Group Members
Muhammad Zia Ul Shams
Hassan Abbas
Saad Zahid
Ch Hassan Saifullah
Shoaib Nadir
Muhammad Umair
Contents
BACKGROUND: ........................................................................................................................ 3
Brief about the company ........................................................................................................ 3
About the project .................................................................................................................... 3
Objective of the project........................................................................................................... 4
Feasibility Methodology .......................................................................................................... 5
Project Management office (PMO) ......................................................................................... 5
RAWALPINDI-ISLAMABAD METRO BUS SERVICE ROUTE ................................................... 6
WORK BREAKDOWN STRUCTURE ......................................................................................... 7
PHASES OF MBS RAWALPINDI-ISLAMABAD ......................................................................... 8
Phase-to-Phase Relationships ............................................................................................... 9
Enterprise Environmental Factors .......................................................................................... 9
ORGANIZATIONAL STRUCTURE:...........................................................................................10
PROJECT CHARTER ...............................................................................................................11
General Information ..............................................................................................................11
Executive Summary ..............................................................................................................11
Project Purpose.....................................................................................................................11
Assumptions ........................................................................................................................12
Project Authority ....................................................................................................................12
Project Manager ....................................................................................................................12
Project Organization Description ...........................................................................................12
Resources .............................................................................................................................13
SOME IMPORTANT STAKEHOLDERS ....................................................................................14
PROJECT SCOPE ....................................................................................................................15
SECTION 2: Project Scope ...................................................................................................17
Project Scope........................................................................................................................17
Section 3: project mile stones................................................................................................17
CHANGE MANAGEMENT ........................................................................................................18
COMMUNICATION MANAGEMENT .........................................................................................18
PROCUREMENT MANAGEMENT ............................................................................................18
RESOURCE MANAGEMENT ...................................................................................................19
OUTSTANDING ISSUE ........................................................................................................19
APPROVALS AND PAYMENT OPTIONS .............................................................................19
REFRENCES ........................................................................................................................19
PROJECT FEASIBILITY REPORT ...........................................................................................20
Background ...........................................................................................................................20
Market Viability ......................................................................................................................20
BACKGROUND:
Since the twin cities are hub of economic, political, and educational activities, significant commuting
takes place between the twin cities and adjoining areas.
The available public transport is dominated by the private sector, contributing to about 35 per-cent of
the share of overall modes of transportation. This share is now declining due to poor service and
widespread customer dissatisfaction with the available options. The people travelling by public
transport are passing through double agony because despite getting high fares, the transporters do not
finish their routes, thus making the commuters pay extra fare for reaching their destinations by changing
two vehicles from Saddar to Pak Secretariat. Moreover, during peak hours, vehicles are overloaded.
Therefore, the existing public transport system requires a major uplift in level of service and quality. In
order to tackle this problem and provide improved quality of public transport, Government of Punjab,
Rawalpindi Development Authority (RDA) decided to construct the Metro Bus System (MBS) in
Islamabad.
Brief about the company:
Rawalpindi Islamabad Metro Bus project has been divided into two parts i-e Rawalpindi and Islamabad.
