Você está na página 1de 248

EPCC-05 : Rehabilitation and Adaptation

Process Plants, Utilities, Offsites and Pipelines


N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-0002 Rev 0
Page 1 of 8

Project: REHABILITATION AND ADAPTATION PROJECT,


SKIKDA REFINERY, ALGERIA

Owner: NAFTEC Spa

PMC: Engineers India Limited

Package No.: EPCC-05


Package Title: Rehabilitation and Adaptation Process Plants,
Utilities, Offsites and Pipelines

Section: Requirements for quality assurance and


quality control during construction

Discipline: Construction

0 30.10.2007 ISSUED FOR FEED


Constn Proj.
Rev. Prepared Checked
Date Purpose
No by by Approved by

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-0002 Rev 0
Page 2 of 8

INDEX

____________________________________________________________________________
Clause Title Sheet No.
N0.
____________________________________________________________________________

1.0 SCOPE 4

2.0 RESPONSIBILITY 4

3.0 METHODOLOGY

3.1 PROCUREMENT OF MATERIALS REQUIRED 4


FOR THE CONSTRUCTION WORKS

3.2 EXECUTION OF WORKS 4

3.3 QA/ QC AUDITS 7

4.0 DOCUMENTATION AND RECORDS 7

DOCUMENT NO.

INDICATIVE INSPECTION & TEST PLANS 6648-00-19-43-2000


FOR CONSTRUCTION WORKS (pl. refer index on page
2 of 3 for document no.
of disciplinewise ITPs)

INDICATIVE FORMATS FOR REPORTING 6648-00-19-43-5000


INSPECTION & TEST RESULTS (pl. refer index on page
2 of 2 for document no.
of disciplinewise Formats)

REQUIREMENTS FOR POSITIVE MATERIAL 6648-00-19-43-9001


IDENTIFICATION (PMI) AT CONSTRUCTION SITES

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-0002 Rev 0
Page 3 of 8

Abbreviations:

ITP : Inspection & Test Plan

PMC : Project Management Consultant

QA/QC : Quality Assurance/ Quality Control

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-0002 Rev 0
Page 4 of 8

1.0 SCOPE

This document shall be applicable to all construction works to be executed by EPCC


CONTRACTORs.

2.0 RESPONSIBILITY

It is EPCC CONTRACTOR's prime responsibility to arrange/produce the product


conforming to contract specifications and inspect all equipment, materials and works at
various stages of execution as per the approved QA Plans. In addition, they have to
coordinate all efforts in this regard directly with the OWNER/ PMC and other involved
agencies to give adequate confidence that the activities are performed as per agreed
ITPs and necessary documentation is available. Verification by Owner/PMC or his
representative at any stage shall not relieve EPCC CONTRACTOR of his responsibility
towards quality of the product.

The EPCC CONTRACTOR shall comply with all statutory rules & regulations in force
during execution of work and interface with such authorities as required (refer Section-
XVIII for details).

3.0 METHODOLOGY

The management of construction quality control is divided into the following categories:-

(1) Procurement of materials required for the construction work.


(2) Execution of work
(3) QA/QC Audits

3.1 Procurement of Materials Required for the Construction Work

The EPCC CONTRACTOR shall develop list(s) defining the items to be procured along
with proposed Vendors for approval of the Owner/PMC. The list shall comprise of all
items except vessels, equipments, pumps, electrical/ instrumentation panels etc. which
may be available directly ready for installation or requiring small fabrication as per
requirement. The vendor list shall be in line with the contract document. In case, no
vendor list exists in the contract for a particular item, the EPCC CONTRACTOR shall
propose a list of Vendors to Owner/PMC. EPCC CONTRACTOR has to satisfy himself
with the capability of the vendor to deliver the product in time with quality before
proposing him as a prospective vendor. EPCC CONTRACTOR shall submit the QA/QC
plans for all major items and carry out their procurement in line with the approved plans.
The EPCC CONTRACTOR can either provide his own adequate qualified staff for
inspection or employ a separate third-party inspection agency with prior approval to
carry out these functions. Involvement of OWNER/ PMC in the quality control plan, if
required, shall be defined during approval of the same.

3.2 Execution of Work

(i) The QA plans for execution shall be developed by the EPCC CONTRACTOR.
OWNER/ PMC’s approval for the same shall be taken well before start of the
work. The final Inspection & Test Plans (ITPs) and formats, based on the
indicative ITPs and Formats enclosed in document Nos. 6648-00-19-43-2000
and 6648- 00- 19- 43- 5000 respectively, shall be developed by the EPCC

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-0002 Rev 0
Page 5 of 8

CONTRACTOR as per contract specifications for approval by OWNER/ PMC.


For the activities which are identified as Witness or Hold Point, specific
inspection call shall be raised by the EPCC CONTRACTOR with OWNER/ PMC
in the requisite format well in advance.

The indicative ITPs and Formats enclosed in the feed package are for guidance
to the EPCC CONTRACTOR and may not cover some of the activities to be
performed during execution of works under the scope of this contract. The
EPCC CONTRACTOR shall develop Inspection & Test Plans and Formats for all
such activities also and submit the same to OWNER/ PMC for approval, before
actually undertaking such activities.

EPCC CONTRACTOR shall be completely responsible for management of


approved quality plans and OWNER/PMC involvement will be only of
Surveillance in nature to randomly check the works at selective/critical junctures.
Their role shall be to monitor that the EPCC CONTRACTOR is executing the
quality plans as per the approved drawings, employing adequately qualified staff
and other resources for various items of works. Any deviation to the
specifications shall be brought to the notice of OWNER/ PMC in prescribed
formats by EPCC CONTRACTOR for approval.

(ii) It is likely that the EPCC CONTRACTOR may engage sub-contractor(s)/vendors


for performance of the work. EPCC CONTRACTOR shall be responsible for
ensuring the implementation of approved QA plan, contract specifications and
contract conditions through their sub-contractor’s to achieve the quality during all
stages of construction. It shall be the responsibility of the EPCC CONTRACTOR
to ensure proper coordination between his sub- contractor(s) and other agencies
working at site.

The sub-contractor(s)/vendors selection shall be done after evaluation by the


EPCC CONTRACTOR inline with contract requirements and shall be got
approved by Owner/PMC before engaging them for the works.

(iv) Storage

All the materials procured shall be stored/stacked as per the standard norms and
as recommended in various clauses of relevant codes and contract document.
The storage of material shall be such as to avoid damage to life/properties
(physical and chemical) of the materials. The storage shall not cause
deterioration, rusting, mix-up etc. and hamper the other related works in any way.
EPCC CONTRACTOR shall submit his detailed warehouse plan for OWNER/
PMC approval to manage the above in open/covered areas.

The materials susceptible to fire shall be kept away in a separate protected


place.

In general, the materials shall be kept systematically in order of their class, batch
number and identification number, so that they are accessible for the inspection
by OWNER/ PMC whenever required and to avoid the mix up in those materials.

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-0002 Rev 0
Page 6 of 8

(v) Use

The materials shall be stacked in such a way that the lot, which is procured first,
will be consumed first. For materials which are having specific expiry date/ shelf
life shall not be used beyond that date and shall be removed from site. Wherever
there is any doubt about the change in properties of the materials, such materials
shall be sent to reputed approved laboratory for testing and acceptance.

(vi) Inspection

The EPCC CONTRACTOR shall be responsible for carrying out inspection of the
materials brought at site and conducting tests/ checks (at site or in approved
laboratories) at predefined frequencies as per contract. It is the responsibility of
the EPCC CONTRACTOR to ensure that the materials used at site shall conform
to relevant codes/ standards and Manufacturer Test Certificates are available for
correlation as and when required. The EPCC CONTRACTOR shall maintain the
records of all materials brought at site and tests conducted on them.

(vii) In process and final Inspection

EPCC CONTRACTOR shall be responsible to arrange verification of products


during in- process and final inspection. Relevant checks and tests shall be
arranged for the works performed and records maintained. Tolerances achieved
with respect to contract specification and execution drawings for various
activities/processes shall be ascertained and submitted to OWNER/ PMC for
approval. Efforts shall be made to keep checks and controls in such a way that
a non-conforming product is avoided. However, if in an isolated case, the
tolerances are beyond the acceptable values given in the contract/execution
drawings/codes, non-conformance resolution/Deviation permit need to be raised
by the EPCC CONTRACTOR and got approved/resolved from OWNER/ PMC.

The EPCC CONTRACTOR shall arrange verification of ingredients used and


validation of the software used at the batching plant(s). OWNER/ PMC reserve
the right to inspect the working of batching plant including validation of the
software used and calibration of measuring & monitoring devices any time. The
EPCC CONTRACTOR shall ensure the quality of the concrete delivered by the
transit mixers, as applicable and maintain verifiable records.

EPCC CONTRACTOR shall mobilize Portable Alloy Analyser(s) with printout


facility and carry out 'Positive Material Identification (PMI)' of materials and welds
after erection/installation but prior to hydro-testing (refer document No.6648-00-
19-43-9001). Any non-conformance detected shall be removed and replaced
prior to final hydro testing.

The EPCC CONTRACTOR shall develop colour coding scheme of piping


materials to avoid mixing up of material at different stages of construction and
submit it to OWNER/PMC for approval.

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-0002 Rev 0
Page 7 of 8

3.3 QA/QC Audits

During the execution of the works, EPCC CONTRACTOR shall carry out periodical
Quality Audits at least quarterly in all areas of work. These audits will be conducted by a
team of specialists in the respective areas. The auditors shall not be directly involved in
the jobs being audited.

The EPCC CONTRACTOR shall prepare an Audit Plan and Procedure and submit the
same to OWNER/ PMC for approval.

A copy of the Audit Report containing the findings of the Audit team will be submitted to
OWNER/ PMC. After completion of rectification/modifications/corrective actions on the
issues indicated in Audit Report, Compliance Report shall be submitted by the EPCC
CONTRACTOR to OWNER/ PMC for review.

Over and above the EPCC Contractor’s Internal QA/QC Audits outlined above, OWNER/
PMC shall also reserve the right to conduct QA/QC audits at the frequency decided by
them.. EPCC CONTRACTOR shall participate and provide full support to the Audit
Team and furnish all documents/reports/records as desired by the Audit Team. The
EPCC CONTRACTOR shall take all actions required to comply with the findings of the
Audit Report and issue regular Compliance Reports for the same to OWNER/ PMC till all
the findings of the Audit Report are fully complied.

In case major Non conformities are observed during execution of the works OWNER/
PMC reserve the right to appoint an independent person/Third Party Agency to conduct
QA/QC Systems Audit for full/part of the facilities being executed by the EPCC
CONTRACTOR. This audit will be in addition to the audits described above
and may be carried out intermittently/continuously for all or part of the facilities being
executed by the EPCC CONTRACTOR. EPCC CONTRACTOR shall bear the total cost
of such audits and shall participate & provide full support to the Audit Team and ensure
compliance of the audit observations.

4.0 DOCUMENTATION AND RECORDS

All the necessary documentation & records shall be maintained by EPCC


CONTRACTOR till completion of project and handed over to OWNER/ PMC in requisite
copies as a part of completion documents. Wherever OWNER/ PMC personnel were
directly involved particularly in witness and hold point, the copies of the records shall
also be provided to personnel on completing inspection of those activities. The
documentation & records shall include the following as a minimum but not limited to:

i) Approved Quality Assurance Plan

ii) Approved Inspection and Test Plans

iii) Inspection and test documents covering

a) Manufacturer Test Certificate

b) Material Receipt Report including Inspection Release Note, if applicable


and Site Inspection and acceptance Report on quality and quantity of
material

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-0002 Rev 0
Page 8 of 8

c) Site test/laboratory test Report reviewed by EPCC CONTRACTOR for


acceptance vis-à-vis to contract/code requirements for materials/including
PMI report at warehouse

d) In process Verification reports of EPCC CONTRACTOR representative


and OWNER/ PMC as applicable

e) Final verification report including any test checks done for compliance

f) As-built vis-à-vis to contract/drawings including tolerances

g) As-built for erection

h) Non conformance resolution raised by EPCC CONTRACTOR/OWNER/


PMC

i) Concession/Deviation approval by OWNER/ PMC

j) Change order approval by OWNER/ PMC incase there is variation from


contract

k) QA/QC Audit Reports and compliance Reports thereof

l) Mechanical Completion formats

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2000 Rev 0
Page 1 of 3

INDICATIVE

INSPECTION & TEST PLAN (ITP)

FOR

CONSTRUCTION WORKS

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2000 Rev 0
Page 2 of 3

INDEX

S.NO DESCRIPTION DOCUMENT NO. REV.

Indicative Inspection & Test Plans for


1. 6648-00-19-43-2100 0
Mechanical works

Indicative Inspection & Test Plans for


2 6648-00-19-43-2500 0
General works

Indicative Inspection & Test Plans for


3 6648-00-19-43-2600 0
Instrumentation works

Indicative Inspection & Test Plans for


4. 6648-00-19-43-2700 0
Civil works

Indicative Inspection & Test Plans for


5. 6648-00-19-43-2800 0
Electrical works

Indicative Inspection & Test Plans for


6. 6648-00-19-43-2900 0
Pipeline works

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2000 Rev 0
Page 3 of 3

GENERAL NOTE
The enclosed indicative ITPs shall be used as a basis for developing ITPs for specific jobs/
activities to be executed by the EPCC CONTRACTOR. EPCC CONTRACTOR shall obtain
OWNER/PMC’s approval on all such finalized ITPs.

The provisions indicated for stagewise inspection by OWNER/ PMC are the minimum and the
OWNER/ PMC may decide to increase Hold Points/ Witness Points. Activities for which ITP's
are not given, EPCC CONTRACTOR to develop and get the same approved by OWNER/ PMC
well before start of the work.

EPCC CONTRACTOR to submit required reporting formats and job procedures for each activity
listed in ITP's and submit to OWNER/ PMC for approval, well before commencement of the
activity. If the EPCC CONTRACTOR has to deviate from the given ITP for a valid reason, he
shall obtain prior written approval of OWNER/ PMC. EPCC CONTRACTOR to carry out 100%
examination of all activities.

LEGEND
HP : Hold Point ;

A point which requires inspection/verification and acceptance by OWNER/ PMC


before any further processing is permitted.
The EPCC CONTRACTOR shall not process the activity/item beyond a Hold
Point without written approval by OWNER/ PMC except where prior written
permission for further processing is available.

W : Witness Point ;

An activity which requires witnessing by OWNER/ PMC when the activity is


performed.
After proper notification has been provided (notification modalities and period
shall be finalized before hand), the EPCC CONTRACTOR is not obliged to hold
further processing if OWNER/ PMC is not available to witness the activity or does
not provide comments before the date notified. Basis of acceptance shall be as
per relevant technical specification.

Rw : Review of EPCC CONTRACTOR’s documentation.

S : Surveillance Inspection by OWNER/ PMC.


Monitoring or making observations to verify whether or not material/items or
services conform to specified requirements. Surveillance activities may include
audit, inspections, witness of testing, review of quality documentation & records,
personnel qualifications, etc.

WC : 100% Examination by EPCC CONTRACTOR.

Responsibility for execution of the inspection/testing is with the EPCC CONTRACTOR;


OWNER/ PMC only verifies examination or testing done by the EPCC CONTRACTOR at
important stages

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2100 Rev. 0
Page 1 of 2

INDICATIVE
INSPECTION & TEST PLAN (ITP)
MECHANICAL WORKS

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2100 Rev. 0
Page 2 of 2

INDEX

S.NO DESCRIPTION DOCUMENT NO. REV.

MECHANICAL WORKS

1. Above Ground Piping 6648-00-19-43-2110 0

2. Tie-In 6648-00-19-43-2111 0

3. Column Internals 6648-00-19-43-2120 0

4. Fired Heaters 6648-00-19-43-2130 0

5. Refractory & Insulation Works- Fired Heaters 6648-00-19-43-2140 0

6. Equipment Erection (Static) 6648-00-19-43-2150 0

7. Equipment Erection (Rotary) 6648-00-19-43-2160 0

8. Storage Tanks 6648-00-19-43-2180 0

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2110 Rev. 0
Page 1 of 11

INDICATIVE ITP FOR


ABOVE GROUND PIPING
SL. ACTIVITY EPCC OWNER/
NO CONTRACTOR PMC

A. PRIOR TO FABRICATION

1. Incoming Material
a) Documents (MRIR etc.): Review & acceptance WC HP
b) Physical verification WC W

2. Welding Filler Material Approval/Qualification


a) Review of Manufacturer’s Test Certificates/Documents WC* HP*
& Sampling
b) Laboratory Testing, if any
i) Carbon Steel WC Rw
ii) All other materials WC W

3. WPS/PQR
a) Review of proposed procedure WC HP
b) Welding of Test Coupens and subsequent testing
i) Carbon Steel, Stainless Steel (type 304) WC Rw
ii) All other materials WC W

c) Approval of final WPS/PQR. WC HP

4. Welder performance Qualification WC S

4a. Certification & approval of welders. WC HP

5. NDT Procedure Qualification


i) Review of proposed procedure WC HP
ii) Witnessing of Proposed Procedure Testing WC W
iii) Approval of Qualified Procedure WC HP

6. Review of Joint numbering Procedure numbering in WC HP


Isometrics (Big & Small bore)/Sketches

7. Material traceability & Transfer of Heat Nos. WC S


(material traceability not mandatory for utility piping)

* Notwithstanding any other tests/documentation required for qualification/approval of filler metals :


i) For Alloy Steel & Stainless Steel welding filler metals, chemical analysis to be carried out for every
batch.

For NACE filler metals, corrosion tests like HIC, SSCC, etc. to be carried out for every batch. However, HIC/SSCC tests
done earlier & duly witnessed by a reputed third party, will be acceptable.

Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2110 Rev. 0
Page 2 of 11

SL. ACTIVITY EPCC OWNER/


NO. CONTRACTOR PMC

B. FABRICATION (SHOP & FIELD)

1. Material as per piping class (check w.r.t. approved WC S


colour coding procedure), Fit-up check and
Traceability check

2. Pre-heat (if any) WC S

3. Certificate of purity of purging/shielding Gas (if any) WC S

4. Purging rate (if any) and arrangement WC Rw

5. Shielding rate (if any) WC S

6. Baking of Electrodes WC S

7. Inter-pass cleaning & Temperature check. WC S

8. Visual Examination of completed welds WC S

9. Monitoring of PWHT Cycle WC S

9a. Review of Time – Temperature graph


i) CS WC S
ii) AS WC W

10. Hardness Check WC S

11. PT/MT WC S

12. Identification of Joints for Radiography (for Random WC S


Radiography only)

13. Review of Radiographs interpreted by the EPCC


Contractor

i) For Carbon Steel Piping, SS Piping(type 304) WC S


ii) All other materials WC W

Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2110 Rev. 0
Page 3 of 11

SL. ACTIVITY EPCC OWNER/


NO. CONTRACTOR PMC

C PROOF TESTING
(See enclosed checklist in Annex-1)

1. Procedure Review WC HP

2. Preparation of Punch list (Ref. Annex-3) WC S

3. Review of Punch List WC HP

4. Liquidation of check list, if applicable WC HP

5. Correctness of Testing arrangements WC S

6. Scrutiny of test packs for Mechanical & NDT Clearance WC HP

7. Positive Material Identification as per specification after WC S


completion of installation.

8. a) Review of Calibration certificates of pressure Gauges WC HP


b) Field Calibration, if any WC S

9. Air/Water Flushing (preliminary) WC S

10. Visual inspection of all weld joints for leak during


Pneumatic/ Hydrotesting (See Annex-2)
a) Category 'D' services WC S
b) All other services WC W

11. Draining of Water & Air Drying WC S

12. Removal of temporary blinds/supports. WC S

Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2110 Rev. 0
Page 4 of 11

SL. ACTIVITY EPCC OWNER/


NO. CONTRACTOR PMC

13. Boxing up including reinstallation of flappers of check WC S


valves

14. Review of Records of fasteners & gaskets WC S

15. Torque tightening/ tensioning of flange joints, WC S


wherever applicable

INSPECTION & TEST DOCUMENTS

Review Test and Inspection Documents WC Rw

For liquidation of Punch list, see Annex - 3

Note : Pre-commissioning activities such as chemical cleaning, card board blasting, system testing
are not covered by these ITP's. The EPCC Contractor shall develop ITP's for such activities
and obtain Owner/ PMC/ Licensor's approval.

A/G Above Ground NDT Non Destructive Testing


AS Alloy Steel i.e. Cr-Mo steels like A335 NRV Non Return Valve
Gr P11, P5, P9,P22,etc
CS Carbon Steel PMI Positive Material Identification
CSO Car Seal Open PQR Procedure Qualification Record
GAD General Arrangement Drawings PT Penetrant Testing
HIC Hydrogen Induced Cracking PWHT Post Weld Heat Treatment
LO/ LC Lock Open/ Lock Close RF Reinforcement
MT Magnetic Particle Testing SS Stainless Steel like A312 TP 304, 316,
321, 304L, 316L, 316Mo, etc.
NACE National Association of Corrosion SSCC Sulphide Stress Corrosion Cracking
Engineers WPS Welding Procedure Specification

Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2110 Rev. 0
Page 5 of 11

ANNEX – 1
Checklist for Mechanical Clearance - A/G Piping

Project : ___________________________ Report No : ____________________________

Plant/Unit : _________________________ Date : ________________________________

EPCC Contractor : _________________ Area : ________________________________

Loop No : _________________________ INCH MTR : __________________________

Line No (Isometric No.) Rev. GAD No. Rev. P&ID No. Rev.

Items to be checked Accept Remarks


EPCC
Contractor
1. Installation checked as per Isometric w.r.t.
CONFIGURATION : Route, plumb, elevation,
Clearance for thermal
expansion/ insulation
BRANCH : Location, angle, orientation,
type, RF pad, etc.
STEAM TRAP : Direction
2. Installation checked as per GAD w.r.t.
CONFIGURATION : Route, clearance for thermal
expansion/insulation
3. Installation checked as per P&ID
4. Isometrics completed for ( enclosed ):
a. Joint Numbering (Shop & Field Welds)
b. Spool Numbering
c. As-built routing & dimensions
5. Valves(Check Rating, Gaskets, Flow Nos
Direction, Sheet No., Tag No., Spindle
direction, CSO LO/LC, Damage, etc)
Gate Valves
Globe Valves
Check Valves
Control Valves Tag Nos.:
Safety Valves Tag Nos.:
Any other valves :

6. Strainers : Check for clearance, flow


direction, elements

FORMAT NO: ____________________ ( Sht 1/4 )

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2110 Rev. 0
Page 6 of 11

Checklist for Mechanical Clearance - A/G Piping

Item to check Accept Remarks


EPCC
Contractor
7. Flanged Joints
Total Nos.
Check for type of flange
Check for Rating
Check for Alignment, (proper gap & parallelity
Check for Correct Studs & nuts – dia., length, Material,
uniform protrusion of studs, anti seize compound
Check for correct gasket ( type, size, spec., thickness,
etc.)
Torque values used for tightening
8. Seal Welding of Screwed Connections (if Required)
9. Vents/Drains as per Dwg and Provision of additional high
point Vents and/or low point Drains, if reqd.
10. Reinforcement pads as per piping class
11. Orifice Flanges :
Check for Tag No., tapping orientation, tap valve, jack
screw, straight run length of upstream & downstream
12. Local Gauges : Check for accessibility
13. Slope (When Applicable)
14. Supports
a) Guides, Cross Guides, Trunnion, etc.
i) Check for correct type, material & dimension
ii) Check welding
iii) Check for vent hole on pads (if applicable)
iv) Check offset for thermal expansion
v) Check clearance of guide
vi) Check U bolt for slide support
b) Spring Support
i) Verify tag no. and check details as per data
sheet/spring set
ii) Check for locking arrangement and any
damage
during transit, etc.
iii) Check for completeness of installation as per drg.
including welding of mounting cleat/ bracket
iv) Check for locking during installation and pressure test
c) Bracket Support & Inserts with Anchor Fasteners :
i) Check for members dimensions and materials
ii) Check for welding
iii) Check for bolting
iv) Check for appearance/ damage

FORMAT NO: ____________________ ( Sht 2/4 )

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2110 Rev. 0
Page 7 of 11

Checklist for Mechanical Clearance - A/G Piping

Item to check Accept Remarks


EPCC
Contractor
15. Vents/ Drains :
- As per drg.
- Orientation of valve handles
- Clearance for hose
- Requirement of additional vents/ drains (highest/lowest pt.)
16. Earthings :
a) Check for location
b) Check for dimension of lug welding
17. Joists History sheets enclosed for :
17.1 Material Traceability as per Procedure No:__________
(refer enclosed suggested Format)
17.2 Fit ups checked
17.3 NDT Complete (Radiography, MT, PT)
17.4 Stress Relieving & Hardness check complete
17.5 Positive Material Identification (PMI)
18. Checked for Removal/Blinding-off of:
a. Control, Safety and Check Valves
b. In-Line Instruments
c. Rupture Discs
d. Equipment Nozzles
e. Others
19. Supports and Weld/Flanged/Screwed connections free from
insulation or other coverage`
20. Checked Installation of (Indicate Location in Drawings)
a. Temporary Blinds/Spades
b. Temporary Strainers
c. Temporary Dummy-Spools
d. Temporary Gaskets
e. Others
21. Expansion Bellows -
a) Checks prior to installations
- Physical damages
- Transit locks are intact
- Dimensions as per drgs.
b) Check during installation
- Parallelity of mating flanges
- Face to face dimension of mating flanges
- Concentricity of mating flanges
- No stress on expansion bellows
- Record

FORMAT NO: ____________________ ( Sht 3/4 )

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2110 Rev. 0
Page 8 of 11

Checklist for Mechanical Clearance - A/G Piping

Item to check Accept Remarks


EPCC
Contractor
c) Isolation during pressure tests
- Bellow mfg. recommendations on isolation of
bellow during pr. Test to be followed
- If recommended expn. bellow to be dropped
during pr. test.
22. Cleanliness Internally and Externally
23. Rotating Equipment Final Alignment Checked with
piping
24. Removal of unwanted construction supports
25. Instrument tapings provided as per Drawing
26. Physical-Walk-Through – The – Line, checked for
gross irregularities including physical damages,
unwanted tacks, arc strikes, spatters and space for
thermal expansion.
Other :

Remarks

Reviewed by EPCC Contractor (one level higher than the checker)


Name : Designation :
Date :

OWNER/ PMC
Sign :
Date :
Name : Designation :

FORMAT NO: ____________________ ( Sht 4/4 )

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2110 Rev. 0
Page 9 of 11

ANNEX – 2
Piping Hydro Test Release Record – A/G Piping

Project : ______________________________ Report No : __________________________

Plan : ________________________________ Date : _______________________________

EPCC Contractor : ___________________ Area : _______________________________

Loop No : ____________________________ REF P & ID No. : _____________________

INCH MTR : _________________________

From ________________ To _____________

Line No. (s) Isometric No. (s) P&ID No. (s)

Test Medium : Test Duration : Design/Test Pressure :


Test Pressure Gauge Range Calibration Certificate No.: Gauge Calibration Date:
No.

Items to check Accept Witness


EPCC OW
Contractor NER
/
PMC
Field Installation Checklist Prior to Hydro-test Signed
Punch list Prepared Yes No
Pre – Hydrotest Punch items Cleared
Accessibility to Inspection/Witness Locations
Capacity of pressurizing pump checked
Cordon off area for high pressure testing, as required
Pre-hydrotest flushing carried out
IBR/Others test Witnessing Required Yes No
System Released for Pressure Testing :
EPCC Contractor : OWNER/ PMC:

Sign : Name : Sign : Name :


Date : Date :
Designation : Designation:

FORMAT NO: ____________________ ( Sht 1/2 )

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2110 Rev. 0
Page 10 of 11

Piping Hydro Test Record – A/G Piping

ACTIVITY Date Time


Water Filling and Venting started at
Water Filling Completed
Vents Closed
Isolation of Pressurizing pump
Test completed at :
- Water drained
- Air
- Temp Blinds Removed
- Checked for reinstallation of
a. Control & Safety vales
b. On line Instruments
c. Rupture disks
d. Deblinding
e. Others
- Cold setting of spring supports carried out
- Test Result Acceptable Not Acceptable
EPCC Contractor : OWNER/ PMC :

Sign : Sign:

Date : Date:
Name : Designation Name: Designation:

FORMAT NO: ____________________ ( Sht 2/2 )

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2110 Rev. 0
Page 11 of 11

ANNEX - 3
Punchlist

Project : _____________________________ Report No : ___________________________

Plan : _______________________________ Date : ________________________________

EPCC Contractor : ___________________ Area : ________________________________

Loop No : ___________________________ REF P & ID No. : _______________________

Description : _________________________________________________________________

Ref Document : _______________________________________________________________

____________________________________________________________________________

Punch Pri- Description of Location Prepared Action Due Completion


Item ority Punch Items By By date Acceptance
No.

