METHOD STATEMENT FOR REINFORCEMENT WORK

SANKEN CONSTRUCTION (PVT) LTD

PROPOSED MULTI STOREYED CAR PARK PHASE II


FOR CENTRAL BANK OF SRI LANKA, COLOMBO 01.

1. Reinforcement.
1.1 Resources to be used
(a). Tools
i.

Bar cutter

ii.

Bar bending machine

iii.

Bar Bending hacker

(b). Human resources


i.

Engineer

ii.

Technical supervisor

iii.

Bar bender

iv.

Unskilled labour

1.2 Fabrication
Bar bending schedules will be prepared by the Engineer,Cutting and bending are done
at bending yard, under the inspection of Engineer. Following facilities available at
yard
i.
Bar cutters
ii.
Bar benders
iii.
Loading and unloading by crane (Stationary)
1.3 Transportation and Store
Transport 50% of Reinforcement from yard to site is done usingLorries and stored the
Reinforcement on 4x4 with covered by canopy, other 50% of reinforcement is kept
in the yard.
i.
ii.

Loading
Unloading

- Using crane at yard


- Using crane at Site

1.4 Method of fixing


i. The mesh will be kept on the cover blocks.
ii. The mesh will be tied using GI binding wires (Stagger tied).

iii. Side covers will be maintained using cover blocks.


2. Materials
Following diameters of re-bars to be use
Bar diameter

Wight (Kg/m)

T 32

6.313

T 25

3.853

T 20

2.466

T 16

1.578

T 12

0.888

T 10

0.617

T6

0.222

FIGURE 01 Sample rebar arrangement