Você está na página 1de 36

~Dewatering/Ground Water Control~

1
Definition
Ground water can be defined as water which is held
temporarily in the soil above the level of water table

Dewatering is a process to lower down the water table


to give reasonably dry working conditions especially
for excavations activities.

2
Control of Ground Water
Can be divided into two groups:

Permanent exclusion of ground water (cut-off wall to


the flow of ground water)
Temporary exclusion of ground water by lowering
down the water table

3
Control of Ground Water

4
5
Methods which have been developed for cutting off
groundwater flow fall into several categories:

1. Steel Sheet Piling


• Structural,
• Permanent – act as structural wall
• Temporary – enclosure excavation to form cofferdam
• Act as a partially effective cut off and as ground support
• Driven into place before excavation
• Produce vibration and noise due to driving process

6
Cofferdam Basic
Principle

7
8
Diaphragm Wall
Suitable for all types of soil
structural, permanent
In-situ reinforced concrete using bentonite slurry
method
Low installation noise and vibration
Can be used in restricted spaces and can be
installed close to existing foundations
highly effective cutoff as well as ground support
Un economic
9
Diaphragm Wall

10
Slurry Trench Cut-Off
non structural thin cast in situ unreinforced
diaphragm wall
Suitable for silts, sand and gravel
trench excavated with bentonite and backfilled
with impermeable material

11
Thin Grouted Membrane
Thin Grouted membranes - these are permanent curtain
or cut-off non structural walls or barriers inserted in the
ground to enclose the proposed excavation area
cement, chemicals or bentonite is injected into the soil (to
make the soil impermeable)
They are suitable for sands and can be installed rapidly
but they must be adequately supported by earth an both
side
The only limitation is the depth to which the formers can
driven and extracted.

12
THIN GROUTED MEMBRANE
13
Contiguous Piling
Alternative method to the reinforced concrete
diaphragm wall consisting of a series of interlocking
reinforced concrete bored piles
Usual range diameter – 300mm and 600mm
Faced with reinforced rendering or covered with a
mesh reinforcement sprayed with concrete to give
smooth finish (shotcrete/Gunite)

14
Contiguous Piling

15
Freezing
Suitable method for all types of subsoils with a moisture
content in excess of 8% of the voids
Insert freezing tubes into ground and circulate a freezing
solution around the tubes to form ice in the voids
Thus creating a wall of ice to act as impermeable barrier
Circulating solution – magnesium chloride/calcium
chloride at -15 and -25 c
Suitable for excavating deep shafts and driving tunnels

16
Freezing

highly effective cutoff and ground support


17
GROUTING METHOD
 CEMENT GROUT
- form a curtain. Mixture of neat cement and water
 CLAY/CEMENTS GROUT
- suitable for sand and gravels where soil particles are too small for cement grout.
Bentonite with additive (portlansd cement/soluble silicates)
 CHEMICAL GROUTING
- for medium to coarse sands and gravels. The chemical form a permanent gel
 RESIN GROUTING
- for silty fine sand, similar application of chemical grouts
 BITUMINOUS GROUT
- For fine sand to decrease permeability not increase the strength thus unsuitable for
underpinning works
 GROUT INJECTION
- Grouts of all kinds are usually injected into the subsoil by pumping in the mixture at high
pressure through tubes.

18
19
SUMP PUMPING
Pumping from sumps is the most widely used since it can
be applied to all types of ground conditions and is
economical to install and maintain.
The only problem is the settlement: the ground is likely to
move as the water flows towards the sump area.
There is also a risk of instability at the formation level in
supported excavations, owing to the upward movement of
water.
These problems can be partially overcome by positioning
the sump at a corner of the excavation at a level below the
formation level

20
SUMP PUMPING
OPEN PUMPING / SUMP PUMPING

• pumping from sumps and ditches


• least expensive method:
• from the standpoint of direct dewatering cost
• if conditions are wrong, it can result in delays, cost
overrun or catastrophic failures
• must identify those conditions that are not favorable to
open pumping before deciding to proceed with it:
• impairing the foundation of proposed structure or of
existing structure nearby
• delaying the project or escalating cost of excavation
• endangering workers 21
SUMP PUMPING

sump below formation level in corner of


excavation
22
SUMP PUMPING

23
Jetted Sump Detail

24
WELLPOINT SYSTEM

• has been used> 50 years, most versatile


method and effective in all type of soil
• may not be the most economical method for a
given job due to advances in other pre
drainage tool
• most suitable for shallow aquifer (water level
need to be lowered < 6 m)
• multi stages will be used for lowering > 6 m

25
26
well points
27
28
29
30
DEEP BORED WELLS

• Each with individual pump (involve a high unit cost)


• Advances in well design (aquifer analysis) and
construction techniques, and pump technology have
made it practical to utilise deep well
• Best suited to homogeneous aquifers that extended
well below the excavation level
• Can be installed to greater depth (up to 12 m)
• Volume pumped by each well is high thus wider
spacing is practical
• Careful exploration, including a pump test, must be
carried out before undertaking this method

31
DEEP BORED WELL

32
Horizontal Ground Water
Control
Installing into the ground 100mm diameter PVC
perforated suction pipe covered with a nylon filter
sleeve to prevent the infiltration of fine particles
Using special mechine which excavate a narrow
trench, lays the pipe and bacfill the excavation

33
Horizontal Ground Water Control

34
Electo-osmosis
Uncommon method
Costly
Cohesive soils- clay and silts
On the principles that soils carry a nagative charge.
Insert two electrodes and passing electric charge
between them, anode and cathode (well point)
Electric current is passed between the asnode and
cathode causes the positively charged water molecule
to flow the well point.

35
Appropriate dewatering Methods
Effective Grain Size Example Dewatering Method
(D10)

Larger than 0.1mm² Gravel, rock, boulders Sumps, ordinary well


points

0.1 – 004 mm Sand Vacuum wells or well


points

0.004 – 0.0017 mm Silt, clay Electro osmosis

36

Você também pode gostar