Escolar Documentos
Profissional Documentos
Cultura Documentos
Description:
3 D dimension of this part is 160.58mmX86.63mmX53.49 mm
Volume of this part is 35.22 cm^3
To be sure that the design reasonable and injection molding feasible, we used Moldflow
MPI6.1 to analyze
Slide 1
Confidential
Material Property:
The material is specified as GE cycolac C6200 by customer, it can be selected in moldflow
material database directly, property of the material is as below.
1. Melt Density
0.98129 g/cm^3
2. Solid Density 1.1161 g/cm^3
3. Recommended Mold Temperature
4. Recommended Melt Temperature
5. Absolute Max. Melt Temperature
6. Ejection Temperature
248
285
60
82
40000 1/s
0.4 Mpa
PVT graph
Viscosity graph
Confidential
Slide 2
Mesh Statistics:
Fusion mesh will be used according to shape of the part ,the Match percentage is 91.8% and
the Reciprocal percentage is 90.8%, so the mesh can completely meet the requirement of
cool + flow + warp analyze .
Thickness of the mesh is mostly equal to the wall thickness of the part, in order to ensure the
accuracy of analysis results.
Slide 3
Confidential
4+1taper
Submarine gate:
1.0
Cold runner:5
gate location result
Confidential
Slide 4
Left view
Top view
Slide 5
Confidential
Cooling channel
8
Front view
Work piece
Confidential
Slide 6
Process condition :
Note: It is recommended that a molding window analysis should be run before process setting, in order to
determine the optimum fill time. The optimum fill time zone is where the injection pressure and maximum shear
rate and maximum shear stress are lowest together, green zone in pictures as follows.
Slide 7
Confidential
pressureMpa
65
65
0
Water
40
Water
60
Water
60
Confidential
Slide 8
Results explain :
Fill time
Confidential
Slide 9
Note:
These pictures showed the filling step, the parts will be filled entirety.
Confidential
Slide 10
Animation
Confidential
Slide 11
Note:
Temperature at flow front varied from 259.9 to 268.8 , and not be out of the materials melt temperature
range (248 ~285 ).
Confidential
Slide 12
Weld line
Warning:
Weld lines will be occured at area marked by red arrow, change the gate location if necessary.
Confidential
Air
Slide 13
traps
Note:
Most of air traps will be occured at the top of rib, it is necessary to vent at that area to avoid burning or
short shot .
Confidential
Slide 14
Pressure distribution
Note :
Pressure in cavity is not uniform, maximum pressure is 44.39Mpa, pressure lost in runner system is about 20.6Mpa.
Confidential
Slide 15
Confidential
Slide 16
Pressure (Animation)
Note:
Pressure is measured at start of runner system, pressure in barrel is not taken account
Confidential
Slide 17
Clamp force
Note:
Maximum clamp force is 30.70 tonne, so injection machine of 120 tonnage is adequate.
Confidential
Slide 18
Temperature, mold
Note:
Temperature of mold surface is not uniform, there are two hot spots on the part, so it will need an excess cooling
time to cool the part, then cycle time will be longer.
Confidential
Slide 19
Temperature, part
Note:
Temperature of part surface is not uniform, but under the transition temperature(144 ) entirely.
Confidential
Slide 20
animation
Note:
Gates had been frozen at 8.7s, so 7s packing time is adequate.
Slide 21
Confidential
Sink index
Note:
Volumetric shrinkage at ejection and Sink index are uniform at most
most of the part, but there are larger
value at two area marked by red arrow, sink mark will be arise possibly.
possibly.
Confidential
Slide 22
Confidential
Slide 23
Confidential
Slide 24
Confidential
Slide 25
Note:
To view the exact value of warpage, we define a datum plane to measure,
the results are relative to datum plane.
Datum
plane
Detail view
Confidential
Slide 26
Confidential
Slide 27
Note:
To view the exact value of warpage, we define a datum plane to measure,
the results are relative to datum plane.
Datum plane
Detail view
Confidential
Slide 28
the quality, change the gate location to avoid or improve weld lines if necessary ;
Warpage value is high, Diff Shrinkage are the primary cause of warpage.
Slide 29
Confidential
Case2 (revised):
Mold type: 2 plates, submarine gate, cav1*1, moldbase 3035
Runner system and cooling circuit will be determined by moldflow engineer
Note: change the gate location to avoid or improve weld lines
Original case
Revised case
Confidential
Slide 30
Results compare :
Fill time
Confidential
Slide 31
Note:
These pictures showed the filling step, the parts will be filled entirety.
Confidential
Slide 32
Animation
Confidential
Slide 33
Weld line
Note:
Weld lines move to corner of the part after gate location had been changed
Confidential
Slide 34
Pressure distribution
Note :
Pressure is little high than original case.
Confidential
Slide 35
Confidential
Slide 36
Pressure (Animation)
Sink index
Note:
Volumetric shrinkage at ejection and Sink index are uniform at most
most of the part, but there are larger
value at two area marked by red arrow, sink mark will get worse.
Confidential
Slide 37
Confidential
Slide 38
Confidential
Slide 39
Confidential
Slide 40
Confidential
Slide 41
END
Confidential
Slide 42