Você está na página 1de 7

Intermediate school

Activity ID

Activity Name

Intermediate school

Executive Summary
Ex10

Letter of Acceptance

Ex30

Project commencement date

Ex20
Ex40

Contract Signature

right of access to site

External Works and Mobilization


Ext10

Cleaning and Removing obesticals

Ext20

Fixing the fence

Ext40

Surveying

Ext30

Erection of site offices

Sub structure Works


Excavation
Sub10

Footings

Excavations

Sub20

Shuttering plain concrete footing

Sub40

Curing of Plane Concrete Footings

Sub30
Sub50
Sub60
Sub70
Sub80
Sub90

Sub100

Ground Beams

Placing plain concrete footing

Deshuttering plain concrete footing


Shuttering RC footing

Steel fixing RC footing


Placing RC footing

Curing of RC Footings

Deshuttering RC footing

Sub110

Shuttering Ground Beams

Sub130

Placing Ground Beams

Sub120
Sub140
Sub150

Steel Fixing of Ground Beams


Curing of Ground Beams

Deshuttering Ground Beams

Original Start
Duration

Classic Schedule Layout


Finish
Predecessors

422 15-Apr-16

28-Nov-17

0 15-Apr-16

15-Apr-16

0 15-Apr-16
0 15-Apr-16
0 15-Apr-16
0 15-Apr-16
4 15-Apr-16
2 15-Apr-16

15-Apr-16

Ex10

15-Apr-16

Ex30

20-Apr-16

Ex20

18-Apr-16

Ex40

1 19-Apr-16

19-Apr-16

Ext10

1 19-Apr-16

19-Apr-16

Ext10

2 19-Apr-16
63 21-Apr-16
10 21-Apr-16
10 21-Apr-16

20-Apr-16
18-Jul-16

04-May-16
04-May-16

1 13-May-16
5 16-May-16
6 23-May-16
3 31-May-16
3 03-Jun-16
2 08-Jun-16

13 16-May-16
3 16-May-16
5 19-May-16
1 26-May-16
3 27-May-16
1 01-Jun-16

07-Jun-16
09-Jun-16
01-Jun-16

Sub20
Sub40
Sub50
Sub60
Sub70
Sub80
Sub90

Page 1 of 7

JD0.00

JD650.00

JD0.00

JD500.00

0
0
0
0

JD150.00

JD2,000.00

JD2,200.00

JD0.00

JD5,980.00

JD200.00
JD200.00

JD2,460.00

JD200.00

Sub40

JD0.00

JD0.00

JD39,240.00 JD45,220.00
JD2,000.00

JD2,200.00

JD20,500.00 JD22,960.00
JD200.00

JD400.00

JD200.00

JD2,700.00

JD2,900.00

Sub60, Sub110

JD100.00

JD0.00

JD100.00

Sub80

JD810.00

Sub70

JD10.00

JD100.00

JD110.00

JD630.00

JD1,200.00

JD1,830.00

JD180.00

JD11,400.00

JD11,580.00

Sub160

JD300.00

JD0.00

JD300.00

JD115.00

Sub90

Sub100

JD30.00

JD4,750.00

JD150.00

JD5,560.00

