Discipline: Construction
INDEX
____________________________________________________________________________
Clause Title Sheet No.
N0.
____________________________________________________________________________
1.0 SCOPE 4
2.0 RESPONSIBILITY 4
3.0 METHODOLOGY
DOCUMENT NO.
Abbreviations:
1.0 SCOPE
2.0 RESPONSIBILITY
The EPCC CONTRACTOR shall comply with all statutory rules & regulations in force
during execution of work and interface with such authorities as required (refer Section-
XVIII for details).
3.0 METHODOLOGY
The management of construction quality control is divided into the following categories:-
The EPCC CONTRACTOR shall develop list(s) defining the items to be procured along
with proposed Vendors for approval of the Owner/PMC. The list shall comprise of all
items except vessels, equipments, pumps, electrical/ instrumentation panels etc. which
may be available directly ready for installation or requiring small fabrication as per
requirement. The vendor list shall be in line with the contract document. In case, no
vendor list exists in the contract for a particular item, the EPCC CONTRACTOR shall
propose a list of Vendors to Owner/PMC. EPCC CONTRACTOR has to satisfy himself
with the capability of the vendor to deliver the product in time with quality before
proposing him as a prospective vendor. EPCC CONTRACTOR shall submit the QA/QC
plans for all major items and carry out their procurement in line with the approved plans.
The EPCC CONTRACTOR can either provide his own adequate qualified staff for
inspection or employ a separate third-party inspection agency with prior approval to
carry out these functions. Involvement of OWNER/ PMC in the quality control plan, if
required, shall be defined during approval of the same.
(i) The QA plans for execution shall be developed by the EPCC CONTRACTOR.
OWNER/ PMC’s approval for the same shall be taken well before start of the
work. The final Inspection & Test Plans (ITPs) and formats, based on the
indicative ITPs and Formats enclosed in document Nos. 6648-00-19-43-2000
and 6648- 00- 19- 43- 5000 respectively, shall be developed by the EPCC
The indicative ITPs and Formats enclosed in the feed package are for guidance
to the EPCC CONTRACTOR and may not cover some of the activities to be
performed during execution of works under the scope of this contract. The
EPCC CONTRACTOR shall develop Inspection & Test Plans and Formats for all
such activities also and submit the same to OWNER/ PMC for approval, before
actually undertaking such activities.
(iv) Storage
All the materials procured shall be stored/stacked as per the standard norms and
as recommended in various clauses of relevant codes and contract document.
The storage of material shall be such as to avoid damage to life/properties
(physical and chemical) of the materials. The storage shall not cause
deterioration, rusting, mix-up etc. and hamper the other related works in any way.
EPCC CONTRACTOR shall submit his detailed warehouse plan for OWNER/
PMC approval to manage the above in open/covered areas.
In general, the materials shall be kept systematically in order of their class, batch
number and identification number, so that they are accessible for the inspection
by OWNER/ PMC whenever required and to avoid the mix up in those materials.
(v) Use
The materials shall be stacked in such a way that the lot, which is procured first,
will be consumed first. For materials which are having specific expiry date/ shelf
life shall not be used beyond that date and shall be removed from site. Wherever
there is any doubt about the change in properties of the materials, such materials
shall be sent to reputed approved laboratory for testing and acceptance.
(vi) Inspection
The EPCC CONTRACTOR shall be responsible for carrying out inspection of the
materials brought at site and conducting tests/ checks (at site or in approved
laboratories) at predefined frequencies as per contract. It is the responsibility of
the EPCC CONTRACTOR to ensure that the materials used at site shall conform
to relevant codes/ standards and Manufacturer Test Certificates are available for
correlation as and when required. The EPCC CONTRACTOR shall maintain the
records of all materials brought at site and tests conducted on them.
During the execution of the works, EPCC CONTRACTOR shall carry out periodical
Quality Audits at least quarterly in all areas of work. These audits will be conducted by a
team of specialists in the respective areas. The auditors shall not be directly involved in
the jobs being audited.
The EPCC CONTRACTOR shall prepare an Audit Plan and Procedure and submit the
same to OWNER/ PMC for approval.
A copy of the Audit Report containing the findings of the Audit team will be submitted to
OWNER/ PMC. After completion of rectification/modifications/corrective actions on the
issues indicated in Audit Report, Compliance Report shall be submitted by the EPCC
CONTRACTOR to OWNER/ PMC for review.
Over and above the EPCC Contractor’s Internal QA/QC Audits outlined above, OWNER/
PMC shall also reserve the right to conduct QA/QC audits at the frequency decided by
them.. EPCC CONTRACTOR shall participate and provide full support to the Audit
Team and furnish all documents/reports/records as desired by the Audit Team. The
EPCC CONTRACTOR shall take all actions required to comply with the findings of the
Audit Report and issue regular Compliance Reports for the same to OWNER/ PMC till all
the findings of the Audit Report are fully complied.
