Construction
New
Add/Reno
New
New
New
New
New
Add/Reno
New
New
New
New
New
GSF
95,726
227,087
65,679
83,256
132,539
74,056
74,960
52,920
103,650
63,377
132,841
70,701
111,256
Cost/sq ft
$368
$406
$467
$422
$365
$402
$350
$344
$327
$340
$344
$372
$418
$343
$348
Enrollment
545
1010
365
395
985
400
465
270
690
270
800
410
600
Sq ft/child
175
166
210
135
185
161
150
234
166
172
185
177
$53,060,000
$432
750
164
50% Reimbursement
Includes Soft Costs
$33,161,999
$389
750
168
$30,617,963
750
164
$33,588,083
750
168
$32,877,943
Option W1 K-6
Reno
82,000
$27,729,000
$338
360
renovate WW, water isssues can be remedied but students would need to be housed elsewhere during reno construction
building would be gutted and everything new inside with a 50 year life expectancy
228
$17,331,000
$52,604,709
$429
All options above are for the grade configuarations of 2-6 and PreK-1 in separate buildings,
ASC vote on 1/19/16, CF would need renovation for Pre-K - Grade 1, not budgeted
m. theilman 1/21/16
Revised
Construction Cost
Soft Cost
Total Cost
Option W7 2-6
New
includes Swing Space, built behind WW
122,714
$53,060,000
$13,264,800
$66,323,999
50% Reimbursement
Construction &
Soft Costs
$33,161,999
126,000
$48,988,741
$12,247,185
$61,235,927
$30,617,963
122,714
$53,740,933
$13,435,233
$67,176,167
$33,588,083
122,714
$52,604,709
$13,151,177
$65,755,887
$32,877,943
$27,729,000
$6,932,048
$34,660,215
$17,331,000
Option
Revised
82,000