HOJA DE METRADO

ALTERNATIVA N 01
PROYECTO
FECHA

CONSTRUCCION DE ALMACEN PARA LA COMUNIDAD DE SEVITE BAJA,


DISTRITO DE SIVIA - HUANTA - AYACUCHO.

: DICIEMBRE DE 2008

COD.

DESCRIPCION

01
01.01
01.02
01.03

TRABAJOS PRELIMINARES
CARTEL DE IDENTIFICACION DE LA OBRA DE 1.20 X 2.40 m
LIMPIEZA DE TERRENO MANUAL
TRAZO, NIVELES Y REPLANTEO

02
02.01

MOVIMIENTO DE TIERRAS
EXCAVACION DE ZANJAS PARA CIMIENTOS

02.02

EXCAVACIONES DE ZANJAS PARA ZAPATAS

02.03

ELIMINACION MATERIAL EXCEDENTE EN CARRETILLA (50 m)

03
03.01

CONCRETO 1:10 PARA SOLADOS ZAPATA

03.03

CONCRETO 1:8+25% PM PARA SOBRECIMIENTOS

03.05

FALSO PISO DE 4" DE CONCRETO 1:10

04.02.02

04.02.03
04.03
04.03.01

04.03.02

COLUMNAS
CONCRETO f'c=210 kg/cm2 PARA COLUMNAS

m3

16.25

16.25

m3

1.00

71.66

71.66

m3

38.04

m3

0.80
0.80
0.80
0.80
0.80

6.36
4.32
1.92
21.89
3.55

25.00

m3

5.35

m3

71.33

m2

386.34

386.34

m2

13.75

m3

250.00

kg

5.47

m3

1,132.11

kg

87.50

m2

20.40

m3

837.25

kg

51.00

m2

1.00
510.00
510.00

5.88
3.75
3.25
3.05
2.95

0.60
0.60
0.60
0.60
0.60

1.40
1.40
1.40
1.40
1.40

9.87
6.30
2.73
30.74
4.96

25.00

1.00

1.00

0.65

1.00

71.66

1.00

2.00
2.00
1.00
12.00
2.00

6.63
4.50
4.00
3.80
3.70

0.60
0.60
0.60
0.60
0.60

25.00

1.00

1.00

2.00
2.00
1.00
12.00
2.00

6.63
4.50
4.00
3.80
3.70

0.15
0.15
0.15
0.15
0.15

25.00

0.45
0.45
0.45
0.45
0.45

0.89
0.61
0.27
3.08
0.50

0.45
0.45
0.45
0.45
0.45

11.93
8.10
3.60
41.04
6.66

1.00

28.20

13.70

25.00

1.00

1.00

0.55

13.75

25.00
25.00

10.00
25.00

1.00
0.30

0.99
0.02

247.50
3.00

0.25

0.25

3.50

5.47

6.00
38.00
228.00

0.99
0.25
0.02

891.00
213.75
27.36

3.50

87.50

