Akpo

Project

AKPO
A large Nigerian deep offshore development

AFTP/SPE - Akpo Project - 23-06-10 A. Lain / F. Fourni

A LARGE PROJECT OFFSHORE NIGERIA BY TOTAL

1400m water depth, 100 miles off Port Harcourt


44 wells, 10 manifolds, 14 SCR risers, 440 000 ton FPSO
AFTP/SPE - Akpo Project - 23-06-10

A Complex Venture Arrangement


24%
16%

10%
50% NNPC ie
-45% CNOOC
- 5% SAPETRO

PSA (Farm-in Agreement)


PSC

50%
SAPETRO

TOTAL

BRASOIL

OML 130

OPL 246
1998

NNPC

OPL 246
OML 130
2005

Managed through a PSA and a PSC, Partnerships


differ in the 2 contracts, Total Operator for the OML
AFTP/SPE - Akpo Project - 23-06-10

A Complex Venture but still a robust one

3 National Oil Companies !


AFTP/SPE - Akpo Project - 23-06-10

AN HYBRID HIGH TECH SCHEME

Complex sand lobes and channels, critical fluid


Near high pressure / high temperature, gas export to LNG
AFTP/SPE - Akpo Project - 23-06-10

TECHNOLOGY PUSHED TO NEW FRONTIERS

7 SAS, Perforation/ frac. pack in single run in 10 , intelligent completions


118C SPS, 588 bar SCR, FICSS, all electric 180 MW FPSO
AFTP/SPE - Akpo Project - 23-06-10

QUALIFICATIONS FOR TECHNOLOGY RISKS

150 qualification programs


30% initial Test failure, zero Field failure
AFTP/SPE - Akpo Project - 23-06-10

EXECUTION ON A GLOBAL SCALE

32 million man-hours, 14 million in Nigeria


Global IS/IT for central management in Nigeria
AFTP/SPE - Akpo Project - 23-06-10

INNOVATIVE BIDDING SOLUTIONS

EPC reservation agreements signed 8 month ahead of uncertain FID


Currency & commodity hedging, asset reservation, schedule
AFTP/SPE - Akpo Project - 23-06-10

Contractual Strategy
DRILLING
DRILLING&&
COMPLETION
COMPLETION

SPS
SPS

Management
& &
Management
conceptual
studies
conceptual
studies

Procurement
Procurement
Onshore fabrication
Onshore
fabrication

FPSO
FPSO
Hull
Hull
Topsides

TUPNI
TUPNI
DORIS
Engineering
DORIS Engineering

Basic Engineering
FEED
Engineering
Detail Engineering
Detail
Engineering

UFR
UFR&&

Offloading
Offloading
terminal
terminal

LLI

EPSCC
EPSCC
EPS
DRILLING
SAIPEM
DRILLING
EPSCC
EPSCC Technip/HHI
EPS
TUPNI CAMERON

Onshore test
& com.
Onshore
test
& com.
Transportation
Transportation

Drilling: Transocean

Offshore
installation
Offshore
installation

Completion: Global
Santa Fe

Offshore
H.U.
Offshore
H.U.
Offshore commissioning

Offshore commissioning
Start up
Start
up& operation
& operation

TUPNI

Flotel

TUPNI

Defined during Basic phase,


Large & synchronized EPSCC
Selection approved at Project Sanction
AFTP/SPE - Akpo Project - 23-06-10

Time Allowance for Record Nigerian Content

Up to 18 month for capacity building, 50% for learning curve


Delivered quality meets international standards
AFTP/SPE - Akpo Project - 23-06-10

11

An Integrated Project Management


DIRECTOR

VENTURE

SURFACES
FACILITIES
SERVICES

FLOATING,
PRODUCTION,
STORAGE &
OFFLOADING

NIGERIA
INTERFACES

SUBSEA
PRODUCTION
SYSTEM

COMMISSIONING

UMBILICALS,
FLOWLINES &
RISERS

INTERFACES

FIELD GSR

DRILLING &
COMPLETION

FIELD
OPERATIONS

HSEQ

Akpo
Project

Fully integrated project management team till 1st oil


Unified IT tools & EDMS
Lessons learnt from TOTAL deep offshore projects
AFTP/SPE - Akpo Project - 23-06-10

