Activity Name

Activity Duration

Start Date

Excavation works

30

1 January 2013

Plain concreter for foundation

10

1 February 2013

RC foundation

15

12 February 2013

columns necks

10

28 February 2013

Waterproofing

17 March 2013

Filling

10

22 March 2013

slab on grade

10

2 April 2013

ground floor columns

13 April 2013

ground floor slab

15

19 April 2013

10

masonry works

10

19 May 2013

11

plaster works

30 May 2013

12

floors ceramic

7 June 2013

13

walls ceramic

15 June 2013

14

painting works

15

23 June 2013

Finish Date

Lag

31 January 2013
11 February 2013
27 February 2013
10 March 2013
21 March 2013

1 April 2013
12 April 2013
18 April 2013
4 May 2013
29 May 2013
6 June 2013
14 June 2013
22 June 2013
8 July 2013

14