JD180.00

0
0
0
0
0
0
0
0
0
0
0
0
0
0

JD940.00

JD5,875.00

JD6,815.00

16

Sub130

JD675.00

JD2,100.00

JD2,775.00

16

Sub150

JD30.00

JD150.00

JD180.00

Sub140

Sub140

JD500.00

JD0.00

JD0.00

Sub120
Sub130

JD650.00

JD0.00

JD150.00

26-May-16
01-Jun-16

JD0.00

Sub10

Sub120

Sub110

JD0.00

Sub50

31-May-16

JD0.00

JD0.00

JD0.00

18-May-16
25-May-16

JD0.00

JD0.00

JD0.00

Sub50

02-Jun-16

JD0.00

JD0.00

Sub10

Sub30

30-May-16

JD0.00

Sub10

12-May-16
20-May-16

JD0.00

JD0.00

Ext20, Ext30,
Ext40

Sub30

13-May-16

JD0.00

JD0.00

Ext10

Sub10

10-May-16

2 11-May-16

Ex40

06-May-16

2 09-May-16

Budgeted
Material Cost

JD0.00

Ex30

Sub20

09-Jun-16

2 05-May-16

Ext10

Ex20

Ext40, Ext30,
Ext20

26 05-May-16

29-Apr-16 19:53
Budgeted Total
Total Cost Float

Budgeted
Labor Cost

JD153,900.00 JD640,664.90 JD794,564.90

15-Apr-16

15-Apr-16

Successors

Sub210

JD50.00

JD445.00

JD3,180.00

JD70.00
TASK filter: All Activities

JD0.00

JD560.00

JD3,230.00

JD70.00

16
16
16
16

Oracle Corporation

Intermediate school
Activity ID

Column Necks

Activity Name

Sub160

Shuttering Columns Neck

Sub180

Placing Columns Neck

Sub170
Sub190
Sub200

Steel Fixing Columns Neck


Curing Columns Neck

Deshuttering Columns Neck

Isolation and Backfilling


Sub210
Sub220

Slab On Grade

Isolation

Backfilling

Sub230

Shuttering Slab on Grade formwork

Sub250

Placing Slab on grade Concrete

Sub240
Sub260
Sub270

Steel Fixing Slab on Grade


Curing Slab on Grade

Deshuttering Slab on grade Formwork

Super Structure Works


Ground Floor Works

Concrete Works
Columns
Grd.Col10 Shuttering columns

Grd.Col20 Steel fixing columns

Grd.Col30 Placing RC columns

Grd.Col40 Curing RC Columns

Grd.Col50 Deshuttering columns


Stairs
Grd.St10
Grd.St20
Grd.St30
Grd.St40
Grd.St50

Slab

Shuttering Stairs Formworks

Steel Fixing Stairs Formworks


Placing Stairs Formworks
Curing Stairs Formworks

Deshuttering Stairs Formworks

Original Start
Duration

Classic Schedule Layout


Finish
Predecessors

10 10-Jun-16

23-Jun-16

1 15-Jun-16

15-Jun-16

3 10-Jun-16
1 16-Jun-16
3 17-Jun-16
2 22-Jun-16
5 24-Jun-16
1 24-Jun-16
4 27-Jun-16