Further the Rawalpindi part has been divided into three packages. Each package has been assigned to
three different companies. Package I (Flash man hotel to committee chowk) has been awarded to Zahir
Khan & Brothers pvt ltd. Zahir khan & Brothers As a preeminent infrastructure company established over
four decades ago, Zahir khan & Brothers has, over the years, strongly anchored itself to Pakistans
Development efforts. At the time of its conception the company operated solely within Baluchistan
region, but with the passage of time they have expanded the scope of their operations throughout the
country. Today it is acknowledged as a company that continues to empower Pakistan, enabling the
nation to surge ahead in different core sectors. At the heart of all development efforts is the attempt to
touch and improve the quality of lif
About the project
The Metro Bus service Rawalpindi-Islamabad consists of approximately 23 km that starts from flash man
hotel Rawalpindi and end at prime minster secretariat Islamabad. The project has been divided into two
parts i-e
Rawalpindi
Islamabad
The Islamabad Corridor of MBS starts from end of Faizabad interchange at IJP Road at this point. It
runs in between at-grade and takes right turn on 9th Avenue. Along Ninth Avenue (Islamabad) crosses
Kashmir Highway and turns to Jinnah Avenue and ends at Civil Secretariat. The total length of MBS
Islamabad will be 13.6 km. The Islamabad part has been further divided into five packages
Package I:
4.4 km
Package II:
1.1 km
Package III:
2.9 km
Package IV:
Package V:
To facilitate intercity movement of passengers at low cost, high capacity and dedicated lanes
to avoid disruption on the existing flow of traffic;
To provide transport safety, transport productivity, travel reliability, travel choices, and social
equity;
To reduce the fuel consumption by reducing the demand of private vehicle etc;
To reduce the, noise and air pollution resulting from vehicular exhaust; and
To provide an opportunity to laborers and skilled/unskilled staff to work in the project area
Feasibility Methodology:
The methodology adopted to conduct this study was as follows:
Meetings and discussions were held among the members of the EIA consulting team, design
engineers and proponent. This activity was aimed at achieving a common ground of
understanding of various issues of the study.
Planning was carried out to assess data requirements and their sources; time schedules and
responsibilities for their collection; logistics and facilitation needs for the execution of the data
acquisition plan.
Primary and secondary data were gathered through observations during the field survey,
environmental monitoring in the field, concerned departments and published materials to
establish baseline profile for physical, biological and socio-economic environmental conditions.
The impacts of the project on the physical, biological and socio-economic environment
prevalent in the project area were visualized at the design, construction and operational phases.
The adequate mitigation measures and implementation mechanisms were proposed so that the
proponent could incorporate them beforehand in the design phase.
RawalpindiIslamabad MBS
Islamabad Phase
Rawalpindi Phase
Package I
Package I
Package II
Package II
Package III
Package III
Package IV
Package V
Phase-to-Phase Relationships:
When projects have more than one phase, the phases are part of a generally sequential process
designed to ensure proper control of the project and attain the desired product, service, or result. For
MB project Phase to phase relationship is being used for example after the feasibility phase, land
acquisition phase, earth work, piers and then the bridge. In other words its a step by step sequential
process.
Enterprise Environmental Factors:
Disturbance in the daily routine activities of locals and the people visiting educational and
health facilities, like; Hamdard University, Virtual University, the University of Lahore, Allama
Iqbal Open University, Kulsoom International Hospital, Polyclinic etc. during construction;
Air and noise pollution due to the operating of construction machinery during construction
phase of the project;
Removal of vegetation;
trash pooling resulting from improper drainage system and consequent Inconvenience to the
public;
ORGANIZATIONAL STRUCTURE:
The Organizational structure is projectized in which the project manager has full
authority to assign priorities, apply resources, and direct the work of persons assigned to the project.
10
PROJECT CHARTER
General Information.
Project Title: Rawalpindi-Islamabad Metro Bus Project (Package I)
Points of Contact
Position
Project Sponsor
Punjab-federal Government of
Phone
Authorization
Pakistan
Project Director
Zahid Saeed
Resource 1
Fahad Aslam
Executive Summary
The Metro Bus service Rawalpindi-Islamabad consists of approximately 23 km that starts from flash man
hotel Rawalpindi and end at prime minster secretariat Islamabad. The people travelling by public transport
are passing through double agony because despite getting high fares, the transporters do not finish their
routes, thus making the commuters pay extra fare for reaching their destinations by changing two vehicles
from Saddar to Pak Secretariat. Moreover, during peak hours, vehicles are overloaded. Therefore, the
existing public transport system requires a major uplift in level of service and quality. In order to tackle this
problem and provide improved quality of public transport, Government of Punjab, Rawalpindi
Development Authority (RDA) decided to construct the Metro Bus System (MBS) in Islamabad.