In case major Non conformities are observed during execution of the works OWNER/
PMC reserve the right to appoint an independent person/Third Party Agency to conduct
QA/QC Systems Audit for full/part of the facilities being executed by the EPCC
CONTRACTOR. This audit will be in addition to the audits described above
and may be carried out intermittently/continuously for all or part of the facilities being
executed by the EPCC CONTRACTOR. EPCC CONTRACTOR shall bear the total cost
of such audits and shall participate & provide full support to the Audit Team and ensure
compliance of the audit observations.
e) Final verification report including any test checks done for compliance
INDICATIVE
FOR
CONSTRUCTION WORKS
INDEX
GENERAL NOTE
The enclosed indicative ITPs shall be used as a basis for developing ITPs for specific jobs/
activities to be executed by the EPCC CONTRACTOR. EPCC CONTRACTOR shall obtain
OWNER/PMC’s approval on all such finalized ITPs.
The provisions indicated for stagewise inspection by OWNER/ PMC are the minimum and the
OWNER/ PMC may decide to increase Hold Points/ Witness Points. Activities for which ITP's
are not given, EPCC CONTRACTOR to develop and get the same approved by OWNER/ PMC
well before start of the work.
EPCC CONTRACTOR to submit required reporting formats and job procedures for each activity
listed in ITP's and submit to OWNER/ PMC for approval, well before commencement of the
activity. If the EPCC CONTRACTOR has to deviate from the given ITP for a valid reason, he
shall obtain prior written approval of OWNER/ PMC. EPCC CONTRACTOR to carry out 100%
examination of all activities.
LEGEND
HP : Hold Point ;
W : Witness Point ;
INDICATIVE
INSPECTION & TEST PLAN (ITP)
MECHANICAL WORKS
INDEX
MECHANICAL WORKS
2. Tie-In 6648-00-19-43-2111 0
A. PRIOR TO FABRICATION
1. Incoming Material
a) Documents (MRIR etc.): Review & acceptance WC HP
b) Physical verification WC W
3. WPS/PQR
a) Review of proposed procedure WC HP
b) Welding of Test Coupens and subsequent testing
i) Carbon Steel, Stainless Steel (type 304) WC Rw
ii) All other materials WC W
For NACE filler metals, corrosion tests like HIC, SSCC, etc. to be carried out for every batch. However, HIC/SSCC tests
done earlier & duly witnessed by a reputed third party, will be acceptable.
Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S
6. Baking of Electrodes WC S
11. PT/MT WC S
Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S
C PROOF TESTING
(See enclosed checklist in Annex-1)
1. Procedure Review WC HP
Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S
Note : Pre-commissioning activities such as chemical cleaning, card board blasting, system testing
are not covered by these ITP's. The EPCC Contractor shall develop ITP's for such activities
and obtain Owner/ PMC/ Licensor's approval.
Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S
ANNEX – 1
Checklist for Mechanical Clearance - A/G Piping
Line No (Isometric No.) Rev. GAD No. Rev. P&ID No. Rev.
Remarks
OWNER/ PMC
Sign :
Date :
Name : Designation :
ANNEX – 2
Piping Hydro Test Release Record – A/G Piping
Sign : Sign:
Date : Date:
Name : Designation Name: Designation:
ANNEX - 3
Punchlist
Description : _________________________________________________________________
____________________________________________________________________________
Priority: 1. Needed for pressure test 2. Needed for commissioning 3. Needed for start up 4.
