Escolar Documentos
Profissional Documentos
Cultura Documentos
In
Bridge Construction
Work Scheduling
Work scheduling is a tool of planning of project, which decide
in advance about what to do and when to do considering how
to do and who is to do .
It is a time phased plan for performing the work necessary to
complete the project
It is a graphical representation of plan which shows the
starting and completion dates of each activity and the
sequential relationship among the various activities
It
Scheduling Tools
Different Scheduling Tools
Bar Chart
Graphical representation of various activities/works with their
starting and completion time and duration.
In bar chart, activities/works are represented by horizontal
bars and the length of bar indicates the time/duration
required for accomplishment of that particular activity/work
3.
Prepare a schedule for the activities involved in detail engineering survey and design
of a bridge using Bar Chart
S.N.
Activities/Works
Time required
(Days)
10
Gological/Goetechnical Investigation
14
Hydrological Study
35
S.N
.
Duration / Time
Activities/Works
Mangsir 2069
1
Gological/Goetechnical
Investigation
Hydrological Study
Paush 2069
Falgun 2069
4
3 days
10 days
4 days
3 days
8 days
Completion of
study for design
14 days
Draft report
submission
5 days
Approval of
report
35 days
9 days
Example 2
S.N.
Prepare bar schedule and resource aggregation chart for the activities
involved in the construction of the two well foundations by using Bar Chart
Activities/Works
Days required
to complete
Labour
the work
Human Resources
Mason
Carpenter
Bar
bender
Welder
Diversion of stream
10
11
12
13
14
S.N.
Activities/Works
Diversion of stream
Construction of platform of
well
10
11
12
Placement of reinforcement
for well cap
13
14
Duration (Days)
1
9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
Activities/Works
Diversion of stream
Construction of platform of
well
Labour
Mason
Carpenter
Duration (Days)
1
9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
4 4 7 3 5 5 4 4 6 2 5 1 1 1 0 0 0 2 2 2 2 2 2 4 4 6 2 4
1 1 1 1
1 1 1 1
Bar bender
1 1 1 1 1 1 1 1 1 1 1 1
Welder
1 1 1 1
2
1 1 1 1
1 1 1 1
Initial event should be one in network diagram and should contain only
out going arrow.
Network path shall not be turned back. Event should not be dependent
on the succeeding events.
Followed
by
Days require
for the
activity
A Drive piles
20
C,E
D,F
F,H
C,E
G,I
D,F
F,H
G,I
Activity
Network diagram
4 days
20 days
2 days
4 days
4 days
C
2 days
2 days
2 days D
2 days
2 days
10
11