12 01-Jul-16
1 01-Jul-16
3 04-Jul-16
2 07-Jul-16
5 11-Jul-16

1 18-Jul-16

355 19-Jul-16
125 19-Jul-16
73 19-Jul-16
27 19-Jul-16
10 19-Jul-16

8 02-Aug-16
1 12-Aug-16
3 15-Aug-16
5 18-Aug-16

Successors

14-Jun-16

Sub100

Sub170

16-Jun-16

Sub170

Sub190

21-Jun-16
23-Jun-16
30-Jun-16
24-Jun-16
30-Jun-16
18-Jul-16

Sub160
Sub180
Sub190
Sub150, Sub200
Sub210

Sub180
Sub200
Sub210
Sub220
Sub230

27-Nov-17

JD500.00

JD30.00

JD150.00

JD150.00

JD0.00

JD150.00

JD525.00

JD100.00

JD475.00

JD50.00

JD50.00

JD540.00
JD180.00
JD150.00
JD675.00
JD100.00
JD575.00

JD50.00

JD200.00

JD250.00

Grd.Col10

JD30.00

JD100.00

JD60.00

JD6,000.00

JD20.00

JD0.00

JD90.00

JD6,100.00

JD20.00

JD147,270.00 JD601,424.90 JD748,694.90


JD30,180.00 JD120,415.00 JD150,595.00

Sub270

Grd.Col20

JD16,400.00
JD4,813.00
JD1,470.00

12-Aug-16

Grd.Col20

Grd.Col40

JD40.00

24-Aug-16

JD40.00

27-Oct-16
24-Aug-16
01-Aug-16

17-Aug-16

JD380.00

Sub270

10-Jan-17

11-Aug-16

JD300.00

JD80.00

JD4,250.00

Sub260

Sub260

JD610.00

JD2,750.00

Sub240

18-Jul-16

JD1,860.00

JD1,500.00

08-Jul-16

Sub250

JD380.00

JD1,330.00

Sub250

Sub240

15-Jul-16

JD230.00

JD530.00

29-Apr-16 19:53
Budgeted Total
Total Cost Float

JD9,010.00 JD10,710.00

Sub220
Sub230

Budgeted
Material Cost

JD1,700.00

01-Jul-16
06-Jul-16

Budgeted
Labor Cost

Grd.Col10
Grd.Col30
Grd.Col40

Grd.Col30
Grd.Col50
Grd.St10,
Grd.Sb10,
Grd.Bm10

JD2,800.00
JD3.00

JD46,888.00 JD63,288.00
JD11,450.00 JD16,263.00
JD2,400.00
JD3,870.00
JD5,300.00

JD8,100.00

JD150.00

JD153.00

JD3,600.00

JD500.00

JD0.00

JD3,640.00

JD500.00

0
0
0
0
0
0
0
0
0
0
0
0
0
0

227

0
0
0
0
0
0
0

17 25-Aug-16
2 25-Aug-16

16-Sep-16
26-Aug-16

Grd.Col50

Grd.St20

JD3,215.00
JD75.00

JD4,626.00
JD76.00

JD7,841.00
JD151.00

29
29

4 05-Sep-16

08-Sep-16

Grd.St20

Grd.St40

JD440.00

JD2,100.00

JD2,540.00

29

5 29-Aug-16
4 09-Sep-16
2 15-Sep-16

46 25-Aug-16

02-Sep-16
14-Sep-16
16-Sep-16
27-Oct-16

Page 2 of 7

Grd.St10
Grd.St30
Grd.St40

Grd.St30
Grd.St50

Grd.Prt10

JD2,600.00

JD40.00
JD60.00

JD4,186.00

JD2,350.00

JD100.00
JD0.00

JD4,950.00

JD140.00
JD60.00

JD15,406.00 JD19,592.00

TASK filter: All Activities

29
29
29
0

Oracle Corporation

Intermediate school
Activity ID

Activity Name

Grd.Sb10

Shuttering slab

Grd.Sb30

Placing RC slab

Grd.Sb20
Grd.Sb40
Grd.Sb50

Steel fixing slab

Curing Ground Floor Slab


Deshuttering slab

Original Start
Duration

Classic Schedule Layout


Finish
Predecessors

12 25-Aug-16

09-Sep-16

Grd.Col50

Grd.Sb20

3 28-Sep-16

30-Sep-16

Grd.Sb20

Grd.Sb40

12 12-Sep-16
14 03-Oct-16
5 21-Oct-16

Floor Beams
Grd.Bm10 Shuttering Ground Floor Beams

46 25-Aug-16
12 25-Aug-16

Grd.Bm30 Placing Ground Floor Beams

3 28-Sep-16

Grd.Bm20 Steel Fixing of Ground Floor Beams

12 12-Sep-16

Grd.Bm40 Curing Ground Floor Beams

14 03-Oct-16

Finishing Works
Grd.Fin10
Preliminary carpentrary work

52 28-Oct-16
3 17-Nov-16

Grd.Bm50 Deshuttering Ground Floor Beams

5 21-Oct-16

20-Oct-16
27-Oct-16

27-Oct-16
09-Sep-16
27-Sep-16
30-Sep-16
20-Oct-16
27-Oct-16