ACERO fy=4200 kg/cm2 GRADO 60


1/2" C-1
1/4"
ALAMBRE 16

25.00
25.00
25.00

6.00
0.90
0.30

ENCOFRADO Y DESENCOFRADO NORMAL EN COLUMNAS

25.00

1.00

2.00
2.00

14.00
28.50

0.40
0.40

0.60
0.60

6.72
13.68

2.00
2.00
2.00
2.00
2.00
2.00

14.20
28.70
2.20
2.20
0.30
0.30

6.00
6.00
93.00
190.00
558.00
1,140.00

0.99
0.99
0.25
0.25
0.02
0.02

168.70
340.96
102.30
209.00
5.36
10.94

ENCOFRADO Y DESENCOFRADO PARA VIGAS DE CIMENTACION RECTA


2.00
2.00

14.00
28.50

0.60
0.60

16.80
34.20

VIGAS DE CIMENTACION
CONCRETO f'c=175 kg/cm2 PARA VIGAS DE CIMENTACION

ACERO fy=4200 kg/cm2 GRADO 60


1/2"
1/4"
ALAMBRE 16

04.03.03

54.60
2.00
2.00
1.00
12.00
2.00

25.00

UNID.
u
m2
m2

17.00
17.00

6.63
4.50
4.00
3.80
3.70

TOTAL
1.00
510.00
510.00

30.00
30.00

ACERO fy=4200 kg/cm2 GRADO 60


Alambre N 16

04.02
04.02.01

PARCIAL

1.00
1.00
1.00

ENCOFRADO Y DESENCOFRADO NORMAL PARA SOBRECIMIENTO HASTA 0.30 m


DE 0.30 A 0.60 M.
4.00
4.00
2.00
24.00
4.00

04
CONCRETO ARMADO
04.01
ZAPATAS
04.01.01
CONCRETO f'c=210 kg/cm2 PARA ZAPATAS
04.01.02

DIMENSIONES
LARGO ANCHO ALTO

CONCRETO SIMPLE
CONCRETO 1:10 +30% P.G. PARA CIMIENTOS CORRIDOS

03.02

03.04

N DE
VECES

HOJA DE METRADO
ALTERNATIVA N 01
PROYECTO
FECHA

CONSTRUCCION DE ALMACEN PARA LA COMUNIDAD DE SEVITE BAJA,


DISTRITO DE SIVIA - HUANTA - AYACUCHO.

: DICIEMBRE DE 2008

COD.
04.04
04.04.01

04.04.02

DESCRIPCION

ACERO fy=4200 kg/cm2 GRADO 60


1/2"

ALAMBRE 16

05
05.01

06.02
07
07.01
07.02

07.03

REVOQUES ENLUCIDOS Y MOLDURAS


TARRAJEO EN INTERIORES Y EXTERIORES ACABADO CON CEME
TARRAJEO DE SUPERFICIE DE COLUMNAS CON CEMENTO-ARENA
PISOS Y PAVIMENTOS
PISO DE CONCRETO E=2" f'c 140 kg/cm2 X 4 cm PULIDO 1:2 X 1 cm