Complex under-saturated near-critical fluids


RESERVOIR G FLUID SWELL TEST

Significant
amount of
precipitated
asphaltene
sticking to
the wall of
the
transparent
cell

PHASE DIAGRAM
TR

Critical Points

Critical Point
Volatile Oil

Volatile oil

Pressure
PRESSURE

Condensate
Condensate

Temperature
TEMPERATURE
TEMPERATURE

Light Oil (Up to 50API) with High GOR,


Widespread impact on the AKPO development project
AFTP/SPE - Akpo Project - 23-06-10

A Mandatory Meticulous Well Planning

Definition and freezing of the 22 start-up wells at Project Sanction,


delivered as planned at Start-Up
AFTP/SPE - Akpo Project - 23-06-10

Pre-production Interference Testing


Akpo-10
and
Akpo-06
Normalised
Pressure
Response
A-2 and
A-3
normalised
pressure
response
During
Interference with
(PULSER).
during
Interference
test Akpo-15
with A-1
(Pulser)
2.50
2.25

press - Akpo-10
A-3
press - Akpo-06
A-2

1.75
1.50

A-2

2psi response consistent


with test design

1.25
1.00

Akpo-10
Akpo-10

A-3

Akpo-15
Akpo-15

Start Injection on
Akpo-15
A-1

0.75
0.50
0.25

End Injection on
Akpo-15
A-1

0.00

26/12/08

25/12/08

24/12/08

23/12/08

22/12/08

21/12/08

20/12/08

18/12/08

17/12/08

16/12/08

15/12/08

14/12/08

Akpo-6
13/12/08

-0.50
12/12/08

11/12/08

-0.25
19/12/08

Differential Pressure (psi)

2.00

A-1

Akpo-16

Date

Subsea Well Intervention Monitoring System (SWIMS) used for


pressure data recovery, storage and transmittal
AFTP/SPE - Akpo Project - 23-06-10

Akpo-5G

Akpo-5st

A Very Large Drilling Operation


Discovery

Jack Ryan

Stena Tay

Pathfinder

2006
DWD

2007

2008

2009

709 days

J Ryan
S- Tay

751 days
305
days
305
days

DWP

4 drilling units, 2000 rig days, 3.6 Millions man hours


Two flagship rigs : Transocean Deepwater Discovery and Jack Ryan
AFTP/SPE - Akpo Project - 23-06-10

Rig specialization to push the performance limit


Transocean Jack Ryan

Well testing
equipment on Jack
Ryan
Management decision to dedicate one rig for drilling, one rig for completion
Savings in rig upgrades and service costs, efficient specialized rig crew
AFTP/SPE - Akpo Project - 23-06-10

Batch drilling helps for continuous improvement


Deep Water Discovery
Top-Hole Duration

Mud Mat/TGB in
moon pool

Batch operations improved learning process


Sustained continuous progress for two years
AFTP/SPE - Akpo Project - 23-06-10

Batch completions for quality & performance


X-Tree installation time

Performance achieved, keeping high quality standards


by batching operations of frac. pack, completions and X-trees
AFTP/SPE - Akpo Project - 23-06-10

22 wells delivered ON TIME

AKPO strong management achieved a GREAT step


in the efficiency of deep water well delivery
AFTP/SPE - Akpo Project - 23-06-10

10 km

Subsea Layout, a Key Feature of the Development

12k
m
An Optimized Sub-Sea Layout with multi Drilling Centers, taking onboard
SCR constraints and Flow Assurance requirements, frozen at FEED
AFTP/SPE - Akpo Project - 23-06-10

21

Flow Assurance: a major factor in project definition

Shut-down

WELL READY

SUBSEA
SYSTEM
PROTECTED

TO RESTART

NO TOUCH
TIME 4-hour

INJECTION
OF METHANOL
STABILISED CRUDE
CIRCULATION
DEPRESSURISATION
OF WELL, JUMPER,
MANIFOLD
AND RISER

FLOW LINE / RISER INSULATION


PERFORMANCES

Flow assurance influences field architecture,


requires early definition
AFTP/SPE - Akpo Project - 23-06-10

Time

STANDARDIZED DRILL CENTRE LAYOUT


SUBSEA UMBILICAL
TERMINATION
MANIFOLD
MODULE
.