10-Jan-17
21-Nov-16

Grd.Sb30
Grd.Sb40

Grd.Bm30
Grd.Bm40

Windows

2 04-Jan-17

05-Jan-17

Grd.Fin60

Grd.Fin80

Finishing Carpentary work

2 06-Jan-17

09-Jan-17

Grd.Fin70

Grd.Fin110

Ground Floor Completion

0 10-Jan-17

10-Jan-17

Grd.Fin80,
Grd.Fin90

Grd.Prt20

First Floor Works

Insulations

2 15-Nov-16

16-Nov-16

137 28-Oct-16

09-May-17
Page 3 of 7

JD50.00

Grd.Prt10

JD200.00

JD1,800.00

Grd.Fin70

16-Nov-16
14-Nov-16

Grd.Bm50

Grd.Fin40

15 14-Dec-16

14 28-Oct-16
12 28-Oct-16

JD3,000.00

Grd.Fin10,
Grd.Fin20

Painting

Brick works

Grd.Bm30

Grd.Fin30

Grd.Fin40

Partions
Grd.Prt10

JD200.00

Grd.Prt20

13-Dec-16

09-Jan-17

JD50.00

Grd.Prt10

JD13,780.00
JD200.00

5 07-Dec-16

2 06-Jan-17

Grd.Sb50

JD90.00

Plastering Smooth Coat

Finishing electrical work

JD90.00

Grd.Bm40

Grd.Fin50

Grd.Fin90

JD6,000.00

Grd.Bm20

Grd.Bm10

06-Dec-16
03-Jan-17

JD3,000.00

JD846.00

Grd.Sb30

Grd.Bm20

5 30-Nov-16

Grd.Fin60

Budgeted
Material Cost

Grd.Col50

Plastering Splach and rough coat

29-Nov-16

Budgeted
Labor Cost

JD4,186.00
JD846.00

Grd.Fin40

4 24-Nov-16

23-Nov-16

Grd.Sb10

Preliminary electrical work


Floor Tiling

5 17-Nov-16

27-Sep-16

Grd.Fin20
Grd.Fin30

Successors

Grd.Prt20

Grd.Fin30

Grd.Fin40,
Grd.Fin50

Grd.Fin70

Grd.St50,
Grd.Sb50,
Grd.Bm50
Grd.Prt10

Grd.Fin30

JD2,000.00

29-Apr-16 19:53
Budgeted Total
Total Cost Float

JD2,056.00

JD2,902.00

JD7,200.00

JD7,290.00

JD150.00
JD0.00

JD9,000.00
JD200.00
JD200.00

JD15,406.00 JD19,592.00
JD2,056.00
JD2,902.00
JD6,000.00

JD9,000.00

JD150.00

JD200.00

JD7,200.00
JD0.00

JD7,290.00

JD200.00

0
0
0
0
0
0
0
0
0

JD73,527.00 JD87,307.00
JD4,800.00
JD5,000.00

227
229

JD31,500.00 JD33,300.00

227

JD8,000.00 JD10,000.00

227

Grd.Fin60,
Grd.Fin50

JD900.00

JD2,691.00

JD3,591.00

227

Grd.Fin70

JD900.00

JD3,060.00

JD2,691.00

JD3,591.00

227

Grd.Fin80,
Grd.Fin90

JD200.00

JD6,600.00

JD6,800.00

227

Grd.Fin110

JD200.00

JD2,000.00

JD0.00

JD5,000.00

JD200.00

JD7,000.00

227

JD0.00

227

JD2,520.00
JD2,520.00

JD6,860.00
JD6,860.00

JD9,380.00
JD9,380.00

227
0

JD0.00

JD0.00

JD0.00

227

JD34,990.00 JD141,278.90 JD176,268.90

142

Grd.Fin60

Grd.Fin110
P.D10, P.D20,
P.D30, R.W10
Grd.Prt20,
Fir.Col10

Grd.Fin10,
Grd.Fin20

JD0.00

JD5,385.00

JD0.00

TASK filter: All Activities

JD8,445.00

227

227

Oracle Corporation

Intermediate school
Activity ID

Activity Name

Concrete Works
Columns
Fir.Col10
Shuttering columns
Fir.Col20

Steel fixing columns

Fir.Col40

Curing Rc Columns

Fir.Col30
Fir.Col50
Stairs
Fir.St10
Fir.St20
Fir.St30
Fir.St40
Fir.St50

Placing RC columns
Deshuttering columns

JD3,870.00

JD100.00

JD130.00

Fir.Col20

1 15-Nov-16

15-Nov-16

Fir.Col20

Fir.Col40

JD40.00

3 16-Nov-16
2 21-Nov-16

14-Nov-16
18-Nov-16
22-Nov-16

Fir.Col10
Fir.Col30
Fir.Col40

Fir.Col30
Fir.Col50

Fir.St10,
Fir.S&B10

JD30.00

JD51,330.00 JD67,740.00
JD7,440.00
JD8,750.00
JD2,030.00
JD2,330.00
JD2,280.00

JD100.00

JD0.00

JD2,320.00

JD100.00

0
0
0
0
0
0
0

JD1,580.00
JD100.00

JD1,970.00
JD113.00

JD3,550.00
JD213.00

44
44

