Você está na página 1de 16

Reclosers

Lecture 13: Distribution


Protection

Automatic circuit reclosers are


common on overhead utility
distribution systems

Reclosers
Sectionalizers
Coordination
Secondary Network Systems
ELCT 751

Distribution Protection

Overcurrent protection device


including the switchgear and the
protective relay logic
1

conventional oil recloser has


switchgear and relay logic in
same package
electronic reclosers may be
packaged for use with separate
control and relay logic package

Typical
T i l sequence: two
t
fast
f t ((or
instantaneous) operations then
two delayed operations
Other sequences may be used,
such as one fast, two delayed
3

Recloser trips on fault and


recloses in a sequence of
operations

Distribution Protection

FAST OPERATIONS
(CONTACTS ARE CLOSED)

Reclosing may be blocked for


downstream hot line work
Recloser locks out after sequence
is complete
Distribution Protection

ELCT 751

Recloser Sequence: permanent


fault
CURRENT

Reclosers

ELCT 751

Recloser trips on fault and


recloses in a sequence of
operations

Types of reclosers

Distribution Protection

Distribution Protection

Reclosers

Reclosers

ELCT 751

ELCT 751

DELAYED OPERATIONS
(CONTACTS ARE CLOSED)

TIME

FAULT INITIATED

ELCT 751

RECLOSING INTERVALS
(CONTACTS ARE OPEN)

Distribution Protection

RECLOSER LOCKS
OPEN (LOCKOUT)
6

Recloser Technology

Recloser Technology

Interrupting medium may be oil,


vacuum, or compressed gas
Controls can be either hydraulic
with series trip coil or electronic
with shunt trip coil

Available in single-phase or threephase packages


pole mounting for line sectionalizing
station mounting instead of line
circuit breaker

Three-phase devices may use


single-pole tripping with three-pole
lockout or three-pole tripping with
three-pole lockout
ELCT 751

Hydraulic controls use oil pumped


through an orifice to perform timing
Electronic controls use programmable
electronics

Distribution Protection

ELCT 751

Recloser Technology

Distribution Protection

Reclosers

Insulation may be oil, air,


compressed gas, or solid dielectric
Old technology example: oil
p g medium,,
insulation,, oil interrupting
hydraulic (oil) timing
New technology example: solid
dielectric insulation, vacuum
interrupter, programmable electronic
timing, data logging (etc.)
ELCT 751

Distribution Protection

ELCT 751

Usually oil interrupting medium,


oil insulation, series trip coil
Series trip coil usually has
minimum trip setting of 2 times
coil continuous current rating

Distribution Protection

10

Hydraulic Recloser

Hydraulic Recloser

ELCT 751

Distribution Protection

11

Example: 200 A frame size


recloser could have series trip coil
rated at 140 A (continuous)
giving a minimum trip current of
2 x 140 A = 280 A
Due to limitations of hydraulic
logic: Limited number of different
time-current curves available
ELCT 751

Distribution Protection

12

Electronically Controlled
Recloser

Electronically Controlled Recloser


Minimum trip setting is not
fixed by coil

Often a vacuum interrupting


medium
Usually a shunt trip coil fed
from a bushing CT with
electronic timing

Example: Recloser with 560 A


continuous current rating could
be set for 100, 140, 200, 280,
400, 560, 800, or 1120 A trip
Greater variety of time-current
curves

Minimum trip setting is not fixed


by coil
ELCT 751

Distribution Protection

13

ELCT 751

Recloser Ratings
voltage ratings (nominal RMS line
voltage)
interrupting ratings (RMS
symmetrical short-circuit current)
some method of changing trip
setting
Distribution Protection

15

Primary advantage of recloser is


realized when most faults are
temporary
Overhead MV lines usually experience
many temporary faults
Underground MV lines usually
experience relatively fewer temporary
faults
ELCT 751

16

Idea of coordination:

Recloser must coordinate with


other overcurrent protection,
upstream and downstream
Details of coordination covered
later

Distribution Protection

Distribution Protection

Recloser Application

Recloser Application

ELCT 751

14

Recloser Application

All reclosers have

ELCT 751

Distribution Protection

Recloser is to clear all temporary


faults downstream of recloser
without damage to downstream
fuses
coordinating with downstream
reclosers and sectionalizers
17

ELCT 751

Distribution Protection

18

Recloser Application

Recloser Application
Electronic controls give much
greater choice of time-current
curves than hydraulic