Priority: 1. Needed for pressure test 2. Needed for commissioning 3. Needed for start up 4.
Needed for plant acceptance
EPCC Contractor : OWNER/ PMC :
Sign : Sign :
Date : Date :
Name : Designation : Name : Designation :

FORMAT NO: ____________________ Sh. 1/1

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2111 Rev 0
Page 1 of 1

INDICATIVE ITP FOR TIE-IN


Sl. EPCC Owner/
Activity
No. Contractor PMC

1 Bevel/Thickness WC HP
2. Fit up WC HP
3 Root run welding WC HP
4 DP check of root run WC HP
5. Final Welding WC HP
6. PWHT (if applicable) WC HP
7. DP check of final welding WC HP
8 Radiography check WC HP
9. Hydrostatic test (if applicable) WC HP

INSPECTION & TEST DOCUMENTS

Review Test and Inspection Documents WC Rw

Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2120 Rev 0
Page 1 of 2

INDICATIVE ITP FOR


COLUMN INTERNALS
SL. EPCC OWNER/
ACTIVITY
NO. CONTRACTOR PMC

INSTALLATION OF COLUMN INTERNALS

A. Before Installation

1. Internal Installation Procedure including identification WC Rw


of confined space hazards & mitigation thereof

2. Material inspection
a) Review of Manufacturer’s Test Certificates/ WC HP
TPI Inspection Release Note
b) Positive Material Identification, if required in Field WC HP

3. Level check on TSRs WC S

4. Check for downcomer clearance and Tray clearance WC S

5. Distance between TSRs WC S

B. After Installation

Check for

1. Exit weir height WC S

2. UDFC WC S

3. Tightness of bolts WC S

4. Orientation and tightness of clamps WC S

Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2120 Rev 0
Page 2 of 2

SL. EPCC OWNER/


ACTIVITY
NO CONTRACTOR PMC

5. Provision of lock nuts/seal plates WC S

6. Correctness of installation of shimming/bolting for top WC S


downcomer

7. Correctness of gasketing (if any) WC S

8. Tray to tray distance and level of trays WC S

9. Leak testing of seal pans as applicable WC S

10. Damaged, missing valves and valve movements for valve WC S


trays

11. Fitting of proper valve combination WC S

12. Damage to deck components WC S

13. Level and alignment of inlet weir and exit weir WC S

14. Check for slots on tray components to be fully covered WC S

15. Gaps at downcomer ends WC S

16. Removal of temporary plugs after testing WC S

17. Cleaning of all trays & inside of equipment WC S

18. Certification of installation by Vendor’s representative WC* HP

19. Final boxing up, if any WC* HP**

INSPECTION & TEST DOCUMENTS

Review Test and Inspection Documents WC Rw

* Vendor Representative to Check 100%


** By Owner/ Process Licensor

Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2130 Rev. 0
Page 1 of 4

INDICATIVE ITP FOR


FIRED HEATERS

SL. EPCC OWNER/


ACTIVITY
NO. CONTRACTOR PMC

A. PRIOR TO FABRICATION

1. Incoming Material:
a) Documents: Review & acceptance WC HP
b) Physical verification WC W

2. Welding Filler Material Approval/Qualification


a) Review of Manufacturer's Test Certificate/Documents WC HP*
b) Laboratory testing, if any
i) Carbon Steel WC Rw
ii) Alloy Steel/Stainless Steel WC W

3. WPS/PQR
a) Review of proposed Procedure WC HP

b) Welding of Test Coupens and subsequent testing WC W

c) Approval of final WPS/PQR WC HP

4. Welder performance Qualification Test WC S

5. Certification & Approval of welders before deployment on WC HP


job

6. NDT Procedure Qualification


i) Review of proposed Procedure WC HP
ii) Witnessing of Proposed Procedure Testing WC W
iii) Approval of Qualified Procedure WC HP

7. Joint Numbering for coils/ pressure parts WC S

B. FABRICATION

STEEL WORK

1. Materials as per AFC drawing WC S

2. Dimensional check WC S

3. Fit-up check WC S

Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2130 Rev. 0
Page 2 of 4

SL. EPCC OWNER/


ACTIVITY
NO. CONTRACTOR PMC

4. Radiography, as applicable
a) RT Marking (for random/spot radiography only) WC S
b) RT Interpretation WC S

5. Completion of structures as per AFC drawings WC W

COIL WORK

1. Material as per specification (check w.r.t. approved colour WC W


coding procedure) and traceability

1a. Dimensional checks WC S


1b. Fit-up check for butt joints and socket joints WC S
1c. Fit-up checks for branch joints WC S

2. Pre-heat (if any) WC S

3. Certificate of purity of purging/shielding Gas (if any) WC S

4. Purging rate (if any) and arrangement WC S

5. Shielding rate (if any) WC S

6. Baking of Electrodes WC S

7. Inter-pass cleaning & Temperature check. WC S

8. Visual check of completed welds having


- Random Radiography WC S
- 100% Radiography WC S

9. Monitoring of PWHT Cycle WC S

9a. Review of Time – Temperature graph WC W

10. Hardness Check


(i) For C.S. Coils WC S
(ii) For A.S. Coils WC S
(iii) For Heater coils of A.S. material WC W

11. PT/MT WC W

12. Radiography marking (for Random Radiography only) WC S

Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2130 Rev. 0
Page 3 of 4

SL. EPCC OWNER/


ACTIVITY
NO. CONTRACTOR PMC

13. Radiography Interpretation/ Review


i) For Carbon Steel and SS304 coils WC S
ii) For Alloy Steel and other SS WC W

14. Check Shot for Radiography WC W

15. Clearance for Hydrostatic testing WC HP

16. Positive Material Identification, as applicable WC W

17. Hydrostatic testing WC HP

C. ERECTION

1. Review of foundation check as per AFC drawing WC W

2. Lifting of radiant section columns and their alignment WC S

3. Bottom plate fit-up & welding WC S

4. Radiant shell courses fit-up and welding WC S

5. Weld visual inspection WC S

6. Review of radiographs interpreted by the EPCC WC W


Contractors

7. Cutout
a) Marking for burners, sight doors, soot blowers WC S
b) Marking for balance cut outs WC S
c) Cutting WC S

8. Coil erection in Radiant section


a) Fixing of coil support castings WC S
b) Clearance for erection of coil WC W
c) Alignment of completed coil work WC W

9. Assembly and erection of convection box


a) Erection Procedure review WC S
b) Structural including plate work WC S
c) End tube sheets and intermediate tube sheets with WC S
support brackets
d) Clearance of coil erection WC W
e) Erection of box (if applicable) WC W

Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2130 Rev. 0
Page 4 of 4

SL. EPCC OWNER/


ACTIVITY
NO CONTRACTOR PMC

10. Check Shot for radiography for coil field joints WC W

11. Clearance for Hydrostatic testing WC HP

12. Hydrostatic Testing WC HP

13. Erection, fit-up & welding of stack


i) Erection procedure WC W
ii) Erection WC S
iii) Alignment WC W

14. Erection Fit-up, welding of ducts and its support structural WC S

15. Radiography, as required on steel work


i) RT Marking WC S
ii) RT Interpretation WC W

16. FD & ID Fan ** **

17. Installation of auxiliary equipment


a) Burner alongwith ignition system and transformer WC W
b) Soot blower alongwith sequential control panel and WC W
electrical wirings
c) Damper with control panel and winch WC W
d) Air pre-heater (cast, glass, plate) and steam air heater WC W
e) Skin thermocouples WC W

18. Erection of all Platforms, ladders, Hand rails & WC S


miscellaneous structures

19. Insulation/ refractory lining WC S

20. Final Painting # #

21. Liquidation of checklist WC HP

22. Final inspection and acceptance WC HP

INSPECTION & TEST DOCUMENTS

Review Test and Inspection Documents WC Rw

# as per painting ITP


** as per separate ITP for FD & ID fan

Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2140 Rev. 0
Page 1 of 5

INDICATIVE ITP FOR


REFRACTORY & INSULATION WORKS-FIRED HEATERS

SL. EPCC OWNER/


ACTIVITY
NO. CONTRACTOR PMC

A. RADIANT SECTION

1. Radiant shell
Fixing of Ceramic fibre blanket
i) Material inspection
- Manufacturing test certificates WC Rw
- Testing, if any WC W
ii) Clearance for hot work WC W
iii) Marking of studs WC S
iv) Welding of studs with approved WPS&PQR WC S
v) Surface cleaning WC S
vi) Check for individual layers of ceramic WC W
fibre blankets and SS foils
vii) Check for overlap of ceramic blanket WC S
viii) Fixing of speed fix washer and cup lock WC S
ix) Cleaning and final inspection WC HP

2. Arch Plate
i) Material inspection
- Manufacturing test certificates WC Rw
- Testing, if any WC W
ii) Clearance for hot work WC W
iii) Marking of studs/anchors WC S
iv) Welding of studs/anchors with approved WPS & PQR WC S
v) Surface cleaning WC S
vi) Check for individual layers of Ceramic WC S
Fibre Blankets (CFB) modules and SS foils
vii) Check for overlap of CFB and modules WC S
viii) Cleaning and final inspection WC HP

3. Floor Plate
Laying of castable/fire bricks
i) Material inspection
- Manufacturing test certificates WC Rw
- Testing, if any WC W

Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2140 Rev. 0
Page 2 of 5

SL. EPCC OWNER/


ACTIVITY
NO. CONTRACTOR PMC

ii) Clearance for hot work WC W


iii) Surface cleaning WC S
iv) Check Shelf life prior to application WC W
v) Check for undulations on floor WC S
vi) Check for castable mix WC W
vii) Check for proper compaction WC S
viii) Check for thickness of castable WC S
ix) Curing WC S
x) Cleaning after laying of castable WC S
xi) Check for cracks and repair WC W
xii) Fixing of tar paper, if applicable WC S
xiii) Cleaning and final inspection WC HP

B. CONVECTION SECTION

1) Convection walls
Laying of castable
i) Material inspection
- Manufacturing test certificates WC Rw
- Testing, if any WC W
ii) Clearance for hot work WC W
iii) Marking of studs/anchors WC S
iv) Welding of studs/anchors with WC S
approved WPS & PQR
v) Surface cleaning WC W
vi) Check for undulations on wall WC S
vii) Check for castable mixing WC W
viii) Check for proper compaction WC S
ix) Check for thickness of castable WC S
x) Curing WC S
xi) Cleaning after laying of castable WC S
xii) Check for cracks and repair WC W
xiii) Cleaning and final inspection WC HP

2) End tubesheets
Laying of castable
i) Material inspection
- Manufacturing test certificates WC Rw
- Testing, if any WC W
ii) Clearance for hot work WC W

Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2140 Rev. 0
Page 3 of 5

SL. EPCC OWNER/


ACTIVITY
NO. CONTRACTOR PMC
iii) Marking of studs/anchors WC S
iv) Welding of studs/anchors with WC S
approved WPR & PQR
v) Surface cleaning WC S
vi) Check for castable mixing WC W
vii) Check for proper compaction WC S
viii) Check for thickness of castable WC S
ix) Curing WC S
x) Cleaning after laying of castable WC S
xi) Check for cracks and repair WC W
xii) Cleaning and final inspection WC HP

3) Breeching Plate
Laying of castable
i) Material inspection
- Manufacturing test certificates WC Rw
- Testing, if any WC W
ii) Clearance for hot work WC W
iii) Marking of studs/anchors WC S
iv) Welding of studs/anchors with WC S
approved WPR & PQR
v) Surface cleaning WC S
vi) Check for undulations on plate WC S
vii) Check for castable mixing WC W
viii) Check for proper compaction WC S
ix) Check for thickness of castable WC S
x) Curing WC S
xi) Cleaning after laying of castable WC S
xii) Check for cracks and repair WC W
xiii) Cleaning and final inspection WC HP

4) Header box
Laying of castable
i) Material inspection
- Manufacturing test certificates WC Rw
- Testing, if any WC W
ii) Clearance for hot work WC W
iii) Marking of studs/anchors WC S
iv) Welding of studs/anchors with WC S
approved WPR & PQR
v) Surface cleaning WC S
vi) Check for undulations on box WC S

Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2140 Rev. 0
Page 4 of 5

SL. EPCC OWNER/


ACTIVITY
NO. CONTRACTOR PMC

vii) Check for castable mixing WC W


viii) Check for proper compaction WC S
ix) Check for thickness of castable WC S
x) Curing WC S
xi) Cleaning after laying of castable WC S
xii) Check for cracks and repair WC W
xiii) Cleaning and final inspection WC HP

C STACK
Laying of castable
i) Material inspection
- Manufacturing test certificates WC Rw
- Testing, if any WC W
ii) Clearance for hot work WC W
iii) Marking of studs/anchors WC S
iv) Welding of studs/anchors with WC S
approved WPR & PQR
v) Surface cleaning WC S
vi) Check for undulations on stack shell WC S
vii) Check for castable mixing WC W
viii) Check for proper compaction WC S
ix) Check for thickness of castable WC S
x) Curing WC S
xi) Cleaning after laying of castable WC S
xii) Check for cracks and repair WC W
xii) Cleaning and final inspection WC HP
D
HOT AIR DUCT

i) Material inspection
- Manufacturing test certificates WC Rw
- Testing, if any WC W
ii) Clearance for insulation WC W
iii) External Surface cleaning WC S
iv) Provide spacer rings/anchors WC S
v) Check for thickness of the mineral wool insulation WC S

Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2140 Rev. 0
Page 5 of 5

SL. EPCC OWNER/


ACTIVITY
NO. CONTRACTOR PMC

vi) Check for staggering of joints in insulation WC S


vii) Check for providing expansion joints WC W
viii) Overlapping of metal sheet as per specification WC S
ix) Overlap on joints for aluminium sheeting WC W
as per specifications
x) Sealing aluminium sheeting WC S

Final inspection & acceptance WC HP

INSPECTION & TEST DOCUMENTS

Review Test and Inspection Documents WC Rw

Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2150 Rev. 0
Page 1 of 3

INDICATIVE ITP FOR


EQUIPMENT ERECTION (STATIC)

SL. EPCC OWNER/


ACTIVITY
NO CONTRACTOR PMC

1. BEFORE ERECTION
a. Review of foundation acceptance report WC Rw

b. Incoming material
i) Documents : Review & Acceptance WC Rw
ii) Physical verification, if required WC W

c. Readiness for erection

i) Centre line marking on equipment and foundation WC S

ii) Level of foundation (shims/ packing with marking WC S


to be prepared & kept ready)

iii) Correctness of no. & size of Foundation bolts WC S

iv) Hole dia and no. of holes in base/ structure of WC S


equipment columns

v) Matching equipment base bolt holes with actual WC S


foundation bolt layout

vi) Marking orientation WC S

vii) Checking the threads of bolts & nuts WC S

viii) Chipping & roughening of foundation WC S

d. Outside cleaning, coating/wrapping, painting WC W


(for underground equipment only)

2. ERECTION SCHEMES FOR CRITICAL EQPTS

a. Review of rigging procedure WC HP

3. SAFETY TEST

a. Load test of cranes, lifting beams, slings and shackles, WC Rw


length and dia. of sling & condition of wire rope by
competent authority

Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2150 Rev. 0
Page 2 of 3

SL. EPCC OWNER/


ACTIVITY
NO CONTRACTOR PMC

4. DURING ERECTION

a. Orientation to be checked WC S

b. Placement of packing as per AFC drg. WC S

c. Placement of Main & trailing crane as per approved WC S


rigging procedure

d. Orientation of equipment as per AFC drg. WC S

5. AFTER ERECTION

a. Tightening of Bolts and Providing washers WC S

b. Leveling and Alignment of equipments.


i) Critical equipments/ ODCs WC HP
ii) Others WC W

c. Corresponding requirement elevation & WC S


distance between nozzles in special cases.

d. Cleaning of Sleeves before grouting WC S

e. Grouting
i) Acceptance of Specified grouting materials WC HP
ii) Placement of grouting WC S
iii) Curing of grout. WC S

f. Final tightening of bolts WC S

Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2150 Rev. 0
Page 3 of 3

Sl. EPCC OWNER/


Activity
No. Contractor PMC

6. PACKED EQUIPMENTS

1. Before Installation

a. Identify the material, check thickness, dimensions, WC S


no. and angle of fingers of packing rings

2. During Installation

a. Degreasing and cleaning of packing material WC S

b. Check packing support plate WC S

c. Check for stacked or dumped packing as per WC S


specifications

d. Check for nesting WC S

e. Check that packings are touching bed limiter WC S

INSPECTION & TEST DOCUMENTS

Review Test and Inspection Documents WC Rw

Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2160 Rev. 0
Page 1 of 3

INDICATIVE ITP FOR


EQUIPMENT ERECTION (ROTARY)

SL. EPCC OWNER/


ACTIVITY
NO. CONTRACTOR* PMC

1. PRE – ERECTION ACTIVITIES

a. Review of foundation acceptance report WC HP

b. Material Supply
- Owner's supply including templates, if any WC Rw
- EPCC Contractor's supply & check testing, if any WC HP
-
c. Readiness for erection
i. Level of foundation (shims/packing with markings to WC S
be prepared & kept ready)
ii. Marking/Centre line of foundation & equipment WC S
iii. No./dia./length of anchor bolts, depth WC S
of pockets, verticality of pockets
iv. Chipping, roughing & cleaning of pockets/top of
foundation
A. Normal equipments WC S
B. Critical equipments WC HP
v. Acceptance of grouting materials as per WC HP
specifications/ Manufacturer’s recommendations

2. LIFTING TACKLES

a. Certificate from competent authority WC Rw


b. Load test of Cranes/Lifting beams/slings/ shackles/ WC Rw
Wire ropes, etc. for weight of equipments to be handled

3. VISUAL INSPECTION OF EQPT. TAG/IDENTIFICATION


NO.
a. For any damage WC S
b. Free shaft rotation WC S

4. Drilling & Tapping, holes in the base plate of eqpt. WC S


(if reqd.)

5. Submission of Rigging procedure (for critical equipments WC HP


only)

* Inspection by Vendor/Manufacturer for all critical equipments

Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2160 Rev. 0
Page 2 of 3

SL. EPCC OWNER/


ACTIVITY
NO. CONTRACTOR* PMC

6. DURING ERECTION

a. Level/elevation of base frame WC S

b. Checking of foundation bolts (for WC S


location, threading, greasing, etc.)

c. Checking orientation of equipment WC S

d. Placement of Crane(s), if applicable WC S

e. Elevation/level of equipment and placement of WC S


shims/packings as per AFC drawings

f. Distance between couplings WC S

g. Rough alignment of equipment WC S

h. Availability of Vendor’s engineer at site WC HP


(For critical equipments)

i. Cleaning of pockets/ grouting of foundation bolts’ WC S


pockets/base frame

j. Erection of auxiliary equipment/ Accessories WC S

k. Final alignment of equipment


- Without piping WC W
- With piping (After tightening the flange bolts) WC W

l. All protection & safety guards installation WC S

* Inspection by Vendor/Manufacturer for all critical equipments

Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2160 Rev. 0
Page 3 of 3

SL. EPCC OWNER/


ACTIVITY
NO. CONTRACTOR* PMC

7. POST ERECTION ACTIVITIES

a. Curing of grout WC S

b. Auxiliary connections to be mounted on eqpts as per WC S


drawing.

c. Final tightening of bolts WC S

d. Chemical cleaning of equipment parts/ connected piping WC S

e. Boxing up of equipment & connected piping WC S

f. Log book maintenance (For rotating of shaft and any WC S


other activity to be performed as per vendor’s
recommendations)

g. No load run of motors WC W

h. Re-coupling of motor & reconfirmation of alignment. WC W

INSPECTION & TEST DOCUMENTS

Review Test and Inspection Documents WC Rw

* Inspection by Vendor/Manufacturer for all critical equipments

Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2180 Rev.0
Page 1 of 5

INDICATIVE ITP FOR


STORAGE TANKS
SL. EPCC OWNER/
ACTIVITY
NO. CONTRACTOR PMC

A. PRIOR TO FABRICATION
1. Review Acceptance Report of the tanks foundation WC HP

2. Incoming Material
- Documents Review WC HP
- Physical verification WC W

3. Welding Filler Material Approval/Qualification


a) Review of Manufacturer’s Test Certificate/ WC* HP
Documents
b) Laboratory testing, if any
i) Carbon Steel WC Rw
ii) Alloy Steel/Stainless Steel WC Rw
iii) Low Temperature Services WC HP

4. WPS/PQR
a) Review of proposed procedure WC HP
b) Testing
i) Carbon Steel WC Rw
ii) Alloy Steel/Stainless Steel WC HP
c) Approval of Final WPS/PQR WC HP

5. a) Welder performance Qualification Test WC S


b) Certification & approval of welders WC HP

6. NDT Procedure Qualification


i) Review of Proposed Procedure WC HP
ii) Witnessing of the proposed procedure testing WC HP
iii) Approval of Qualified Procedure WC HP

7. Review of Joint numbering in drawings WC HP

8. Review fabrication, erection, testing procedures for WC HP


job

B. FABRICATION/ERECTION BOTTOM

1. Blast cleaning & painting of underside of bottom WC W


plates
* Notwithstanding any other tests/documentation required for qualification/approval of filler metals :
i) For Alloy Steel & Stainless Steel welding filler metals, chemical analysis to be carried out for every batch.
ii) For Low Temperature application, Impact testing to be carried out for every batch of the filler metal, to be
witnessed by PMC/Owner.
iii) For NACE filler metals, corrosion tests like HIC, SSCC, etc. to be carried out for every batch. However,
HIC/SSCC tests done earlier & duly witnessed by a reputed third party, will be acceptable.

(Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S)

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyright EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2180 Rev 0
Page 2 of 5

SL. EPCC OWNER/


ACTIVITY
NO CONTRACTOR PMC

2. Plate lay out, overlap and fit up WC S

3. Sequence of welding WC S

4. Size and positioning of backing plate for annular plates WC S

5. Baking of electrodes WC S

6. Inter-pass cleaning WC S

7. Visual check of welding WC S

8. PT/MT/NDT of annular plate butt welds and bottom plate WC W


butt welds (As applicable)

9. Vacuum box test for bottom plate welding WC S

SHELL

1. Shell course alignments and fit-up of vertical and WC W


circumferential joints before welding

2. a) Check Shell diameter, circularity, perpendicularity, WC S


straight edge before welding.
b) Check Shell diameter, circularity, perpendicularity, WC W
straight edge after welding.

3. Visual check of welding and Back chipping WC S

4. Inner side welding visual check WC S

5. Location, size, alignment and fit-up of nozzles & other WC W


openings

6. R.F. Pads fit-up/welding WC S

7. PWHT of shell, RF pads, Nozzles, manholes, etc. (As WC HP


applicable)

8. Radiography marking (for Random radiography only) WC HP

9. Curb angle and Wind girders fit-up/welding WC S

Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2180 Rev 0
Page 3 of 5

SL. EPCC OWNER/


ACTIVITY
NO CONTRACTOR PMC

10. PT/MT of nozzles, wind girders and other attachments WC W


(as applicable)

11. RF pads pneumatic test WC HP

12. Shell to bottom fit up WC W

13. Shell to bottom I/S welding root run visual/Oil chalk test WC W

14. Shell to bottom O/S welding visual and PT WC W

15. Fabrication and erection of stair ways WC S

16. Cleats welding for insulation WC S

17. Review of radiographs interpreted by the contractors WC W

FIXED ROOF

1. Blast cleaning and painting Roof Structure, underside of WC W


Roof plates

2. Location and Welding of Roof supports WC S

3. Alignment and welding of Roof structures WC S

4. Plate layout, overlap and fit-up WC S

5. Visual check of roof welds WC S

6. Location, size and alignment of roof nozzles, man-holes WC W


vents, etc.

Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2180 Rev 0
Page 4 of 5

SL. EPCC OWNER/


ACTIVITY
NO CONTRACTOR PMC
7. PWHT (as applicable)
i) Procedure review WC HP
ii) PWHT cycle monitoring WC W
iii) Time-Temp Chart Review WC HP

8. RF pads fit-up & Welding WC S

9. RF pad pneumatic testing WC W

10. PT/MT of Nozzles, vents & other attachments WC W

11. Welding of Roof plate with shell/ curb angle WC S

FLOATING ROOF

1. Temporary staging spacing and levels WC S

2. Plate layout, overlap, fit-up/welding WC S

3. Availability of approved calculations for design of buoys WC HP

4. Buoys fabrications WC S

5. Vacuum testing of roof-plate welds WC W

6. Location of sleeve supports WC S

7. Pad plate welding with roof and sleeve support WC S

8. Fixing and welding of Buoys WC S

9. Initial – lift WC S

10. Supports fixing through sleeves WC S

11. Seal welding of support sleeves from beneath after WC S


dewatering

12. Air test of Buoys WC W

13. Pontoon welding WC S

Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2180 Rev 0
Page 5 of 5

SL. EPCC OWNER/


ACTIVITY
NO CONTRACTOR PMC

14. Location, fixing and welding of man holes, drains etc WC W

15. Shell to pontoon clearance WC W

16. Seal fixing WC W

17. Floating Roof Testing, as required e.g. flooding etc. WC W

C. TESTING

1. Correctness of testing arrangements especially size of WC S


blind flanges/vents/drains/ temporary piping.

2. Mechanical / Inspection clearances WC HP

3. Earthing of ladder & shell WC HP

4. Settlement readings during water filling WC HP

5. Hammer test WC HP

6. Air pressure test WC HP

7. Vacuum test WC HP

8. Roof collapsibility test in case of floating roof tanks WC HP

9. Calibration of tanks from Statutory authorities WC Rw

INSPECTION & TEST DOCUMENTS

Review Test and Inspection Documents WC Rw

NOTE : 1) For cleaning & painting, please refer ITP No. 6648-00-19-43-2501
2) For Insulation, please refer ITP No. 6648-00-19-43-2505

Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2500 Rev. 0
Page 1 of 2

INDICATIVE

INSPECTION & TEST PLAN (ITP)

FOR

GENERAL WORKS

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2500 Rev. 0
Page 2 of 2

INDEX

S.NO DESCRIPTION DOCUMENT NO. REV.

GENERAL WORKS

1. Painting 6648-00-19-43-2501 0

2. Insulation 6648-00-19-43-2505 0

3. Refractory Lining 6648-00-19-43-2510 0

4. Ceramic Fibre Lining 6648-00-19-43-2515 0

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2501 Rev 0
Page 1 of 2

INDICATIVE ITP FOR


PAINTING

SL. EPCC OWNER/


ACTIVITY
NO. CONTRACTOR PMC

A. BEFORE FABRICATION

1. a) Approved supplier, product and supplier's materials test WC HP


certificate
b) Check manufacturing date, expiry period and shelf life WC HP

2. a) Physical condition of materials; WC HP


original manufacturers packing/ containers
b) Confirm identification/ Transfer of identification of WC Rw
materials before painting

3. a) Adequacy of blasting machine capacity for blast cleaning WC Rw


b) Type and quality of abrasive being used for blast cleaning WC Rw
c)Adequacy of Airless spray equipment, air spray equipment WC Rw
and paint brushes

4. Performance test of paint applicator and blast cleaning WC W


operator

5. Check quality of dry air for blast cleaning and spray WC S


application

6. Inspection of blast cleaning operation


- Inspect for surface cleanliness by visual stds. of WC S
ISO 8501/SSPC
- Measurement of surface profile by WC S
Micrometer/Elkometer/Stylus instrument

7. Wet film thickness and over coating interval for each coat of WC S
paint during application

8. Dry film thickness after final coat WC S


9. Inspection of final curing/ drying, adhesion, hardness, WC W
surface finish, sagging, hiding and pinhole detection

10. Painting identification band/ code, etc. WC S


11. Acceptance prior to shifting to fabrication shop, if applicable WC S

Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2501 Rev 0
Page 2 of 2

SL. EPCC OWNER/


ACTIVITY
NO. CONTRACTOR PMC

B. AFTER INSTALLATION

1. a) Approved supplier product : WC HP


Suppliers materials test certificate
b) Manufacturing date, expiry period and shelf life WC HP

2. Physical condition of materials; original manufacturers WC HP


packing/ containers

3. Confirm completion of

a) Hydro testing of piping WC S


b) Mechanical clearance of structure & equipments WC Rw

4. a) Adequacy of surface preparation tools and tackles WC Rw


b) Check the quality of surface preparation WC S

5. a) Performance test for paint applicator for spray WC W


application
b) Adequacy of airless spray equipment and air spray WC Rw
equipment and paint brushes and quality of dry air for
paint application

6. Wet film thickness and over coating interval for each WC S


coat of application

7. Dry film thickness after final coat WC S

8. Inspection of final curing/ drying, adhesion, hardness, WC S


surface finish, sagging, hiding and pinhole detection

9. Identification of colour bands, direction marking WC S

10. Final Acceptance WC HP

INSPECTION & TEST DOCUMENTS


Review Test and Inspection Documents WC Rw

Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2505 Rev 0
Page 1 of 1

INDICATIVE ITP FOR


INSULATION

SL. EPCC OWNER/


ACTIVITY
NO CONTRACTOR PMC

1. PRIOR TO APPLICATION OF INSULATION


a. Material Test certificates from supplier of WC Rw
insulation material and acceptance thereof
b. Check testing, if required WC Rw*

2. DURING APPLICATION OF INSULATION


a. Surface preparation WC S

b. Fixing of spacer rings and checking their spacing WC S

c. Fixing of support rings and checking their spacing WC S


in case of vertical piping

d. Fixing of insulation lugs and angle rings in case of WC S


vessels, tanks, etc.

e. Thickness of insulation WC S

f. Aluminium foil for S.S. Piping/Vessels WC S

g. Overlap of cladding at vertical and horizontal joints WC S

h. Expansion joints, if any WC S

i. Inspection windows WC S

j. S.S. foil for S.S. piping WC S

k. Final finish WC W

3. ADDITIONAL CHECKS FOR COLD INSULATION


a. Wooden supports WC S

b. Vapour barrier WC S

c. Vapour sealant WC S

d. Insul coat WC S

INSPECTION & TEST DOCUMENTS


Review Test and Inspection Documents WC Rw

Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2510 Rev 0
Page 1 of 2

INDICATIVE ITP FOR


REFRACTORY LINING

SL. EPCC OWNER/


ACTIVITY
NO. CONTRACTOR PMC

PRIOR TO START OF LINING


a. Material Test certificates from suppliers WC Rw

b. Field tests and tests from approved laboratories WC W/ Rw

c. Availability of Refractory specialist at site WC HP


(Contactor’s/ Vendor’s)

DURING LINING

a. INSULATING FIRE BRICKS

i. Clearance for completion of structural works WC S


including cleats/ lugs/ anchors/ hooks, etc.

ii. Cleanliness of the surfaces to be lined WC S

iii. Insulating layer application, wherever applicable WC S

iv. Metal foil application, wherever applicable WC S

v. Checking of bricks for their soundness WC S


(squareness, cracks and for any other damages)

vi. Mix proportion WC W

vii. Laying of bricks as per specifications WC S

viii. Line and verticality WC W

ix. Identifying location of expansion joints WC W

x. Filling expansion joints, wherever applicable WC W

xi. Finishing works WC S

Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2510 Rev 0
Page 2 of 2

SL. EPCC OWNER/


ACTIVITY
NO CONTRACTOR PMC

b. INSULATING CASTABLE CONCRETE

i. Clearance for completion of structural steel work WC W


including cleats/ support lugs/ anchors/hooks, etc.

ii. Cleanliness of the surface to be lined WC W

iii. Insulating layer application, wherever applicable WC S

iv. Metal foil application, wherever applicable WC S

v. Fixing of wire mesh WC S

vi. Fixing of shuttering/ scaffolding and providing WC S


pockets for pouring mortar

vii. Mix proportion WC W

viii. Identifying location of expansion joints WC S

ix. Ramming of mortar for achieving uniform density WC S

x. Filling expansion joints, wherever applicable WC S

xi. Wetting of previous layer prior to casting the WC S


Construction joints

xii. Pointing WC S

xiii. Curing WC S

INSPECTION & TEST DOCUMENTS


Review Test and Inspection Documents WC Rw

NOTE : Surveillance/witness may be increased in case of boilers, heaters, etc. as per


specific requirements given in the specifications.

Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2515 Rev 0
Page 1 of 1

INDICATIVE ITP FOR


CERAMIC FIBRE LINING

SL. EPCC OWNER/


ACTIVITY
NO CONTRACTOR PMC

PRIOR TO START OF LINING

i. Material Test certificates from suppliers WC Rw

ii. Field tests and tests from approved laboratories, if WC Rw


applicable

iii. Availability of Refractory specialist at site WC HP


(EPCC Contactor’s/ Vendor’s/PMCs)

DURING LINING

i. Clearance for completion of structural works WC W


including welding of cleats/ lugs/ anchors/hooks, etc.

ii. Cleanliness of surfaces to be lined WC S

iii. Laying of Ceramic fibre blanket layer wise WC S


(As per AFC drawings)

iv. Provision of cups locks/ arrangement for CF lining WC S


holding

v. Identifying location of expansion joints WC S

vi. Filling expansion joints as per specifications/ AFC WC S


drawings

vii. Finishing works WC S

INSPECTION & TEST DOCUMENTS

Review Test and Inspection Documents WC Rw

Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2600 Rev.0
Page 1 of 2

INDICATIVE

INSPECTION & TEST PLAN (ITP)

INSTRUMENTATION WORKS

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyright EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2600 Rev.0
Page 2 of 2

INDEX

S.NO DESCRIPTION DOCUMENT NO. Rev.

INSTRUMENTATION WORKS
FIELD INSTRUMENTATION WORKS

1. Incoming Material Check 6648-00-19-43 - 2601 0


2. Shop Fabrication 6648-00-19-43 - 2602 0
3. Calibration of Instruments 6648-00-19-43 – 2603 0
4. Fabrication, Erection of Cable Duct 6648-00-19-43 – 2604 0
5. Fabrication, Erection of Cable Tray, Angle Tray for Cable 6648-00-19-43 – 2605 0
Laying & Tube Laying
6. Fabrication, Installation of Instrument Support/ Stanchions, 6648-00-19-43 – 2606 0
Panel Supports, Canopies, JB Supports
7. Installation of Field Instruments 6648-00-19-43 – 2607 0
8. Installation of Impulse Lines 6648-00-19-43 – 2608 0
9. Cable Laying, Glanding and Termination 6648-00-19-43 – 2609 0
10. Installation of Junction Boxes, Local Control Panel 6648-00-19-43 – 2610 0
11. Fabrication & Erection of Air Lines and Tubing of 6648-00-19-43 – 2611 0
Pneumatic Lines
12. Installation of Level Switches, Level Gauges and Float 6648-00-19-43 – 2612 0
Type Level Instruments
13. Installation of Test Thermowells, Temperature Gauges and 6648-00-19-43 – 2613 0
Temperature Elements
14. Loop Checking 6648-00-19-43 – 2614 0
15. Impulse Piping 6648-00-19-43 – 2615 0
CONTROL ROOM INSTRUMENTATION WORKS

16. Incoming Material Inspection and Panel Erection 6648-00-19-43 – 2631 0


17. Fabrication & Erection of Cable Trays 6648-00-19-43 – 2632 0
18. Laying, Glanding & Termination of Interconnection Cables, 6648-00-19-43 – 2633 0
Prefabricated Cables, System Cables, Power Cables and
Field Cables
19. Power ‘ON’ of Panels and Pre-commissioning of the 6648-00-19-43 – 2634 0
System
20. Field Loop Checking and ‘System Acceptance Test’ 6648-00-19-43 - 2635 0

Pl. refer document No.6648-00-19-43-2111 for Tie-In.

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2601 Rev.0
Page 1 of 1

INDICATIVE ITP FOR INCOMING MATERIAL CHECK


(FIELD INSTRUMENTATION WORKS)

SL. EPCC OWNER/


ACTIVITY
NO. CONTRACTOR PMC

1. Material receipt as per material specifications / WC W


standards

2. Proper storage of owner supplied items & EPCC WC S


contractor supplied items

INSPECTION & TEST DOCUMENTS

Review Test and Inspection documents WC Rw

Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2602 Rev.0
Page 1 of 1

INDICATIVE ITP FOR SHOP FABRICATION


(FIELD INSTRUMENTATION WORKS)

SL. EPCC OWNER/


ACTIVITY
NO. CONTRACTOR PMC

1. Material receipt as per purchase specification WC W

2. Qualification of WPS /Welders WC W

3. Usage of approved consumables WC HP

4. Following proper job procedure WC Rw

5. NDT WC W

6. PWHT & Hardness test WC W

7. Shop testing WC W

8. Painting and Storage WC S

INSPECTION & TEST DOCUMENTS

Review Test and Inspection documents WC Rw

Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2603 Rev.0
Page 1 of 1

INDICATIVE ITP FOR CALIBRATION OF INSTRUMENTS


(FIELD INSTRUMENTATION WORKS)

SL. EPCC OWNER/


ACTIVITY
NO. CONTRACTOR PMC

1. Availability of approved standard calibrated test WC S


equipments

2. Validity of calibration equipments WC S

3. Air conditioning, dust free environment WC S

4. Availability of approved data sheets, calibration WC Rw


procedures, standards, vendor’s manuals

5. Usage of appropriate tools and tackles WC S

6. Usage of qualified /trained personnel WC S

7. Mounting of instruments, instrument tag & model WC S


during calibration

8. Checking of Instrument ranges, supply & output for WC S


proper connections

9. Calibration of local gauges WC Rw

10. Calibration of electronic instruments/control valves WC S

11. Calibration of safety valves, shutdown valves and WC W


trip switches

12. Calibration of special instruments /float type WC W


instruments

13. Ensuring procedure and record WC Rw

14. Plugging of free entries WC S

15. Stamping of calibration date on instruments WC S

INSPECTION & TEST DOCUMENTS

Review Test and Inspection documents WC Rw

Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2604 Rev.0
Page 1 of 1

INDICATIVE ITP FOR FABRICATION, ERECTION OF CABLE DUCT(GI)


(FIELD INSTRUMENTATION WORKS)

SL. EPCC OWNER/


ACTIVITY
NO. CONTRACTOR PMC

1. Availability of correct material WC S

2. Usage of proper tools and tackles WC S

3. Use of approved consumables WC S

4. Correctness of dimensions of duct WC S

5. Welding as per Standards / specifications WC Rw

6. Installation & alignment of support as per structural WC Rw


drg. & Documents

7. Painting of support WC S

8. Grinding of sharp edges before erection WC S

9. Alignment of cable duct WC S

10. Covering of duct after completion of cable laying / WC S


dressing

11. Usage of proper clamp & fasteners WC S

12. Installation of guide supports WC S

INSPECTION & TEST DOCUMENTS

Review Test and Inspection documents WC Rw

Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2605 Rev.0
Page 1 of 1

INDICATIVE ITP FOR FABRICATION, ERECTION OF CABLE TRY,


ANGLE TRAY FOR CABLE LAYING AND TUBE LAYING
(FIELD INSTRUMENTATION WORKS)

SL. EPCC OWNER/


ACTIVITY
NO. CONTRACTOR PMC

1. Correct size & routing of tray/angle WC S

2. Supporting as per standards / specifications WC S

3. Removal of sharp edges and sharp bends WC S

4. Fastening / welding of trays / angles WC S

5. Check for fouling with piping / structures WC S

6. Check for any obstruction / space for maintenance WC S

INSPECTION & TEST DOCUMENTS

Review Test and Inspection documents WC Rw

Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2606 Rev.0
Page 1 of 1

INDICATIVE ITP FOR FABRICATION, INSTALLATION OF INSTRUMENT


SUPPORT/STANCHIONS, PANEL SUPPORTS, CANOPIES,
JB SUPPORT
(FIELD INSTRUMENTATION WORKS)

SL. EPCC OWNER/


ACTIVITY
NO. CONTRACTOR PMC

1. Availability of correct material WC -

2. Usage of proper tools and tackles WC -

3. Availability of approved Junction Box layout and WC Rw


instrument location plan

4. Correctness of dimensions, height etc. WC S

5. Approved welder, consumables, standards WC Rw

6. Check for installation, hole to hole dimension & WC S


alignment / fit up

7. Check for no sharp edges WC S

8. Painting WC S

9. Ensure physical walk through the line WC S

10. Maintenance space WC S

11. Providing of vent holes on stanchion WC -

12. Sealing of vent holes WC Rw

INSPECTION & TEST DOCUMENTS

Review Test and Inspection documents WC Rw

Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2607 Rev.0
Page 1 of 1

INDICATIVE ITP FOR INSTALLATION OF FIELD INSTRUMENTS


(FIELD INSTRUMENTATION WORKS)

SL. EPCC OWNER/


ACTIVITY
NO. CONTRACTOR PMC

1. Availability of approved location plans, piping WC Rw


GADs, P&ID, vendor’s manual etc.

2. Installation of proper support / instrument WC Rw


stanchion, canopy

3. Instrument tag as per P &ID, model & make as per WC S


instruments data sheet

4. Physical walk through the line WC S

5. Alignment of the instruments WC S

6. Mounting of accessories as per instrument data WC S


sheet

7. Visibility & maintenance clearance WC S

INSPECTION & TEST DOCUMENTS

Review Test and Inspection documents WC Rw

Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2608 Rev.0
Page 1 of 1

INDICATIVE ITP FOR INSTALLATION OF IMPULSE LINES


(FIELD INSTRUMENTATION WORKS)

SL. EPCC OWNER/


ACTIVITY
NO. CONTRACTOR PMC

1. Direction of flow, tapping orientation, standard, WC S


piping material

2. Upstream & downstream straight runs WC S

3. Usage of appropriate tools & tackles WC -

4. Usage of approved welder, consumables & WC Rw


procedures

5. No burrs & sharp edges on tube bends WC S

6. Correctness & hardness of tubes and fittings WC Rw

7. Smooth bends/ free draining WC S

8. Ferrule punching WC S

9. Supporting as per standards/ specifications WC S

10. Direction of valves / valve manifolds WC S

11. NDT, PWHT, DT Radiography WC HP

12. Usage of approved sealant etc. WC Rw

13. Testing WC HP

14. Material Traceability WC S

15. PMI (before Leak Test) WC HP

INSPECTION & TEST DOCUMENTS

Review Test and Inspection documents WC Rw

Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2609 Rev.0
Page 1 of 1

INDICATIVE ITP FOR CABLE LAYING, GLANDING & TERMINATION


(FIELD INSTRUMENTATION WORKS)

SL. EPCC OWNER/


ACTIVITY
NO. CONTRACTOR PMC

1. Correctness of cable type as per cable schedule WC S

2. Measurement & routing WC S

3. Check cable for continuity, insulation resistance, WC S


megger values

4. Identification tags/ tag plates & proper dressing & WC S


clamping

5. Separation of signal / thermocouple and power WC S


cables

6. Cable glands as per area classification, size of WC S


cable, JB entry etc.

7. Identification / ferrule and dressing inside junction WC S


boxes and instrument

8. Crimpable type lugs and proper crimping WC S

9. Telephone wire connection inside JB WC S

10. Shield wire dressing / sleeving and termination WC S

11. Insulation of shield wire on instrument end WC S

INSPECTION & TEST DOCUMENTS

Review Test and Inspection documents WC Rw

Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2610 Rev.0
Page 1 of 1

INDICATIVE ITP FOR INSTALLATION OF JUNCTION BOXES (JB),


LOCAL CONTROL PANEL (LCP)
(FIELD INSTRUMENTATION WORKS)

SL. EPCC OWNER/


ACTIVITY
NO. CONTRACTOR PMC

1. Correct tag, type, location, size of junction box / WC S


LCP

2. Correct cable entries WC S

3. Alignment & fasteners WC Rw

4. Tightening of fasteners WC S

5. Tightening & numbering of terminal blocks WC Rw

6. Availability of telephone sockets (for JBs) & WC S


earthing point

7. Earthing of JB / LCP WC S

8. Plugging of free entries with correct plugs WC S

9. Wiring of various hardwares in LCP s per approved WC S


wiring drawings

10. Protection of JB and LCP WC S

INSPECTION & TEST DOCUMENTS

Review Test and Inspection documents WC Rw

Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2611 Rev.0
Page 1 of 1

INDICATIVE ITP FOR FABRICATION & ERECTION OF AIR LINES AND


TUBING OF PNEUMATIC LINES
(FIELD INSTRUMENTATION WORKS)

SL. EPCC OWNER/


ACTIVITY
NO. CONTRACTOR PMC

1. Availability of AFC air distribution drawings WC Rw

2. Usage of correct size, thread etc. Jigs/ die sets for WC S


threading of pipes

3. Packing material / sealant used at thread joints WC S

4. Providing of three piece union at each loop for easy WC S


maintenance

5. Drain & vent assemblies WC S

6. Tightening at joints WC S

7. Supporting and clamping WC S

8. Test air lines as per standards / specifications and WC W


record

9. Check for inlet, outlet, signal, test and drain WC S


connection on the instrument

10. Check for correct supply as per data sheets WC S

11. Flush lines before connection WC S

12. Ensure punching of ferrules WC S

13. Tagging at both ends of tubes WC S

INSPECTION & TEST DOCUMENTS

Review Test and Inspection documents WC Rw

Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2612 Rev.0
Page 1 of 1

INDICATIVE ITP FOR INSTALLATION OF LEVEL SWITCHES, LEVEL


GAUGES AND FLOAT TYPE LEVEL
(FIELD INSTRUMENTATION WORKS)

SL. EPCC OWNER/


ACTIVITY
NO. CONTRACTOR PMC

1. Usage of correct flanges and piping materials WC S

2. Deployment of approved welding man power, WC S


usage of approved consumables & procedures

3. Alignment of flanges, visibility of gauges and WC S


orientation of instrument

4. Verticality of the instrument WC S

5. Installation of float, displacer, instrument WC S


accessories as per data sheet / vendor’s instruction
manuals

6. QA/QC clearances for welding & testing WC HP

7. Tightness of guide wires WC S

8. Usage of correct size, rating & type of gasket and WC S


stud/nuts as per PMS

9. Required tightness of the stud/nuts WC S

10. Testing as per standards and specifications WC W

INSPECTION & TEST DOCUMENTS

Review Test and Inspection documents WC Rw

Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2613 Rev.0
Page 1 of 1

INDICATIVE ITP FOR INSTALLATION OF TEST THERMOWELLS,


TEMPERATURE GAUGES AND TEMPERATURE ELEMENTS
(FIELD INSTRUMENTATION WORKS)

SL. EPCC OWNER/


ACTIVITY
NO. CONTRACTOR PMC

1. Correctness of range, rating, immersion length (U WC S


length) as per P &ID / Instrument data sheets

2. Check for tapping size, orientation, location as per WC S


P&ID

3. Usage of correct size, rating & type of gasket and WC S


stud/nuts as per PMS

4. Required tightness of stud/nuts WC S

5. Visibility & orientation of gauges WC S

6. Plugging of free entries with correct size plugs WC S

INSPECTION & TEST DOCUMENTS

Review Test and Inspection documents WC Rw

Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2614 Rev.0
Page 1 of 1

INDICATIVE ITP FOR LOOP CHECKING


(FIELD INSTRUMENTATION WORKS)

SL. EPCC OWNER/


ACTIVITY
NO. CONTRACTOR PMC

1. Completeness of installation as per standards & WC S


specifications

2. Liquidation of punch point list as per ITP WC HP

3. Availability of standard calibration equipment WC Rw

4. Coordination with DCS vendor WC S

5. Simulation of instruments as per specifications WC W

6. Re calibrate / fine tune instruments for accurate WC W


response

7. Check for interlocks and response of final control WC W


element

8. Ensure proper response and record WC Rw

9. Loop acceptance WC HP

INSPECTION & TEST DOCUMENTS

Review Test and Inspection documents WC Rw

Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2615 Rev.0
Page 1 of 11

INDICATIVE ITP FOR IMPULSE PIPING

(FIELD INSTRUMENTATION WORKS)


SL.
NO ACTIVITY EPCC OWNER/
CONTRACTOR PMC

A. PRIOR TO FABRICATION

1. Incoming Material
a) Documents (MRIR etc.): Review & acceptance WC HP
b) Physical verification WC W

2. Welding Filler Material Approval/Qualification


a) Review of Manufacturer’s Test Certificates/Documents WC* HP*
& Sampling
b) Laboratory Testing, if any
i) Carbon Steel WC Rw
ii) Alloy Steel/Stainless Steel WC S/Rw
iii) All other Materials including NACE CS and CS for H2 WC W
Service

3. WPS/PQR
a) Review of proposed procedure WC HP
b) Welding of Test Coupens and subsequent testing
i) Carbon Steel, Stainless Steel WC Rw
ii) Alloy Steel WC W
iii) All other Materials including NACE CS and CS for H2 WC W
Service
c) Approval of final WPS/PQR. WC HP

4. Welder performance Qualification WC S

4a. Certification & approval of welders. WC HP

5. NDT Procedure Qualification


i) Review of proposed procedure WC HP
ii) Witnessing of Proposed Procedure Testing WC W
iii) Approval of Qualified Procedure WC HP

6. Review of Joint numbering Procedure, numbering in WC W


Isometrics (Big & Small bore)/Sketches

7. Material traceability & Transfer of Heat Nos. WC S


(Material Traceability not required for utility services)

* Notwithstanding any other tests/documentation required for qualification/approval of filler metals :


i) For Alloy Steel & Stainless Steel welding filler metals, chemical analysis to be carried out for every batch.
ii) For low temp. services piping, Impact testing to be carried out for every batch of the filler metal, to be
witnessed by Owner/ PMC.

For NACE filler metals, corrosion tests like HIC, SSCC, etc. to be carried out for every batch. However, HIC/SSCC tests
done earlier & duly witnessed by a reputed third party, will be acceptable.

Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2615 Rev.0
Page 2 of 11

SL. EPCC OWNER/


ACTIVITY
NO. CONTRACTOR PMC

B. FABRICATION (SHOP & FIELD)

1. Material as per piping class (check w.r.t. approved WC S


colour coding procedure), Fit-up check and
Traceability check

2. Pre-heat (if any) WC S

3. Certificate of purity of purging/shielding Gas (if any) WC S

4. Purging rate (if any) and arrangement WC Rw

5. Shielding rate (if any) WC S

6. Baking of Electrodes WC S

7. Inter-pass cleaning & Temperature check. WC S

8. Visual Examination of completed welds WC S

9. Monitoring of PWHT Cycle WC S

9a. Review of Time – Temperature graph


i) CS WC S
ii) AS WC W

10. Hardness Check WC S

11. PT/MT WC S

12. Identification of Joints for Radiography (for Random WC S


Radiography only)

13. Review of Radiographs interpreted by the EPCC


Contractor

i) For Carbon Steel Piping, SS Piping(type 304) WC S


ii) For Alloy Steel Piping and other SS piping WC W
iii) For H2, NACE piping, other exotic material WC HP
piping

Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2615 Rev.0
Page 3 of 11

SL. ACTIVITY EPCC OWNER/


NO. CONTRACTOR PMC

C PROOF TESTING
(See enclosed checklist in Annex-1)

1. Procedure Review WC HP

2. Preparation of Punch list (Ref. Annex-3) WC S

3. Review of Punch List WC HP

4. Liquidation of check list, if applicable WC HP

5. Correctness of Testing arrangements WC S

6. Scrutiny of test packs for Mechanical & NDT Clearance WC HP

7. Positive Material Identification as per specification after WC S


completion of installation.

8. a) Review of Calibration certificates of pressure Gauges WC HP


b) Field Calibration, if any WC S

9. Air/Water Flushing (preliminary) WC S

10. Visual inspection of all weld joints for leak during


Pneumatic/ Hydrotesting (See Annex-2)
a) Category ‘D’ services WC S
b) All other services WC W

11. Draining of Water & Air Drying WC S

12. Removal of temporary blinds/supports. WC S

Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2615 Rev.0
Page 4 of 11

SL. ACTIVITY EPCC OWNER/


NO. CONTRACTOR PMC

13. Boxing up including reinstallation of flappers of check WC S


valves

14. Review of Records of fasteners & gaskets WC S

15. Torque tightening/ tensioning of flange joints, WC S


wherever applicable

INSPECTION & TEST DOCUMENTS

Review Test and Inspection Documents WC Rw

For liquidation of Punch list, see Annex - 3

Note : Pre-commissioning activities such as chemical cleaning, card board blasting, system testing
are not covered by these ITP's. The EPCC Contractor shall develop ITP's for such activities
and obtain Owner/ PMC/ Licensor's approval.

A/G Above Ground NDT Non Destructive Testing


AS Alloy Steel i.e. Cr-Mo steels like A335 NRV Non Return Valve
Gr P11, P5, P9,P22,etc
CS Carbon Steel PMI Positive Material Identification
CSO Car Seal Open PQR Procedure Qualification Record
GAD General Arrangement Drawings PT Penetrant Testing
HIC Hydrogen Induced Cracking PWHT Post Weld Heat Treatment
LO/ LC Lock Open/ Lock Close RF Reinforcement
MT Magnetic Particle Testing SS Stainless Steel like A312 TP 304, 316,
321, 304L, 316L, 316Mo, etc.
NACE National Association of Corrosion SSCC Sulphide Stress Corrosion Cracking
Engineers
WPS Welding Procedure Specification

Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2615 Rev.0
Page 5 of 11

ANNEX – 1
Checklist for Mechanical Clearance - IMPULSE Piping

Project : ___________________________ Report No : ____________________________

Plant/Unit : _________________________ Date : ________________________________

EPCC Contractor : _________________ Area : ________________________________

Loop No : _________________________ INCH MTR : __________________________

Line No (Isometric No.) Rev. GAD No. Rev. P&ID No. Rev.

Items to be checked Accept Remarks


EPCC
Contractor
1. Installation checked as per Isometric w.r.t.
CONFIGURATION : Route, plumb, elevation,
Clearance for thermal
expansion/ insulation
BRANCH : Location, angle, orientation,
type, RF pad, etc.
STEAM TRAP : Direction
2. Installation checked as per P&ID

3. Isometrics completed for ( enclosed ):


a. Joint Numbering (Shop & Field Welds)
b. Spool Numbering
c. As-built routing & dimensions

4. Valves(Check Rating, Gaskets, Flow Nos


Direction, Sheet No., Tag No., Spindle
direction, CSO LO/LC, Damage, etc)
Gate Valves
Globe Valves
Check Valves
Control Valves Tag Nos.:
Safety Valves Tag Nos.:
Any other valves :

5. Strainers : Check for clearance, flow


direction, elements

FORMAT NO: ____________________ ( Sht 1/4 )

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2615 Rev.0
Page 6 of 11

Checklist for Mechanical Clearance - IMPULSE Piping

Item to check Accept Remarks


EPCC
Contractor
6. Flanged Joints
Total Nos.
Check for type of flange
Check for Rating
Check for Alignment, (proper gap & parallelity
Check for Correct Studs & nuts – dia., length, Material,
uniform protrusion of studs, anti seize compound
Check for correct gasket ( type, size, spec., thickness,
etc.)
Torque values used for tightening

7. Seal Welding of Screwed Connections (if Required)

8. Vents/Drains as per Dwg and Provision of additional high


point Vents and/or low point Drains, if reqd.

9. Orifice Flanges :
Check for Tag No., tapping orientation, tap valve, jack
screw, straight run length of upstream & downstream

10. Local Gauges : Check for accessibility

11. Supports as per drg. and specifications

FORMAT NO: ____________________ ( Sht 2/4 )

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2615 Rev.0
Page 7 of 11

Checklist for Mechanical Clearance - IMPULSE Piping

Item to check Accept Remarks


EPCC
Contractor
12. Vents/ Drains :
- As per drg.
- Orientation of valve handles
- Clearance for hose
- Requirement of additional vents/ drains (highest/lowest pt.)

13. Earthings :
a) Check for location
b) Check for dimension of lug welding

14. Joists History sheets enclosed for :


14.1 Material Traceability as per Procedure No:__________
(refer enclosed suggested Format)

14.2 Fit ups checked

14.3 NDT Complete (Radiography, MT, PT)

14.4 Stress Relieving & Hardness check complete

14.5 Positive Material Identification (PMI)


Checked for Removal/Blinding-off of:
a. Control, Safety and Check Valves
b. In-Line Instruments
c. Rupture Discs
d. Equipment Nozzles
e. Others

15. Supports and Weld/Flanged/Screwed connections free from


insulation or other coverage`

16. Checked Installation of (Indicate Location in Drawings)


a. Temporary Blinds/Spades
b. Temporary Strainers
c. Temporary Dummy-Spools
d. Temporary Gaskets
e. Others

FORMAT NO: ____________________ ( Sht 3/4 )

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2615 Rev.0
Page 8 of 11

Checklist for Mechanical Clearance - IMPULSE Piping

Item to check Accept Remarks


EPCC
Contractor
17. Cleanliness Internally and Externally

18. Removal of unwanted construction supports

19. Instrument tapings provided as per Drawing

20. Physical-Walk-Through – The – Line, checked for


gross irregularities including physical damages,
unwanted tacks, arc strikes, spatters and space for
thermal expansion.
Other :

Remarks

Reviewed by EPCC Contractor (one level higher than checker)


Name : Designation :
Date :

OWNER/ PMC
Sign :
Date :
Name : Designation :

FORMAT NO: ____________________ ( Sht 4/4 )

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2615 Rev.0
Page 9 of 11

ANNEX – 2
Piping Hydro Test Release Record – IMPULSE Piping

Project : ______________________________ Report No : __________________________

Plan : ________________________________ Date : _______________________________

EPCC Contractor : ___________________ Area : _______________________________

Loop No : ____________________________ REF P & ID No. : _____________________

INCH MTR : _________________________

From ________________ To _____________

Line No. (s) Isometric No. (s) P&ID No. (s)

Test Medium : Test Duration : Design/Test Pressure :


Test Pressure Gauge Range Calibration Certificate No.: Gauge Calibration Date:
No.

