SCAFFOLDING WORKS
III. CONCRETING WORKS
IV. REBAR WORKS
V. MASONRY WORKS
VI. PLUMBING WORKS
VII. STEELWORKS
Cost of Project :
Qty. Unit Unit Cost Amount Total Cost
NON-ENGINEERING BASIC ITEMS
SUPERVISION
1 - Engineering Assistant 8 days 524.00 4,192.00 4,192.00
TOTAL DIRECT COST 4,192.00
OVERHEAD EXPENSES 210.00
PHYSICAL CONTINGENCIES 168.00
MISCELLANEOUS EXPENSES 42.00 420.00
TOTAL COST OF SUPERVISION 4,612.00
ENGINEERING BASIC ITEMS
I. LAYOUTING & EXCAVATION WORKS
A. Materials:
4 pcs. - 2" x 4" x 10' Coco Lumber 27 bd.ft. 21.00 567.00
1 pcs. - 2" x 3" x 10' Coco Lumber 5 bd.ft. 21.00 105.00
#100 Nylon Chord 1 roll 110.00 110.00
4" C.W. Nail 1 kg. 51.00 51.00 833.00
B. Labor:
1 - Carpenter 1 day 366.00 366.00
2 - Laborers 1 day 341.00 682.00 1,048.00
TOTAL DIRECT COST 1,881.00
OVERHEAD EXPENSES 94.00
PHYSICAL CONTINGENCIES 75.00
MISCELLANEOUS EXPENSES 19.00 188.00
TOTAL COST OF ITEM I 2,069.00
II. FORMS & SCAFFOLDING WORKS
A. Materials:
3 pcs. - 2" x 2" x 6' Coco Lumber 6 bd.ft. 21.00 126.00
7 pcs. - 2" x 2" x 8' Coco Lumber 19 bd.ft. 21.00 399.00
6 pcs. - 2" x 4" x 6' Coco Lumber 24 bd.ft. 21.00 504.00
12mm thk. X 1.20m x 2.40m Ordinary Plywood 1 sht. 750.00 750.00
2" C.W. Nail 1 kg. 54.00 54.00
4" C.W. Nail 2 kgs. 51.00 102.00 1,935.00
B. Labor:
1 - Carpenter 2 days 366.00 732.00 732.00
TOTAL DIRECT COST 2,667.00
OVERHEAD EXPENSES 133.00
PHYSICAL CONTINGENCIES 107.00
MISCELLANEOUS EXPENSES 27.00 267.00
TOTAL COST OF ITEM II 2,934.00
III. CONCRETING WORKS
A. Materials:
Portland Cement 16 bags 235.00 3,760.00
Washed Sand 1 cu.m. 1,000.00 1,000.00
Gravel (G-3/4) 2 cu.m. 1,000.00 2,000.00 6,760.00
B. Labor:
1 - Mason/Steelman 2 days 366.00 732.00
1 - Carpenter 2 days 366.00 732.00
1 - Plumber 2 days 366.00 732.00
Republic of the Philippines
ZAMBOANGA CITY WATER DISTRICT
Pilar Street, Zamboanga City
43,218.00 Php
BILL OF MATERIALS & COST ESTIMATES
Item Description
2 - Laborers 2 days 341.00 1,364.00 3,560.00
TOTAL DIRECT COST 10,320.00
OVERHEAD EXPENSES 1,032.00
PHYSICAL CONTINGENCIES 413.00
MISCELLANEOUS EXPENSES 103.00 1,548.00
TOTAL COST OF ITEM III 11,868.00
IV. REBAR WORKS
A. Materials:
10mm x 6.00m DRSB 13 pcs. 165.00 2,145.00
Hacksaw Blade 3 pcs. 53.00 159.00
#16 G.I. Tie-wire 4 kgs. 65.00 260.00 2,564.00
B. Labor:
1 - Mason/Steelman 1 day 366.00 366.00 366.00
TOTAL DIRECT COST 2,930.00
OVERHEAD EXPENSES 293.00
PHYSICAL CONTINGENCIES 117.00
MISCELLANEOUS EXPENSES 29.00 439.00
TOTAL COST OF ITEM IV 3,369.00
V. MASONRY WORKS
A. Materials:
100mm Gravel 1 cu.m. 795.00 795.00
Washed Sand 0.20 cu.m. 1,000.00 200.00 995.00
B. Labor:
1 - Mason/Steelman 1 day 366.00 366.00
1 - Laborer 1 day 341.00 341.00 707.00
TOTAL DIRECT COST 1,702.00
OVERHEAD EXPENSES 170.00
PHYSICAL CONTINGENCIES 68.00
MISCELLANEOUS EXPENSES 17.00 255.00
TOTAL COST OF ITEM V 1,957.00
VI. PLUMBING WORKS
A. Materials:
25mm. x 63mm. Brass Tail Piece 2 pcs. 138.00 276.00
25mm. x 90
o
ANSI B16.3 Class 150 Std. G.I. Elbow 5 pcs. 36.00 180.00
25mm. Brass Safety Valve, w/ Lock Head (Key Type) 1 pc. 527.00 527.00
25mm. Brass Ball Valve, w/ Lock Wing 1 pc. 457.00 457.00
25mm. x 19mm. x ANSI B16.3 Class 150 Std. G.I. Reducer 1 pc. 11.00 11.00
19mm. Brass Single Adaptor, Pack Joint/Clamp Type 1 pc. 250.00 250.00
25mm. ANSI B16.3 Class 150 Std. G.I. Coupling 1 pc. 22.00 22.00
25mm. x 19mm. ANSI B16.3 Class 150 Std. G.I. Reducing Coupling 2 pcs. 23.00 46.00
25mm. x 25mm. ANSI B16.3 Class 150 Std. G.I. Tee 1 pc. 34.00 34.00
19mm. Brass Faucet Hose Bibb 2 pcs. 220.00 440.00
25mm. x 50mm. ASTM A53-90A G.I. Nipple (Standard BSP Thread, Both Ends) 2 pcs. 22.00 44.00
