Escolar Documentos
Profissional Documentos
Cultura Documentos
Abstract
Underbalanced Drilling is the natural and inevitable
technological progression of horizontal drilling developed in
the United States Austin Chalk formation, primarily for field
re-development and now extended to new reservoirs where
impairment is a key issue.
Horizontal drilling greatly improved recovery and productivity
rates, particularly in redevelopment of existing and often
pressure depleted reservoirs, but still encountered many of the
drilling problems associated with conventional directionally
drilled wells. In the case of mud losses, impairment and
formation damage, the problems increased due to the wellbore
being open for much longer and of course having much greater
length through the reservoir section. Operators around the
world quickly saw the advantages of horizontal drilling, which
rapidly became a standard field development technique,
onshore and offshore where the geology and reservoir were
compatible with this method of development. The same now
applies to underbalanced drilling. The advantages are quickly
being seen and the technology employed where the geology
and reservoir are suitable.
The majority of hydrocarbons being exploited today are found
in existing fields or in complex and lower quality reservoirs.
This is where underbalanced drilling technology can improve
recovery and in some cases reduce development costs.
Development of UBD Technology Internationally
The two first major onshore underbalanced drilling projects in
Europe took place in Germany, beginning in 1995 and
continuing into 1996. Both of these projects involved the
low head or reduced overbalanced drilling of pressure
depleted reservoirs which were to be utilised for gas storage,
the operators being BEB and RWE-DEA. Due to the very low
reservoir pressure, in the case of the RWE-DEA project, foamdrilling techniques were employed. The Ulsen reservoir
drilled by BEB had a higher reservoir pressure enabling the
drilling to be performed with KCl water and nitrogen. Both
projects successfully achieved the technical objectives set out
at the project inception and would have experienced extremely
difficult drilling problems if they had been drilled
conventionally.
These projects were a milestone for Europe, paving the way to
the move offshore into the North Sea. The technology was
slowly gaining acceptance so it could be successfully and
safely deployed in the applications required both onshore and
offshore. A key factor in this was the approval given by the
Regulatory Authorities, albeit initially in the form of reduced
overbalanced drilling, rather than full underbalance.
By 1996 offshore coiled tubing UBD projects were under trial
with success - offshore Denmark by Maersk and by NAM
onshore in the Netherlands. Other smaller projects were
executed by Pentex Oil and Candecca Resources onshore UK.
A four well UBD programme was executed by WAPET in
Australia using a conventional rig, jointed pipe and a rotating
BOP, (1995).
The major breakthroughs came in 1997, firstly with the Shell
project offshore in the Southern North Sea in the Leman gas
field. This project was a re-entry in the Leman field of an
existing well drilled low head rather than fully
underbalanced. The success of the project, compared with the
results of conventional drilling of the same pressure depleted
formation, in another well, gave Shell encouragement to
continue the trial of UBD technology on a further programme
of horizontal wells in tight gas sands which are fully
pressured. The programme is ongoing today with
considerable technical success and technological achievement
in the advancement of underbalanced operations.
The second major project was the Arun Gas Field redevelopment by Mobil in North Sumatra, Indonesia. This
project faced many technical challenges with low bottom hole
pressures, and abnormally high temperatures. The project has
been very successful, and continues today.
Other operators also conducted projects in Argentina and
onshore in Spain, making 1997 an important year for the
development of the technology.
BEN GEDGE
SPE/IADC 52833
SPE/IADC 52833
Coiled Tubing units have performed tasks on live wells for the
last 20 years as have snubbing units for the last 60 years.
Air Drilling, which has been used since the 1950s has
employed very effectively many of the principles now
incorporated into underbalanced drilling.
1.
4.
2.
3.
5.
6.
Heavy Slips
Traveling Plate
Traveling Slips
Stationary Slips
Annular BOP
Hydraulic Cylinders
Equalizing Spool
Bleed Valves
Single Gate Ram BOP
SPE/IADC 52833
Kelly Drive
Assembly
Inner Packer
Outer Packer
Bearing
Hydraulic Fluid Inlet
Surge
Bottle
Seal
Outlet Flange
Bottom Flange
BEN GEDGE
SPE/IADC 52833
Flare Knockout
Vertical Four
Phase Separators
Pressurized Lab
Solids Transfer
Control Manifold
SPE/IADC 52833
Modules Include:
Separator (PT-20)
Fluid out (PM1)
Metering (PM7)
Divertor Manifold
Choke Manifold
Slurry Pump (on skid base)
BEN GEDGE
SPE/IADC 52833
Northlands
Separation
System
Calibrated
Site
Glasses
Dual Pressure Relief
Gas Measurement
Water Dump Line
SPE/IADC 52833
Wellsite Fluid
Storage
Northlands
Separation
System
Natural Gas Supply
Primary Choke Manifold
RBOPTM
Horizontal Separator
2nd Flow Manifold
Quick Bleed
Power Supply
10
BEN GEDGE
SPE/IADC 52833
***
*
**
**
**
**
*
**
SPE/IADC 52833
11
Ben Gedge
Northland Energy Services