Province Issues

Bukidnon
FMR -Absence of DPWH Residence Engineer assigned at the
FMR Sub-project
-Price increase of aggregates in all quarry sites in Bukid-
non by virtue of Provincial Ordinance
CIP -Issue on the IPs rituals that hinders the prompt sub-
project implementation
Lanao del
Norte
FMR -issues on the joint inspection with DPWH, MLGU and DAR
for immediate turn-over of FMR completed 2013
-Issues on sub-project implementation such as MLGU equi-
ty and release of tranches to DPWH
Misamis
Oriental
PWS -delayed submission of documents required by CPMO
CIP -issue on the lowest bidder in the amount of P17.6m with
a disparity of P4.2m with respect to the ABC of P21 m plus
FMR -Issue on the submission of MLGU equity in the form of
SPA
ARISP III Regional Assessment April 11, 2014 PRYCE PLAZA
Agreement Reached
-RPMO to send a letter to DPWH Regional Office requesting to
assign one(1) Residence Engineer to man the FMR sub-project.
-RPMO to write a letter to DPWH Regional Office on the price escala-
lation of the aggregates and request the same to submit technical
documents for this purpose.
-DAR to conduct coordination meeting with Provincial and Regional
NCIP regarding the notice of exemption/DAR to send letter to NCIP
Manila requesting for notice of exemption
-RPMO to write letter to DPWH Regional Office for a scheduled joint
sub-project inspection and date for turn-over
-Call for an inter agency coordination meeting with stakeholders
(DPWH, LGU & NIA) to thresh out problems in the finishing phase of
sub-project implementation
-PPMO to request MLGU Libertad to waive the proposed PWS should
they have no more interest on the same since the ARISP III Project
would end on August 2014
-RPMO to coordinate with NIA Regional Office on the review and
evaluationj of the bid
-RPMO to write all MLGUs on the immediate submission of their FMR
equity