Items to check Accept Witness


EPCC OW
Contractor NER
/
PMC
Field Installation Checklist Prior to Hydrotest Signed
Punch list Prepared Yes No
Pre – Hydrotest Punch items Cleared
Accessibility to Inspection/Witness Locations
Capacity of pressurizing pump checked
Cordon off area for high pressure testing, as required
Pre-hydrotest flushing carried out
Statutory Authorities/Others test Witnessing Required Yes No
System Released for Pressure Testing :
EPCC Contractor : OWNER/ PMC:

Sign : Name : Sign : Name :


Date : Date :
Designation : Designation:
FORMAT NO: ____________________ ( Sht 1/2 )

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2615 Rev.0
Page 10 of 11

Piping Hydro Test Record – IMPULSE Piping

ACTIVITY Date Time


Water Filling and Venting started at
Water Filling Completed
Vents Closed
Isolation of Pressurizing pump
Test completed at :
- Water drained
- Air
- Temp Blinds Removed
- Checked for reinstallation of
f. Control & Safety vales
g. On line Instruments
h. Rupture disks
i. Deblinding
j. Others
- Cold setting of spring supports carried out
- Test Result Acceptable Not Acceptable
EPCC Contractor : OWNER/ PMC :

Sign : Sign:

Date : Date:
Name : Designation Name: Designation:

FORMAT NO: ____________________ ( Sht 2/2 )

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2615 Rev.0
Page 11 of 11

ANNEX - 3
Punchlist

Project : _____________________________ Report No : ___________________________

Plan : _______________________________ Date : ________________________________

EPCC Contractor : ___________________ Area : ________________________________

Loop No : ___________________________ REF P & ID No. : _______________________

Description : _________________________________________________________________

Ref Document : _______________________________________________________________

____________________________________________________________________________

Punch Prio- Description of Location Prepared Action Due Completion


Item rity Punch Items By By date Acceptance
No.

Priority: 1. Needed for pressure test 2. Needed for commissioning 3. Needed for start up 4.
Needed for plant acceptance
EPCC Contractor : OWNER/ PMC :
Sign : Sign :
Date : Date :
Name : Designation : Name : Designation :

FORMAT NO: ____________________ Sh. 1/1

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2631 Rev.0
Page 1 of 1

INDICATIVE ITP FOR INCOMING MATERIAL INSPECTION & PANEL


ERECTION
(CONTROL ROOM INSTRUMENTATION WORKS)

SL. EPCC OWNER/


ACTIVITY
NO. CONTRACTOR PMC

1. Check for receipt of materials/ panels as per WC W


purchase requisition, inspection release note, bill of
materials, etc.

2. Ensure proper storage of materials at site WC S

3. Ensure shifting of panels into the control room WC S


without damage

4. Check for hole to hole dimensions of the base WC S


frames with the as built drawings of the panels

5. Check alignment, fastening, welding & painting of WC S


the base frame.

6. Ensure erection of panels as per approved layout WC S


drawing, after completion of all welding works

7. Check for tagging/identification of all panels WC S

INSPECTION & TEST DOCUMENTS

Review Test and Inspection Documents WC Rw

Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2632 Rev.0
Page 1 of 1

INDICATIVE ITP FOR FABRICATION & ERECTION OF CABLE TRAYS


(CONTROL ROOM INSTRUMENTATION WORKS)

SL. EPCC OWNER/


ACTIVITY
NO. CONTRACTOR PMC

1. Ensure availability of latest revision of approved WC Rw


tray layout drawings.

2. Ensure welding & painting of supports before WC S


erection of panels.

3. Check for fastening and joining of cable trays. WC S

4. Ensure no sharp edges. WC S

5. Ensure covering of cable trays for unarmoured and WC W


system cable trays

6. Erect separate cable trays for power and signal WC S


cables. Check for separation distance between the
power & signal cable

INSPECTION & TEST DOCUMENTS

Review Test and Inspection Documents WC Rw

Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2633 Rev.0
Page 1 of 1

LAYING, GLANDING & TERMN OF INTERCON. CABLES, PREFAB


CABLES, SYSTEM CABLES, POWER CABLES & FIELD CABLES
(CONTROL ROOM INSTRUMENTATION WORKS

SL. EPCC OWNER/


ACTIVITY
NO. CONTRACTOR PMC

1. Check for receipt of correct size & type of cables as WC Rw


per cable schedule

2. Testing of cable before laying as per specification WC Rw


(continuity, megger, etc.)

3. Ensure exact distance and cut cables accordingly WC Rw

4. Tag of cables as per specification WC S

5. Confirm availability of proper cable gland size, type WC Rw


of specified thread

6. Tightening of check nut (after termination) WC S

7. Cable continuity & insulation resistance WC S

8. Dressing of cables inside PVC Duct and covering of WC S


PVC Duct after complete cabling.

9. Ferruling of cables WC S

10. Ensure usage of sleeved crimp able type lugs WC S

11. Crimping of lugs WC S

12. Correct tightness of cables in the terminal block WC S

13. Correct numbering of terminal blocks WC S

14. Continuity of fuses in terminal blocks WC S

INSPECTION & TEST DOCUMENTS

Review Test and Inspection Documents WC Rw

Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2634 Rev.0
Page 1 of 1

INDICATIVE ITP FOR POWER ‘ON’ OF PANELS AND PRE-


COMMISSIONING OF THE SYSTEM
(CONTROL ROOM INSTRUMENTATION WORKS)

SL. EPCC OWNER/


ACTIVITY
NO. CONTRACTOR PMC

1. Check earth pit resistance WC HP

2. Check earth connection to system earth, panel WC HP


earth etc.

3. Ensure interconnectivity of panel earth bus WC W

4. Check incoming power supply and termination of WC W


the power cables

5. Power ‘ON’ the system and observe system booting WC W


and self diagnostic check.

6. Reload the softwares, if necessary WC S

7. Check for alarms by switching ‘ON’/‘OFF’ the sub WC S


systems

8. Start simulation of individual loops from respective WC S


‘Field Terminal Blocks’ (FTBs)

9. Observe the response and tune the controllers WC S

10. Check the interlocks as per P&ID WC W

11. Record the input & outputs WC Rw

12. Check for proper, trend reports, logging reports/shift WC Rw


reports & alarm, sequence and functioning of all
peripheral units.

13. Check for back-up operation of PLC cards, system WC W


memory & power supply switch over

14. Check for lighting and ventilation fan operation WC S

15 Check functioning of complex loop WC W

INSPECTION & TEST DOCUMENTS

Review Test and Inspection Documents WC Rw

Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2635 Rev.0
Page 1 of 1

INDICATIVE ITP FOR FIELD LOOP CHECKING AND ‘SYSTEM


ACCEPTANCE TEST’
(CONTROL ROOM INSTRUMENTATION WORKS

SL. EPCC OWNER/


ACTIVITY
NO. CONTRACTOR PMC

1. Ensure record as per loop checking sheet duly WC Rw/HP


signed

2. Check for system booting, bus-degradation, scan WC W


time, loop error, etc.

3. Check for operation of sub systems and peripheral WC W


systems

4. Check for ‘Back-up’ system operations WC W

5. Ensure feedback/commands from/to electrical WC W


system

6. System acceptance WC HP

INSPECTION & TEST DOCUMENTS

Review Test and Inspection Documents WC Rw

Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2700 Rev. 0
Page 1 of 2

INDICATIVE
INSPECTION & TEST PLAN (ITP)
CIVIL, STRUCTURAL AND
ARCHITECTURAL WORKS

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2700 Rev. 0
Page 2 of 2

INDEX

S.NO DESCRIPTION DOCUMENT NO. REV.

GENERAL CIVIL WORKS


1. Preliminary Civil works 6648-00-19-43-2701 0
2. Site Grading 6648-00-19-43-2703 0
3. Excavation 6648-00-19-43-2704 0
4. Back Filling 6648-00-19-43-2705 0
5. Underground Piping Works (RCC/CI) 6648-00-19-43-2706 0
6. WBM Roads 6648-00-19-43-2707 0
7. Black Topping (Premix Carpeting) 6648-00-19-43-2708 0
8. Tanks Pads 6648-00-19-43-2709 0
9. Micro Grading 6648-00-19-43-2710 0
10. Underground Piping (Carbon Steel) 6648-00-19-43-2740 0

STRUCTURAL WORKS
1. Plain Cement Concrete 6648-00-19-43-2741 0
2. RCC (Sub-Structure) 6648-00-19-43-2742 0
3. RCC (Super Structure) 6648-00-19-43-2743 0
4. Flooring/ Pavement 6648-00-19-43-2745 0
5. Brick Work 6648-00-19-43-2746 0
6. Structural Works 6648-00-19-43-2747 0

ARCHITECTURAL WORKS
1. Plastering 6648-00-19-43-2772 0
2. Roofing Accessories 6648-00-19-43-2779 0

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2701 Rev. 0
Page 1 of 1

INDICATIVE ITP FOR

PRELIMINARY CIVIL WORKS

Sl. EPCC Owner/


Activity
No. Contractor PMC

1 Boundary markings and submission of drgs./sketches WC S

2 a) Review of calibration certificates of instruments/ testing WC HP


equipments
b) Field calibration, if any WC W

3 Block levels, contour plans, establishing permanent bench WC S


marks with ref. to Standard B.Ms. by check levels and
submission of relevant drgs. & records

4 Protection of control points, permanent bench marks and WC S


regular rechecking

5 Submission of Master plan showing monuments, structures WC S


exposed rocks, weirs, water works, ponds, underground
services if crossing that area, etc.

INSPECTION & TEST DOCUMENTS


Review Test and Inspection Documents WC Rw

Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2703 Rev. 0
Page 1 of 1

INDICATIVE ITP FOR

SITE GRADING
Sl. EPCC Owner/
Activity
No. Contractor PMC

1. Clearing and stripping of soil including disposal of WC S


unsuitable material
2 a) Review of calibration certificates of instruments/ testing WC HP
equipments
b) Field calibration, if any WC W

3. Taking and plotting of initial joint levels at specified WC W


intervals for cutting as well as filling areas
4. Classification (Levels of strata) and testing of filling soil for WC S
suitability including preparation of Lead Charts to
filling/disposal areas.
5. Proper warning of explosions, misfires and storage of WC S
explosive materials (As applicable).
6. Breaking up of clods, lumps, etc. at the time of filling and WC S
compaction.
7. Identification and suitability of borrow areas for filling WC S
soil/murrum including verification of payments for royalty,
etc.
8. Compaction test for earth filling in specified layers including WC W/Rw
finished areas.
9. Verification of final finished grade levels. WC S
10. Computation of Earth works. WC Rw
11. Record of tree cuttings, stacking of blasted rocks and other WC S
quarry materials including handing over to Owner
12. Preparation of “As built drawings” indicating culverts, other WC Rw
open drainage facilities etc.
13. Removal of Surplus earth/excavated material and leveling WC S
in disposal areas.
14. Resolution of obstacles/hindrances WC S

INSPECTION & TEST DOCUMENTS


Review Test and Inspection Documents WC Rw

Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2704 Rev. 0
Page 1 of 1

INDICATIVE ITP FOR

EXCAVATION

Sl. EPCC Owner/


Activity
No. Contractor PMC

1. a) Review of calibration certificates of instruments/ testing WC HP


equipments
b) Field calibration, if any WC W

2. Layout checking WC S
3. Taking initial levels WC S
4. Slopes of excavation, benching, overburden, shoring & WC S
strutting (in case of deep excavation)
5. Check for sub-soil water, dewatering requirements as per WC S
specifications.
6. Bottom level of excavation and compaction WC S
7. Stacking of different type of soils separately WC S
8. List of obstacles encountered (cables, pipes, conduits, etc) WC S
9. Barricading of excavated pits for safety & protection from WC S
rain

FOR HARD ROCK

1 Obtaining license from Statutory authorities for undertaking WC Rw


blasting operations
2 Storing of explosive materials as per explosive rules WC S
3 Prominent display of red flags around the area to be blasted WC S
4 Check the dimensions of bore holes WC S
5 Stacking of hard rock for useable/non useable including WC S
handing over to owner

INSPECTION & TEST DOCUMENTS


Review Test and Inspection Documents WC Rw

Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2705 Rev. 0
Page 1 of 1

INDICATIVE ITP FOR

BACKFILLING
Sl. EPCC Owner/
Activity
No. Contractor PMC

1. Selection of materials/selected earth WC W

2. Check for treatment of soil, if any WC S

3. a) Calibration certificates of instruments/ testing WC Rw


equipments
b) Field calibration, if any WC W

4. Filling in specified layers, consolidating, watering. WC S

5. Compaction tests for layers WC W/Rw

6. Filling to required levels WC S

INSPECTION & TEST DOCUMENTS


Review Test and Inspection Documents WC Rw

Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2706 Rev. 0
Page 1 of 1

INDICATIVE ITP FOR

UNDERGROUND PIPING (RCC/CI)


Sl. EPCC Owner/
Activity
No. Contractor PMC

1. Checking of material WC W
2. Adequate slope, benching in excavation for safety purposes WC S
(if required)

3. a) Calibration certificates of instruments/ testing WC Rw


equipments
b) Field calibration, if any WC W

4. Layout, line & level WC S


5. Laying & jointing, grouting at manholes/chambers WC S
6. Check for supports/ firm bed/ sub soil water level WC S
7. Testing for leakages by blocking pipe ends WC S
8. Hydro-testing and other tests, Removal of blockages, WC S
Cleaning & flushing of system

9. Backfilling in layers WC S
10. Check for MS rungs in proper position, inlet/outlet pipe WC S
levels in manholes

11. Preparation of “As-built drawings” WC Rw

INSPECTION & TEST DOCUMENTS


Review Test and Inspection Documents WC Rw

Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2707 Rev. 0
Page 1 of 1

INDICATIVE ITP FOR

WBM ROADS
Sl. EPCC Owner/
Activity
No. Contractor PMC

1. a) Review of calibration certificates of instruments/ testing WC HP


equipments
b) Field calibration, if any WC W

2. Layout checking including Road crossings and taking initial WC S


levels

3. Approval of source & checking/testing of materials WC HP


(wherever required)

4. Filling (if any), compaction, providing cambers in sub-base WC S


including levels

5. Spreading metal to required thickness, line & levels, dry WC S


rolling including spreading of screening material

6. Check for camber and levels over metalling WC S

7. Spreading murrum/ sand, watering and rolling WC S

8. Checking thickness after each layer and rectification thereof WC W


(if any)

9. Checking quantity of aggregate by excavation of trial pits WC W

INSPECTION & TEST DOCUMENTS


Review Test and Inspection Documents WC Rw

Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2708 Rev. 0
Page 1 of 1

INDICATIVE ITP FOR

BLACK TOPPING (PREMIX CARPETING)

Sl. EPCC Owner/


Activity
No. Contractor PMC

1. Approval of source of materials WC Rw

2. a) Review of calibration certificates of instruments/ testing WC HP


equipments
b) Field calibration, if any WC W

3. Surface preparation & check for camber/level WC S

4. Checking/ testing of material wherever required WC W

5. Tack coat application WC S

6. Premix carpeting (including thickness of carpeting) and WC S


rolling

7. Seal coat (including thickness of seal coat) WC S

8. Check for camber and levels WC S

9. Check for bitumen temperature and consumption WC S

10. Premix sample check test (As applicable) WC W

11. Removal of surplus earth WC S

12. Berm preparation WC S

13. Final Inspection WC HP

INSPECTION & TEST DOCUMENTS


Review Test and Inspection Documents WC Rw

Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2709 Rev. 0
Page 1 of 1

INDICATIVE ITP FOR

TANK PADS
Sl. EPCC Owner/
Activity
No. Contractor PMC

1. Approval of source of materials WC Rw


2. Stripping the area WC S

3. a) Review of calibration certificates of instruments/ testing WC HP


equipments
b) Field calibration, if any WC W

4. Layout and marking of ground level WC S

5. Excavation to required level, compaction of sub-base WC W

6. Checking/ testing of materials WC W


7. Filling selected materials in specified layers, rolling, WC S
watering

8. Compaction tests WC W/Rw

9. Gravel filling under annular ring with compaction and WC W


adding graded filler material (As applicable)

10. Anti-corrosive layer, consolidation WC S

11. Premix carpeting on side slopes WC S

12. Preparation of “As-built drawing” for erection WC Rw

13. Check for settlement of pads during hydrostatic testing of WC W


tanks

INSPECTION & TEST DOCUMENTS


Review Test and Inspection Documents WC Rw

Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2710 Rev. 0
Page 1 of 1

INDICATIVE ITP FOR

MICRO GRADING

Sl. EPCC Owner/


Activity
No. Contractor PMC

1. a) Review of calibration certificates of instruments/ testing WC HP


equipments
b) Field calibration, if any WC W

2. Taking initial levels WC S

3. Clearing/ Removal of extra soil, debris, etc. from site by WC S


transportation

4. Taking final levels WC S

5. Verification of gradient of ground WC S

6. Finishing of ground surface by hand compactor/ Roller (As WC S


applicable)

7. Final inspection WC HP

INSPECTION & TEST DOCUMENTS


Review Test and Inspection Documents WC Rw

Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2740 Rev. 0
Page 1 of 5

INDICATIVE ITP FOR

UNDERGROUND PIPING (CARBON STEEL)

Sl. EPCC Owner/


Activity
No. Contractor PMC

A. PRIOR TO FABRICATION

1. Checking/ testing of incoming materials WC S

2. Welding Filler Material Approval/Qualification


i) Review of Manufacturer's Test Certificates/ other WC Rw
documents
ii) Testing, if any WC Rw

3. WPS/PQR
i) Review of proposed Procedure WC HP
ii) Testing WC W/Rw
iii) Approval of Final WPS WC HP

4. Welder Performance Qualification Test WC W


4a. Certification & approval of welders WC HP

5. NDT Procedure Qualification


i) Review of proposed Procedure WC HP
ii) Testing WC HP
iii) Approval of Qualified procedure WC HP

6. Preparation of sketches from General Arrangement WC Rw


drawings

7. Joint numbering WC Rw

8 Approval of colour coding scheme WC HP

9. Monitoring of colour coding on pipes & fittings WC S

B. FABRICATION (SHOP & FIELD)

1. Material as per piping class (check w.r.t. approved colour WC W


coding procedure)
i) Fit-up check WC S
ii) Dimensional check WC S

Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2740 Rev. 0
Page 2 of 5

Sl. EPCC Owner/


Activity
No. Contractor PMC

2. Pre-heat (if any) WC S

3. Check for purity of purging/shielding Gas (if any) WC S

4. Purging (if any) WC S

5. Shielding rate (if any) WC S

6. Baking of Electrodes WC S

7. Inter-pass cleaning & Temperature check. WC S

8. Visual check of completed welds WC S

9. PT/MT WC S

10. Radiography marking (for Random Radiography) WC W

11. Radiography Interpretation WC W

C. HYDROSTATIC/ PNEUMATIC TESTING

1. Procedure Review WC HP

2. Correctness of Testing arrangements WC S

3. Calibration of Pressure Gauges WC W

4. R.F. Pad testing, if any WC HP

5. Scrutiny of test packs for Mechanical & NDT WC HP


Clearance (Refer Annexure-1)

6. Air/Water Flushing (preliminary) WC S


6a. Addition of corrosion inhibitors, if required – Approval WC HP
of make & quality

Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2740 Rev. 0
Page 3 of 5

Sl. EPCC Owner/


Activity
No. Contractor PMC

7. Pneumatic/ Hydrostatic testing WC W

8. Draining of water & Air drying WC W

D. LAYING

1. Trench excavation and levels WC S

2. Cleaning of pipe surface WC S

3. Approval of wrapping/coating material manufacturers WC HP

4. Approval of agency for wrapping & coating WC HP

5. Sample test of coating materials in approved laboratory WC Rw

6. Procedure qualification for wrapping & coating WC HP

7. Application of primer WC S

8. Coal tar temperature WC S

9. Coating & wrapping WC S

10. Check Thickness of coating (if applicable) WC W

11. Review Calibration Certificate of Holiday tester WC HP

12. Holiday testing WC W

13. Peel test WC HP

Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2740 Rev. 0
Page 4 of 5

Sl. EPCC Owner/


Activity
No. Contractor PMC

14. Lifting arrangement WC S

15. Lowering (levels & orientation of branches) WC S

16. Checking of wrapping & coating for damages during WC W


lowering, their repair, Holiday Testing, etc.

17. Back filling & compaction WC S

18. Location, Brickwork, plaster of valve pit WC S

19. Top cover & Finish of valve pit WC S

E. SYSTEM COMPLETION

1. Tie in joints * *

2. Scrutiny of test packs for system testing WC Rw


(Refer Annexure-1)

3. System testing WC HP

INSPECTION & TEST DOCUMENTS

Review Test and Inspection Documents WC Rw

* For Tie-In, pl. refer ITP No.6648-00-19-43-2111

Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2740 Rev. 0
Page 5 of 5

ANNEXURE – 1

Sl. EPCC Owner/


Activity
No. Contractor PMC
A. MECHANICAL COMPLETION RECORD (U/G Piping)

1. Clearance for flushing & testing WC Rw

1a Mechanical clearance
- Conformity with drawing WC Rw
- Material as per Specification WC Rw

1b Welding & NDT clearance


- Material as per Specification WC Rw
- Fit-up check record WC Rw
- Visual check of completed welds WC Rw
- PT/MT WC Rw
- Radiography WC Rw
- PWHT & hardness WC Rw
- RF pad testing WC Rw

2 Flushing & Pressure testing WC HP

3. Coating & wrapping


- Surface preparation WC Rw
- Primer application WC Rw
- Coating, wrapping & peel test WC Rw
- Holiday check WC Rw

4. Laying
- Trench leveling WC Rw
- Lowering & checking for damages in WC Rw
wrapping & coating, their repair,
Holiday testing, etc.
- Backfilling WC Rw

Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2741 Rev. 0
Page 1 of 1

INDICATIVE ITP FOR

PLAIN CEMENT CONCRETE (PCC)


Sl. EPCC Owner/
Activity
No. Contractor PMC

1. a) Calibration certificates of instruments/ testing WC Rw


equipments
b) Field calibration, if any WC W

2. Checking of layout and materials, compaction of sub -grade WC S

3. Mix proportion WC S

4. Check for shuttering, dewatering if any. WC S

5. Concreting with proper compaction WC S

6. Checking of top level of PCC WC S

7. Curing WC S

INSPECTION & TEST DOCUMENTS


Review Test and Inspection Documents WC Rw

Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2742 Rev. 0
Page 1 of 1

INDICATIVE ITP FOR REINFORCED CEMENT CONCRETE (RCC)


(SUB-STRUCTURE)

Sl. EPCC Owner/


Activity
No. Contractor PMC

1. a) Calibration certificates of instruments/ testing WC Rw


equipments
b) Field calibration, if any WC W
2. Checking of layout & condition of PCC/ leveling course WC S
3. Checking/ testing of materials WC S
4. Design of mix WC Rw
5. Inspection of concrete delivered by batching plants/ transit WC S
mixers/ concrete mixers
6. Check for line & level of shuttering including its condition, WC S
quality and rigidity.
7. Check for sub-soil water & dewatering arrangement, if any WC S
8. Reinforcement & covers to reinforcement WC W
9. Inserts, Anchor bolts and pipe sleeves, pockets, dowels, WC S
etc.
10. Pour Card WC HP
11. Check for obstacles encountered (Electrical conduits, pipe WC S
lines, etc.)
12. Concreting, testing, compaction & finishing WC S
13. Casting of cubes WC W
14. Curing WC S
15. Testing of cubes WC W
16. Removal of shuttering WC S
17. Check for water tightness, rendering, if any WC S
18. Preparation of As-built drawings WC Rw

INSPECTION & TEST DOCUMENTS


Review Test and Inspection Documents WC Rw

Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2743 Rev. 0
Page 1 of 1

INDICATIVE ITP FOR REINFORCED CEMENT CONCRETE (RCC)


(SUPER STRUCTURE)
Sl. EPCC Owner/
Activity
No. Contractor PMC
1. a) Calibration certificates of instruments/ testing WC Rw
equipments
2. b) Field calibration, if any WC W
3. Checking of layout WC S

4. Checking/ testing of materials WC W/Rw

5. Design of mix WC Rw

6. Inspection of concrete delivered by batching plants/ transit WC S


mixers/ concrete mixers
7. Check for line & level of shuttering and scaffolding/ vertical WC S
bracing including hoisting arrangements.

8. Reinforcement & covers to reinforcement WC W

9. Inserts, bolts, pipe sleeves, MS rungs, concealed electrical WC S


conduits, fan hooks, dowels, etc. including welding if any

10. Pockets/ openings WC S

11. Expansion joints, if any WC S

12. Pour Card WC HP

13. Concreting, testing, compaction & finishing WC S

14. Casting of cubes WC W

15. Curing WC S

16. Testing of cubes WC W

17. Removal of formwork/ stayings WC S

18. Verification of dimensions viz AFC drawings and tolerances WC S

19. Check for water tightness, rendering, if any WC S

20. Preparation of As built drawings WC Rw

INSPECTION & TEST DOCUMENTS


Review Test and Inspection Documents WC Rw

Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2745 Rev. 0
Page 1 of 1

INDICATIVE ITP FOR

FLOORING/PAVEMENT

Sl. EPCC Owner/


Activity
No. Contractor PMC

1. Approval of source of materials WC Rw


2. a) Review of calibration certificates of instruments/ testing WC HP
equipments
b) Field calibration, if any WC W

3. Layout checking/ excavation of all new foundations WC S


4. Checking/ testing of materials WC S
5. Mix proportion/Design Mix WC W
6. Check for proper back filling/compaction/ completion of sub WC Rw
- Structure works
7. Check for edges of shuttering, alternate panels WC S
8. Check for slopes, thickness of flooring WC S
9. Shuttering, reinforcement (if any) WC S
10. Check for expansion joints/ Construction joints WC S
11. Check for concealed pipe embedment, earthing, if any WC S
12. Check for dividing strips, if any WC S
13. Concreting, testing, finishing, test cubes WC W
14. Checking for line, levels, slopes, joints, thickness of flooring WC S
viz. AFC drawings
15. Curing WC S
16. Grinding & polishing, if applicable WC S
17. Testing of concrete cubes (as applicable) WC W
18. Preparation of “As Built Drawings” including underground WC Rw
facilities if any

INSPECTION & TEST DOCUMENTS


Review Test and Inspection Documents WC Rw

Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2746 Rev. 0
Page 1 of 1

INDICATIVE ITP FOR

BRICK MASONRY
Sl. EPCC Owner/
Activity
No. Contractor PMC

1. Checking/ testing of bricks (as applicable) WC W

2. Cleaning of surface WC S

3. Wetting of bricks WC S

4. Cement mortar proportion WC S

5. Staging & scaffolding WC S

6. Hacking of concrete surface WC S

7. Check for bond/closers, thickness of joints . WC S

8. Line, level & plumb WC S

9. Raking out joints, keys in brick work, if any WC S

10. Check for RCC bonds/Reinforcement/PCC flooring, in case WC S


of partition brick work

11. Embedment of fixtures WC S

12. Curing WC S

13. Preparation of 'As Built' Drawings WC Rw

INSPECTION & TEST DOCUMENTS

Review Test and Inspection Documents WC Rw

Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2747 Rev 0
Page 1 of 1

INDICATIVE ITP FOR


STRUCTURAL WORKS
S. EPCC OWNER/
ACTIVITY
NO CONTRACTOR PMC
A PRE – FABRICATION ACTIVITIES
1. a) Review of calibration certificates of instruments/ testing equipments WC HP
b) Field calibration, if any WC W
2. Checking of structural steel material supplied by the Contractor/ WC Rw
Manufacturers test certificate/ testing (as applicable)

3. Welding Filler material approval/ qualification


a) Manufacturing test certificates/ documents WC Rw
b) Testing, if any WC Rw
4. WPS/ PQR WC W
5. Welders performance qualification WC W
6. Layout checking WC S
7. Welding equipment and accessories WC S
8. Preparation and approval of Fabrication drawings WC Rw
B FABRICATION ACTIVITIES
1 Materials as per design drawing WC Rw
2 Check straightness and non-warping of members WC S
3 Dimensional and fit-up checks including provision of slopes for WC S
deflection wherever required
4 Visual check for welding WC S
5 Grinding including surface preparation for painting and application of WC Rw
primer
6 Checking paint as per specs, shelf-life, etc. WC S
7 Application of specified paint, painting thickness, etc. WC W
C FIELD ERECTION ACTIVITIES
1 Lifting arrangements including test certificates of lifting tackles WC S/Rw
2 Correctness of location WC S
3 Orientation of bracing, lugs WC S
4 Alignment & levels WC S
5 Field welding (if any) WC W
6 Grouting WC S
7 Finishing coat of paint, thickness of paint etc. WC W
8 Preparation of As-built drawings WC Rw
INSPECTION & TEST DOCUMENTS
Review Test and Inspection Documents WC Rw
Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2772 Rev. 0
Page 1 of 1

INDICATIVE ITP FOR

PLASTERING
Sl. EPCC Owner/
Activity
No. Contractor PMC

1 Check for completeness of all hidden jobs like piping, WC S


conduiting, etc.