XMAS
TREE

WELLHEAD
HYDRAULIC
FLYING
LEADS
HORIZONTAL
CONNECTORS &
DOGHOUSES

MANIFOLD
PILE

SYSTEM DESIGNED FOR MAXIMUM AVAILABILITY


AFTP/SPE - Akpo Project - 23-06-10

OTC 23
- 20993

Akpo Subsea Production Facilities

AFTP/SPE - Akpo Project - 23-06-10

Running Xmas Trees

50 tons at the end of the riser to be accurately positioned


and connected to the wellhead
AFTP/SPE - Akpo Project - 23-06-10

Jumper installation & Connection

Connector Running Tool

150 line pipe subsea connections completed at First OIL


AFTP/SPE - Akpo Project - 23-06-10

One Riser Concept Selected at Pre-Basic Stage

Main Factors
Water depth
Flow Assurance
WD : 1300m

No Gas lift
Generic concept
Local content
Bidding process

15

900 m

SCR + wet insulation: best solution for AKPO


AFTP/SPE - Akpo Project - 23-06-10

27

Flexible Joint Qualification


Early maturity assessment during FEED
Extensive qualification during detail engineering

Fluid compatibility testing


Hyper-Elastic law development for FEA
Resistance to explosive decompression
Ageing stiffening and impact on design
Fatigue resistance under pressure cycles

Early Maturity Assessment defined qualification scope for FJ design


Full scale test confirmed manufacturing process & design fitness for severe conditions
AFTP/SPE - Akpo Project - 23-06-10

28

SCR Pre-installed, Recovered & Transfered to FPSO


Step 1 : FDS
picks up FL
Head

FPSO

SCR
transferred
to FPSO
SCR load
transfer from
FDS to FPSO
pulling rig

Pulling
rig

Transfer wire
passed to FDS
from FPSO
pulling rig

Step 2 : FL
head on FDS

SCR laying

SCR including
Flex-joint ready
to transfer

FLET

AFTP/SPE - Akpo Project - 23-06-10

29

AKPO FPSO
Hull: 310m x 61m x 31m
Living Quarter: 240 POB
2 million barrels storage
Oil processing: 185,000 bbl/d
Water injection: 420,000 bbl/d
Produced water treatment:
150,000 bbl/d
Gas treatment: 530 mmscfd
Gas export: 290 mmscfd
Gas injection: 210 mmscfd

110,000 tons fabricated & moored in 1400 m water depth,


14 Steel Catenary Risers
AFTP/SPE - Akpo Project - 23-06-10

Re-Injection

An Hybrid Gas Injection - Gas export FPSO

Gas

Gas Export

Condensate

Akpo Central

Condensate

Akpo East

Akpo Central

B, EF, G

WI

Flexibility to maintain liquid production


Gas export to LNG production
AFTP/SPE - Akpo Project - 23-06-10

An all-electric FPSO

Single 160 Mw power generation plant, shorter commissioning & start-up


Higher availability & lower maintenance cost
AFTP/SPE - Akpo Project - 23-06-10

32

E&I decentralized Technical Buildings

Easier and earlier commissioning before sail-away


Easier start-up of FPSO facilities
AFTP/SPE - Akpo Project - 23-06-10

33

Field Integrated Control and Safety System


Hull

Topsides

Subsea

Downhole

Global ICSS approach selected during FEED


No barrier to communication
AFTP/SPE - Akpo Project - 23-06-10

34

Tow Opportunity between Korea and Nigeria

High state of readiness once on location


Team continuity between onshore and offshore
AFTP/SPE - Akpo Project - 23-06-10

35

Simultaneous Operations Strategy

3 drilling rigs, 4 construction vessels, 1 flotel and FPSO


SCR installation, hook up, commissioning while producing
AFTP/SPE - Akpo Project - 23-06-10

36

2 Years of Active People Development

Mobilise and train early - start production early


AFTP/SPE - Akpo Project - 23-06-10

High Production Delivery Performance

Cumulative
Production

Align project activities completion with production goals


AFTP/SPE - Akpo Project - 23-06-10

PLAN
ACTUAL

AKPO Operations: the Keys to Success

Integrated Project organisation


Technological expertise
Deep offshore operational experience
Early operators mobilisation
Focused Nigerians development
Robust site organisation
Personal Commitment

Operations success
is the AKPO Project teams overall success
AFTP/SPE - Akpo Project - 23-06-10