Mission: To create and develop a safe environment for the sole purpose of providing opportunities
for families to engage in order to heal, re-unite, and to improve the success of the childs transition
back into the community.
Concept: Renovate the current Maluhia cells into a homely environment where families can gather
and communicate with one another. Transform the 3 cells into a Family Room, Dining Room &
Counseling Room.
Design Plan
Family Room: This room will be utilized as an area for the child and their family to gather and
socialize with one another in a comfortable setting. There will also be a kids toy area at the back of
the room for any young toddlers or children to play in while the rest of the family engages. This room
will also serve as an entertainment room for the children as there will be a TV and video game system
available for their use.
Floor Plan for New Family Room
Mural Wall
Toy Box
Side
Table
Side
Table
Couch
Side
Chair
Side
Chair
Coffee Table
Area Rug
Wall mounted TV
Dining Room: The dining room will be just that, a place where the family can all sit down and share a
meal together. There will also be a kids dining area at the back of the room for the younger children to
sit and eat.
Floor Plan for New Dining Room
Kids
Dining
Area
Individual
Dining
Chairs
Dining Table
Bench Seat
Tattoo Wall
Counseling Room: This is a smaller, more intimate space and therefore will serve as a one-on-one
counseling room.
Floor Plan for New Counseling Room
Side Table
Window
Treatment
Ottoman
Chalk Wall
Paint
Area Rug
Door to
remain
Budget
Construction Estimate:
Cost for wood flooring material and labor
Bead Board
Painting
Plumbing
Demo
ONP Project Managing
TOTAL
$21,600
$9,000
$12,000
$6,000
$6,000
$4,875
$59,475
Lighting Estimate:
Replace all interior fluorescent lamps and ballasts including emergency fixtures. Total of 80
light fixtures
All 4 emergency fixtures will be replaced with T8 emergency ballast and T8 cool white lamps
All other 4 fixtures will be replaced with T8 lamps and ballast
Recessed emergency will be replaced with equivalent lamp and ballast
2 fixture will be replaced with T8 emergency ballast and T8 lamp
Subtotal
Tax
TOTAL
$10,289.79
$484.85
$10,774.64
Furniture Estimate:
Living Room Furniture and Kids Toy Area
Dining Room & Kids Dining Furniture and Tattoo Wall Art
Counseling Room Furniture and chalkboard wall paint
TOTAL
$1,913.94
$1,107.99
$1,705.00
$4,726.93