2. Check for grading of sand, Mix proportion WC S

3 Sample preparation for finish and its approval WC W

4 Neeru application on plaster (as applicable) WC S

5. Hacking and cleaning the surface, removing loose WC S


particles, wetting the surface

6. Checking of plaster thickness, plumb & even surface WC S

7. Check for grooves, openings, rounding off the corners, WC S


hollowness in plaster

8 Curing WC S

INSPECTION & TEST DOCUMENTS


Review Test and Inspection Documents WC Rw

Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2779 Rev. 0
Page 1 of 1

INDICATIVE ITP FOR

ROOFING ACCESSORIES

Sl. EPCC Owner/


Activity
No. Contractor PMC

1. Check for material including Manufacturers test WC W


certificate (as applicable) and sequence of sheeting

2. Check for mitring, overhang, laps, etc. WC S

3. Slopes line, level of sheets, barge boards, ridges & WC S


gutters, over hang of sheets

4. Bolting by drilling only, length of bolts, nos., anodizing WC W


and type of washers

5 Check for slopes of rain gutters, down take pipes, WC S


north lighting curves/ supports for gutters

6 Check for leakage/ passing of light WC S

INSPECTION & TEST DOCUMENTS


Review Test and Inspection Documents WC Rw

NOTE : Fixing arrangement need to be reviewed with respect to contract specifications.

Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2800 Rev 0
Page 1 of 2

INDICATIVE

INSPECTION & TEST PLAN (ITP)

ELECTRICAL WORKS

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2800 Rev 0
Page 2 of 2

INDEX

S.NO
DESCRIPTION DOCUMENT NO. REV.

1. Installation/ Erection & Testing of Power 6648-00-19-43-2801 0


Transformer

2. Installation/ Erection & Testing of Motor 6648-00-19-43-2805 0

3. Installation/ Erection & Testing of 6648-00-19-43-2810 0


Generator

4. Installation/ Erection & Testing of Switch 6648-00-19-43-2815 0


Gears/ PCC/ MCC/ EMCC

5. Installation/ Erection & Testing of EHT/ 6648-00-19-43-2820 0


HT Main Bus & Allied Equip.

6. Cable Laying 6648-00-19-43-2825 0

7. Lighting System 6648-00-19-43-2830 0

8. Earthing System 6648-00-19-43-2835 0

9. Installation of Bus duct 6648-00-19-43-2840 0

10. Cable Termination 6648-00-19-43-2845 0

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2801 Rev 0
Page 1 of 3

INDICATIVE ITP FOR

INSTALLATION/ERECTION & TESTING OF POWER TRANSFORMER


Sl. EPCC Owner/
Activity
No. Contractor PMC

1. Incoming Material inspection at site


a) Owner supplied WC Rw
b) EPCC CONTRACTOR supplied including check testing, if WC HP
any

2. Check foundation, its cleanliness, level and centre lines, Anchor WC S


bolts/insert plates, their position & straightness, flatness of
contacting surface for transformer skid. In case of Rail mounted
type, check centre line and levels of rails.

3. Check the Transformer no. and rating as per drawings and WC S


purged gas/ air pressure & oil leakage, physical damage etc.

4. Check availability of all accessories and Transformer oil WC S

5. Check sequence of installation e.g. main tank first + radiators + WC S


accessories + internal check as per installation flow chart.

6. Ensure the cleanliness of connecting part e.g. flange parts and WC S


maintenance of duly tight Blank flanges until just before
commencement of assembly

7. Check bushing cracks, chips or presence of paint or dirt. WC S


Bushing should be cleaned as per vendor’s instruction. Check
explosion vent assembly & healthiness of diaphragm

8. Ensure the internal check is done by vendors’ supervisor and he WC Rw


submits the reports to OWNER/ PMC duly signed by him and
EPCC CONTRACTOR

9. After completing assembly of all parts, filling of tank and OLTC WC S


to be performed, prior to filling the Transformer oil, each drum
must be tested against di-electric strength for minimum as per
specifications

Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2801 Rev 0
Page 2 of 3

Sl. EPCC Owner/


Activity
No. Contractor PMC

10. Check & ensure bus duct connection at both ends. WC W

11. Ensure cable connection at the cable and box their colour WC W
coding & tightness (if required, use of spring and flat washers on
the appropriate faces to be confirmed) and cleanliness of
lapping surfaces. For multiple cable connection, check for
correctness of R.R., YY, BB grouping

12. If specified, fill the cable end box with tested transformer oil and WC S
ensure oil levels

13. Check the use of proper size conductors/ cables for HV/LV, WC W
neutral connection and their connection to NGR or earth grid/
earth point. Measure earth resistant of earth points

14. Check equipment earthing, connections, tightness and earth WC W


resistance value

15. Ensure earthing of tertiary winding WC W

16. Check leakage and oil level WC S

17. Check proper installation of Dessicauts (Reactivate the silica gel WC S


to blue; oil traps to be filled up)

18. Measure winding resistance at each tap WC S

19. a. Test insulation resistance & PI WC S


b. Assure heat run/ dehydration of transformer WC W
c. Check final IR value after dehydration WC S
and temp. Vs IR curve to ensure drying

20. Test vector group polarity, magnetizing current, magnetic WC W


balancing

Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2801 Rev 0
Page 3 of 3

Sl. EPCC Owner/


Activity
No. Contractor PMC

21. Test transformation ratio at each tap points (injecting 3 phase, WC W


415 V at primary)

22. Assure laying, terminating & connection of all control cables WC S

23. Check Bucholtz's relay operation by air injection for both WC W


transformer & OLTC, MOG alarm and trip contacts’ function

24. Check setting of Fan control (auto & manual), OTI, WTI- alarm WC W
and trip

25. Check tap changer control/operation-both auto & manual – WC S


without energizing the transformer. Ensure master/ followers’
correct functioning

26. Final residual check to confirm removal of all temporary WC S


supports/ spacers, tags, accumulation of air in Buchhelz relay,
oil, if any, etc., which might have been used as protection/ and
identification during transportation and erection

27. Check operation of cooling system WC S

28. Check transformer protection relay settings as per Relay Setting WC W


diagram

29. Mechanical Acceptance Test WC HP

INSPECTION & TEST DOCUMENTS

Review Test and Inspection Documents WC Rw

Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2805 Rev 0
Page 1 of 2

INDICATIVE ITP FOR

INSTALLATION/ERECTION & TESTING OF MOTOR


Sl. Activity EPCC Owner/
No. Contractor PMC

1. Check for foundation, its level & centre line markings, ensure WC Rw
the depth of anchor grouting pockets and straightness of
anchor bolts. Foundation should be thoroughly cleaned before
placement of motor

2. Check motor name plate, identify the equipment referring to WC S


vendor’s shop floor test certificate and construction drawing

3. Check motor as per area classification drgs duly approved by WC S


CCE

4. Check for installation of motor, its leveling, alignment and WC Rw


coupling with driven equipment (before coupling magnetic
centering must be ensured)

5. Ensure fixing of all accessories, temperature indicators, WC S


cooling system, lubricating pumps, etc.

6. Ensure pedestal insulation WC S

7. Check lubrication of bearings, their suitability and level. For WC S


lubricants, vendor instructions and specifications to be followed

8. Assure sealing of all exposed outlets during erection/ assembly WC S

9. Ensure Air-gap as per vendor instruction (for big machines WC S


assembled at site)

10. Ensure all spacers and blockings used for transportation and WC S
erection have been removed

11. Check proper earthing of the motor and earth connection. WC W

Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2805 Rev 0
Page 2 of 2

Sl. EPCC Owner/


Activity
No. Contractor PMC

12. a. Check IR and PI for the motor and IR for auxiliary WC W


circuits like heaters and Thermal detectors, excitor
(for system motor only), etc.

b. In case of low IR/PI, dehydrate the motor by suitable WC W


method as per vendors’ recommendation.
13. Measure winding Resistance (if specified) WC S

14. Inspect space heater and control cable connections. Ensure WC S


the tightness of connection, proper glanding and earthing of
armour, correct phase sequence of supply cable as per hire
mark and closing the covers of terminal boxes.
15. Check for de-coupling of motor for no-load run and ensure the WC W
re-coupling of the motor after verification of original alignment.
16. Set the temperature indicators (alarm/ trip) and vibration WC S
monitors (if any)
17. Check motor protection relay settings as per Relay Setting WC W
diagram
18. Mechanical Acceptance Test WC HP

INSPECTION & TEST DOCUMENTS

Review Test and Inspection Documents WC Rw

Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2810 Rev 0
Page 1 of 3

INDICATIVE ITP FOR

INSTALLATION/ERECTION & TESTING OF GENERATOR


Sl. EPCC Owner/
Activity
No. Contractor PMC

1. Check for foundation, its level & centre line markings, ensure WC Rw
the depth of anchor grouting pockets and straightness of
anchor bolts. Foundation should be thoroughly cleaned before
placement of equipment

2. Check equipment name plate, identify the equipment referring WC S


to vendor’s shop floor test certificate and construction drawing

3. Check equipments as per approved area classification WC S


drawings

4. Assure sealing of all exposed outlets during erection/ assembly WC S

5. Check for installation of equipment, its leveling, alignment and WC Rw


coupling with driven equipment (before coupling magnetic
centering must be ensured)

6. Ensure fixing of all accessories, temperature indicators, WC W


cooling system, lubricating pumps, etc.

7. Ensure pedestal insulation WC W

8. Check lubrication of bearings, their suitability and level. For WC S


lubricants, vendor instructions and specifications to be followed

9. Ensure Air-gap as per vendor instruction (for big machines WC W


assembled at site)

Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2810 Rev 0
Page 2 of 3

Sl. EPCC Owner/


Activity
No. Contractor PMC

10. Ensure all spacers and blockings used for transportation WC S


and erection have been removed

11. Check earthing of the equipment and earth connection WC HP


including NGR. Ensure earth resistance

12. a. Check IR and PI for the equipment and WC W


IR for auxiliary circuits like heaters and
Thermal detectors, excitor PMG, etc.

b. In case of low IR/PI, dehydrate the WC W


equipment by suitable method as per
vendors’ recommendation.

13. Measure winding Resistance (if specified) WC S

14. Inspect exciter control panel/ space heater and control WC S


cable connections. Ensure the tightness of connection,
proper glanding and earthing of armour correct phase
sequence of supply cable as per hire mar mark and
closing the covers of terminal boxes.

15. Set the temperature indicators (alarm/ trip) and vibration WC S


monitors

16. Check the generator P.T. WC W

Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2810 Rev 0
Page 3 of 3

Sl. Activity EPCC Owner/


No. Contractor PMC

17. Check generator control panel , its wiring as per drg. Relay & WC W
their calibration & setting, functional checks, etc.

18. Perform relay testing and operations

a. Diff. relay operation WC W

b. Over Current (O/C) relay operation WC W

c. Short circuit O/C relay operation. Draw short CRT curve & WC W
compare with shop test results.

19. Perform Negative phase sequence test & confirm the WC W


operation of the relay

20. Perform Earth Fault (E/F) test & see the operation of E/F WC W
relay

21. Perform open circuit test & draw the open CRT curve for WC W
comparison

22. Check for synchronizing & manual excitation behavior WC W

23. Check AVR operation & setting WC W

24. Mechanical acceptance test WC HP

INSPECTION & TEST DOCUMENTS

Review Test and Inspection Documents WC Rw

NOTE : Activity pertaining to Sl. No. 5 will be checked by Mechanical group.

Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2815 Rev 0
Page 1 of 3

INDICATIVE ITP FOR

INSTALLATION/ERECTION & TESTING OF SWITCH


GEARS/PCC/MCC/EMCC
Sl. EPCC Owner/
Activity
No. Contractor PMC

1. Check the layout of base channels/frames and assure the WC S


correct provisions for grouting/welding and cable entry
openings

2. Ensure level and centre lines are within the prescribed limits WC S
and they match with the requirements of incoming Bus-ducts, if
any

3. Assure proper grouting/welding of the base channels/frames WC S

4. Ensure proper handling of the panels WC S

5. Check sequence wise (starting from centre or Bus-duct panel) WC S


installation final leveling and bolting up

6. Check main bus bar connection at all shipping sections and WC S


shrouding at all tap-off points

7. Check inter panel wiring after fixing of loose accessories and WC S


wiring

8. Assure the level of flooring for smooth opening of panel doors WC S


and drawing out and in operation of Breaker Trolleys

9. Check interchangeabilities of circuit breakers WC S

10. Check equipment earthing & continuity of earth bus WC HP

Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2815 Rev 0
Page 2 of 3

Sl. EPCC Owner/


Activity
No. Contractor PMC

11. Ensure thorough cleaning, removal of temporary spacers, WC S


supports, any foreign materials and dusting the panels

12. Verify the correctness, in accordance with the drawings, of all WC Rw


type of relays, test blocks, control switches, meters and
instruments, motor starters, fuses, space heaters, etc.

13. Check name plate for each breaker, inspect and test the WC W
operating mechanics (Mechanically), interlocks, contacts, arc
chutes, auxiliary devices and adjustments as required

14. Visually check all relays and meters for removal of shipping WC W
blocks and for mechanical damage. Ensure their range against
approved drawings, inspect calibration, testing and setting for
each relay and meter.

15. Visually check name plates of CT’s and PT’s and ensure their WC W
ratio accuracy, class and proper grounding against approved
drawings. Test their polarity knee point and ratio. Primary
injection tests at three points on the characteristics curve
submitted by the manufacturer’s

16. Test and witness I.R. value of the power and control bus WC HP

17. Test and witness high pot tests, if specified WC HP

18. Ensure tightness of connection of control wiring WC S

Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2815 Rev 0
Page 3 of 3

Sl. EPCC Owner/


Activity
No. Contractor PMC

19. Inspect secondary injection test and ensure tripping of C.B. WC W


through protection relays

20. Inspect primary injection & check the breaker tripping through WC W
protective relays, check ammeter indications

21. Switch on AC & DC control supply. Check the sequence of WC HP


operation of breakers electrically, local and remote interlock;
ensure proper alarm and announciation and indications in
SW/GR/MCC/Control Panel. Auto Change- over should be
ensured. Verify tripping of breakers at 70% of nominal control
voltage

22. Measure contact resistance and ensure simultaneous closing and WC W


making of breaker contacts, if specified

23. Mechanical Acceptance Test WC HP

INSPECTION & TEST DOCUMENTS

Review Test and Inspection Documents WC Rw

Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2820 Rev 0
Page 1 of 1

INDICATIVE ITP FOR

INSTALLATION/ERECTION & TESTING OF EHT/HT MAIN BUS &


ALLIED EQUIP.
Sl. Activity EPCC Owner/
No. Contractor PMC

1. Check the insulators wall bushing for any damage like chips WC S
or cracks. Ensure proper installation of the insulators &
bushing

2. Check the clearance between conductor to ground & WC S


conductor to floor level. Ensure minimum clearance
between two conductor Bus

3. Check the anchoring of the conductor bus and terminal/ WC S


Tap. Off connections

4. Ensure correctness of phase sequence WC W

5. Check earth connections and measure earth resistance of WC W


the supporting structures of insulators

6. Check IR value of the conductor bus phase to phase and WC W


each phase to earth

7. Check high voltage tests keeping all the CB’s and isolators WC W
closed but PT’s should be disconnected

8. Check hot line insulator washing equipment and system- WC S


Nozzle position & resistivity of water

9. Check type and class of lighting arrestor, its earth WC W


connection and earth resistance

10. Mechanical Acceptance Test WC HP

INSPECTION & TEST DOCUMENTS

Review Test and Inspection Documents WC Rw

Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2825 Rev 0
Page 1 of 2

INDICATIVE ITP FOR

CABLE LAYING
Sl. EPCC Owner/
Activity
No. Contractor PMC

1. Survey the cable route as per AFC drawings, identify any WC W


possible obstruction like road/pipe rack crossing, heat sources
etc. and finalize the cable route

2. Complete all road/pipe crossings etc. as per drawing WC S

3. Prepare cable drum schedule to avoid wastage and minimize WC Rw


cable joints.

4. Ensure entire route is available for cable trench WC S

5. Ensure availability of cables of required size and length WC S

6. Verify and ensure the dimensions of buried trench as per AFC WC S


drawings (in case of buried cables)

7. Ensure readiness of cable trays and installation of GI pies (for WC S


cable protection) wherever required.

8. Ensure the initial bed of sand is provided as per standard and WC S


its thickness

9. Lay cables as per the cable schedule, minimizing criss- WC S


crossing of cables within the trench (1st layer)

10. Provide cable tags at specified locations WC Rw

11. Record IR value of cables of first layer after sand filling. WC W

12. Provide second layer of sand, and ensure proper clearance WC S


between HT/LT cables (wherever applicable)

13. Complete layer wise laying of cables and sand filling WC S

14. Record IR value of cables of each layer after sand filling WC S

15. Provide final layer of sand WC S

16. Ensure cable trenches in hazardous areas are filled with sand WC S

Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2825 Rev 0
Page 2 of 2

Sl. EPCC Owner/


Activity
No. Contractor PMC

17. Provide bricks/slabs for cable protection in buried trenches. WC S

18. Back fill the trenches with earth and compact properly after WC S
ensuring the completion of earthing works if any as per earthing
layout drawings.

19. Install cover slabs and seal the trenches in plant/offsite areas WC S
after ensuring the completion of earthing works if any.

20. Remove surplus earth generated as per provisions in the WC S


contract.

21. Provide cable markers as per the specifications at identified WC Rw


locations

INSPECTION & TEST DOCUMENTS

Review Test and Inspection Documents WC Rw

Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2830 Rev. 0
Page 1 of 1

INDICATIVE ITP FOR


LIGHTING SYSTEM
Sl. EPCC Owner/
Activity
No. Contractor PMC
1 The lighting fittings are checked for damage/ lack of WC W
accompanying documents (for specialised items). The items
usually include lighting fixtures, control gear box, glands,
flameproof/ non-flameproof equipment/ fittings, lighting
poles/ accessories, lighting mast, fans, receptacles,
certificates from recognized authorities for Class IIA, IIB, IIC
explosion proof/ flameproof fixtures/ plugs/ sockets.

2 ensure that the lighting fixtures during installation are not WC S


interfering with any other plant equipment. In case of any
fouling, a change of location is to be suggested & OWNER
approval to be taken to proceed.

3 receptacles will be mounted as per the drawings & WC S


standards.

4 on walkways, platforms & outdoor areas, lighting fixtures will WC W


be located nearer to landing of stairs/ ladders, gauges, flow
meters etc.

5 plugs for spare entry/ sockets to be provided (especially in WC S


hazardous areas). lighting poles/ fixtures shall be erected
manually on concrete foundations as per the drawings.

6 earth continuity for all individual sockets/ outlets as well as WC S,Rw


for the complete lighting system will be checked.

7 the lighting circuit numbers shall be maintained as indicated WC S


in the drawing.

8 luminaries for emergency purpose shall carry identification WC S


marks.

For Outdoor Lighting

9 the poles are welded or bolted to the base/ foundation. The WC S


verticality of the poles are checked and alignment adjusted
accordingly.

10 cable termination, earthing, etc are done and the JB sealed. WC S

11 touch-up painting or galvoseal application to be done at WC S


affected areas to arrest corrosion.

INSPECTION & TEST DOCUMENTS


Review Test and Inspection Documents WC Rw
Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2835 Rev. 0
Page 1 of 2

INDICATIVE ITP FOR


EARTHING SYSTEM
Sl. EPCC Owner/
Activity
No. Contractor PMC

1. Ensure that all the materials to be used for earthing are in WC W


accordance to the contract specifications and inspected &
cleared by the OWNER/ consultant representatives before
putting in use.

2. Ensure the earthing layouts are surveyed & confirmed before WC S


commencement of excavation to avoid re-works/ interference/
fouling with other underground installations.

3. Ensure the electrodes have a clean surface, free from non- WC S


conducting materials like paint, grease etc.

4. Check the earth pit are backfilled by using alternate layers of WC S


charcoal & common salt and will be individually numbered for
identification.

5. Check the top level of the earth pit is matched to the finished WC S
grade level.

6. Check earthing grids are installed as per the pre-determined WC S


layout & earthing conductors will be at a depth specified in the
specifications from the grade level.

7. Ensure the weld joints made are by overlapping of the strip WC S


equivalent to double the width of the strip and three sides being
continuously welded.

8 Check all joints for the conductors below the grade level are WC S
welded & suitably protected by application of two coats of
bitumen & rapping with Jute. The earthing strips laid above
ground shall be welded and will be protected by applying two
coats of bitumen.

9. Ensure the joints are inspected before the coat application & WC S
backfilling.

10. Ensure from every earth electrode two distinct connections are WC S
made to the main earth grid.

11. Ensure all the risers are protected against mechanical damage & WC S
are clamped to the walls, columns, etc.

12. Ensure all the MV & HV electrical equipment are doubly earthed WC S
by connecting two points on the equipment to the earth grid. Rest
of the structural, mechanical, piping shall be connected to the
earth grid as per the contract specifications & drawings.

Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2835 Rev. 0
Page 2 of 2

Sl. EPCC Owner/


Activity
No. Contractor PMC

13. all process pipelines shall be bonded & earthed at entry & exit WC S
points of battery limit of hazardous area.

14. Ensure lightning protection grid is connected to individual WC W


electrode and are bonded to the main earth grid by two or more
points as per the drawings.

15. Ensure each lighting fixture & receptacle are earthed through the WC S, Rw
extra core provided in the lighting cable. ( Normally, the third core
of a 3 core cable)

16. Remove surplus earth generated as per provisions in the WC W


contract.

INSPECTION & TEST DOCUMENTS

Review Test and Inspection Documents WC W

Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2840 Rev. 0
Page 1 of 1

INDICATIVE ITP FOR INSTALLATION OF BUS DUCT


Sl. EPCC Owner/
Activity
No. Contractor PMC
1. Incoming Material
a) Owner supplied WC Rw
b) EPCC CONTRACTOR supplied including check testing, if any WC HP

2. Ensure that the PCCC terminal box & the transformer terminal WC S
boxes are inspected & cleared to proceed with the bus duct
installation.

3. Check the equipment no. and rating as per drawings, physical WC S


damage etc.

4. Check availability of all accessories WC S

5. Inspect the bus duct insulators for any physical damage, which WC S
may have occurred during transit.

6. Check bushing cracks, chips or presence of paint or dirt. Bushing WC S


should be cleaned as per vendor’s instruction.

7. Ensure the various sections of the bus duct enclosures are WC S


coupled together by using proper gaskets & bellows as specified.

8. Ensure the bus bars are properly fixed & coupled on the insulator WC Rw
and ensure that the correct phases are connected at both ends.

9. Ensure the bus bar bolts are tightened to the required torque WC S
values (preferably between 60 to 70 N Mtr) using calibrated torque
wrench.

10. Ensure the bus bar joints are insulated using manufacturers WC S
recommended materials, wherever required.

11. Prior to closing of the bus duct cover, ensure that the bus duct WC W
enclosures are cleared of tools/ loose materials and debris.

12. Ensure the enclosure of bus duct & support structures should be WC S
earthed to the earthing grid as per the drawing.

13. Check touch up painting wherever necessary on completion of WC S


installation.

14. Ensure the wall sealing is done & sun shields provided as per the WC S
drawings.

15. Verify the bus bar joints are clean/ polished & not oxidised before WC W
bolt-up connection.

INSPECTION & TEST DOCUMENTS


Review Test and Inspection Documents WC Rw
Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2845 Rev. 0
Page 1 of 1

INDICATIVE ITP FOR CABLE TERMINATION


(The cables covered in this section are multi-core as well as single core HT & LT cables.)
Sl. EPCC Owner/
Activity
No. Contractor PMC

1. Ensure proper tagging of the cable at both ends. WC S

2. Ensure that the cables are laid separately for HT & LT system. WC S

3. Ensure cables are properly dressed, clamped & glanded using WC S


suitable sizes of cable glands.

4. Ensure sufficient cable length is kept on both ends for future WC S


Re-termination if need arises.

5. Ensure proper bending radius while laying to avoid twisting. WC S

6. Ensure cable segregation, spacing & depths maintained are as WC S


per the specifications

7. Ensure usage of correct sizes of lugs shall be used for WC S


termination.

8. Ensure all cores are firmly terminated to terminals provided in WC S


individual feeders.

9. Ensure earthing of armour is done properly. WC S

10. Ensure continuity & IR value checks are done on the cable WC W
from panels to equipments.

11. Ensure that unused entries are plugged tightly in panels, motor WC S
terminal boxes, JB’s, etc

12. Ensure each underground cable is properly tagged as per the WC S


Instruction of Engineer In charge

13. Ensure on completion of cable termination, the cable trenches WC S


are backfilled & trench covers put back in position.

14. Ensure all cable openings & GI conduit entries are properly WC S
sealed.

INSPECTION & TEST DOCUMENTS

Review Test and Inspection Documents WC Rw

Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2900 Rev.0
Page 1 of 2

INDICATIVE

INSPECTION & TEST PLAN (ITP)

PIPELINE WORKS

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2900 Rev.0
Page 2 of 2

INDEX
S.NO DESCRIPTION DOCUMENT NO. REV.

PIPELINE WORKS
1. Handing Over/Taking over of line pipe at 6648-00-19-43-2901 0
Dump Yard
2. Receipt, Handling & Storage of Line pipes 6648-00-19-43-2902 0
and other free issue materials
3. Procurement, Receipt & Storage of EPCC 6648-00-19-43-2903 0
Contractor supplied materials
4. Row Survey, Clearing & Grading 6648-00-19-43-2904 0

5. Trenching 6648-00-19-43-2905 0

6. Blasting 6648-00-19-43-2906 0

7. Pipe taking over, handling, hauling & 6648-00-19-43-2907 0


stringing
8. Cold Field Bending of Pipes 6648-00-19-43-2908 0

9. Concrete Coating 6648-00-19-43-2909 0

10. Main Line welding 6648-00-19-43-2910 0

11. Repair of ARC burns on pipes/Arc strikes 6648-00-19-43-2911 0

12. Field joint coating & repair 6648-00-19-43-2912 0

13. Lowering of main line & OFC cables 6648-00-19-43-2913 0

14. Back filling 6648-00-19-43-2914 0

15. Cased crossings 6648-00-19-43-2915 0

16. Open cut crossings 6648-00-19-43-2916 0

17. Major Water crossings 6648-00-19-43-2917 0

18. Hydro Testing of strings for crossings 6648-00-19-43-2918 0

19. Installation of pipeline markers 6648-00-19-43-2919 0

20. Hydrostatic Testing & De-watering 6648-00-19-43-2920 0

21. Main line sectionalizing valve (SV) installation 6648-00-19-43-2921 0

22. Final clean UP & restoration 6648-00-19-43-2922 0

23. Calibration of instrument 6648-00-19-43-2923 0

24. OFC Laying 6648-00-19-43-2924 0

25. OFC Jointing & Testing 6648-00-19-43-2925 0

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2901 Rev.0
Page 1 of 1

INDICATIVE ITP FOR

HANDING OVER/TAKING OVER OF LINE PIPE AT DUMP YARD

Sl. EPCC Owner/


Activity
No. Contractor PMC

1 Submission & approval of work procedure WC Rw

2 Grading and stripping of dumpsites WC S

3 Checking of coating material, pipe dia., cleaning, heat WC W


nos. & other markings, bevel edges, correlating with
Release Note by laying contractor

4 Stacking of pipes in a pyramid fashion with proper WC S


packing.

5 Segregation of defective pipes having beveled end WC S


defects, damaged coatings, improper cleaning, etc.

6 Repairs, if any WC W

7 Signing of Joint Record for handing over/ taken over WC W

INSPECTION & TEST DOCUMENTS

Review test and inspection documents WC Rw

The above activities will be under EIL if warehousing is in EIL scope of work

Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2902 Rev.0
Page 1 of 1

INDICATIVE ITP FOR

RECEIPT, HANDLING & STORAGE OF LINE PIPES AND


OTHER FREE ISSUE MATERIALS

Sl. EPCC Owner/


Activity
No. Contractor PMC

1 Submission & approval of work procedure WC Rw

2 Material Issue Voucher WC W

3 Visual check for damages of coating, bevel & other WC W


damages, inside cleaning, and re-fixing of end caps

4 Identification of correct grade, type, specification, heat WC S


no., pipe no., etc. of materials

5 Holiday test of pipes WC S/W *

6 Storage/stacking of line pipes as per specs WC S

7 Drum testing of OFC WC W

8 Loading & transportation as per spec. WC S

9 Electrical items WC W

INSPECTION & TEST DOCUMENTS

Review test and inspection documents WC Rw

* wherever damage reported before taking over

Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2903 Rev.0
Page 1 of 1

INDICATIVE ITP FOR

PROCUREMENT, RECEIPT & STORAGE OF


EPCC CONTRACTOR SUPPLIED MATERIALS

Sl. EPCC Owner/


Activity
No. Contractor PMC

1. Submission & approval of work procedure WC Rw

2. Receipt of all PO & PR/MR WC HP

3. Physical verification of materials with PO for any WC S


damage

4. Verification of batch no./specification/Inspector's hard WC W


stamp, etc.

5 Verification of test certificates/ Release Notes & WC HP


correlation with the materials received at site.

