Aslamolakum
Plz find below reply from SEC-ISD for further
action.
Regards,
Mohammed Naveed
Transmission Engineer A
Civil and Electromechanical project div woa
-
Project Department - WOA
: MNaveed@ngrid.sa
: +9661 26516467 EXT:109
: +966 542213797
: +9661 26537362
Dear all,
Ok, materials are approved
Regards,
: MFAlShehri@se.com.sa
: +9661 26537541
Aslamoalakum
We are still waiting for the reply as the installation
work has been held up at the site.
Regards,
Mohammed Naveed
Transmission Engineer A
Civil and Electromechanical project div woa
-
Project Department - WOA
: MNaveed@ngrid.sa
: +9661 26516467 EXT:109
: +966 542213797
: +9661 26537362
Aslamoalakum
Plz find below reply from MS AECC for reivew and
approval.
Regards,
Mohammed Naveed
Transmission Engineer A
Civil and Electromechanical project div woa
-
Project Department - WOA
: MNaveed@ngrid.sa
: +9661 26516467 EXT:109
: +966 542213797
: +9661 26537362
Dear sir,
As per the below mail Mechanical manual realise available in the fm-200 system in above the
cylinder.
This for your information and please give approval without further delay.
Thanks,
Best Regards,
Musharrif Ali Khan
Mechanical Engineer
Advanced Energy Company
Aslamoalakum
Plz reply to below email from SEC-ISD.
Regards,
Mohammed Naveed
Transmission Engineer A
Civil and Electromechanical project div woa
-
Project Department - WOA
: MNaveed@ngrid.sa
: +9661 26516467 EXT:109
: +966 542213797
: +9661 26537362
Dear all,
Is there mechanical release for FM-200 System? Where is the
location of it?
then ISD will decide for approval or not.
Metaeb Fadel ALShehri
Loss Prevention Engineer A
Safety and Environmental Prevetnion div.
: +9661 26537302
: +966 555601070
: MFAlShehri@se.com.sa
: +9661 26537541
Aslamoalakum
As per discussion plz reply to below request.
Regards,
Mohammed Naveed
Transmission Engineer A
Civil and Electromechanical project div woa
-
Project Department - WOA
: MNaveed@ngrid.sa
: +9661 26516467 EXT:109
: +966 542213797
: +9661 26537362
Aslamolakum
Still waiting.
Regards,
Mohammed Naveed
Transmission Engineer A
Civil and Electromechanical project div woa
-
Project Department - WOA
: MNaveed@ngrid.sa
: +9661 26516467 EXT:109
: +966 542213797
: +9661 26537362
Aslamoalakum
With reference to our meeting regarding UL listing
of FM 200 accessories would you plz inform about
the acceptance of the same so that site work can
be started.
Regards,
Mohammed Naveed
Transmission Engineer A
Civil and Electromechanical project div woa
-
Project Department - WOA
: MNaveed@ngrid.sa
: +9661 26516467 EXT:109
: +966 542213797
: +9661 26537362
Dear sir,
Kindly be informed that as per the meeting our subcontractor and SEC-ISD regarding the
approval of Fm -200 accessories in last Sunday we will submit all UL-LISTED documents and
accessories to SEC-ISD.
But till now didn't receive any confirmation your side.
Please urgently confirm your side to start installation and complete our work.
This is for your information.
Thanks,
Best Regards,
Musharrif Ali Khan
Mechanical Engineer