Idea of coordination:
Recloser is to clear all temporary
faults downstream of recloser
Permanent
Permanent faults downstream of
recloser are cleared by
downstream device
if it sees fault
before recloser locks out
ELCT 751

Distribution Protection

Example below shows recloser curves


matching IEC time-overcurrent relay
curves for circuit breakers
May allow complete freedom to tailor
curves for specific application
19

ELCT 751

Distribution Protection

20

IEC TOC Curves

100

Sectionalizers
10
Time [sec]

Automatic circuit sectionalizer is


similar to a recloser, but:

0.1

10

sectionalizer does not interrupt


fault current
sectionalizer does not have timecurrent curve

100

Current [per unit of trip]

Inverse
Very Inverse
Extremely Inverse
ELCT 751

Distribution Protection

21

ELCT 751

Automatic circuit sectionalizer is


similar to a recloser, but:
sectionalizer counts the number
off circuit
i i interruptions
i
i
(presumed
(
d
to be due to upstream recloser or
station breaker) and locks out
after preset number (while
upstream device is open)
Distribution Protection

22

Sectionalizer Operation

Sectionalizers

ELCT 751

Distribution Protection

23

Sectionalizer operation
sectionalizer senses overcurrent
and arms to count
when
h currentt ffalls
ll below
b l
the
th
sectionalizer setting, it counts
when count sequence is
complete, sectionalizer locks
open
ELCT 751

Distribution Protection

24

Sectionalizers

Sectionalizer Application

Replace fuse on close-to-station tap


fuse coordination is difficult due to
large available short-circuit current

Set sectionalizer count one


fewer than upstream recloser

Replace
ep ace second
seco d recloser
ec ose where
ee
recloser-to-recloser coordination is
difficult

Example: Four-shot recloser


followed by three-shot
sectionalizer

both reclosers may operate


simultaneously if close together
ELCT 751

Distribution Protection

25

ELCT 751

Recloser-sectionalizer-recloser
combination not recommended
unless studied carefully
Recloser-sectionalizer-fuse
Recloser sectionalizer fuse
combination may need study

Set sectionalizer count one


fewer than upstream recloser
p
(three-pole
(
p
Use three-phase
trip) recloser with three-phase
sectionalizer

Sectionalizer can count downstream


device operations
Considered in more detail later.

Otherwise, sectionalizer could


attempt to interrupt fault current
causing failure
Distribution Protection

27

ELCT 751

Sectionalizer Technology
Series coil senses fault current and
arms counting mechanism
After preset count sequence, contacts
opened

Electronic controls
Shunt coil feeding programmable
electronic controls
Set actuation level, memory time
Distribution Protection

Distribution Protection

28

Sectionalizer Settings

Hydraulic controls

ELCT 751

26

Sectionalizer Problems

Sectionalizer Application

ELCT 751

Distribution Protection

29

Set minimum actuation current


at 80% of minimum trip current
of upstream recloser
Hydraulic controls: use same
series coil rating for both units
Electronic controls: must be set
for proper value
ELCT 751

Distribution Protection

30

Sectionalizer Settings

Sectionalizer

Electronic recloser feeding


hydraulic sectionalizer: Minimum
actuating current of sectionalizer
= 1.6 X series coil rating.
Compare to recloser minimum
trip stetting.
ELCT 751

Distribution Protection

31

ELCT 751

Coordination

Coordination minimizes number


of customers out of service
Coordination speeds the
troubleshooting, so minimizes the
duration of the outage

ELCT 751

Distribution Protection

33

32

Typical System
FEEDER #1

HV SYSTEM

Proper coordination ensures


that minimum equipment is
taken out of service to clear the
fault

Distribution Protection

FEEDER #2

FUSE

ELCT 751

SECTIONALIZER

RECLOSER

Distribution Protection

34

Fuse-to-fuse coordination

Fuse-to-fuse coordination

The protected fuse is upstream;


the protecting fuse is
downstream

Protecting fuse A must clear the


fault before protected fuse B is
damaged

Fuse A is the protecting fuse;


fuse B is the protected fuse
Protecting fuse A must clear the
fault before protected fuse B is
damaged
ELCT 751

Distribution Protection

PROTECTED
FUSE (B)
FEEDER

PROTECTING
FUSE (A)
35

ELCT 751

Distribution Protection

36

TIME [SEC]

Time-current curves for both


fuses
Proper coordination requires
maximum clearing time of
protecting
p
g fuse less than minimum
melt time of protected fuse

FUSE B (PROTECTED)