6. Field testing, if any as required WC Rw

INSPECTION & TEST DOCUMENTS

Review test and inspection documents WC Rw

Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2904 Rev.0
Page 1 of 1

INDICATIVE ITP FOR

ROW SURVEY, CLEARING & GRADING

Sl. EPCC Owner/


Activity
No. Contractor PMC

1 Taking over ROU from client/owner WC Rw

2 Calibration/testing of survey equipments


a) Review of certificates WC Rw
b) Rechecking , if any WC HP

3 Submission & approval of work procedure WC Rw

4 Staking markers for IPs, TPs, Km thickness change and WC S


others

5 Availability of approved AFC alignment sheets WC HP

6 Recording of level before & after ROW grading WC S

7 Centre line of pipeline and location/width of turning WC W/S *


points

8 Setting of reference line and TBM WC S

9 Establishment of width of ROW with reference to the WC S


existing pillars as per alignment sheet

10 Existence of structure/obstruction WC W/S *

11 Restricted ROW WC W/S *

INSPECTION & TEST DOCUMENTS

Review test and inspection documents WC Rw

* W : In case ROU is in Owner’s Scope


S : In case ROU is in EPCC contractor’s scope

Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2905 Rev.0
Page 1 of 1

INDICATIVE ITP FOR

TRENCHING

Sl. EPCC Owner/


Activity
No. Contractor PMC

1 Submission and approval of work procedure WC Rw

2 Center line/dimensions of trench w.r.t established WC S


markers & stacks or existing U/G line (in case of existing
ROW)

3 Measurement of trench depth WC S

4 Detail of under-ground structures encountered and its WC S


safety

5 Provision of warning signs & safety regulation WC S

6 Maintenance of motorable road WC S

7 Preservation of aerable soil WC S

8 Level and width of excavated trenches WC S

9 Bottom padding in trench, if required WC S

10 Restricted ROW WC W

11 Profile survey of trench at TP/crossing WC W

INSPECTION & TEST DOCUMENTS

Review test and inspection documents WC Rw

Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2906 Rev.0
Page 1 of 1

INDICATIVE ITP FOR


BLASTING

Sl. EPCC Owner/


Activity
No. Contractor PMC

1 Submission & approval of work procedure WC HP

2 Centre line of trench / dimension WC W

3 Notice to all concerned authorities WC S

4 Removal of super structures WC W

5 Submit details of all explosive materials for approval & WC HP


license for blasting

6 Availability of qualified supervisor WC Rw

7 Examine blasting material before use WC S

8 Trial blast & vibration recording for each rock and WC HP


trench type

9 Ensure area is clear of human beings and animals WC S

10 Ensure firing of all spots, misfires to be brought to WC Rw


notice

11 Recording of all safety regulations WC Rw

12 Fuses, inflammable materials, insertion of cartridge WC S

13 Firing WC S

14 Details of underground utilities encountered WC W

15 Bottom padding in trench, if required WC W

16 Profile of trench to suit vertical and horizontal bends WC S

INSPECTION & TEST DOCUMENTS

Review test and inspection documents WC Rw


Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2907 Rev.0
Page 1 of 1

INDICATIVE ITP FOR

PIPE TAKING OVER, HANDLING, HAULING & STRINGING

Sl. EPCC Owner/


Activity
No. Contractor PMC

1 Submission & approval of work procedure WC Rw

2 Verification of pipe dia./ length/ ovality/ inside WC S


cleanliness, damage during transportation/ pipe no./
heat no./ yard coating no., holiday checking etc. & its
documentation during taking over of pipes from dump
yards

3 Presence of bevel protector (Metal guard ) WC S

4 Proper stacking & tieing of pipe on trailor WC S

5 Stringing of correct dia./thickness of pipes in ROW on WC W


sand bags

6 Repair of damaged coating WC S

7 Use of proper slings WC S

8 Proper angular placement/TP WC S

INSPECTION & TEST DOCUMENTS

Review test and inspection documents WC Rw

Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2908 Rev.0
Page 1 of 1

INDICATIVE ITP FOR

COLD FIELD BENDING OF PIPES

Sl. EPCC Owner/


Activity
No. Contractor PMC

1 Submission & approval of work procedure WC Rw

2 Bending procedure qualification and approval including WC HP


performance test of bending machine

3 Survey check WC S

4 Setting up of pipe orientation for L-Seam WC S

5 Bending operation; degree/pull etc. WC S

6 Visual check after bending incl. radius angle etc. WC S

7 Gauge check WC W

8 Holiday checking WC W

9 Disbondment check WC W

10 Availability of straight length on ends WC W

11 Numbering for identification w.r.t. TP WC S

INSPECTION & TEST DOCUMENTS

Review test and inspection documents WC Rw

Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2909 Rev.0
Page 1 of 1

INDICATIVE ITP FOR

CONCRETE COATING

Sl. EPCC Owner/


Activity
No. Contractor PMC

1 Submission & approval of work procedure WC Rw

2 Coating procedure approval WC Rw

3 Logging of activities WC S

4 Holiday test of pipes before placing of reinforcement


wires etc./ repair WC W

5 Raw material inspection & testing wherever required WC HP

6 Wire mesh application WC S

7 Approval of concrete mix design WC HP

8 Preparation of concrete mix & pouring WC S

9 Visual check of coated pipe WC S

10 Repairs WC S

11 Water curing/ curing with compound WC S

12 Cube testing WC S

13 Megger checking WC HP

14 Marking of completed pipes, cleaning & fixing of end WC HP


caps

INSPECTION & TEST DOCUMENTS

Review test and inspection documents WC Rw

Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2910 Rev.0
Page 1 of 1

INDICATIVE ITP FOR

MAIN LINE WELDING

Sl. EPCC Owner/


Activity
No. Contractor PMC

1 Submission & approval of work procedures WC Rw

2 Filler material
a) Approval of Make WC HP
b) Review of manufacturer’s test certificates/documents WC HP
c) Testing, as required WC HP

3 WPS/PQR
a) Review of proposed WPS WC HP
b) Procedure Qualification Test WC HP
c) Approval of final WPS & PQR WC HP

4 Welders
a) Performance qualification test WC W
b) Review of radiographs of qualification test piece WC HP
c) Final approval of welders WC HP

5 NDT Procedure Qualification


a) Review of proposed procedure WC HP
b) Procedure Qualification Test WC W

6 Bevel inspection & inside cleaning of pipes WC S

7 Line-up/pre heating & root welding WC S

8 Lowering of pipe on sand bags & removal of line-up clamp WC S

9 Weld visual & writing welder nos. beside completed welds WC S

10 Placement of night caps/end caps WC S

11 Interpretation of weld radiographs WC HP

12 Other NDT’s WC W/Rw

13 Visual check of repaired welds WC S

14 Destructive Testing of production welds WC HP

15 All weld tensile test and bend tests for each batch of WC HP
electrodes (used for other than root pass welding )

16 Confirmation check of radiography of weld joints WC W

INSPECTION & TEST DOCUMENTS

Review inspection & test documents WC Rw


Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2911 Rev.0
Page 1 of 1

INDICATIVE ITP FOR

REPAIR OF ARC BURNS ON PIPES/ARC STRIKES

Sl. EPCC Owner/


Activity
No. Contractor PMC

1 Submission & approval of work procedure WC Rw

2 Visual check for arc burns on pipe surface WC S

3 Removal of arc burns by grinding WC S

4 DP/MP test on the ground area (arc burn area) WC W

5 Wall thickness check of arc burn repair area WC W

6 UT on the arc burn area, if required WC W

INSPECTION & TEST DOCUMENTS

Review test and inspection documents WC Rw

Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2912 Rev.0
Page 1 of 1

INDICATIVE ITP FOR

FIELD JOINT COATING & REPAIR

Sl. EPCC Owner/


Activity
No. Contractor PMC

1 Submission & approval of work procedure WC Rw

2 Approval of coating procedure WC HP

3 Approval of coating materials WC HP

4 Qualification of insulators/application WC HP

5 Surface preparation/preparation at shop coating WC S


(chamfering etc.)

6 Heating of pipe surface and mixing & application primer WC S

7 Temperature measurement prior to application WC S

8 Application of sleeves/tapes WC S

9 Visual check for irregularities, thickness etc. WC S

10 Holiday check WC W

11 Peel test, wherever required WC HP

12 Repairs and Holidays WC W

INSPECTION & TEST DOCUMENTS

Review test and inspection documents WC Rw

Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2913 Rev.0
Page 1 of 1

INDICATIVE ITP FOR

LOWERING OF MAIN LINE & OFC CABLES

Sl. EPCC Owner/


Activity
No. Contractor PMC

1 Submission and approval of work procedure WC Rw

2 Clearance for lowering WC HP

3 Inspection of trench for depth , debris etc. WC S

4 Soft soil/sand padding , if required WC W

5 Holiday check prior/during Lowering after removing end WC HP


caps

6 Calibration of Holiday detector WC W

7 Location of pipe center line w.r.t. trench center & fixing WC S


of end caps

8 Tests on optical fibre cable/HDPE duct as applicable WC Rw


(before laying)

9 Lowering of optical fibre cable/HDPE duct WC W

10 Checking of levels WC S

11 Post padding WC S

INSPECTION & TEST DOCUMENTS

Review test and inspection documents WC Rw

Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2914 Rev.0
Page 1 of 1

INDICATIVE ITP FOR

BACK FILLING

Sl. EPCC Owner/


Activity
No. Contractor PMC

1 Submission & approval of work procedure WC Rw

2 Post padding by soft soil/sand, if required WC S

3 Placement of warning tape over OFC/HDPE duct WC S

4 Field concrete coating, if required WC S

5 Proper backfilling with crown WC S

6 Compaction of backfilling at crossings etc. WC S

7 Replacement of aerable soil, if required WC S

INSPECTION & TEST DOCUMENTS

Review test and inspection documents WC Rw

Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2915 Rev.0
Page 1 of 2

INDICATIVE ITP FOR

CASED CROSSINGS

Sl. EPCC Owner/


Activity
No. Contractor PMC

1 Submission & approval of Work Procedure WC Rw

2 Approval from competent authority to start the work WC S

3 Preparation of constn. drg. and schedule for boring as WC Rw


per contract/specs.

4 Approval of construction drg. from competent authority WC S


for length & depth of casing pipe in case of boring in
EPCC contractor’s scope

5 Preliminary survey & marking of P/L centre line WC W

6 Preparation of boring pit & level check WC S

7 Fitness check of casing pipe (out of roundness, dent WC S


etc.)
8 Welding of casing pipe WC S

9 Visual checks of casing pipe after welding WC W

10 Visual check of inside of the casing pipe & carrier pipe WC S

11 Boring operation WC S

12 Installation of casing vent and drain pipes WC S

13 Coating/Painting of vent and drain pipes WC S

14 Fabrication of carrier Pipe string WC *

15 Pre hydrotest of carrier pipe WC HP

16 NDT WC *

17 Field joint coating & holiday check WC *

Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2915 Rev.0
Page 2 of 2

Sl. EPCC Owner/


Activity
No. Contractor PMC
18 Approval of insulation material, spacing of insulator & WC Rw
tightness etc.

19 Installation of insulators WC W

20 Welding of nose piece to carrier pipe WC S

21 Insertion of Carrier Pipe WC W

22 Installation of end seals WC W

23 Electrical circuiting & resistance checks before WC W


backfilling

24 Boring completion reports & preparation of As Built WC Rw


Drgs.

25 Obtaining/submission of NOC from competent authority WC S

INSPECTION & TEST DOCUMENTS

Review test and inspection documents WC Rw

* as per Main Line Welding ITP No. 6648-00-19-43-2910

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2916 Rev.0
Page 1 of 1

INDICATIVE ITP FOR

OPEN CUT CROSSINGS


Sl. EPCC Owner/
Activity
No. Contractor PMC

1 Submission & approval of work procedure WC Rw

2 a) Approval from competent authority, if required WC S


to start the work
b) Crossing drawings, wherever required WC Rw

3 Fabrication of crossing string WC *

4 NDT WC *

5 Hydro test of the crossing string, if applicable & reqd. WC HP

6 Field joint coating WC *

7 Survey, marking centre line of P/L WC W

8 Holiday testing while lowering in the trench & fixing of WC HP


end caps after lowering

9 Concrete coating, if required WC *

10 Laying of HDPE pipe for OFC or MS conduit for HDPE WC *


pipe

11 Paddings & backfilling with selected soil as required WC S

12 Crossing completion report WC Rw

13 Excess earth disposal WC S

14 Installation of warning markers WC W

15 Obtaining & submission of NOC from competent WC Rw


authority

INSPECTION & TEST DOCUMENTS

Review test and inspection documents WC Rw

* as per Main Line welding ITP No. 6648-00-19-43-2910

Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2917 Rev.0
Page 1 of 1

INDICATIVE ITP FOR

MAJOR WATER CROSSINGS

Sl. EPCC Owner/


Activity
No. Contractor PMC

1 Submission & approval of work procedure WC Rw


2 Approval of competent authority to start the work WC S

3 Preliminary survey, marking reference line & TBM WC S


4 Crossing drawings duly approved by Engg. or statutory WC Rw
approvals, wherever required
5 Fabrication of string WC *
6 NDT WC *
7 Trenching WC S
8 Hydro test of the crossing string WC HP
9 Field joint coating WC HP
10 Holiday testing of the entire string WC W
11 Lowering / pulling WC W
12 Concrete coating , if required WC **
13 Laying of HDPE pipe for OFC WC W
14 Paddings & backfilling WC S
15 Gauging & Post - hydro test WC HP
16 Bank protection WC S
17 Post laying survey/As Built Drgs WC W
18 Crossing completion report WC S
19 Warning marker WC S
INSPECTION & TEST DOCUMENTS

* As per Main Line Welding ITP No. 6648-00-19-43-2910


** As per Concrete Coating ITP No. 6648-00-19-43-2909

Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2918 Rev.0
Page 1 of 1

INDICATIVE ITP FOR

HYDRO TESTING OF STRINGS FOR CROSSINGS

Sl. EPCC Owner/


Activity
No. Contractor PMC

1 Submission & approval of work procedure WC Rw

2 Fabrication of string WC *

3 NDT clearance WC HP

4 Inside cleaning of pipe string/gauging WC HP

5 Calibration certificate for pressure / temperature gauges WC Rw

6 Welding of test headers WC S

7 Water filling & venting WC S

8 Pressurization WC S

9 24 hour hold-up period - recording pressure / WC W


temperature for every hour

10 Visual inspection of weld/ pipe, wherever feasible WC W

11 Post hydro testing of major water crossings WC HP

12 Compilation of test records WC S

13 Draining of hydrotest water from the pipeline & fixing of WC W


end caps

INSPECTION & TEST DOCUMENTS

Review test and inspection documents WC Rw

* as per Main Line welding ITP No.6648-00-19-43-2910

Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2919 Rev.0
Page 1 of 1

INDICATIVE ITP FOR

INSTALLATION OF PIPE LINE MARKERS

Sl. EPCC Owner/


Activity
No. Contractor PMC

1 Submission & approval of work procedure WC Rw

2 Approval of " Sample " markers WC Rw

3 Fabrication of pipe line / OFC markers as per drawing WC S

4 Surface preparation & primer application WC S

5 Pre -casting of markers ( ROU boundary marker ) WC S

6 Installation of correct type marker at correct location as WC W


per drawing

7 Primer touch-up, finish painting & stenciling WC S

INSPECTION & TEST DOCUMENTS

Review test and inspection documents WC Rw

Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2920 Rev.0
Page 1 of 1

INDICATIVE ITP FOR


HYDROSTATIC TESTING & DE-WATERING
Sl. EPCC Owner/
Activity
No. Contractor PMC
1 Submission & approval of work procedure WC Rw
2 Mechanical clearance of the pipe section WC HP
(Part “B” of pipe book)
3 Submission of water test laboratory report including WC Rw
recommendations for corrosion inhibitor and its testing (if
reqd.), oxygen scavengers and bactericides
4 Calibration certificates for dead weight tester, pressure WC Rw
gauges, pressure/temperature recorders temp. sensor, water
meter etc.
5 Installation of temporary piping, equipments, filters, WC S
provisions for launching and receiving pigs etc.
6 Installation of water holding devices or piping from WC S
water sources etc.
7 Ensuring communication system WC S
8 Ensuring safety requirements WC S
9 Review of filling pump & pressurizing pump data WC W
10 Cleaning by air pigging WC W
11 Gauging pig run and gauge plate inspection WC HP
12 Flushing by water driven pigs WC S
13 Installation of temperature sensors WC S
14 Installation of launching and receiving WC S
headers and pigs
15 Filling operations and chemical dosing
a) Filling rate WC S
b) Chemical injection rate as approved WC S
c) Back pressure control to avoid air entrapment WC S
16 Thermal stabilization WC HP
17 Air volume confirmation test WC HP
18 Pressurization
a) Rates as per approved procedure WC S
b) Recording of temperature & pressure at every two hours WC HP
during 24 hours hold period
c) Bleed off water measurement WC W
19 Detection of leaks if any and extension of hydro test duration WC HP
20 Rectification & stocking/marking of damaged pipes WC W
21 Acceptance and evaluation of recorded data WC HP
22 Depressurization and de-watering to the WC W
accepted point
23 Swabbing operation WC S
24 Acceptance after swabbing operation and drying WC HP
25 Reinstatement WC W

INSPECTION & TEST DOCUMENTS


Review test and inspection documents WC Rw
Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2921 Rev.0
Page 1 of 1

INDICATIVE ITP FOR

MAIN LINE SECTIONALIZING VALVE (SV) INSTALLATION

Sl. EPCC Owner/


Activity
No. Contractor PMC

1 Submission & approval of work procedure WC Rw

2 Approval of WPS WC Rw

3 Pup piece welding & pre fabrication of valve assembly WC W

4 NDT clearance WC HP

5 Hydro test WC HP

6 Valve installation & tie-in WC W

7 NDT clearance after tie-in welding WC HP

8 Field coating/Holiday inspection WC W

9 Concrete foundation with insulation sheet on top WC W

10 Holiday checking, padding, backfilling WC HP

11 Miscellaneous Civil / Structural works as per drawing WC S

12 Painting of above ground structures WC S

INSPECTION & TEST DOCUMENTS

Review test and inspection documents WC Rw

Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2922 Rev.0
Page 1 of 1

INDICATIVE ITP FOR

FINAL CLEAN UP & RESTORATION

Sl. EPCC Owner/


Activity
No. Contractor PMC

1 Submission & approval of work procedure WC Rw

2 Restoration of water ways, roads, land structures, WC S


ecology etc.

3 Restoration of river banks and check protections as per WC S


approved drawings

4 Sorting and grouping of surplus piping material for WC S


returning to the owner and for scrapping

5 Transporting all scrap and disposable from ROW WC S

6 Inspect restoration of ROW to the condition as per spec. WC S

7 Installing all markers on the ROW and verify the activity WC W


with respect to As Built Drawings

8 Obtaining signature of land owners / statutory authorities WC Rw


on final restoration document

INSPECTION & TEST DOCUMENTS

Review test and inspection documents WC Rw

Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2923 Rev.0
Page 1 of 1

INDICATIVE ITP FOR

CALIBRATION OF INSTRUMENT

Sl. EPCC Owner/


Activity
No. Contractor PMC

1 Submission & approval of work procedure WC Rw

2 Physical verification of instruments WC W

3 Review of calibration certificates for test equipments WC Rw

4 Field calibration of instruments wherever required WC W

INSPECTION & TEST DOCUMENTS

Review test and inspection documents WC Rw

Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2924 Rev.0
Page 1 of 1

INDICATIVE ITP FOR

OFC LAYING

Sl. EPCC Owner/


Activity
No. Contractor PMC

1 Submission & approval of work procedure WC Rw

2 Review and approval of alignment sheets WC Rw

3 Review of manufacturer test certificate of HDPE & cable WC Rw

4 Trench inspection WC S

5 HDPE pipe installation WC S

6 C.S. piping installation (boring) WC S

7 Cable laying/blowing WC S

8 Padding / warning mat WC S

9 Route markers – Mechanical & Electronic and joint pit WC S


markers

10 Joint pit WC W

11 As-Built drawings WC Rw

INSPECTION & TEST DOCUMENTS

Review test and inspection documents WC Rw

Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-2925 Rev.0
Page 1 of 1

INDICATIVE ITP FOR

OFC JOINTING & TESTING

Sl. EPCC Owner/


Activity
No. Contractor PMC

- Submission & approval of work procedure WC Rw

1 Drum Testing

1a Physical inspection WC S

1b Measurement of fibre attenuation WC W

2 Jointing

2.1 Before splicing (after laying)

a) Record fibre attenuation of both the fibre being spliced WC W

2.2 Measurement of splice loss WC W

3 Link Testing

3.1 Measurement of link loss from either side OFC between WC W


two stations after jointing

INSPECTION & TEST DOCUMENTS

Review test and inspection documents WC Rw

Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-5000 Rev.0
Page 1 of 2

INDICATIVE FORMATS

FOR REPORTING

INSPECTION & TEST RESULTS

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-5000 Rev.0
Page 2 of 2

INDEX

S.NO DESCRIPTION DOCUMENT NO. REV.

1. Indicative Formats for Mechanical works 6648-00-19-43-5100 0

2. Indicative Formats for Instrumentation works 6648-00-19-43-5600 0

3. Indicative Formats for Civil works 6648-00-19-43-5700 0

4. Indicative Formats for Electrical works 6648-00-19-43-5800 0

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-5100 Rev. 0
Page 1 of 2

INDICATIVE

FORMATS

FOR

MECHANICAL WORKS

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-5100 Rev. 0
Page 2 of 2

INDEX

S.NO DESCRIPTION DOCUMENT NO. REV.

1. Daily Material Traceability Report 6648-00-19-43-5101 0


(For Piping/Heater)

2. Daily Fit-up Inspection Report 6648-00-19-43-5102 0


(For Piping/Heater)

3. Daily Weld Visual Inspection Report 6648-00-19-43-5103 0


(For Piping/Heater)

4. Radiography Interpretation Report 6648-00-19-43-5104 0


(For Piping/Heater)

5. Line Wise Record (History Sheet) 6648-00-19-43-5105 0


(For Piping/Heater)

6. Flushing Completion Report 6648-00-19-43-5106 0

7. Execution Scheme for Foundations 6648-00-19-43-5107 0

8. Tie-In 6648-00-19-43-5108 0

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-5101 Rev. 0
Page 1 of 1

DAILY MATERIAL TRACEABILITY REPORT


(FOR PIPING/HEATER)

Contract No. : Report No. :


EPCC Contractor : Date :

S. Line/ Area Dia. Joint Spool Component Manufacturer Heat/Batch Colour Verified Remarks
No. Heater No. No. No. No. No. Code Contractor PMC/Owner*
*

NOTE : A sketch of the spool may be enclosed.


* As per approved Inspection & Test Plans (ITPs)

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-5102 Rev. 0
Page 1 of 1

DAILY FIT-UP INSPECTION REPORT


(FOR PIPING/HEATER)

REPORT NO : ______________
DATE : ____________________

A/R
Sl. Line/Heater Joint Type
Area No. Dia Inspection Remarks
No. No. No. (*)
Clearance

A : Accepted
R : Rejected

(*)
G - BUTT WELD
S - SOCKET WELD
B - BRANCH WELD __________________
M - MITRE WELD EPCC CONTRACTOR

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-5103 Rev. 0
Page 1 of 1

DAILY WELD VISUAL INSPECTION REPORT


(FOR PIPING/HEATER)

REPORT NO : ______________
DATE : ____________________

Weld
Sl. Heater/Line No./ Area Type Welder Acceptance
Dia Joint Remarks
No. Drawing NO. No. (*) No.(s) Yes/No
No.

(*)
G = BUTT WELD
S = SOCKET WELD TOTAL IN DIA. =
B = BRANCH WELD PREVIOUS =
M = MITRE WELD TILL DATE =

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-5104 Rev. 0
Page 1 of 1

RADIOGRAPHY INTERPRETATION REPORT


(FOR PIPING/HEATER)

RADIOGRAPHY TECHNIQUE : SWSI/DWSI/DWDI PROJECT :___________


SOURCE IR 192, X RAY, COBALT OWNER : ____________
FILM TYPE & NAME : __________________________ REPORT NO : ________
IQI : _________________________ DATE : ______________
RADIOGRAPHY PROCEDURE NO.

Sl. Heater/ Area Dia Joint Welder Radio- Segment Results Joint
No. Line No. No. No. No. Graphy No. Status
A/R/H

SWSI - SINGLE WALL SINGLE IMAGE, DWDI - DOUBLE WALLL DOUBLE IMAGE
DWSI - DOUBLE WALL SINGLE IMAGE

A - ACCEPTED, R - REPAIR
H - HOLD

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-5105 Rev. 0
Page 1 of 1

LINE WISE RECORD (HISTORY SHEET)


(FOR PIPING/HEATER)

HEATER/LINE NO. ……………………. % RADIOGRAPHY ____________

Radio-
Stress PMI
Visual graphy PMI Base
(**) Release Hard- Heat/ Accep-
Sl. Area (*) Welder Inpn. Accep- Weld Metal Manuf-
Dia. Joint Chart ness Batch tance Remarks
No. No. Type No. Report tance ACC Comp- acturer
No. No. No. Date
No. Report. Date onent
(Material)
Date

(*)
G - BUTT WELD
S - SOCKET WELD (**) Joint No are to be posted from the dalily
B - BRANCH WELD fit up reports
M - MITRE WELD Where ever lsos are not available

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-5106 Rev. 0
Page 1 of 1

FLUSHING COMPLETION REPORT

PROJECT : ______________________ REPORT NO: __________________


PLANT : ________________________ DATE : ________________________
EPCC CONTRACTOR : _________________

System Area
Loop Nos. Unit
Ref. P&ID No. Test Reports – Enclosed

The above system has been cleaned/flushed/tested as per the


requirement of drawings and specifications and cleared for
operation.

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-5107 Rev. 0
Page 1 of 1

PROJECT : EXECUTION SCHEME FORMAT :


PLANT : SHEET NO:
EPCC CONTRACTOR FOR FOUNDATIONS DATE OF CHECKING :
:

FDN NO: DRG NO:


PCD / BCD ______________

GROUT THK ____________

( ) TOP OF BOLT

( ) TOP OF
CONCRETE

PCO
BOLT HT.

PCD
BOLT HT.

AS PER
DESCRIPTION ACTUAL DEVIATION REMARKS
DRG

N
C/L CO ORDINATES

EL. TOP OF CONCRETE


NO. OF BOLTS & SIZE
HEIGHT OF BOLTS
POD OF BOLTS
POCKET CLEARING
F D N. ROUGHENING
EL. TOP OF GROUT

REMARKS :

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-5108 Rev 0
Page 1 of 1

TIE-IN POINT INSPECTION

Unit Job No.

Tie-in Point No.


Line No.
P&ID No.

Line Size
Material

Chkd by Chkd by
EPCC
S.No. Activity OWNER/PMC Remarks
Contractor
Sign./date
Sign./date
1. Bevel/Thickness

2. Fit up Check material,


thk, root gap etc.
3. Root run welding

4. DP check of root run

5. Final Welding

6. PWHT (if applicable)

7. DP check of final welding

8. Radiography check

9. Hydrostatic test (if applicable)

* Details attached separately

TIE-IN POINT IS ACCEPTED

_______________ _________________
EPCC Contractor OWNER/PMC

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-5600 Rev 0
Page 1 of 2

INDICATIVE

FORMATS

FOR

INSTRUMENTATION WORKS

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-5600 Rev 0
Page 2 of 2

INDEX

S.
DESCRIPTION DOCUMENT NO. REV.
NO

1. Cable/ Tube Drum Cutting Plan 6648-00-19-43-5601 0

2. Calibration Report for Control Valves/On/Off Valves/ 6648-00-19-43-5602 0


Shut Down Valves

3. Fit-up Inspection Report 6648-00-19-43-5603 0

4. Instrument Cable Laying Report 6648-00-19-43-5604 0

5. Instrument Cable Megger Report 6648-00-19-43-5605 0

6. Junction Box/LCP Installation Report 6648-00-19-43-5606 0

7. Instrument Air Line/Pneumatic Tube Erection Report 6648-00-19-43-5607 0

8. Level Instrument Installation Report 6648-00-19-43-5608 0

9. Installation Report for Test T/W, TG, TC, RTD 6648-00-19-43-5609 0

Pl. refer document No.6648-00-19-43-5100 for Impulse piping formats.