Placing Stairs

1 30-Nov-16

30-Nov-16

Fir.St20

Fir.St40

JD220.00

JD807.00

JD1,027.00

44

Steel Fixing Stairs


Curing Stairs

Deshuttering Stairs

Placing RC slab and beams


Deshuttering slab and beams

Finishing Works
Fir.Fin20
Preliminary carpentrary work

3 25-Nov-16
2 01-Dec-16
1 05-Dec-16

53 23-Nov-16
11 23-Nov-16
21 08-Dec-16
2 06-Jan-17

14 10-Jan-17
5 30-Jan-17

66 06-Feb-17
2 20-Feb-17

02-Dec-16
05-Dec-16
03-Feb-17
07-Dec-16
05-Jan-17
09-Jan-17
27-Jan-17

03-Feb-17

09-May-17
21-Feb-17

Fir.St30
Fir.St40

JD10,380.00 JD10,500.00

Fir.S&B30
Fir.S&B40

JD200.00

0
0
0

JD1,800.00

JD30,215.00 JD32,015.00

142

Fir.Fin70

Page 4 of 7

JD0.00

JD200.00

Fir.Fin20, Fir.Fin30 Fir.Fin50

04-May-17
08-May-17

JD200.00

JD150.00

0
0

142
145

2 03-May-17

08-May-17

Fir.Prt10

JD50.00

JD24,100.00 JD36,700.00

44

JD89,948.90 JD108,528.90
JD3,500.00
JD3,700.00

Windows

2 05-May-17

Fir.S&B50

JD12,600.00

44

JD18,580.00
JD200.00

Fir.Fin80

2 05-May-17

Fir.S&B30

44

Fir.Fin40

Fir.Prt20

Fir.Fin50

Finishing electrical work

JD70.00

JD120.00

03-Apr-17

Finishing Carpentary work

JD0.00

JD70.00

Fir.S&B40

10 21-Mar-17

02-May-17

JD70.00

JD50.00

Fir.S&B20

Fir.S&B10

Plastering Smooth Coat

21 04-Apr-17

JD20.00

JD2,170.00

JD41,920.00 JD55,440.00
JD7,290.00
JD7,840.00

Fir.Fin60

Painting

Fir.Prt10

JD1,000.00

JD13,520.00
JD550.00

10 07-Mar-17

20-Mar-17

Fir.St50

JD1,170.00

Fir.S&B20

Plastering Splach and rough coat

06-Mar-17

Fir.St30

Fir.Col50

Fir.Fin50

6 27-Feb-17

24-Feb-17

Fir.St10

Preliminary electrical work


Floor Tiling

5 20-Feb-17

29-Nov-16

Fir.Fin30

Fir.Fin100

JD3,030.00

Grd.Prt10

JD16,410.00
JD1,310.00
JD300.00

Fir.St20

Curing Slab and beams

Fir.Fin90

JD840.00

03-Feb-17
22-Nov-16
04-Nov-16

Fir.Col50

Fir.S&B40

Fir.Fin70

Budgeted
Material Cost

71 28-Oct-16
18 28-Oct-16
6 28-Oct-16

6 07-Nov-16

29-Apr-16 19:53
Budgeted Total
Total Cost Float

Budgeted
Labor Cost

05-Dec-16
24-Nov-16

Steel fixing slab and beams

Fir.Fin40

Successors

9 23-Nov-16
2 23-Nov-16

Fir.S&B20

Fir.S&B50

Classic Schedule Layout


Finish
Predecessors

Shuttering Stairs Formworks

Slab and Beams


Fir.S&B10 Shuttering slab and beams
Fir.S&B30

Original Start
Duration

Fir.Prt20

Fir.Fin40

Fir.Fin40
Fir.Fin70,
Fir.Fin60
Fir.Fin70

Fir.Fin50, Fir.Fin60 Fir.Fin80


Fir.Fin80
Fir.Fin80

Fir.Fin90,
Fir.Fin100
Fir.Fin10
Fir.Fin10

JD2,000.00
JD1,000.00
JD1,000.00
JD6,300.00

JD200.00
JD200.00

JD2,000.00

JD8,000.00 JD10,000.00

142

JD4,000.00

JD5,000.00

JD4,000.00

JD5,000.00

142

JD6,600.00

JD6,800.00

142

JD24,000.00 JD30,300.00
JD0.00

JD5,000.00

TASK filter: All Activities

JD200.00

JD7,000.00

142
142
142
142

Oracle Corporation

Intermediate school
Activity ID

Activity Name

Fir.Fin10

First Floor Completion

Partions
Fir.Prt10
Fir.Prt20

09-May-17

Bricks work

10 06-Feb-17
9 06-Feb-17

17-Feb-17
16-Feb-17

Insulations

1 17-Feb-17

17-Feb-17

137 06-Feb-17

16-Aug-17

6 14-Feb-17

21-Feb-17

Concrete Works
Columns
Sec.Col10 Shuttering columns
Sec.Col20 Steel fixing columns