FUSE A (PROTECTING)
MINIMUM MELT CURVE
SHIFTED TO 75% TIME
MAX. CLEARING TIME

To check coordination, plot both


time-current curves on same graph
CURRENT [A]
ELCT 751

Distribution Protection

37

ELCT 751

Distribution Protection

1 10

Fuse Preheating
Time [sec]

Load currents and high ambient


p
temperatures

Conservative rule of thumb to


maintain coordination:

39

Recloser-Fuse Coordination

0.01
10

ELCT 751

1 10

100

10K
10K
15K
15K

1 10

Current [A]

tot clear
min melt
tot clear
Distribution
min
melt Protection

40

Recloser feeding a fuse:

Fast operations of recloser should


protect entire downstream line
( far
(as
f as possible)
ibl ) from
f
temporary faults (fuse saving)
Fuse link should not be damaged
by fast operation
Distribution Protection

Recloser-Fuse Coordination

Recloser feeding a fuse:

ELCT 751

10

0.1

Shift minimum melt curve of protected


fuse to 75% time (shown on previous
slide)
Distribution Protection

100

Since fuse operation is thermal, fuse


preheating should be considered:

ELCT 751

38

41

Fuse saving
Fuse link should not be damaged
by fast operation
Permanent fault should cause
fuse to blow on first delayed
operation
ELCT 751

Distribution Protection

42

Recloser
operation - fuse link heating
V pu

Fuse link heating

1
t

0
Ipu
If
OPEN

OPEN

OPEN

LOCKS OUT

FUSE LINK
TEMPERATURE

CLOSED

FUSE SHOULD NOT


BE DAMAGED HERE
ELCT 751

CLOSED

CLOSED

If reclosing interval is longer than


link thermal time constant, link
may cool completely

FUSE SHOULD BLOW DURING ONE


OF THESE DELAYED OPERATIONS

Distribution Protection

43

If reclosing interval is shorter


than link thermal time constant,
link mayy not cool at all
If detailed calculations are not
done, assume no cooling to be
conservative
Distribution Protection

ELCT 751

Distribution Protection

44

Recloser-fuse coordination

Fuse link heating

ELCT 751

Fuse link heats during the


recloser closed periods and
cools during the open periods

Assume no cooling of fuse link


Assume recloser sequence is
2 2
2A2B
two fast (A curve) followed by
two delayed (B curve) operations

45

ELCT 751

Distribution Protection

46

Fuse and recloser time-current


curves showing coordination

Recloser-fuse coordination

TIME

Plot 2 times recloser A curve to


compare with fuse minimum
melt curve
Plot 2A+B to compare with fuse
maximum clearing time

FUSE MIN
MELT TIME

FUSE MAX CLEARING TIME

2XA+B
RECLOSER CURVES
2XA
A

CURRENT

COORDINATION RANGE
ELCT 751

Distribution Protection

47

ELCT 751

Distribution Protection

48

Recloser fuse coordination

Fuse-Recloser Coordination

Less conservative calculations can be


done
compare 1.75 times A curve to fuse link
min melt time
compare B to fuse link max clearing time

Calculate the actual cooling based on


thermal time constant of fuse link in
cutout and ambient temperature
ELCT 751

Distribution Protection

49

Exception: power fuse


protecting substation
transformer on HV side

ELCT 751

51

ELCT 751

Recloser-Recloser Coordination

Distribution Protection

52

Time from trip to reclose

Maximum clearing time of


downstream (protecting) recloser
less than minimum response time
of upstream (protected) recloser
Distribution Protection

50

Reclosing Interval

Electronically controlled units


are simply coordinated with
manufacturers time-current
curves:

ELCT 751

Distribution Protection

Hydraulically controlled units need


about 12 cycles of margin between
adjacent
dj
t unit
it to
t coordinate
di t
If margin is 2-12 cycles the units
might operate simultaneously
If margin is less than 2 cycles, the
units will operate simultaneously

Must
Must coordinate with MV circuit
breaker and any downstream
reclosers
Considered in section on
substation protection
Distribution Protection

Not
N t recommended
d d and
d nott
considered here

Recloser-Recloser Coordination
Use time-current curves to
coordinate

Fuse-Recloser Coordination

ELCT 751

Reclosers downstream of fuses


are not common

53

Fixed by design of hydraulic


units: 1
1-2
2 sec
Programmable in electronic units:
2 sec for example

ELCT 751

Distribution Protection

54

Reclosing Interval
Programmable in electronic units
set from instantaneous to 60 sec
instantaneous is usually too fast to
allow temporary faults to clear
2 seconds is a common setting
longer settings, e.g. 5 sec, may aid
coordination with source-side
circuit breakers or fuses
ELCT 751