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation Process
Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-5601 Rev.0
Page 1 of 1

CABLE/TUBE DRUM CUTTING PLAN


REPORT NO : ______________________________ DATE : ______________________________

LOCATION : ______________________________ AREA : ______________________________

Length as per
Sl. Cable/Tube Drum Drum Actual Test
From To Cable/Tube Balance Remarks
No. Size No. Length Length Reports
Schedule

___________________ _____________
(EPCC CONTRACTOR) (OWNER/PMC)

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-5602 Rev.0
Page 1 of 1

CALIBRATION REPORT FOR CONTROL VALVES/ON/OFF VALVES/SHUT DOWN VALVES


REPORT NO: _____________________________ DATE : _____________________

Instrument details : Master calibration instrument details:


Tag No. Type :
Model No.: Model No.:
Sl.No.: Sl.No. :
Manufacturer : Testing agency :
Range : T/C No.:
Ref. Data Sheet : Validity upto :
Calibration date :

E/P Valve Position Indicator


Input
Positioner With Positioner Without Positioner Stroke Action Remarks
% Actual Output INC DEC DIFF INC DEC DIFF
0
25
50
75
100
Acceptance criteria : As per CV/SDV/instrument data sheet

(a) Hysteris with Positioner (Within + 1% FS) …….….. Yes/ No (d) Shutdown Valve Stroke Speed ……………….….
(b) Hysteris without Positioner (within + 5% FS)……… Yes/No (e) Air Fail Action checked ……………. Open/Close
(c) Linearity Checked ……………………………………. Yes/No (f) Solenoid Power Supply …………………………….
(g) Solenoid Valve OP Checked …………… Yes/No
REMARKS
___________________ _____________
(EPCC CONTRACTOR) (OWNER/PMC)

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-5603 Rev.0
Page 1 of 1

FIT UP INSPECTION REPORT

REPORT NO. : ________________________ DATE : _____________________

Line No./ Material Inspection clearance


Sl. Area Spool Joint Heat Joint Thickness Type of
Isometric Traceability EPCC Owner/ Remarks
No. No. No. No. No. dia (Inch) (mm) Joint
No. R.No. & Date Contractor PMC

No. of Joints Inch Dia.


Today Previous Cumulative Today Previous Cumulative

___________________ _____________
(EPCC CONTRACTOR) (OWNER/PMC)

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-5604 Rev.0
Page 1 of 1

INSTRUMENT CABLE LAYING REPORT

REPORT : ________________________________ DATE : _______________________________

Act. Verification by
Sl. Cable Cable Gland Gland
From To Length Dressing Clamping Glanding Ferruling Termination EPCC Owner/ Remarks
No. Tag Type Type Size
(m) Contractor PMC

___________________ _____________
(EPCC CONTRACTOR) (OWNER/PMC)

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-5605 Rev.0
Page 1 of 1

INSTRUMENT CABLE MEGGER REPORT


REPORT NO : ________________________________ DATE : ___________________

Details of Megger instrument: Sl. No.


Make : Test certificate No. :
Model No. :
Validity uoto :

Sl. Insulation Resistance (IR) Test


Cable Identification Tag ** Cable Length Remarks
No. Test voltage Core to core Core to Earth

Remarks :

Acceptance criteria : As per cable data sheet


** Cable identification tag details with From-To type

___________________ _____________
(EPCC CONTRACTOR) (OWNER/PMC)

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-5606 Rev.0
Page 1 of 1

JUNCTION BOX/LCP INSTALLATION REPORT

REPORT NO : _____________________________ DATE : _________________________

Sl. Gland Verification by


Tag no. Type Location Support Instln Alignment Earthing Plugging Painting EPCC Owner/ Remarks
No. type
Contractor PMC

___________________ _____________
(EPCC CONTRACTOR) (OWNER/PMC)

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-5607 Rev.0
Page 1 of 1

INSTRUMENT AIR LINE/PNEUMATIC TUBE ERECTION REPORT


REPORT NO : ___________________________ DATE : _______________________________

REF. DRAWING : _________________________ REV. : ________________________________

Check for Test Gauge details Test Pr. Verification by


Hook Joints
Sl. Tag Sl/ Cal Joint
Up From To Union/ Support Painting Flushing Range Valid Leak EPCC Owner/
No. No. Drain Vent BOM Model report Kg\Cm
2 Tightening
STD Loop
2
(Kg\Cm ) Upto Test Contractor PMC
No. No.

Remarks :

___________________ _____________
(EPCC CONTRACTOR) (OWNER/PMC)

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation Process
Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-5608 Rev.0
Page 1 of 1

LEVEL INSTRUMENT INSTALLATION REPORT


REPORT NO.: _____________________________________ DATE : ____________________________

REF. DRAWING : __________________________________ REV. : _____________________________

Check for correctness of Instln. Test Gauge details Verification by


Hydro
Sl. Tag Model Serial PMS Flange Check for Sl/ Cal
Location Stud/ Verti- Orien- Range Test EPCC Owner/
No. No. No. No. Class Rating Flanges Gasket Float/ Model 2 Report/
nut cality tation (Kg/Cm ) Result Contractor PMC
Displacer No. Validity

Acceptance criteria: Instrument Installation Standard

Remarks:

___________________ _____________
(EPCC CONTRACTOR) (OWNER/PMC)

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation Process
Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-5609 Rev.0
Page 1 of 1

INSTALLATION REPORT FOR TEST T/W, TG, TC, RTD

REPORT NO:. ______________________________________ DATE : __________________________

Immersion Tightness Verification by


Sl. Tag Range PMS Flange Tapping Orien- Stud/
Location Length Gasket of stud/ Plugging EPCC Owner/ Remarks
No. No. Deg C Class Rating Size tation Nut
(mm) Nut Contractor PMC

___________________ _____________
(EPCC CONTRACTOR) (OWNER/PMC)

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-5700 Rev. 0
Page 1 of 2

INDICATIVE

FORMATS

FOR

CIVIL WORKS

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-5700 Rev. 0
Page 2 of 2

INDEX

S.NO DESCRIPTION DOCUMENT NO. REV.

1. Calibration of Instruments 6648-00-19-43-5701 0

2. Determination of Dry Density and 6648-00-19-43-5702 0


Moisture Content

3. Sieve Analysis 6648-00-19-43-5703 0

4. Cement Testing 6648-00-19-43-5704 0

5. Pour Card 6648-00-19-43-5705 0

6. Crushing Strength of Cubes 6648-00-19-43-5706 0

7. Bricks Testing 6648-00-19-43-5707 0

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-5701 Rev. 0
Page 1 of 1

FORMAT FOR CALIBRATION OF INSTRUMENTS

Project : Job No. :

OWNER : EPCC CONTRACTOR :

Name of Work :

Accepted
Name of Next
Sl. Model Certificate Calibrated Calibration EPCC PMC/
Equipment/ Calibration Remarks
No. No. No. By Date Cont- OWN-
Apparatus Due on
ractor ER

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-5702 Rev. 0
Page 1 of 1

FORMAT FOR DETERMINATION OF DRY DENSITY


AND MOISTURE CONTENT

Project : Job No :

OWNER : EPCC CONTRACTOR :

Name of Work :

Location : Layer No :

S. Test Nos:
Description Relation Remarks
No. 1 2 3 4 5 6
1. Wt. of mould + wt. of wet W1 gm
soil
2. Wt. of mould W2 gm
3. Wt. of wet soil (W1 – W2) gm
4. Volume of mould V cc
5. Density of wet soil Dw = (W1 – W2)/V gm/cc
6. Wt. of wet sample taken Ww gm
7. Wt. of sample after drying Wd gm
8. Moisture Content Mc = (Ww – Wd)/wdx100%
9. Dry density Dd = Dw/(1+Mc) gm/CC
10. Laboratory Max dry gm/cc
density
11. Degree of Compaction %
12. Required degree of %
compaction
13. Optimum Moisture Content %
(OMC)

_____________________________ ____________________ ______________


( TESTED BY/LAB-IN-CHARGE ) ( EPCC CONTRACTOR ) ( PMC/OWNER )

Date :

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-5703 Rev. 0
Page 1 of 1

FORMAT FOR SIEVE ANALYSIS

Project : Job No :

OWNER : EPCC CONTRACTOR :

Name of Work :

Wt. of Sample taken : Date on which sample taken :

FINE AGGREGATE

S. Sieve Weight Percentage Cumulative % Fineness Zone Remarks


No. Size Retained (gm) Retained % Retained Passing Modulus

1. 4.75mm
2. 2.36mm
3. 1.18mm
4. 600 u
5. 300 u
6. 150 u
7. Pan

COARSE AGGREGATE Wt. of Sample taken :


1. 20mm
2. 10mm
3. 4.75mm
4. 2.36mm

_________________________ ___________________ _____________


(TEST BY/LAB-IN-CHARGE) EPCC CONTRACTOR) (PMC/OWNER)

Date :

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-5704 Rev. 0
Page 1 of 1

CEMENT TEST RESULTS

Project : Job No :
Owner : PMC :
EPCC Contractor :
Name of Work :
Brand of Cement : Consignment No. :
Wt. of sample taken : Sample Collected on:
Room Temperature :

A. CONSISTENCY
Trial Wt. of Wt. of % of Water Reading Consistency Remarks
No. Cement Water on
(gm) Added Indicator
(gm) (mm)

B. SETTING TIME
Trial Wt. of Wt. of W/C Time Time Initial Final Setting Remarks
No. Cement Water Ratio Recorded Recorded Set Set Set
(gm) Added when at set
(gm) Water
Added

C. FINENESS
Trial No. Wt. of Cement Retained on % Retained Remarks
Sample used 90 µ sieve
in gm

D. COMPRESSIVE STRENGTH
Cube Size : 7.06X7.06X7.06 cm
Trial Mix Date of Age of Crushing Crushing Crushing Remarks
No. Proportion Casting Testing Specimen Surface Load Strength
Area (Cm2) (Kg) (Kg/Cm2)

______________________________ ___________________ ____________


( TESTED BY )/LAB-IN-CHARGE ( EPCC CONTRACTOR ) ( OWNER/PMC)

Date:

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-5705 Rev. 0
Page 1 of 2

FORMAT FOR POUR CARD


Programme of concreting
EPCC CONTRACTOR : OWNER :
Name of work :
1. Reference document :
2. Type of structure : Location :
3. Levels From : To :
4. Grade of concrete/ Approved Design Mix
5. Brand name, Grade and Consignment no. of cement
6. Estimated volume of concrete :
7. Quantity of cement required :
8. Reinforcement checking details :
No. Dia. Length
a) Laps
b) Separators
c) Chairs
d) Any other

Remarks

9. Pre pour inspection details Checked NA


a) Survey/ Layout
b) Sub soil compaction
c) Completion of underground works
d) Cleanliness
e) Cover to reinforcement
f) Anchor bolts
g) Sleeves/ pockets
h) Water stops
i) Formwork
j) Slopes
k) Construction/ Expansion joints
l) Admixtures
m) Any other

Remarks

10. Clearance for Electrical/ Mechanical Electrical Mechanical


works required/ not required :

11. The above structure is finally inspected on at AM/PM and found/ not found
satisfactory for concreting.
Remarks, if any

(EPCC CONTRACTOR) (PMC) (OWNER)


Name Name Name
Designation Designation Designation
Date Date Date

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-5705 Rev. 0
Page 2 of 2

FORMAT FOR POUR CARD


Observation during concreting

EPCC CONTRACTOR : OWNER :


Name of work :
1. a) Quality of coarse aggregates
Satisfactory Not satisfactory

b) Quality of fine aggregates


Satisfactory Not satisfactory

c) Bulkage of sand taken into account


Yes No

2. Quality of water
Satisfactory Not satisfactory

3. Machinery mobilization Nos. Stand by


a) Mixture machine
b) Ready mixed concrete dumpers
c) Vibrators
d) Pumps
e) Hoists
4. Pour start time : AM/PM ; Date :
5. Slump
6. W/C Ratio
8. Type of weather
Normal Abnormal

Details of abnormality :
(Precautions taken for <50C and >400C, rainy season)
10. Number of cubes taken :
11. Quantity of concrete poured :
12. Pour completion time : AM/PM ; Date :
13. Curing method :

Traditional Curing compound

Blankets/ foils/ gunny bags Others (specify)

14. Period for removal of form work :


15. Any defect(s) observed during concreting :

(EPCC CONTRACTOR) (PMC) (OWNER)


Name Name Name
Designation Designation Designation
Date Date Date

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-5706 Rev. 0
Page 1 of 1

FORMAT FOR CRUSHING STRENGTH OF CUBES

Project : Job No :

OWNER : EPCC CONTRACTOR :

Name of Work : Grade of Concrete :

Type of Cement : W/C Ratio :

Max. size of Aggregate :

Cube Id. Type & Date Of Age Dimensions of Vol. Wt. Unit Sur- Crus- Crushing Remarks
No. Mark Location (days) Cube of of WT. ace hing Strength
3 2
on of Struc. Cube Cube (Kg/m ) Area Load (Kg/Cm )
2
cube Cast Test L B H (m3) (Kg) (m ) (Kg)
(m) (m) (m)

_____________________________ ________________ _____


( TESTED BY)/LAB-IN-CHARGE (EPCC CONTRACTOR ) ( PMC )

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-5707 Rev. 0
Page 1 of 1

WATER ABSORPTION, CRUSHING STRENGTH & EFFLORESCENCE


TESTS FOR BRICKS

Project : Job No :

OWNER : PMC :

EPCC Contractor :

Name of Work :

S. Frog Wt. of Absorption Wt. of % of Efflore- Av. Size Crushing Rem-


No. Mark oven Period wet Water scence of Brick arks
Dried (hr) Brick Absorption Observed (LXBX H)
3
Brick (gm) After Cm
(gm) Drying

Surface Load Stren-


Area (Kg) gth
(Cm2) (Kg/Cm2)

___________________________ __________________ ___________


(TESTED BY/LAB-IN-CHARGE) EPCC CONTRACTOR OWNER/PMC

Date :

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-5800 Rev. 0
Page 1 of 2

INDICATIVE

FORMATS

FOR

ELECTRICAL WORKS

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-5800 Rev. 0
Page 2 of 2

INDEX

S.NO DESCRIPTION DOCUMENT NO. REV.

1. HV Switch Board 6648-00-19-43-5801 0

2. Transformers 6648-00-19-43-5802 0

3. ON Load Tap Changer 6648-00-19-43-5803 0

4. Neutral Grounding Resistor 6648-00-19-43-5804 0

5. MV Switch Board 6648-00-19-43-5805 0

6. Battery Set and Charger 6648-00-19-43-5806 0

7. HV Motor 6648-00-19-43-5807 0

8. MV Motor 6648-00-19-43-5808 0

9. DG Set 6648-00-19-43-5809 0

10. Cable Installation 6648-00-19-43-5810 0

11. Electrical Heat Tracing System 6648-00-19-43-5811 0

12. Lighting Installation 6648-00-19-43-5812 0

13. Earthing Installation 6648-00-19-43-5813 0

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-5801 Rev. 0
Page 1 of 6

TEST PROFORMA
HV SWITCHBOARD

Project : Job No. :


Name of Work :
EPCC CONTRACTOR :
Tag No.

1.0 Voltage : Manufacture :


Current : Type of Breaker : VCB/SF6/MOCB
Fault level :
Section 1 fed from :
Section 2 fed from :
Control supply :

2.0 GENERAL CHECKS : (Put tick (9) if satisfactory, otherwise give details)

2.1 Installation

General cleaning of panels and Cleaning & Inspection of


assembly insulators

Earthing of the panel (Double Floor level


earthing)

Busbar alignment and connections Bus trunking and tightness of


nut and bolt connections

Glands, termination & spacing of Sealing of cable entries and


cables Vermin proofing

Taping of exposed portion of cables Tightness of cable connections


(if required)

Tagging of ferruling of cables Leakage of oil if any

Pressure of SF6 gas Dielectric strength of oil

CB closing & tripping mechanism Circuit breaker-Main contacts


alignment

Auxiliary contacts change over Control switches & keys

Drive & limit switches functioning

Rating of fuse as per approved drg. Relay cleaning & operation

Indication lamps Meters ranges


Danger board

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-5801 Rev. 0
Page 2 of 6

2.2 Circuit Checking :

CT & current circuits PT & PT circuits

Control circuit Alarm & signaling circuit

Meters & metering circuit Interlocks

2.3 Pre-Commissioning Checks

Control, protection and signaling circuit


operation

Bus shrouds and safety features

Operation of manual Auto transfer circuit and


interlocks

Insulation resistance of main bus and control

Settings of relays & timers as per drawings


(Attach Relay setting details with this format for
Incomers, Bus couples, DG incomes (if
available))

Interlocks & inter tripping

External interface with ECS/DCS/ Annunciation


panel

3.0 TEST RESULTS

3.1 Insulation, Resistance Measurement

Megger used: Ambient Temp:

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-5801 Rev. 0
Page 3 of 6

INSULATION RESISTANCE (I.R.) IN MEGA OHMS


RY YB BY RE YE BE

a. Busbars Section-1

Section-2

b. Busduct/Cables Section-1

(Incomer) Section-2

c. Outgoing feeders (Panel no./


Feeder Designation

3.2 Current Transformer

Panel No. :

Feeder Designation :

3.2.1

Protection
Manufacturer's Data Metering
Core 1 Core 2 Core 3
Ratio

VA rating

Accuracy Class

Serial nos.

3.2.2 Tests & Checks: (Put tick (9) if satisfactory)

a. Polarity check (inconformity with the drawing)

b. Check CT earthing

c. Wiring correctness & continuity check


and tightness of connections

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-5801 Rev. 0
Page 4 of 6

d. Test results:

Protection
Tests Metering
Core 1 Core 2 Core 3
i) Ratio measurement

ii) Insulation Resistance


(Measured)
Primary to Earth

Secondary to Earth

Primary to secondary

3.3 Potential Transformer Panel No.:

3.3.1 Manufacturer's Data

Ratio :

VA rating :

Class :

Type :

Serial Nos. :

3.3.2 Tests and Checks

a) Ratio Measurements

b) Polarity check :

c) Wiring correctness &


tightness of connections :

d) Check PT earthing :

e) Insulation resistance
measured :

Primary to earth :
Secondary to earth :
Primary to earth :

f) Check fuses rating :

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-5801 Rev. 0
Page 5 of 6

3.4 Relays

3.4.1 Protective current relays

Test conducted and


Component found satisfactory
S. Type and
NEMA Code code as per as per field test
No. Range
vendor drawing report
(Put '9' mark)
1.

2.

3.

3.4.2 Voltage, Auxiliary relays and timers

Test conducted and


found satisfactory
S. Type and
Circuit Symbol NEMA Code as per field test
No. Range
report
(Put '9' mark)
1.

2.

3.

Note : 1. For each relay, site pre-commissioning checks and tests shall be carried out in
accordance with manufacturer’s instructions manual and test readings are
recorded.
2. IDMTL, and instantaneous relays and other protective relays shall be checked for
proper operation at minimum of 3 settings which shall include relay protection co-
ordination setting values for IDMTL & instantaneous relays.
3. Correctness of CT polarity and connections for differential protection circuit shall
be ensured through 3 phase primary injec5tion transformer kits for in zone & out
zone.
4. Enclose Relay Test reports along with the report

4.0 COMMISSIONING

Clearance from all agencies Electrical Inspector’s clearance

Operation of breaker in test Tripping of breaker thro’


position protective relays

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-5801 Rev. 0
Page 6 of 6

Meggar results of cable


(Attach format E-10 For H.T. Meggar readings of equipment
Cables & Enclose Megger value being charged (busbar,
taken before commissioning). transformer or motor)
(Attach format E-2/ET
depending upon equipment
being charged if it is other than
H.V. Switchboard).

Pre commissioning test results of Relays settings done as


equipment to be charged required
(transformer/motor etc. (Enclose Relay Setting details
with this Format)

5.0 OPERATIONAL CHECKS

Condition of equipment after


energisation

Magnetisining/starting current

Phase matching of two sections (in case of incomer breaker)

Auto transfer ckt, operation Time :

Manual transfer ckt. Operation

6.0 REMARKS (if any)

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-5802 Rev. 0
Page 1 of 5

TEST PROFORMA
TRANSFORMERS

Project : Job No. :


Name of Work :
EPCC CONTRACTOR :

1.0 MANUFACTURER’S DATA

Type S.No. Year of


Manufacture

Kva rating Primary voltage Primary current

Frequency Secondary voltage Secondary current

Vector group % impedance No. of taps

2.0 GENERAL CHECKS : tick (9) if found satisfactory correct otherwise give
details.

2.1 Installation

Installation of transformer Transformer Earthing

Neutral earthing Oil level

Leakage of oil Tap changer Position

Condition of bushings Cable box, glands, lugs


terminations

Winding and Oil Breather/sillicagel

Temperature indicator-settings Oil level indicator

Size of the Primary/Secondary Thermometer pocket filled with


cable as per schedule oil

Position of valves Wiring for auxiliaries

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-5802 Rev. 0
Page 2 of 5

Marshalling box Buchholz Relay mounting

Explosion vent Fuse rating for circuits

Cooling fan Stopper provided

Fire extinguisher (Provided in sub Danger boards


station)

2.2 Value of Earth Resistance : Date of Measurement :

Neutral earth Electrodes :

Electrodes for transformer body earthing :

3.0 DIELECTRIC STRENGTH OF THE OIL :

Withstand voltage Breakdown


Top sample

Bottom sample

4.0 INSULATION RESISTANCE

TEMPERATURE AT THE TIME OF TESTING

H.V. winding to earth L.V. winding to earth H.V. to L.V. winding


Meggar Range used Meggar Range used Meggar Range used

R15 R60 K=R60/R15 R15 R60 K R15 R60 K

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-5802 Rev. 0
Page 3 of 5

5.0 MEASUREMENT OF WINDING RESISTANCE:

Temperature at the time of testing:

H.V. Winding L.V. Winding

Tap 1 Tap 2 Tap 3 Tap 4 Tap 5 Current Voltage Resistance


injected Drop
A- a-b
B
B- b-c
C
C- c-a
A

6.0 VECTOR GROUP SHORT A-a HV Terminals A B C


LV Terminals abc

Voltage group on HV side Voltage measured on LV side


VAB VBC VCA VBb VBC VCb VCc Remarks

Vector Group:

7.0 VOLTAGE RATIO

TAP : Voltage applied on H.V. Side Voltage on L.V. Side Av Ratio


A-B B-C C-A a-b b-c c-a

Tap1

Tab2

Tab3

Tab4

Tab5

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-5802 Rev. 0
Page 4 of 5

8.0 OPERATION OF BUCHHOLZ RELAY : Alarm at; Tripping at:

9.0 OPERATION OF COOLING PUMP & FAN

Control circuit

Overall relays

Direction of Rotation

Interlocks

Temperature at which fans start

10. CHECKING OF EXTERNAL CIRCUITS

Operation of protection relays

Signaling circuit

Alarm/blinkers

Breaker tripping through relays

Meters & metering ckt.

LV section isolation

11.0 OPERATION CHECKS

Vibrations : Any abnormal noise : Magnetization current :

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-5802 Rev. 0
Page 5 of 5

Temperature reading :

Load Current Load Current Load Current


Time 30’ 60’ 120’ 240’ 30’ 60’ 120’ 240’ 30’ 60’ 120’ 240’
Interval
Temp

12.0 REMARKS :

a)
b)
c)

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-5803 Rev. 0
Page 1 of 1

TEST PROFORMA
ON LOAD TAP CHANGER

Project : Job No. :


Name of Work :
EPCC CONTRACTOR :

1.0 MANUFACTURER’S DATA

Type : Name of manufacturer :

Sl.no. :

Voltage : Current :

No. of steps : Step voltage :

Motor rating :

2.0 GENERAL CHECKS : (Put tick (9) if satisfactory otherwise give details).

Installation of OLTC :

OLTC earthing :

Installation of associated :
(Remote control panel & earthing)

3.0 TEST

3.1 I.R. value of Motor :


I.R. value of cables :

3.2 Scheme checking of OLTC and :


remote control panel in manual,
auto mode for correct operation

3.3 Tap change time between successive :


steps

3.4 Master/follower operation :

4.0 REMARKS 3.5 AVR setting =

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-5804 Rev. 0
Page 1 of 1

TEST PROFORMA
NEUTRAL GROUNDING RESISTOR

Project : Job No. :


Name of Work :
EPCC CONTRACTOR :

1.0 MANUFACTURER’S DATA

Type : Name of manufacturer :


Rated resistance :
Voltage : Current and time :

2.0 GENERAL CHECKS : (Put tick (9) if satisfactory, otherwise give details)

Installation of NGR :

General cleanliness :

Condition of bushings :

NGR Cubicle earthing :

Incoming and outgoing cable/earth :

3.0 TEST

Insulation resistance with respect to earth :

Megger used :

Ambient temperature :

Resistance value measured :

4.0 REMARKS

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-5805 Rev. 0
Page 1 of 6

TEST PROFORMA
MV SWITCH BOARD

Project : Job No. :


Name of Work :
EPCC CONTRACTOR :

1.0 SWITCHBOARD DETAILS TAG No.

Manufacturer : Type :
Bus rating : Fault level :
Section 1 fed from :
Section 2 fed from :

2.0 GENERAL CHECKS : (Put tick (9) if satisfactory, otherwise give details)

2.1 Installation

Switchboard leveling and grounting Vermin proffing and - )


Assembly of panels & cleaning

Busbar alignment & connections Unused cable entries covering


)

Bus trunking and tightness of nut Glands termination and spacing


and bolt connections of cables

Floor level Taping of exposed portion of


cable

Tagging & ferruling cables Tightness of cable connections

Cleaning and inspection of Control switches, keys and


insulators, bushings indication lamps

Earthing of panel and cables Danger Board

Nomenclature of various feeders Alignment of power and auxiliary


contacts

Switchfuse units and door interlocks

Circuit breaker closing & tripping Bus trunking and tightness of nut
mechanism and bolt connections

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-5805 Rev. 0
Page 2 of 6

Glands termination and spacing of Cleaning and inspection of


cables insulators, bushings

Control switches, keys and Earthing of panel and cables


indication lamps

Switch fuse units and door


interlocks

Safety interlocks of breaker

Fuses, bimetal relays, ranges


matching with load

Inspection of arc chutes Circuit breaker release/relays –


ranges matching with load

2.2 Circuit Checking :

CT & current circuits PT circuits

Shorting link provided for unused


terminals

Control circuit Alarm & signaling circuit

Meters & metering circuit Interlocks

2.3 Pre-Commissioning Checks

Control, protection & signaling circuit operation

Operation of manual/auto transfer circuit & interlocks

Insulation resistance of main bus and control circuit

Settings of relays & timers interlocks & inter tripping

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-5805 Rev. 0
Page 3 of 6

3.0 TEST RESULTS

3.1 Insulation, Resistance Measurement

Megger used: Amb. Temp:;

INSULATION RESISTANCE (I.R.) IN MEGA OHMS


RY YB BY RE YE BE RN YN BN

a. Busbars Section-1

Section-2

b. Busduct/ Section-1
Cables
(Incomer) Section-2

c. Outgoing feeders (Panel


no./Feeder Designation

3.2 Current Transformer

Panel No. :

Feeder Designation :

3.2.1

Manufacturer's Data Metering Protection

Ratio

VA rating

Accuracy Class

Serial nos.

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-5805 Rev. 0
Page 4 of 6

3.2.2 Tests & Checks: (Put tick (9) if satisfactory)

a. Polarity check (inconformity with the drawing)

b. Check CT earthing

c. Wiring correctness & continuity check


and tightness of connections

d. Test results:

Tests Metering Protection

i) Ratio measurement

ii) Insulation Resistance


(Measured)
Primary to Earth

Secondary to Earth

Primary to secondary

3.3 Potential Transformer Panel No.:

3.3.1 Manufacturer's Data

Ratio :

VA rating :

Class :

Type :

Serial Nos. :

3.3.2 Tests and Checks

a) Ratio Measurements

b) Polarity check :

c) Wiring correctness &


tightness of connections :

d) Check PT earthing :

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-5805 Rev. 0
Page 5 of 6

e) Insulation resistance
measured :
Py-G :
Sy-G :
Py-Sy :

f) Check fuses rating :

3.4 Relays/Releases

Component Test conducted and


S. Type and
NEMA Code code as per found satisfactory
No. Range
vendor drawing (Put '9' mark)
1.

2.

3.

3.4.2 Voltage, Auxiliary relays and timers

Test conducted and


S. Component code Type and
NEMA Code found satisfactory
No. as per vendor drg. Range
(Put '9' mark)
1.

2.

3.

Note : 1. Site precommissioning checks and tests shall be carried out in accordance with
manufacturer’s instructions manual and test readings are recorded.

4.0 COMMISSIONING

Clearance from all agencies Electrical Inspector’s clearance

Operation of breaker in test Tripping of breaker thro’


position protective relays

Meggar results of cable Meggar readings of equipment


being charged (busbar,
transformer or motor)

Test results of equipment to being Relays, Releases settings done


charged as required
(transformer/motor etc.

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-5805 Rev. 0
Page 6 of 6

5.0 OPERATIONAL CHECKS

:
Phasing of bus sections

Auto transfer circuit operation & time :

Manual transfer circuit operation for incomers :


and bus tie

6.0 REMARKS

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-5806 Rev. 0
Page 1 of 2

TEST PROFORMA
BATTERY SET AND CHARGER

Project : Job No. :


Name of Work :
EPCC CONTRACTOR :
Tag No.