Sec.Col30 Placing RC columns


Sec.Col50 Curing Rc Columns

Sec.Col40 Deshuttering columns

Sec.St20
Sec.St30
Sec.St40
Sec.St50

Classic Schedule Layout


Finish
Predecessors

0 09-May-17

Second Floor Works

Stairs
Sec.St10

Original Start
Duration

71 06-Feb-17
18 06-Feb-17
6 06-Feb-17
1 22-Feb-17
3 23-Feb-17
2 28-Feb-17

P.D10, P.D20,
P.D30, R.W10

Fir.St50,
Fir.S&B50

Fir.Prt20,
Sec.Col10

Fir.Prt10

Fir.Fin20,
Fir.Fin30

Budgeted
Material Cost

JD3,880.00
JD3,850.00
JD30.00

JD0.00

JD0.00

142

JD4,633.90
JD4,168.40

JD8,513.90
JD8,018.40

142
0

JD465.50

JD495.50

142

JD34,990.00 JD152,760.50 JD187,750.50

74

15-May-17
01-Mar-17
13-Feb-17

Fir.Prt10

Sec.Col20

JD16,410.00
JD1,310.00
JD300.00

22-Feb-17

Sec.Col20

Sec.Col50

JD40.00

27-Feb-17

01-Mar-17

Sec.Col10
Sec.Col30
Sec.Col50

Sec.Col30
Sec.Col40

Sec.St10,
Sec.S&B10

JD840.00
JD30.00

JD0.00

29-Apr-16 19:53
Budgeted Total
Total Cost Float

JD51,330.00 JD67,740.00
JD7,440.00
JD8,750.00
JD2,030.00
JD2,330.00
JD3,030.00

JD3,870.00

JD100.00

JD130.00

JD2,280.00

JD100.00

JD0.00

JD2,320.00

JD100.00

0
0
0
0
0
0
0

9 02-Mar-17
2 02-Mar-17

14-Mar-17
03-Mar-17

Sec.Col40

Sec.St20

JD1,580.00
JD100.00

JD1,970.00
JD113.00

JD3,550.00
JD213.00

44
44

Placing Stairs

1 09-Mar-17

09-Mar-17

Sec.St20

Sec.St40

JD220.00

JD807.00

JD1,027.00

44

Steel Fixing Stairs


Curing Stairs

Deshuttering Stairs

Sec.S&B20 Steel fixing slab and beams

Sec.S&B30 Placing RC slab and beams

3 06-Mar-17
2 10-Mar-17
1 14-Mar-17

53 02-Mar-17
11 02-Mar-17
21 17-Mar-17
2 17-Apr-17

Sec.S&B50 Curing Slab and beams

14 19-Apr-17

Finishing Works
Sec.Fin10
Preliminary carpentrary work

66 16-May-17
2 30-May-17

Sec.S&B40 Deshuttering slab and beams

Sec.Fin80

Fir.Fin90,
Fir.Fin100

Budgeted
Labor Cost

Shuttering Stairs Formworks

Slab and Beams


Sec.S&B10 Shuttering slab and beams

Sec.Fin20

Successors

Preliminary electrical work


Floor Tiling

5 09-May-17
5 30-May-17
6 06-Jun-17

08-Mar-17
13-Mar-17
14-Mar-17

15-May-17
16-Mar-17
14-Apr-17
18-Apr-17

08-May-17
15-May-17
16-Aug-17
31-May-17
05-Jun-17
13-Jun-17

Page 5 of 7

Sec.St10
Sec.St30
Sec.St40

Sec.St30
Sec.St50

Sec.Prt10

JD1,170.00

JD20.00
JD70.00

Sec.Col40

Sec.S&B20

JD13,520.00
JD550.00

Sec.S&B20

Sec.S&B50

JD120.00

Sec.S&B10
Sec.S&B30
Sec.S&B50

Sec.S&B30
Sec.S&B40
Sec.Prt10

Sec.Prt20

Sec.Fin80

Sec.Fin10,
Sec.Fin20

Sec.Fin30

Sec.Prt20

Sec.Fin80

JD1,000.00

JD12,600.00
JD50.00

JD50.00
JD0.00

JD2,170.00

JD70.00
JD70.00

JD41,920.00 JD55,440.00
JD7,290.00
JD7,840.00
JD10,380.00 JD10,500.00

JD24,100.00 JD36,700.00
JD150.00

JD200.00

JD0.00

JD200.00
JD200.00

JD18,580.00 JD101,430.50 JD120,010.50


JD200.00
JD3,500.00
JD3,700.00
JD2,000.00
JD1,800.00

JD8,000.00 JD10,000.00

JD30,215.00 JD32,015.00

TASK filter: All Activities

44
44
44
0
0
0
0
0
0

74
77
74
74

Oracle Corporation

Intermediate school
Activity ID

Activity Name

Sec.Fin30

Plastering Splach and rough coat

Sec.Fin70

Plastering Smooth Coat

Sec.Fin90

Windows

Sec.Fin50
Sec.Fin110

Sec.Fin40

Sec.Fin60

Partions