Project Purpose
The overall objective of the proposed project is to augment public transport services in the city with
provision of safe, efficient and comfortable traffic facility to the commuters of the area. The proposed
project will greatly benefit the commuters by providing better quality and environmental friendly public
transport, reducing number of vehicles on the road, thus reducing fuel consumption and consequent air
emissions from vehicular exhaust
11
Assumptions
The people travelling by public transport are passing through double agony because despite
getting high fares, the transporters do not finish their routes, thus making the commuters
pay extra fare
There is no pre existing quality transport facility in the twin cities
It will provide transport safety, transport productivity, travel reliability, travel choices, and
social equity;
To reduce the traffic conflicts/accidents due to reduction in number of vehicles on road;
To help save the travelling time by reduction in traffic congestion;
To reduce the fuel consumption by reducing the demand of private vehicle etc
Project Authority
Authorization
Project Manager
12
Resources
Resources
Funding
Sponsor Funded
Project Team
Project Manager: Overlook the entire project throughout its life cycle,
measuring project progress and conforming to the quality standards
(QA).
Facilities
Equipment
Software Tools
Other
13
14
PROJECT SCOPE
Project Overview
Since the twin cities are hub of economic, political, and educational activities, significant commuting
takes place between the twin cities and adjoining areas.
The available public transport is dominated by the private sector, contributing to about 35 per-cent of
the share of overall modes of transportation. This share is now declining due to poor service and
widespread customer dissatisfaction with the available options. The people travelling by public
transport are passing through double agony because despite getting high fares, the transporters do not
finish their routes, thus making the commuters pay extra fare for reaching their destinations by changing
two vehicles from Saddar to Pak Secretariat. Moreover, during peak hours, vehicles are overloaded.
Therefore, the existing public transport system requires a major uplift in level of service and quality. In
order to tackle this problem and provide improved quality of public transport, Government of Punjab,
Rawalpindi Development Authority (RDA) decided to construct the Metro Bus System (MBS) in
Islamabad.
About the project
The Metro Bus service Rawalpindi-Islamabad consists of approximately 23 km that starts from flash man
hotel Rawalpindi and end at prime minster secretariat Islamabad. The project has been divided into two
parts i-e
Rawalpindi
Islamabad
The Islamabad Corridor of MBS starts from end of Faizabad interchange at IJP Road at this point. It
runs in between at-grade and takes right turn on 9th Avenue. Along Ninth Avenue (Islamabad) crosses
15
Kashmir Highway and turns to Jinnah Avenue and ends at Civil Secretariat. The total length of MBS
Islamabad will be 13.6 km. The Islamabad part has been further divided into five packages
Package I:
4.4 km
Package II:
1.1 km
Package III:
2.9 km
Package IV:
Package V:
Objective/ Purpose
The overall objective of the proposed project is to augment public transport services in the city with
provision of safe, efficient and comfortable traffic facility to the commuters of the area. The proposed
project will greatly benefit the commuters by providing better quality and environmental friendly public
transport, reducing number of vehicles on the road, thus reducing fuel consumption and consequent air
emissions from vehicular exhaust. Implementation of the project is envisaged having the following
specific objectives:
To facilitate intercity movement of passengers at low cost, high capacity and dedicated lanes
to avoid disruption on the existing flow of traffic;
To provide transport safety, transport productivity, travel reliability, travel choices, and social
equity;
To reduce the fuel consumption by reducing the demand of private vehicle etc;
To reduce the, noise and air pollution resulting from vehicular exhaust; and
To provide an opportunity to laborers and skilled/unskilled staff to work in the project area
16
Procurement of land
Structural Dimensions
Transform (Steel form work with concrete pump & batching plant)
Architectural Drawings
Foundation excavation
In the event that the Project Manager subcontracts work, all subcontractors employees will be
verified by the Project Manager to be bonded and will hold trade licenses and credentials.
Project Manager has agreed to the terms of the fixed price contract and schedule.
During planned project execution, Project Manager will provide periodic progress reports to the
sponsor.
Following any schedule delay, Project Manager agrees to provide progress reports on a weekly basis
until the schedule has been caught up.