25mm. x 250mm. ASTM A53-90A G.I. Nipple (Standard BSP Thread, Both Ends) 2 pcs. 51.00 102.00
25mm. x 1.00m. ASTM A53-90A G.I. Nipple (Standard BSP Thread, Both Ends) 1 pc. 205.00 205.00
25mm. Water Meter 1 pc. 3,583.00 3,583.00
25mm x 10.00m Teflon Tape 5 pcs. 28.00 140.00
100mm x 100mm Stainless Steel C-Cover Floor Drain 1 pc. 189.00 189.00
50mm. x 60.00m P.E. Pipe Tubing, SDR-11 20 mtrs. 126.00 2,520.00 9,026.00
B. Labor:
1 - Plumber 1 day 366.00 366.00 366.00
TOTAL DIRECT COST 9,392.00
OVERHEAD EXPENSES 470.00
PHYSICAL CONTINGENCIES 376.00
MISCELLANEOUS EXPENSES 94.00 940.00
TOTAL COST OF ITEM VI 10,332.00
VII. STEELWORKS
A. Materials:
6mm. thk x 50mm. x 50mm. x 6.00m Angle Bar 1 pc. 1233.00 1,233.00
6mm. thk x 25mm. x 6.00m Flat Bar 1 pc. 748.00 748.00
6011 Welding Rod 10 pcs. 5.00 50.00 2,031.00
B. Labor:
1 - Welder 1 day 366.00 366.00 366.00
C. Equipment Rental
1 - Unit Welding Machine 1 day 3,128.00 3,128.00 3,128.00
TOTAL DIRECT COST 5,525.00
OVERHEAD EXPENSES 276.00
PHYSICAL CONTINGENCIES 221.00
MISCELLANEOUS EXPENSES 55.00 552.00
TOTAL COST OF ITEM VII 6,077.00
NON-ENGINEERING BASIC ITEMS
SUPERVISION
ENGINEERING BASIC ITEMS
I. LAYOUTING & EXCAVATION WORKS
II. FORMS & SCAFFOLDING WORKS
III. CONCRETING WORKS
IV. REBAR WORKS
V. MASONRY WORKS
VI. PLUMBING WORKS
VII. STEELWORKS
PROJECT COST
Prepared by: Checked & Reviewed by: Approved by:
FELIXBERTO R. CAARE, JR. MARIE CLAIRE C. BONGO MARLI ACOSTA-DE FIESTA
Reseacher/Analyst A (J.O.) Principal Engineer C
Planning & Development Section Planning & Development Section
Recommending Project Implementation: Approved for Project Implementation:
ARNULFO A. ALFONSO LEONARDO REY D. VASQUEZ
Department Manager General Manager
Maintenance Department
S U M M A R Y
4,612.00 Php
2,069.00 Php
2,934.00 Php
11,868.00 Php
3,369.00 Php
1,957.00 Php
10,332.00 Php
6,077.00 Php
43,218.00 Php
Officer-In-Charge
Planning & Design Division
PROJECT : PROPOSED ONE UNIT - 25mm. DIAMETER COMMUNAL FAUCET (STAND POST)
Location :
Project Cost :
Project Duration : Eight (8) Calendar Days
Manpower Requirements : 8 Manpower (1-Engineering Assistant, 2-Laborers, 1-Mason/Steelman, 1-Carpenter, & 1-Plumber)
1 2 3 4 5 6 7 8 9 10
NON-ENGINEERING BASIC ITEMS
SUPERVISION 10.67%
ENGINEERING BASIC ITEMS
I. LAYOUTING & EXCAVATION WORKS 4.79%
II. FORMS & SCAFFOLDING WORKS 6.79% # #
III. CONCRETING WORKS 27.46%
IV. REBAR WORKS 7.80% #
V. MASONRY WORKS 4.53% #
VI. PLUMBING WORKS 23.91%
VII. STEELWORKS 14.06%
TOTAL PROJECT COST 100%
CASH OUTLAY REQUIREMENT
TARGETED COMPLETION THIS PERIOD
COMMULATIVE COMPLETION TO DATE
Recommending
Prepared by: Reviewed & Checked by: Approved by: Project Implementation: Approved for Project Implementation:
FELIXBERTO R. CAARE, JR. MARIE CLAIRE C. BONGO MARLI ACOSTA - DE FIESTA ARNULFO A. ALFONSO LEONARDO REY D. VASQUEZ
Researcher/Analyst A (J.O.) Officer-In-Charge Officer-In-Charge Department Manager C General Manager
Planning & Development Section Planning & Development Section Planning & Design Division Maintenance Department
Republic of the Philippines
ZAMBOANGA CITY WATER DISTRICT
Pilar St., Zamboanga City
GANTT CHART
43,218.00 Php
Work Item Amounts % Perfected
C A L E N D A R D A Y S
4,612.00 PhP
2,069.00 PhP
2,934.00 PhP
11,868.00 PhP
3,369.00 PhP
1,957.00 PhP
10,332.00 PhP
6,077.00 PhP
43,218.00 Php
43,218.00
100.00%
100.00%
Approved for Project Implementation:
LEONARDO REY D. VASQUEZ
Republic of the Philippines
ZAMBOANGA CITY WATER DISTRICT
Pilar St., Zamboanga City

Você também pode gostar