Sec.Prt10
Sec.Prt20

27-Jun-17

Sec.Fin80

10 28-Jun-17

11-Jul-17

Sec.Fin30

2 10-Aug-17

11-Aug-17

Sec.Fin40

Finishing Carpentary work

2 14-Aug-17

15-Aug-17

Sec Floor Completion

0 16-Aug-17

16-Aug-17

Painting

Finishing electrical work

Insulations

1 29-May-17

29-May-17

137 16-May-17

23-Nov-17

6 24-May-17

31-May-17

Thd.Col50 Curing Rc Columns

Thd.Col40 Deshuttering columns

Thd.St30

15-Aug-17
29-May-17
26-May-17

Thd.Col30 Placing RC columns

Thd.St20

2 14-Aug-17

09-Aug-17

10 16-May-17
9 16-May-17

Thd.Col20 Steel fixing columns

Thd.St10

21 12-Jul-17

Bricks work

Concrete Works
Columns
Thd.Col10 Shuttering columns

Thd.St50

Classic Schedule Layout


Finish
Predecessors

10 14-Jun-17

Third Floor Works

Stairs
Thd.St40

Original Start
Duration

71 16-May-17
18 16-May-17
6 16-May-17
1 01-Jun-17
3 02-Jun-17
2 07-Jun-17

Successors

Budgeted
Labor Cost

Sec.Fin40,
Sec.Fin70
Sec.Fin40

JD1,000.00

JD200.00

Sec.Fin90

Sec.Fin50,
Sec.Fin60
Sec.Fin110

Sec.Fin50,
Sec.Fin60

P.D10, P.D20,
P.D30

Sec.Fin30,
Sec.Fin70

Sec.Fin90

Sec.St50,
Sec.S&B40
Sec.Prt10

JD1,000.00

Sec.Fin90

Sec.Fin110

Sec.Prt20,
Thd.Col10

Sec.Fin10,
Sec.Fin20

JD6,300.00

JD200.00

JD2,000.00
JD0.00

JD3,880.00
JD3,850.00

Thd.Col20

Thd.Col50

JD40.00

Thd.Col50

Thd.Col40

Thd.St40,
Thd.S&B10

JD5,000.00

74

JD6,600.00

JD6,800.00

74

JD200.00

74

JD0.00

74

JD0.00

JD5,000.00
JD0.00

JD7,000.00

JD16,115.50 JD19,995.50
JD15,650.00 JD19,500.00

JD840.00
JD30.00

JD465.50

74

74
74
0

01-Jun-17

Thd.Col30

JD4,000.00

JD24,000.00 JD30,300.00

JD46,990.00 JD186,970.50 JD233,960.50

Thd.Col20

08-Jun-17

74

74

Sec.Prt10

06-Jun-17

JD5,000.00

JD495.50

JD16,410.00
JD1,310.00
JD300.00

Thd.Col30

29-Apr-16 19:53
Budgeted Total
Total Cost Float

JD4,000.00

JD30.00

22-Aug-17
08-Jun-17
23-May-17

Thd.Col10

Budgeted
Material Cost

JD51,330.00 JD67,740.00
JD7,440.00
JD8,750.00
JD2,030.00
JD2,330.00
JD3,030.00

JD3,870.00

JD100.00

JD130.00

JD2,280.00

JD100.00

JD0.00

JD2,320.00

JD100.00

0
0
0
0
0
0
0

Shuttering Stairs Formworks

9 09-Jun-17
2 09-Jun-17

21-Jun-17
12-Jun-17

Thd.Col40

Thd.St50

JD1,580.00
JD100.00

JD1,970.00
JD113.00

JD3,550.00
JD213.00

44
44

Placing Stairs

1 16-Jun-17

16-Jun-17

Thd.St50

Thd.St20

JD220.00

JD807.00

JD1,027.00

44

Steel Fixing Stairs


Curing Stairs

Deshuttering Stairs

Slab and Beams


Thd.S&B10 Shuttering slab and beams

Thd.S&B20 Steel fixing slab and beams

Thd.S&B30 Placing RC slab and beams

3 13-Jun-17
2 19-Jun-17
1 21-Jun-17

53 09-Jun-17
11 09-Jun-17
21 26-Jun-17
2 25-Jul-17

15-Jun-17
20-Jun-17
21-Jun-17

22-Aug-17
23-Jun-17
24-Jul-17
26-Jul-17
Page 6 of 7

Thd.St40
Thd.St10
Thd.St20

Thd.St10
Thd.St30

Thd.Prt10

JD1,170.00

JD20.00
JD70.00

Thd.Col40

Thd.S&B20

JD13,520.00
JD550.00

Thd.S&B20

Thd.S&B50

JD120.00

Thd.S&B10

Thd.S&B30

JD1,000.00

JD12,600.00

JD50.00
JD0.00

JD2,170.00

JD70.00
JD70.00

JD41,920.00 JD55,440.00
JD7,290.00
JD7,840.00
JD10,380.00 JD10,500.00

JD24,100.00 JD36,700.00

TASK filter: All Activities

44
44
44
0
0