17
CHANGE MANAGEMENT
Project manager will co-ordinate with the sponsor with the change request and business case
/justification.
Cost manager will verify the cost implications pertaining to the change.
The change will be updated in the project management plan and the update represented.
COMMUNICATION MANAGEMENT
The sponsor will be notified by the Project Manager via e-mail or telephone of all the urgent issues.
Issue notification will include the time constraints and the impacts that shall notify the urgency of
the request.
The progress report will be presented by the Project manager to the management and the team
leaders.
Weekly meetings will be conducted between the Project Manager and the Managers.
PROCUREMENT MANAGEMENT
The Procurement Manager will maintain a Procurement Management Plan in accordance with the
Project Plan. The procurement plan will document the following:
How / when and by what means the resources(material, equipment, etc.) will be contracted
All procurements will be monitored by the procurement manager and project manager shall be kept
in loop at all times.
In an event of any change in the scope, it shall be the responsibility of the project manager to notify
the procurement manager in a timely manner and the procurement manager will acquire the
relevant resources.
All procurements shall be obtained through open bid in order to obtain the best quality in the least
possible price. (construction equipment)
18
Procurement process
Procurement of material required for the initial testing will be done by the project manager as per
the requirement provided by the sponsor.
In case of sub-contraction involvement, PM will be responsible for the monitoring and controlling of
the material and service.
RESOURCE MANAGEMENT
All materials and services to be delivered as part of the project along with cost estimates and quality
information.
OUTSTANDING ISSUE
Project manager will be responsible not only for workmanship but also for all reporting and report
related matters, change requests, Etc.
Any delay caused by the sponsor will be charged accordingly man hours, opportunity cost, time
delay cost.
No payment shall be delayed more than one week from the date of invoice.
REFRENCES
All architectural designs and blue prints of the project will be submitted to CDA/RDA for approval
and record purposes.
19
The people of Twin cities travelling by public transport are passing through double agony because despite
getting high fares, the transporters do not finish their routes, thus making the commuters pay extra fare for
reaching their destinations by changing two vehicles from Saddar to Pak Secretariat. Moreover, during peak
hours, vehicles are overloaded.
Therefore, the existing public transport system requires a major uplift in level of service and quality. In
order to tackle this problem and provide improved quality of public transport, Government of Punjab,
Rawalpindi Development Authority (RDA) decided to construct the Metro Bus System (MBS) in
Islamabad. The total length of the route from Saddar to Pak Secretariat will be approximately 23 KM.
The route will consist of 24 Bus Stations, TEN bus stations will be established in Rawalpindi and Fourteen
in Islamabad. An 8.6 KM elevated track, consisting of 10 bus stops, would be constructed from
Flashmans Chowk in Saddar to Faizabad. From Faizabad it turns towards Islamabad using IJP Road and
enters Jinnah Avenue via 9th Avenue and continues towards Pak Secretariat.
Market Viability:
Since the twin cities are hub of economic, political, and educational activities, significant commuting
takes place between the twin cities and adjoining areas. The need of such quality transport system is
necessity.
Target Market;
The target audience for this project is the general population of Rawalpindi and Islamabad, travelling daily
between the twin cities.
Competitive Advantage
Metro bus service is one unique of its kind; it will provide quality and environmental friendly transport
facility to the public.
Will provide transport safety, transport productivity, travel reliability, travel choices, and
social equity;
Will reduce the traffic conflicts/accidents due to reduction in number of vehicles on road;
20
Will reduce the fuel consumption by reducing the demand of private vehicle etc;
Excavation and Vibrations due to construction machinery may affect the structure stability of
the buildings during construction.
Disturbance in the daily routine activities of locals and the people visiting educational and
health facilities, like; Hamdard University, Virtual University, the University of Lahore, Allama
Iqbal Open University, Kulsoom International Hospital, Polyclinic etc. during construction;
Air and noise pollution due to the operating of construction machinery during construction
phase of the project;
21
Removal of vegetation;
trash pooling resulting from improper drainage system and consequent Inconvenience to the
public;
Cost:
The total cost of package I is expected to be Rs 4,701,404,017/. Break up of cost is given below
Sr No
Description
Amount in Rs.