1.0 Manufacture : Type of battery :

Equipment No. : No. of cells :

Name plate details :


(Charger)

2.0 GENERAL CHECKS : (Put tick (9) if satisfactory, otherwise give details)

CHARGER PANEL
BATTERY SET

Levelling and grouting Batteries and racks installation

Vermin proofing and blanking of Level of electrolyte in each cell


spare holes

Leakage of electrolyte in cell if


any

Earthing of panel Specific gravity

Control switches, meters, fuses, Number plates of cells and


indication lamps functioning O.K. connection links

All circuit cards are firmly seated in General cleaning & tightness of
their sockets all cables connection

Termination, glands & spacing of all Battery connection and Polarity


cables

Anticorrosive coating (Vaseline)


provided on terminals

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-5806 Rev. 0
Page 2 of 2

3.0 INSULATION RESISTANCE TEST (CABLES)

Megger used

Input Phase to phase : _________________


Power supply cable phase to earth : _________________
Battery cables Positive to negative : _________________
Positive to earth : _________________
Negative to earth : _________________

4.0 CIRCUIT CHECKING & WIRING VERIFICATION :

Float/boost chargers :

Rectifier and output circuit :

Alarm circuits, indication lights :

Interlocks

5.0 COMMISSIONING CHECKS

AC input voltage :
DC output voltage, variation :
Operating temperature in cabinet :
(No hot spot)
Battery voltage :
Battery trickle charge current :
Abnormal noise if any :

6.0 TEST READINGS OF CHARGE/DISCHARGE CYCLE OF BATTERY SET(TO BE


ATTACHED SEPARATELY)

7.0 REMARKS (if any)

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-5807 Rev. 0
Page 1 of 4

TEST PROFORMA
H.V. MOTOR

Project : Job No. :


Name of Work :
EPCC CONTRACTOR :
Tag No.

1.0 MANUFACTURER’S DATA

Motor Tag No. :


Make : S.No. : Enclosure : Ex(d)/Ex(e)/
Ex(n) Rotor/voltage :
RPM : Stator Current : Rotor current :
Power factor : Connections : Class of insulation :
Type of coupling : Type of mountg : Applicable code :
Duty : Method of starting :

2.0 GENERAL CHECKS : (Put tick (9) if satisfactory, otherwise give details)

2.1 Motor

Bushigs/insulators Lubrication & Greasing

Condition of bearings Ventilation/cooling system

Slip rings-brush gear and bedding External inspection

Polarity of windings External inspection


Provided/not provided

Bearing/windings temp. Indicator Bearing oil level indicator

Insulation resistance of windings

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-5807 Rev. 0
Page 2 of 4

2.2 Installation

Motor enclosure protection Levelling of motor


appropriate to area classification
of location

Alignment and coupling Earthing of motor and cable box

Tightness of foundation Bolts Pedestal insulation

Heaters and heater circuit

2.3 Supply Cables And Connections

Suitability of cables box for Cable laying, tagging


required size of cable
Bushings/insulators

Termination of armour Cable gland suitability and


tightness

Blanking of holes Condition of epoxy

Suitability of lugs Termination connection


tightness

Taping of exposed portion of Gaskets of terminal lease for


cable IP55 and for outdoor boxes
suitability

2.4 Push Button Station

FLP/industrial Meters & indication lamsp

Earthing Name plates

Cable laying, ferruling, Cleaning of contracts, switches,


termination push buttons

Operation of control ckt

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-5807 Rev. 0
Page 3 of 4

2.5 External Circuits/Equipments

Local Panel/control room


interface connections

Feeding Circuit breaker at Cooling fan/lubrication pump


sending end tested and found
ready for commissioning

Interlocks

3.0 INSULATION RESISTANCE : Temperature oC Megger range:

3.1 Power Cable & Motor :

Rotor
Stator Supply cable
Quantity Meggar Remarks
RE YE BE Wegs-E RE YE BE RY YB BR

R15

R60

3.2 Control Cable :

4.0 MEASUREMENT OF RESISTANCE :

Description Stator Rotor Remarks

Between Terminals U-V V-W W-U

Resistance

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-5807 Rev. 0
Page 4 of 4

5.0 COMMISSIONING

Clearance from other concerned agencies

Test results

Tripping of breaker on protections

Interlocks

Operation of control and signaling ckt.

5.1 operational checks (Repeated starts to be avoided)

Direction of Rotation Starting current kick

No load current of all phases

Full load current of all phases Bearing condition/ temperature after


4 hours run

Temperature of windings after 4 Vibrations


hrs. run

Any abnormal sound Cooling air flow direction

5.2 V-Characteristics of Motor (For Synchronous Motor)

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-5808 Rev. 0
Page 1 of 3

TEST PROFORMA
M.V. MOTOR

Project : Job No. :


Name of Work :
EPCC CONTRACTOR :

1.0 MANUFACTURER’S DATA

Make : S.No. : Type :


Voltage : Current : Speed :
Frame size : KW : Connections :
Sq.cage/slipring : Enclsoure : Mounting type :

2.0 GENERAL CHECKS : (Put tick (9) if satisfactory, give details)

2.1 Motor

Installation of motor Size of Power and Control


Cables same as given in
schedule

Free hand rotation Cable glanding and termination

Lubrication and greasing Weather proofing to terminal


box

Ventilation/cooling system Any visible external damage

Type of PB Station FLP/ Industrial Area classification of location


and Motor suitability

Ammeter range and CT ratio Motor suitability

Earthing of motor & PB station Tagging of cables

Connections Star/Delta Starting Star/Delta/Soft start

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-5808 Rev. 0
Page 2 of 3

B. STARTER MODULE

EPCC CONTRACTOR Feeder

Matching of fuse with motor rating

Matching of OLR with the motor rating

Matching of switch motor rating

Matching of EPCC CONTRACTOR with motor


rating

Cleanliness and tightness of all connections


(in the case of breaker feeder the thermal, magnetic release ranges (and/or other
protective devices), breaker rating etc. shall be checked with motor rating.

3.0 TESTING

3.1 Insulation Resistance Megger Range :

UE VE WE UV VW VW
Power cable :
Motor :
Control cable between line to
line:

3.2 Thermal Relay Checking

Relay range :
Tripping time at twice rated current of motor :

4.0 COMMISSIONING

Clearance from concerned agencies obtained :

Wiring schematic operation verified :

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-5808 Rev. 0
Page 3 of 3

4.1 Operational Checks : (Repeated start to be avoided)

‘At no load’

Starting current : Stating time :

Direction of rotation : Current of all phases :

Vibration : Voltage :

Any abnormal sound : Cooling fan operation :

Temperature rise after 4 hours run:

Load run R Phase Y Phase B Phase

Current of all phases :

Voltage :

Vibration : RY = YB = BR =

Bimetal relay set at : (after load run) No load run: Load run:

5.0 REMARKS

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-5809 Rev. 0
Page 1 of 4

TEST PROFORMA
D.G. SET

Project : Job No. :


Name of Work :
EPCC CONTRACTOR :

1.0 MANUFACTURER’S DATA

Engine Alternator

Rating :
Type Designation :
Fuel tank capacity :
Battery :
Charging system :
Excitation type :
Method of start : Air/battery

2.0 GENERAL

Installation, alignment & grouting :

General cleanliness :

Cable termination & tightness of all connection :

Earthng of DG set and control panels :


(Enclose Earthing Values taken)
(Enclose Relay Test Reports)

Generator neutral earthing grouting :

Fuelling connection & valves in correct position :

Fuel leaks, (if observed, shall set right) :

Lube oil circuit and oil level :

Radiator filled up with clean soft water :

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-5809 Rev. 0
Page 2 of 4

Instruments & control devices installation :

Battery sets, charger and control panel :

3.0 INSULATION RESISTANCE TEST

I. ALTERNATOR MEGGAR USED:


Winding to earth

R15
R60
K = R60
------
R15

II. FIELD WINDING

III. POWER CABLE RE RY RN


YE YB YN
BE BR BN
NE

4.0 WINDING RESISTANCE

Stator :

Rotor :

5.0 COMMISSIONING

Tripping of breaker on protections :

Operation of excitation, control & signaling ckt. :

Interlocks :

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-5809 Rev. 0
Page 3 of 4

Operation of all protective devices and setting :

Operation of AVR circuit :

Auto and manual transfer circuits :

Starting circuit functioning :

6.0 OPERATIONAL CHECKS

All instruments reading on engine operating panel :

Voltage frequency excitation current :

Bearing condition/temp. After 4 hrs. run :

Any abnormal sound :

Vibrations :

Fuel, lubrication and cooling circuits :

AMF Feature :

Paralleling of DG sets (if available) :

Radiator filled up with clean soft water :

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-5809 Rev. 0
Page 4 of 4

7.0 LOAD RUN

Voltage :

Current of all phases :

Excitation current :

Frequency :

Power factor :

Winding temperature rise :

Bearing condition :

8.0 REMARKS

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-5810 Rev. 0
Page 1 of 2

TEST PROFORMA
CABLE INSTALLATION

Project : Job No. :


Name of Work :
EPCC CONTRACTOR :

1.0 CABLE DETAILS

Make : Type : Cable tag :

From : To : Size :

Voltage : Length : No. of runs :

No. of straight through joints if any :

2.0 GENERAL CHECKS : (Put tick (9) if satisfactory, otherwise give details)

Laying :

Lugs (size, material and crimping) :

Earthing of armour/Screen :

Phasing/continuity

Cable support :

Cable gland (size & proper fixing) :

Cable entry cutout sealing :

Inspect cable protective measures :

Cable Gland plate Non magnetic/Aluminium : (Applicable for


Single core
cables)
Earthing of armour
(as per job spec) :

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-5810 Rev. 0
Page 2 of 2

3.0 HIGH POT TEST AND INSULATION RESULTS

3.1 Insulation, Resistance before the Hipot Test:

Megger used: Ambient Temp:

Description R to E Y to E B to E RY YB BR

R15

R60

K = R60
R15

3.2 High Pot Test ** :

Voltage applied value kV Leakage current in mA

30 sec. 1 minute 5 minutes

* Between Red and Earth

* Between Yellow and Earth

* Between Blue & Earth

** With other cores connected to earth

** Applicable for H.V. Cables and for those M.V. Cables where st-through
joints are made.

3.3 Insulation Resistance After The High Pot Test :

Megger used : Ambient temp. :

Description R to E Y to E B to E RY YB BR
R15

R60

K = R60
R15

4.0 REMARKS

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-5811 Rev. 0
Page 1 of 5

TEST PROFORMA
ELECTRICAL HEAT TRACING SYSTEM

Project : Job No. :


Name of Work :
EPCC CONTRACTOR :

PART-I : TRACER

1.0 TRACER DATA

Circuit no. :
LDP No./FDR No. :
Heater type :
Heater cable length :
Drawing no. :
Spiraling details, if any :
Area :
Line no. :
Maintenance temperature :
Heat loss/mt. :

2.0 GENERAL CHECKS

- Laying and covering of tracer complete length :

- Heater continuity :

- Power cable continuity :

- Tightness and cleanliness of connections at

a. FLP JB :

b. Thermostat :

- Number of splice connectors (if used) :

- Tag plates :

- Warning plates online :

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-5811 Rev. 0
Page 2 of 5

3.0 TEST RESULTS

Insulation in M Ω

Megger used :

Ambient temperature :

3.1 Ph. To Earth N1 to Earth Set Ph. No.1


(Load disconnected)
Circuit power cable

3.2 Line 1 to earth Line 2 to earth


Heater cable

4.0 COMMISSIONING CHECKS

- Heater cable input resistance value measured at pipe temp. :

- Control circuit functional checks and operation :

- Calibration check at the temperature controller set point :


o
- Thermostat set at : C

- Commissioning clearance obtained :

5.0 AFTER COMMISSIONING

5.1 Inrush current value : Duration :

5.2 At stready state conditions

Voltage V :
Load current I :
Pipe temperature :
Power output (V X I) : Watts
Calculated value from guaranteed curve (at the pipe temp.) : Watts

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-5811 Rev. 0
Page 3 of 5

Project : Job No. :


Name of Work :
EPCC CONTRACTOR :

PART-II : LOCAL DIST. PANEL

1.0 SWITCHBOARD DETAILS

Manufacturer :
Bus rating :
Section fed from :
Feeder rating (Amb.) :
No. of outgoing switchfuse :
feeders with contactor (used)
No. of outgoing spare feeders type : Indoor/outdoor
Fault level :
LDP no. :
Location :

2.0 GENERAL CHECKS : (Put tick if satisfactory, otherwise give details)

2.1

Assembly of panels and cleaning :

Vermin proof :

Bus bar arrangement and connection :

Unused cable holes covering :

Bus trunking and tightness of nuts and bolts connection :

Gland termination and spacing of cables floor level :

Tapping of exposed portion of cables :

Tagging and ferruling of cables :

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-5811 Rev. 0
Page 4 of 5

Tightness of cable connection :

Cleaning and inspection of insulators, bushings :

Control switches, keys and indication lamps :

Earthing of panel & cables :

Danger Board :

Nomenclature of various feeders :

Switchfuse units and door interlocks :

Alignment of power and auxiliary contacts :

Earth leakage circuit breaker :

Fuses :

Door covers all bolts are provided properly :

2.2 Circuit Checking

CT & current circuits :

Control circuits :

Alarm & signaling circuit :

Meters & metering circuit :

Interlocks :

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-5811 Rev. 0
Page 5 of 5

2.3 Pre-Commissioning Checks

Control, protection and Signaling circuit operation :

Insulation resistance of main bus & control circuit :

ELCB operation :

3.0 TEST RESULTS

Megger used : Amb. Temp. :

I.R. in M Ω

RE YE BE NE RY YB BR RN YN BN

a. Bus bars:
b. Incoming :
Cables

4.0 COMMISSIONING

Clearance from all agencies

Checking all outgoing switch fuse feeders kept off)


before energization of panel

5.0 AFTER COMMISSIONING

5.1 Voltage V :

5.2 Load current IR = IY = IB = I Neutral =

6.0 REMARKS

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-5812 Rev. 0
Page 1 of 3

TEST PROFORMA
LIGHTING INSTALLATION

Project : Job No. :


Name of Work :
EPCC CONTRACTOR :

1.0 MANUFACTURER’S DATA : MLDB/LIGHTING PANEL/POWER PANEL

Rated voltage :

Rated current :

Incomer rating :

Rating of branch circuit feeders :


and connected load

Panel tag no. :

2.0 GENERAL CHECKS : (Put tick (9) if satisfactory, otherwise give details)

2.1

Check
Panel Installation Mark
Remarks
Check general cleaning of panels and assembly

Inspect earthing of panel

Inspect glands termination and spacing of cables

Check tightness of all connections including cable


connection
Check circuit numbering and

Check dust vermin proofing

Check explosion prot3ction of field equipment in


hazardous area
LPs, PPs : FLP

Jbs : FLP/Ex(e)

Sockets : FLP

Gas Group : IIA IIB or IIC

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-5812 Rev. 0
Page 2 of 3

2.2

Check
Lighting Installation Mark
Remarks
Check the operation and setting of time
switches, photo-electric cells, EPCC
CONTRACTORs (wherever provided)

Check lamp fittings for neatness of


connections, suspension, weatherproofness

Spot check wall sockets, test the voltage of


each socket test the earthing continuity

Insert all lamps and measure illumination level

3.0 INSULATION RESISTANCE TEST

3.1 Panel

R Phase to Earth : Between R Y :

Y Phase to Earth : Between YB :

B Phase to Earth : Between B R :

Neutral to earth : R, Y, B to N :

3.2 Incoming Cable

RE : RY :

YE : YB :

BE : BR :

NE : R, Y, B to N :

3.3 OUTGOING CIRCUITS

Phase to Neutral : Size :

Phase to Earth : (Without lamps being in place)

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-5812 Rev. 0
Page 3 of 3

4.0 MEASURE LOAD CURRENT IN EACH PHASE ARE RECORD:

IR :

IY :

IB :

IN :

(If required adjust circuit loads for load balancing in each phase)

5.0 REMARKS

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-5813 Rev. 0
Page 1 of 2

TEST PROFORMA
EARTHING INSTALLATION

Project : Job No. :


Name of Work :
EPCC CONTRACTOR :

1.0 EARTH SYSTEM DATA

Type of electrode :
Total number of electrodes :
Main grid size :
Material :

2.0 GENERAL CHECKS Put tick if satisfactory otherwise give details.

Construction of electrodes as per PMC/OWNER standard :

Size of earth conductor for various equipment satisfactory as per layout :


drawing

Cleanliness and tightness of connector :

Inspect bolted and clamped connectors, at all earth plates. :

3.0 TESTS

3.1 Measured earth resistance of each electrode in ohms

Electrode No. Measured Resistance in ohms

1. ---------------------

2. ---------------------

3. ---------------------

4. ---------------------

5. ---------------------

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-5813 Rev. 0
Page 2 of 2

3.2 Measurement of Earth Grid Resistance


(With all electrodes connected to grid)

a. At system neutral earth :


b. At one point on each earthing system used to
earth electrical equipment enclosure :
c. At one point on each earthing system usedto earth
wiring system such as metal conduits etc. :
d. At one point on each fence enclosing electrical
equipment :

4.0 REMARKS

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-9001 Rev 0
Page 1 of 9

REQUIREMENTS

FOR

POSITIVE MATERIAL IDENTIFICATION


(PMI)

AT

CONSTRUCTION SITES

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-9001 Rev 0
Page 2 of 9

TABLE OF CONTENTS

_________________________________________________________________________
CLAUSE NO. TITLE PAGE NO.
_________________________________________________________________________

1.0 SCOPE 3

2.0 DEFINITIONS 3

3.0 SPECIFIC APPLICABILITY 3

4.0 REFERENCES 4

5.0 GENERAL REQUIREMENTS 4

6.0 EXTENT OF PMI 5

7.0 PMI IN WAREHOUSE 5

8.0 PMI OF PIPING AND HEATER COIL COMPONENTS 5

9.0 TESTING METHODOLOGY 6

10.0 CHARACTERISTIC ELEMENTS 6

11.0 CALIBRATION 6

12.0 SITE VERIFICATION OF ANALYZER 7

13.0 PERSONNEL QUALIFICATION 7

14.0 ACCEPTANCE CRITERIA 7

15.0 REJECTION CRITERIA 7

16.0 DOCUMENTATION 8

ATTACHMENT (REPORTING FORMAT)

I. FORMAT FOR PMI TEST REPORT - 6-82-0002-F1 (1 SHEET)

_______________________________________________________________________

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-9001 Rev 0
Page 3 of 9

1.0 SCOPE

1.1 This specification applies to metallic alloy materials used in piping, heater coils, storage
tanks, vessels etc. at construction sites. Positive Material Identification (PMI) is to be
carried out on owner supplied material as well on materials purchased by the EPCC
contractor.

1.2 Any deviation from this specification must be approved by Owner/PMC in the prescribed
format.

1.3 Carbon steels are excluded from the scope of this specification.

2.0 DEFINITIONS

2.1 Positive Material Identification (PMI)

The term Positive Material Identification (PMI) refers to determination/verification of alloy


type or its composition using portable or mobile spectrometer/alloy analyzer.

Chemical spot checking, resistivity testing, eddy current testing, electromagnetic alloy
sorting, thermoelectric testing shall not be considered as PMI for the purpose of this
specification.

3.0 SPECIFIC APPLICABILITY

3.1 The following items require PMI unless specifically exempted through a Waiver/Deviation
permit by Owner/PMC.

3.1.1 All pressure containing piping components including, thermowells instrument manifolds,
RTJ gaskets, fasteners etc..

3.1.2 Tubular products used in the fabrication of heaters.

3.1.3 Pressure - containing instrument housings (e.g. gauge glass housings, orifice meter tubes).

3.1.4 Internal metallic linings/cladding, and weld overlay, done at site, used for protection against
corrosive environments.

3.1.5 Tubing

3.1.6 Stud, bolts and nuts

3.1.7 Plates

3.1.8 All pressure containing welds.

3.1.9 Any other components or materials specifically designated for PMI on the purchase
order/contract.

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-9001 Rev 0
Page 4 of 9

3.2 Exclusions

The following items are exempted unless specifically designated for PMI in the purchase
order/contract.

3.2.1 Gaskets (spiral wound or carbon steel only).

3.2.2 Internal instrument parts.

3.2.3 Internal machinery parts.

3.2.4 Internal non pressure - containing baffles, trays, tray clips, supports, pall-rings, support
rings, etc.

3.2.5 Electrical components.

3.2.6 Non pressure - containing welds, including seal welds, piping supports welds, structural
parts.

3.2.7 Internal valve components.

3.2.8 Compression-type ferrules and fittings for use with 3/4 inch (19mm) outside diameter and
smaller tubing.

4.0 REFERENCES

American Society of Mechanical Engineers (ASME) BPV Code Section-II Part A,B,C and D

ASME B 31.3

American Society for Testing and Materials (ASTM): As applicable

Material Verification Program for New and Existing Alloy Piping Systems : API RP 578

Any other material specification referenced by the Purchase Order/Contract.

5.0 GENERAL REQUIREMENTS

5.1 The test methods outlined in this specification are intended to identify the nominal
composition of alloy materials. These test methods are not intended to establish the
conformance of a material to a particular alloy specification.

5.2 PMI shall not be considered as a substitute for required mill test reports listing chemical
composition. In addition, mill test reports shall not be considered as confirming alloy
verification.

5.3 The PMI activity shall be included in the overall quality plan and Inspection & Test Plan for
warehouse and fabrication/erection. The EPCC contractor shall submit to PMC/Owner, a
procedure for PMI to comply with the requirements of this specification. Approval of PMI
procedure shall be obtained from Owner/PMC prior to commencement of
fabrication/erection as the case may be.

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-9001 Rev 0
Page 5 of 9

5.4 A copy of daily PMI records shall be submitted to owner/PMC .

5.5 After installation, but prior to hydrostatic testing/painting/insulation, the EPCC contractor
shall examine all components requiring PMI for proper compliance to this specification. A
record of this final check, as specified below, shall be submitted to PMC/Owner and made
part of the permanent inspection records.

5.5.1 Owner supplied material :

Records signed by EPCC contractor and duly certified by PMC/Owner.

5.5.2 EPCC contractor supplied material :

Records signed by EPCC contractor and certified by an approved third party inspection
agency.

5.6 After acceptance, all components shall be marked with a suitable paint mark. Markings
must be permanent and readily visible. These markings are in addition to markings
required by other codes/specifications/Technical Notes.

5.7 Controls shall be established to keep the non conforming items identified till proper
resolution of non conformity.

5.8 PMC/Owner shall have the right to witness the performance of any PMI test.

6.0 EXTENT OF PMI

PMI shall be done on each component (100 percent PMI inspection) including welds,
unless specifically exempted by Owner/PMC.

However, one stud & nut assembly for each flange joint shall require PMI. All studs & nuts
in a piping hydro test loop shall require PMI, if any non conformity is detected.

7.0 PMI IN WAREHOUSE

PMI testing to be performed as part of the receiving inspection at warehouse.

The extent of PMI shall be as specified in 6.0. However, if PMI testing has been carried out
at vendor/manufacturer’s shop and relevant certified records and correlation with incoming
material is available, PMI testing at warehouse need not be done.

PMI testing done as a part of receiving Inspection shall not be regarded as an alternative to
PMI testing of the installed system.

8.0 PMI OF PIPING AND HEATER COIL COMPONENTS

PMI testing (irrespective of PMI done at earlier stages) shall be carried out when piping
loops/heater coils have been cleared for hydrostatic testing by PMC/Owner. Hydrostatic
Testing shall be carried out only when non conforming components have been

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-9001 Rev 0
Page 6 of 9

replaced with conforming components and subsequent Non Destructive Testing, Post Weld
Heat-Treatment, Hardness checking etc., as required by specifications have been
completed. PMI records shall form a part of piping/heater inspection records. EPCC
contractor shall demonstrate to PMC that each & every component of the piping system
and heater coils has been subjected to PMI by providing line wise records of PMI.

9.0 TESTING METHODOLOGY

In general, portable X-Ray Fluorescence (XRF) type alloy analyzers such as Oxford
Instruments’ X-Met 3000 TX, X-Met 2000 Metal Master, NITON’s XLt or NITON II or
similar analyzer shall be used for carrying out PMI. Identification of characteristic alloying
elements (see 10.0 for examples), which distinguishes the material from other materials,
will be sufficient. However, in case of doubt, Owner/PMC may insist on complete analysis.

The surface of the component to be subjected to PMI shall be free from grease, oil, paint or
oxides. Testing shall be done after proper surface cleaning and other requirements outlined
by the manufacturer of the portable alloy analyzer. Modification, if any, of these procedures
must be approved by Owner/PMC.

10.0 CHARACTERISTIC ELEMENTS

Material Specification Characteristic Elements

ASTM A 335 Gr P11


Gr P5
Cr, Mo
Gr P22
Gr P9

ASTM A 312 Type 304 Cr, Ni


Type 316 Cr, Ni, Mo
Type 321 Cr, Ni, Ti
Type 347 Cr. Ni, Columbium, Tantalum

Characteristic elements for materials not listed above shall be proposed by the EPCC
contractor for approval of the owner/PMC

11.0 CALIBRATION

11.1 Instruments used for PMI shall have the sensitivity to detect the alloying elements in the
specified ranges. Instruments or methods used for examination shall be of the type that will
provide quantitative, recordable, elemental composition results for positive identification of
the alloy elements present.

11.2 Each alloy analyzer shall be calibrated using known alloy standards for intended materials
to be checked by PMI. A calibration certification from the Manufacturer or his authorized
agency shall be submitted to PMC/Owner for records. As such, calibration at site is not
envisaged.

11.3 PMC/Owner shall review the procedure and qualification and witness sample alloy
verification tests to confirm that the procedures, equipment and personnel are capable of
providing consistent and accurate results.

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-9001 Rev 0
Page 7 of 9

12.0 SITE VERIFICATION OF ANALYZER

Verification using Standard samples supplied by institutes such as ASM (American Society
of Metals) for the intended materials type and grade shall be performed each day before
using the analyzer. Such a verification shall be done again if PMI test is to be performed
on different grade or type of material.

13.0 PERSONNEL QUALIFICATION

The persons performing the PMI test should be knowledgeable about properties of
material, all aspects of operation of PMI equipment including the method of testing.
Qualification/experience documents of the person performing the PMI test including his
training and experience shall be submitted to PMC/owner for review and approval.

14.0 ACCEPTANCE CRITERIA

14.1 Base Metal

PMI test results showing presence of characteristic elements upto 10% less than the
minimum specified value in the material specification or upto 10% more than the maximum
specified value in the material specification shall be acceptable.

14.2 Deposited Weld Metal

For deposited weld metal between base metals of the same specification using matching
consumables, the recorded presence of characteristic elements upto 12.5% less than the
minimum specified value in the welding consumables specification and upto 12.5% more
than the maximum specified value in the welding consumable specification shall be
acceptable.

15.0 REJECTION CRITERIA

15.1 If the PMI test results fall outside the acceptable range as given in 14.0 above, the EPCC
contractor shall obtain a quantitative check analysis performed by a laboratory acceptable
to PMC/owner for a complete chemical analysis. Results of this analysis shall be submitted
to PMC/Owner, with EPCC contractor’s recommendation, for final decision.

Decision of PMC/Owner shall be final in this regard.

15.2 If any material component or weld is found unacceptable all other represented materials (
e.g. in case of fasteners, supports ) or weld shall be considered suspect. The EPCC
contractor has the following options.

15.2.1 Scrapping all those represented materials and components and replacing with new
components or welds.

15.2.2 Performing 100% examination of the remainder of the represented materials/ components
and replacing each item that fails the PMI check..

15.2.3 If the performance of any verification activity is unacceptable to PMC/Owner or if any


material has been incorrectly identified, all further tests shall be subject to PMC/Owner
approval until the problem is corrected.

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-9001 Rev 0
Page 8 of 9

16.0 DOCUMENTATION

16.1 Print out from alloy analyzer, in original, duly certified by the EPCC contractor.

16.2 PMI report as per format No. PMI-F1

16.3 Basis and action for resolving and documenting PMI non conformances .

16.4 EPCC contractor shall demonstrate to PMC/owner that all components requiring PMI have
been subjected to PMI testing and accepted.

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved


EPCC-05 : Rehabilitation and Adaptation
Process Plants, Utilities, Offsites and Pipelines
N A F T E C .S P A
Section: VI – 3 Construction
6648-00-19-43-9001 Rev 0
Page 9 of 9

(Format No. PMI-F1 Rev 0)

REPORT NO: ______

POSITIVE MATERIAL IDENTIFICATION TEST REPORT

EPCC contractor _____________________ Date of PMI_____________________

Project __________________________ Inspection Agency ________________

Location ________________________ PMI Equipment model ____________

Line No. /ISO Drg. No_____________ Make & Serial No. _______________
/Heater No./Drawing No

Result
Sr. Material Material
Part Identification (Accepted/Rejected
No. As per Drg./spec as per PMI
/Retest)

___________________ ________________ ______________


(EPCC CONTRACTOR) (PMI AGENCY) (PMC/OWNER )

EPCC05_VI.3_Constn._QA/QC_Rev.0 Copyrights EIL – All rights reserved

Você também pode gostar