0
0

Oracle Corporation

Intermediate school
Activity ID

Activity Name

Thd.S&B50 Curing Slab and beams

Thd.S&B40 Deshuttering slab and beams

Finishing Works
SW10
Stone works For All Floors

Original Start
Duration

Classic Schedule Layout


Finish
Predecessors

14 27-Jul-17

15-Aug-17

66 23-Aug-17
57 05-Sep-17

23-Nov-17
22-Nov-17

5 16-Aug-17

22-Aug-17

Thd.S&B30
Thd.S&B50
Thd.Prt10

Thd.Fin10

Preliminary carpentrary work

2 06-Sep-17

07-Sep-17

Thd.Prt20

Thd.Fin80

Floor Tiling

6 13-Sep-17

20-Sep-17

Thd.Fin10,
Thd.Fin20

Thd.Fin20

Preliminary electrical work

5 06-Sep-17

12-Sep-17

Thd.Prt20

Thd.Fin30

Plastering Splach and rough coat

10 21-Sep-17

04-Oct-17

Thd.Fin70

Plastering Smooth Coat

10 05-Oct-17

18-Oct-17

Thd.Fin30

Thd.Fin90

Windows

2 17-Nov-17

20-Nov-17

Thd.Fin40

Thd.Fin50

Finishing Carpentary work

2 21-Nov-17

22-Nov-17

Thd.Fin90

Thd.Fin100

Third Floor Completion

0 23-Nov-17

23-Nov-17

Thd.Fin50,
Thd.Fin60

Thd.Fin40

Thd.Fin60

Partions
Thd.Prt10
Thd.Prt20

Roof Works
R.W10

Project Delivary

Painting

Finishing electrical work

22-Nov-17

10 23-Aug-17
9 23-Aug-17

05-Sep-17
04-Sep-17

Insulations

1 05-Sep-17

05-Sep-17

Screed and Roofing Works

3 23-Nov-17

27-Nov-17

Handeling Over Mobilization

P.D30

Handeling Over roof and external works

P.D40

2 21-Nov-17

16-Nov-17

Bricks work

P.D10
P.D20

21 19-Oct-17

Handeling Over 4 Floors

Project Completion Date and


demobilization

3 23-Nov-17

27-Nov-17

0 28-Nov-17

28-Nov-17

0 28-Nov-17

28-Nov-17

0 28-Nov-17
0 28-Nov-17
0 28-Nov-17

Thd.Fin80

Thd.Fin30,
Thd.Fin70

Thd.Fin90

Thd.St30,
Thd.S&B40
Thd.Prt10

Grd.Fin110,
Fir.Fin10,
Thd.Fin100

Successors
Thd.S&B40

Budgeted
Labor Cost

Budgeted
Material Cost

JD200.00

JD0.00

JD50.00

Thd.Prt10

P.D20, P.D30,
P.D10
Thd.Fin80

JD200.00

JD30,580.00 JD135,640.50 JD166,220.50


JD12,000.00 JD34,210.00 JD46,210.00

3
3

JD200.00

Thd.Fin80

JD2,000.00

Thd.Fin40,
Thd.Fin70

JD1,000.00

Thd.Fin90

JD6,300.00

Thd.Fin30

JD1,800.00

Thd.Fin40

JD1,000.00

Thd.Fin50,
Thd.Fin60

JD200.00

Thd.Fin100

JD2,000.00

Thd.Fin100

JD200.00

R.W10

JD0.00

JD3,880.00
JD3,850.00

Thd.Prt20,
SW10

P.D10, P.D20,
P.D30

JD200.00

JD3,700.00

JD30,215.00 JD32,015.00

JD8,000.00 JD10,000.00

JD4,000.00

JD5,000.00

JD4,000.00

JD5,000.00

JD6,600.00

JD6,800.00

JD200.00

JD0.00

JD24,000.00 JD30,300.00

JD0.00

JD5,000.00
JD0.00

JD7,000.00

JD16,115.50 JD19,995.50
JD15,650.00 JD19,500.00

JD120.00
JD120.00

0
0
0

JD465.50

JD495.50

JD0.00

JD120.00

JD0.00

JD120.00

JD0.00

JD0.00

JD0.00

R.W10, Grd.Fin110, PFir.Fin10,


.D40
SW10, Sec.Fin110
JD0.00

JD0.00

JD0.00

R.W10, Grd.Fin110, PFir.Fin10,


.D40
SW10, Sec.Fin110
JD0.00

28-Nov-17

R.W10,
Grd.Fin110,
Fir.Fin10, SW10,
P.D10, P.D20,
P.D30

Page 7 of 7

JD3,500.00

Thd.Fin10, Thd.Fin20 JD30.00

28-Nov-17

28-Nov-17

JD150.00

29-Apr-16 19:53
Budgeted Total
Total Cost Float

P.D40

JD0.00
JD0.00

TASK filter: All Activities

JD0.00
JD0.00
JD0.00

JD0.00
JD0.00
JD0.00

0
0
0

Oracle Corporation

Você também pode gostar