21,470,780/-
194,537,100/-
120,413,600/-
4.1
3,752,640,590/-
4.2
Structure(NJB/Rigid pavement)
22,259,220/-
4.3
230,690,400/-
4.4
125,575,012/-
152,067,320/-
Ancillary works
117,673,005/-
General items
23,600,000/-
Electrical works
251,765,176/-
Total
5,012,692,20
(311,288,185)
4,701,404,017
22
Purpose
This document describes the Staff Management Plan for the Package I of the Project. The purpose of the
Staff Management Plan is to capture how the project manager will manage the project staff resources
throughout the life of the project. The Staff Management Plan will make certain the project has
sufficient staff possessing the correct skill sets and experience to ensure a successful project completion.
Scope
This Staff Management Plan identifies the process and procedures used to manage staff throughout the
projects life. The plan describes the planning and acquisition of staff, describes the responsibilities
assigned to each staff, and discusses transition of staff to other assignments.
Staff Estimates
This section describes the type of HR and their quantity that will be required for completion of the
project. Approximately 400 employees working on the package I, Employees include
Project Manager
Procurement and Logistics Manager
23
Construction Manager
Construction Workers
Human Resource Manager
Finance and Accounts Manager
Budget Control Team Lead
Risk Manager
Chief Mechanical Engineer
Civil Engineers
Equipment Deployment Engineer
3rd Engineers
Lead Architect and Designers
Electrical Engineers
Security Guards
Staff Acquisition
Internal Acquisition
This section describes the procedure of internal acquisition of the project staff that will not be hired but
will be moved to this project from some other project. Project Manager will assign the existing resources
as and when required by the Project Manager during different phases of the project.
Selection/Recruitment
HR Manager will schedule interviews for the shortlisted candidates. The interviews will be conducted by
HR Manager, Project Manager and respective Manager of the concerned department. After the first
round of interviews, HR Manager will further shortlist the candidates and call the candidates for final
round of interviews
24
Staff Training
Ongoing Staff Training
At the start of the project, the direct or functional managers would review their staff skill sets against
any new roles or responsibilities needed for the phase. Each manager and their staff should discuss
where additional training might be needed to ensure staff has the necessary skills to execute the
activities for each project phase.
Staff Transition
Transition to other Projects
The project manager is responsible for ensuring any pending work is transferred to a remaining staff
member to ensure timely transition and completion of the work. If appropriate, the receiving staff may
request additional training to support the new responsibilities.
Transition at Project Completion
This section describes the process for transitioning staff once the project is completed. It also describes
how the project or department will help to place staff. This section indicates how staff will be released.
Roles and Responsibilities
This section describes the specific roles and responsibilities as they have been tailored for the project.
These are not meant to be job descriptions, but rather a summary of the responsibilities for each role.
Project Manager
The Project Manager is accountable to the Project Director for all the project office management related
activities. The Project Manager plans, guides, and oversees the day-to-day internal activities that support
the Project Office, and assists in the development of the master project schedule and all other project
work plans. The Project Manager is accountable for the development, maintenance, and adherence to
the Project Office infrastructure and supporting methodologies (e.g. processes, procedures, standards,
and templates) that are in compliance with organizations Best Practices and policies.
25
This Communications Management Plan sets the communications framework for this project. It will
serve as a guide for communications throughout the life of the project and will be updated as
communication needs change. This plan identifies and defines the roles of persons involved in this
project. It also includes a communications matrix which maps the communication requirements of this
project. An in-depth guide for conducting meetings details the communications rules and how the
meetings will be conducted, ensuring successful meetings. A project team directory is included to
provide contact information for all stakeholders directly involved in the project.
26
Introduction
Purpose of the Schedule Management Plan
The Schedule Management Plan has the following purposes:
27
28
Appendix