Distribution Protection

55

57

56

ELCT 751

Distribution Protection

58

Relay completely resets after


each fast (A curve) operation
Calculate total net travel until
lockout:

Disk travel:
Each A clearing: relay disk
0 035/0 60 or 5
0.035/0.60
5.8%
8%
Each B clearing: relay disk
0.20/0.60 or 33.3%
Each 2 sec open time: relay disk
2/30 or -6.7%
Distribution Protection

Distribution Protection

Example (Continued)

Example relay-recloser
coordination

ELCT 751

ELCT 751

Electromechanical time overcurrent


relay: 0.60 second trip delay and
30 sec reset time
Hydraulic recloser on 2A2B
sequence
At fault current: A curve gives
0.035 sec and B curve gives 0.20
sec.

Quick check is to compare relay


time-current curve to a
cumulative recloser time current
curve (e.g., 2A+2B in time)
If check shows miscoordination
possible, perform detailed
calculation
Distribution Protection

Station circuit breaker may be


used, with overcurrent relay
logic
Overcurrent relays tend to
integrate recloser times

Example relay-recloser
coordination

Coordination of recloser with


station circuit breaker

ELCT 751

Coordination of recloser with


station circuit breaker

33.3% - 6.7% + 33.3% = 60% <


100%
Relay contacts do not close
Coordination is correct
59

ELCT 751

Distribution Protection

60

10

Example (Continued)
Repeat for 1 sec reclosing
interval
Now relay does not completely
reset after fast operations
Net total relay travel:

Electronic Devices
Electronically controlled reclosers
have more choices of time-current
curves and reclosing intervals
Electronic overcurrent relays have
more choices of time-current curves
and no disk to reset

5.8-3.3+5.8-3.3+33.3-3.3+33.3 =
68.3% <100%
Coordination is still achieved.
ELCT 751

Distribution Protection

Consult relay manufacturers data to


determine reset time (may be a setting)
61

Sectionalizer Coordination

ELCT 751

Distribution Protection

62

Sectionalizer Application

Does not use time-current curves


Sectionalizer will coordinate with
upstream recloser or circuit breaker
if it is set for fewer counts than the
total number of upstream device
operations
Example: four shot upstream
recloser coordinates with a threeshot downstream sectionalizer

Two sectionalizers may be used


in series if the downstream
device is set to one fewer count
than the upstream device
Recloser-sectionalizer-fuse
coordination:

ELCT 751

ELCT 751

Distribution Protection

63

Sectionalizer Application

sectionalizer counts downstream


fuse blowing
2A2B recloser: fuse blows during
first delayed operation,
sectionalizer arms for final count,
then locks out when fuse blows
Distribution Protection

64

Sectionalizer Application

Recloser-sectionalizer-fuse
coordination:

ELCT 751

Distribution Protection

65

Use 1A3B recloser for 3 shot


sectionalizer with downstream
fuse:
Fuse clears on second recloser
count, sectionalizer does not lock
out when fuse blows
ELCT 751

Distribution Protection

66

11

Effect of Distribution
Automation / Remote Control

Sectionalizer Application
Recloser-sectionalizer-recloser
is tricky:

Distribution automation and


remote control of switches is
mostly outside of our scope

Sectionalizer may count either


recloser
Can work with sectionalizer
voltage restraint to prevent
counting downstream operations
ELCT 751

Distribution Protection

Except as it interacts with


overcurrent protection system
67

ELCT 751

Distribution Protection

68

Load break switch

Effect of Distribution
Automation / Remote Control

CB1

S1

Feeder 1
T12

Consider a typical radial feeder


arrangement
g
with normallyy open
p
tie switches and normally closed
sectionalizing switches
Look at feeder reconfiguration

CB2

NO
Tie

S2
Feeder 2

Normal Operation
ELCT 751

Distribution Protection

CB1

S1

69

Feeder 1
T12

CB2

ELCT 751

Distribution Protection

CB1

NO
Tie

S1
T12

S2

CB2

Feeder 2

Fault at X cleared by station breaker


CB1.
Distribution Protection

NO
Tie

S2

Feeder 2

ELCT 751

70

71

Operator opens S1 then closes T12


ELCT 751

Distribution Protection

72

12

Recloser

Recloser Loop Scheme


Consider a recloser loop scheme:

CB1

Feeder use a sectionalizing recloser


Adjacent feeder backs up to normally
open tie recloser
Fault
l trips
i recloser
l
or station
i breaker
b k
If sectionalizing recloser loses voltage,
it trips after 60 second delay
If tie recloser loses voltage, it closes
after 70 second delay
ELCT 751

Distribution Protection

CB1

R1

73

CB2
C

Feeder 1
T12

CB2

R2

Normal Operation
ELCT 751

Distribution Protection

CB1

NO
Tie

T12

R2

CB2
C

75

Network Systems

R2

60 seconds after R1 loses voltage, it


automatically opens, then after 10
more seconds, T12 closes.
ELCT 751

76

MV Feeders

Network Transformers
Network Protectors

MV feeder circuits are radially


connected to network transformers
Transformer secondaries (LV)
networked
Distribution Protection

Distribution Protection

HV Bus
Substation

Full network distribution systems


are rare, except for secondary
networks (downtown areas of
cities) and spot networks (large
buildings)

ELCT 751

NO
Tie

Feeder 2

Fault at X cleared by station breaker


CB1. R1 and T12 lose voltage.
Distribution Protection

74

R1

Feeder 2

ELCT 751

NO
Tie

Feeder 2

Feeder 1
T12

R1

LV Network

Loads

SECONDARY NETWORK
77

ELCT 751

Distribution Protection

78

13

Network Systems
The secondary and spot network
systems are quite flexible in
operation

MV Feeders
HV Bus
Substation
Network Transformers
Network Protectors and Fuses

SPOT NETWORK

LV Network
Loads

ELCT 751

Distribution Protection

79

If one transformer is out of service,,


the remaining units can supply the
load
If a fault occurs on a primary
feeder, the transformer will tend to
feed it
ELCT 751

ELCT 751

Distribution Protection

81

80

Low-Voltage System
Overcurrent Protection

Network Protector
Network protector will disconnect
the transformer if it back-feeds the
MV system
protector will prevent
p
Network p
transformer from being
reconnected unless power will flow
in proper direction
Fuses are often used on network
systems too

Distribution Protection

Devices used are fuses and air


circuit breakers, including:
Molded-case circuit breakers
Insulated-case
I
l t d
circuit
i it breakers
b k
LV power circuit breakers

Time-current curves are used for


coordination in the same way as
already described.
ELCT 751

Time

Insulated-case circuit breakers

Distribution Protection

82

Typical Low-Voltage
Circuit Breaker TimeCurrent (Electronic Trip)
Long time pickup
Long time dela
delay
Short time pickup
Short time delay
Instantaneous
Current

ELCT 751

Distribution Protection

83

ELCT 751

Distribution Protection

84

14

Time

Time

Long time pickup

Long time delay

Short time delay


similar to long
time delay
Current

Current
85

ELCT 751

Distribution Protection

86

Time

Distribution Protection

Time

ELCT 751

Sh
Short
time pickup
k

Instantaneous
Current
ELCT 751

Distribution Protection

LONG-TIME
PICKUP

Current
87

88

As before, coordination is done


with time-current curves

TIME

In all overcurrent protection the


p
downstream device should trip
and clear the fault
Before the fastest upstream device
begins operation
Before system damage becomes
excessive

SHORT-TIME
PICKUP
SHORT-TIME
DELAY

LONG TIME
LONG-TIME
DELAY
(SHORT-TIME
DELAY SIMILAR)

INSTANTANEOUS

CURRENT

INSTANTANEOUS

ELCT 751

Distribution Protection

Coordination

LONG-TIME
PICKUP

LONG-TIME
DELAY

SHORT-TIME
PICKUP

ELCT 751

Distribution Protection

89

ELCT 751

Distribution Protection

90

15

Coordination

Where to go for more information

As before, coordination is
done with time-current curves

Application and Coordination of

Reclosers, Sectionalizers, and


Fuses, IEEE Tutorial 80EHO157-

Compromise
Compromise is sometimes
required: Main purpose is to
protect system from shortcircuits
ELCT 751

Distribution Protection

8-PWR

Distribution System Protection


Manual, Cooper Power Systems

91

ELCT 751

Distribution Protection

92

Where to go for more information


Manufacturers web sites:
www.abb.com,
www.cooperpower.com,
www ch cutler hammer com
www.ch.cutler-hammer.com,
www.ge.com,
www.sandc.com,
www.siemenstd.com,
www.squared.com
ELCT 751

Distribution Protection

93

16

Você também pode gostar