42.50

m2

190.80

m2

381.60

381.60

m2

87.50

87.50

m2

386.34

386.34

m2

95.00

m2

17.60

m2

13.00

m2

60.20

m2

1.75
3.56

2.00
2.00
2.00
2.00
2.00
2.00

14.20
28.70
0.90
0.90
0.30
0.30

4.00
4.00
93.00
190.00
558.00
1,140.00

0.99
0.99
0.25
0.25
0.02
0.02

112.46
227.30
41.85
85.50
5.36
10.94

4.00
4.00

14.00
28.50

0.25
0.25

14.00
28.50

2.00
1.00
2.00
1.00
1.00
1.00
12.00
2.00
-1.00

6.63
6.63
4.50
4.50
4.00
4.00
3.80
3.70
73.20

3.00
2.00
3.00
2.00
3.00
1.00
3.00
3.00
1.00

39.75
13.25
27.00
9.00
12.00
4.00
136.80
22.20
-73.20

2.00

190.80

1.00
87.50

1.00

28.20

2.00
1.00
1.00

30.00
14.00
14.00

1.00
1.00
1.50

60.00
14.00
21.00

2.00
2.00

30.00
14.00

0.20
0.20

12.00
5.60

1.00

4.00

3.25

13.00

2.00
2.00
12.00
2.00

6.63
4.50
3.80
3.70

0.80
0.80
0.80
0.80

10.60
7.20
36.48
5.92

1.00

60.20

60.20

60.20

m2

9.00
22.00
2.00
2.00
2.00
1.00
2.00

1.00
1.00
1.00
1.00
31.00
31.00
31.00

8.26
1.00
1.00

9.00
22.00
2.00
2.00
512.00
31.00
62.00

9.00
22.00
2.00
2.00
512.00
31.00
62.00

u
u
u
u
m2
m
m

1.00

381.60

1.20

457.92

457.92

m2

1.00

66.50

66.50

66.50

m2

4.00

1.00

4.00

4.00

ENCOFRADO Y DESENCOFRADO PARA VEREDAS

09
09.01

CARPINTERIA METALICA
VENTANA METALICA INCLUYE COLOCACION

MALLA METALICA PROTECTORA DE VENTANAS

10
10.01
10.02
10.03
10.04
10.05
10.06
10.07

TECHO CON ESTRUCTURA DE MADERA Y CUBIERTA


TIJERALES T-1
CORREAS DE MADERA TORNILLO DE 2"X3"
ARRIOSTRE DE MADERA TORNILLO DE 1"X3"
FRISO DE MADERA TORNILLO DE 1"X8"
COBERTURA CON CALAMINA GALVANIZADA DE O.80 X 1.80 M
CUMBRERA DE CALAMINA GALVANIZADA
CANALETA DE CALAMINA GALVANIZADA

11
11.01

PINTURA
PINTURA LATEX EN MUROS INTERIORES Y EXTERIORES 2 MANOS

12
12.01

kg

0.25
0.25

VEREDA DE CONCRETO DE 4"

CARPINTERIA DE MADERA
PUERTA DE MADERA APANELADA

11.02

483.42

0.25
0.25

13.70

PINTURA LATEX EN COLUMNAS 2 MANOS


DRENAJE DE AGUAS PLUVIALES
DRENAJE DE AGUAS PLUVIALES CON TUBERIA PVC 3"

UNID.

m3

14.00
28.50

1.00

TOTAL

5.31
2.00
2.00

ALBAILERIA
MURO DE SOGA DE LADRILLO KK

08
08.01

09.02

PARCIAL

ENCOFRADO Y DESENCOFRADO NORMAL EN VIGAS

DESCUENTO VENTANAS
06
06.01

DIMENSIONES
LARGO ANCHO ALTO

VIGAS COLLARIN
CONCRETO EN VIGAS f'c=210 kg/cm2

1/4"

04.04.03

N DE
VECES

HOJA DE METRADO
ALTERNATIVA N 01
PROYECTO
FECHA

CONSTRUCCION DE ALMACEN PARA LA COMUNIDAD DE SEVITE BAJA,


DISTRITO DE SIVIA - HUANTA - AYACUCHO.

: DICIEMBRE DE 2008

COD.

DESCRIPCION

N DE
VECES

13
13.01
13.02
13.03

INSTALACIONES ELECTRICAS
SALIDA DE TECHO C/CABLE AWG TW 2.5 mm (14) + D PVC SAP 19 mm 1.00
SALIDA PARA TOMACORRIENTE BIPOLAR DOBLE CON PVC
1.00
TABLEROS DISTRIBUCION CAJA METALICA CON 12 POLOS
1.00

14
14.01

CONEXION A LA RED EXTERNA, MEDIDORES Y POZA A TIERRA


CONEXION PUESTA A TIERRA

15
15.01

DIMENSIONES
LARGO ANCHO ALTO

PARCIAL

TOTAL

UNID.

12.00
6.00
2.00

12.00
6.00
2.00

12.00
6.00
2.00

pto
pto
pza

1.00

1.00

1.00

1.00

ARTEFACTOS ELECTRICOS
ARTEFACTO FLUORESCENTE DE 32 W

1.00

12.00

12.00

12.00

16
16.01

FLETE
FLETE TERRESTRE

1.00

52,989.44

52,989.44

52,989.44

glb

17
17.01

MITIGACION DE IMPACTO AMBIENTAL


REFORESTACION LATERAL

1.00

1.00

1.00

glb

18
18.01
18.02
18.03

CAPACITACION
FORTALECIMIENTO DE PRODUCTORES AGRICOLAS
RIESGOS DE SALUD
EVENTOS DE CAPACITACION SOBRE ALMACENAJE DE PRODUCTO

1.00
1.00
1.00

1.00
1.00
1.00

1.00
1.00
1.00

glb
glb
glb