Escolar Documentos
Profissional Documentos
Cultura Documentos
26 NOVEMBER 2014
INTRODUCTION TO MINE
SCHEDULING
26 NOVEMBER 2014
MINE SCHEDULING
DEFINITION:
'A LIST OF TASKS TO BE PERFORMED, ESPECIALLY WITHIN A SET
PERIOD'; OR AS A 'PLAN OF PROCEDURE FOR A PROJECT'
MINE SCHEDULING
A MINING SCHEDULE, WHICH TELL US WHEN THINGS OCCUR, CAN
BE CONSTRUCTED BY APPLYING PRODUCTION CONSTRAINTS TO THE
MINING SEQUENCE
MINE SCHEDULING
IMPORTANT BECAUSE A $ RECEIVED TODAY IS MORE VALUABLE
THAN A $ THAT WE MIGHT RECEIVE IN A YEARS TIME
LABOUR AND EQUIPMENT REQUIREMENTS ARE ESTIMATED,
PERFORMANCE RATES AND STANDARD COSTS ARE APPLIED AND
THEN THE MINES PROGRESS AND VIABILITY CAN BE PLANNED AND
MONITORED
MINE SCHEDULING
TYPES OF MINING SCHEDULE
PRODUCTION SCHEDULES
LONG TERM OR LIFE OF MINE (10+ YEARS)
MEDIUM TERM (5 YEARS APPROX.)
SHORT TERM (3 MONTHS 2 YEARS)
EXTREMELY SHORT TERM (DOWN TO A SHIFT, OR FOR SPECIFIC JOBS)
MINE SCHEDULING
TYPES OF MINING SCHEDULE
EQUIPMENT SCHEDULES
LABOR SCHEDULES
FILLING SCHEDULES
CONSUMABLE SCHEDULES
SPECIAL PROJECT SCHEDULES
MINE SCHEDULING
LONG TERM SCHEDULE
USED TO FEED INFORMATION TO THE CALCULATION OF THE MINES NPV
AND CUT-OFF GRADE CALCULATIONS
PROVIDE TARGET DATES FOR ORE RESERVE EXPLORATION DRILLING
SCHEDULES, INCLUDING DEVELOPMENT REQUIRED TO ACCESS THESE
EXPLORATION DRILLING SITES
OF THE
MINE SCHEDULING
MEDIUM TERM SCHEDULE
MAIN PLANNING SCHEDULES INDICATING WHEN PLANNING AND DESIGNS
OF ACCESSES TO NEW AREAS OF THE MINE NEED TO BE COMPLETED
MORE DETAILED THAN THE LONG TERM ONES WITH INDIVIDUAL STOPE ORE
BLOCKS NOMINATED, EACH WITH THEIR OWN TONNES AND GRADES AND
DILUTION AND RECOVERY FACTORS
MINE SCHEDULING
SHORT TERM SCHEDULE
PROVIDE THE MAIN MONTHLY AND QUARTERLY OPERATING TARGETS
DETAILED IN TONNES, GRADES, DILUTIONS AND RECOVERIES FOR EACH
STOPE
MINE SCHEDULING
EXPLORATION DRILLING SCHEDULE
FAIRLY SIMPLE SCHEDULES INDICATING WHEN DRILLING NEEDS TO BE
DONE TO SATISFY THE KEY DATES INDICATED ON THE LONG TERM AND
MEDIUM TERM PRODUCTION SCHEDULES.
MINE SCHEDULING
DEVELOPMENT SCHEDULE
DRAWN UP TO SATISFY THE TARGETS FOR PRODUCTION FROM VARIOUS
AREAS AND STOPES, AS SHOWN ON THE PRODUCTION SCHEDULE
TYPICAL DEVELOPMENT PERFORMANCES FOR UNDERGROUND
DECLINE (SINGLE HEADING): 30 50 M/WEEK
DECLINE (TWO HEADINGS): 50 60 M/WEEK
ACCESS DEVELOPMENT (MULTIPLE HEADINGS: 60 80 M/WEEK)
MINE SCHEDULING
EQUIPMENT SCHEDULE
PREPARED MAINLY FROM PRODUCTION, DEVELOPMENT AND DRILLING
SCHEDULES
MINE SCHEDULING
LABOUR SCHEDULE
PREPARED FROM EARLIER SCHEDULES
SHOW THE NUMBER OF PRODUCTION MAKERS, EXPLORATORY DRILLERS,
DEVELOPMENT CREW MEMBERS, PRODUCTION DRILLERS AND
MAINTENANCE LABOUR REQUIRED AND WORKING ROSTERS FOR EACH
LABOUR
CATEGORIES CAN THEN BE APPLIED TO THE NUMBERS REQUIRED FOR EACH,
AND OVERALL LABOUR COSTS ESTIMATED AT VARIOUS TIMES
MINE SCHEDULING
FILLING SCHEDULE
PREPARED FOR MINES THAT FILL THEIR EXTRACTED STOPES OR OPERATE
SYSTEMS REQUIRING FILL AS PART OF THE PRODUCTION CYCLE
MINE SCHEDULING
CONSUMABLES SCHEDULE
CRITICAL CONSUMABLE REQUIREMENTS ARE USUALLY PREPARED TO
INDICATE TO SUPPLIERS WHEN AND HOW MUCH OF THESE ARE
REQUIRED
MINE SCHEDULING
SPECIAL PROJECT SCHEDULES
USED FOR PREPARATION, DEVELOPMENT, INSTALLATION AND
COMMISSIONING OF MAJOR INFRASTRUCTURE COMPONENTS AT
MINES
PRODUCTION SCHEDULING
MINE SCHEDULING
OBJECTIVES
PROVIDING A STEADY AND BALANCED ORE FEED TO THE MILL
MAXIMISING THE NPV OF THE PROJECT
PROVIDING A STEADY, BALANCED WORK LOAD FOR THE ORE AND
WASTE MINING EQUIPMENT FLEETS
MINE SCHEDULING
SCHEDULING
SCHEDULING IS INTEGRAL TO THE DESIGN AND OPERATION OF AN
OPEN PIT MINE.
THE PROCESS OF DECIDING WHICH BENCH TO EXTRACT, WHEN TO
EXTRACT IT AND HOW THIS FITS INTO THE OVERALL PIT DESIGN IS
INCREASINGLY BECOMING MORE COMPLEX DUE TO THE ADVENT OF
ECONOMIC THEORY AND ADVANCED COMPUTER OPTIMISATION
SOFTWARE.
MINE SCHEDULING
PUSHBACK
A PUSHBACK IS A DESIGN OF WHAT THE PIT WILL LOOK LIKE AT A
SPECIFIC TIME.
PUSHBACKS ARE USED WHERE THE EXACT DESIGN OF THE PIT AT THAT
TIME WILL SIGNIFICANTLY AFFECT OVERALL MINE PROFITABILITY, PIT
SCHEDULING, OR SOME OTHER CHOSEN DESIGN FACTOR (USUALLY
ECONOMIC).
OVER THE MINE LIFE, SUCCESSIVE PUSHBACKS WILL INCREASE IN SIZE
FROM SMALL PITS, TO LARGE PITS, TO THE FINAL PIT.
MINE SCHEDULING
PUSHBACK
MINE SCHEDULING
PUSHBACK
THE PROCESS OF CHOOSING WHEN A PUSHBACK IS NEEDED, IS USUALLY
DONE THROUGH SOME TYPE OF OPTIMISATION PROCESS, WHERE
PUSHBACKS ARE CREATED DUE TO THE POSITIVE EFFECT OF THEIR EXISTENCE
ON THE CHOSEN DESIGN FACTOR.
MINE SCHEDULING
PUSHBACK
MINE SCHEDULING
SIMPLE EXAMPLE
MINE SCHEDULING
ASSUME THE PRODUCTION RATE IS 5 BLOCKS PER YEAR;
THE NET VALUE (PROFIT) FOR AN ORE BLOCK = $60.00
COST OF REMOVING THE WASTE = $30.00 PER BLOCK
CALCULATE THE NPV OF THIS STRATEGY USING 10%
INTEREST RATE. ASSUME CASH-FLOWS ARE REALISED AT THE
END OF EACH YEAR.
MINE SCHEDULING
PRESENT VALUE = FUTURE VALUE/(1+10/100)N
SEQUENCING:
YR 1= 5 WASTE
BLOCKS (BENCH
1)