Needed for plant acceptance
EPCC Contractor : OWNER/ PMC :
Sign : Sign :
Date : Date :
Name : Designation : Name : Designation :
1 Bevel/Thickness WC HP
2. Fit up WC HP
3 Root run welding WC HP
4 DP check of root run WC HP
5. Final Welding WC HP
6. PWHT (if applicable) WC HP
7. DP check of final welding WC HP
8 Radiography check WC HP
9. Hydrostatic test (if applicable) WC HP
Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S
A. Before Installation
2. Material inspection
a) Review of Manufacturer’s Test Certificates/ WC HP
TPI Inspection Release Note
b) Positive Material Identification, if required in Field WC HP
B. After Installation
Check for
2. UDFC WC S
3. Tightness of bolts WC S
Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S
Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S
A. PRIOR TO FABRICATION
1. Incoming Material:
a) Documents: Review & acceptance WC HP
b) Physical verification WC W
3. WPS/PQR
a) Review of proposed Procedure WC HP
B. FABRICATION
STEEL WORK
2. Dimensional check WC S
3. Fit-up check WC S
Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S
4. Radiography, as applicable
a) RT Marking (for random/spot radiography only) WC S
b) RT Interpretation WC S
COIL WORK
6. Baking of Electrodes WC S
11. PT/MT WC W
Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S
C. ERECTION
7. Cutout
a) Marking for burners, sight doors, soot blowers WC S
b) Marking for balance cut outs WC S
c) Cutting WC S
Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S
Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S
A. RADIANT SECTION
1. Radiant shell
Fixing of Ceramic fibre blanket
i) Material inspection
- Manufacturing test certificates WC Rw
- Testing, if any WC W
ii) Clearance for hot work WC W
iii) Marking of studs WC S
iv) Welding of studs with approved WPS&PQR WC S
v) Surface cleaning WC S
vi) Check for individual layers of ceramic WC W
fibre blankets and SS foils
vii) Check for overlap of ceramic blanket WC S
viii) Fixing of speed fix washer and cup lock WC S
ix) Cleaning and final inspection WC HP
2. Arch Plate
i) Material inspection
- Manufacturing test certificates WC Rw
- Testing, if any WC W
ii) Clearance for hot work WC W
iii) Marking of studs/anchors WC S
iv) Welding of studs/anchors with approved WPS & PQR WC S
v) Surface cleaning WC S
vi) Check for individual layers of Ceramic WC S
Fibre Blankets (CFB) modules and SS foils
vii) Check for overlap of CFB and modules WC S
viii) Cleaning and final inspection WC HP
3. Floor Plate
Laying of castable/fire bricks
i) Material inspection
- Manufacturing test certificates WC Rw
- Testing, if any WC W
Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S
B. CONVECTION SECTION
1) Convection walls
Laying of castable
i) Material inspection
- Manufacturing test certificates WC Rw
- Testing, if any WC W
ii) Clearance for hot work WC W
iii) Marking of studs/anchors WC S
iv) Welding of studs/anchors with WC S
approved WPS & PQR
v) Surface cleaning WC W
vi) Check for undulations on wall WC S
vii) Check for castable mixing WC W
viii) Check for proper compaction WC S
ix) Check for thickness of castable WC S
x) Curing WC S
xi) Cleaning after laying of castable WC S
xii) Check for cracks and repair WC W
xiii) Cleaning and final inspection WC HP
2) End tubesheets
Laying of castable
i) Material inspection
- Manufacturing test certificates WC Rw
- Testing, if any WC W
ii) Clearance for hot work WC W
Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S
3) Breeching Plate
Laying of castable
i) Material inspection
- Manufacturing test certificates WC Rw
- Testing, if any WC W
ii) Clearance for hot work WC W
iii) Marking of studs/anchors WC S
iv) Welding of studs/anchors with WC S
approved WPR & PQR
v) Surface cleaning WC S
vi) Check for undulations on plate WC S
vii) Check for castable mixing WC W
viii) Check for proper compaction WC S
ix) Check for thickness of castable WC S
x) Curing WC S
xi) Cleaning after laying of castable WC S
xii) Check for cracks and repair WC W
xiii) Cleaning and final inspection WC HP
4) Header box
Laying of castable
i) Material inspection
- Manufacturing test certificates WC Rw
- Testing, if any WC W
ii) Clearance for hot work WC W
iii) Marking of studs/anchors WC S
iv) Welding of studs/anchors with WC S
approved WPR & PQR
v) Surface cleaning WC S
vi) Check for undulations on box WC S
Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S
C STACK
Laying of castable
i) Material inspection
- Manufacturing test certificates WC Rw
- Testing, if any WC W
ii) Clearance for hot work WC W
iii) Marking of studs/anchors WC S
iv) Welding of studs/anchors with WC S
approved WPR & PQR
v) Surface cleaning WC S
vi) Check for undulations on stack shell WC S
vii) Check for castable mixing WC W
viii) Check for proper compaction WC S
ix) Check for thickness of castable WC S
x) Curing WC S
xi) Cleaning after laying of castable WC S
xii) Check for cracks and repair WC W
xii) Cleaning and final inspection WC HP
D
HOT AIR DUCT
i) Material inspection
- Manufacturing test certificates WC Rw
- Testing, if any WC W
ii) Clearance for insulation WC W
iii) External Surface cleaning WC S
iv) Provide spacer rings/anchors WC S
v) Check for thickness of the mineral wool insulation WC S
Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S
Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S
1. BEFORE ERECTION
a. Review of foundation acceptance report WC Rw
b. Incoming material
i) Documents : Review & Acceptance WC Rw
ii) Physical verification, if required WC W
3. SAFETY TEST
Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S
4. DURING ERECTION
a. Orientation to be checked WC S
5. AFTER ERECTION
e. Grouting
i) Acceptance of Specified grouting materials WC HP
ii) Placement of grouting WC S
iii) Curing of grout. WC S
Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S
6. PACKED EQUIPMENTS
1. Before Installation
2. During Installation
Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S
b. Material Supply
- Owner's supply including templates, if any WC Rw
- EPCC Contractor's supply & check testing, if any WC HP
-
c. Readiness for erection
i. Level of foundation (shims/packing with markings to WC S
be prepared & kept ready)
ii. Marking/Centre line of foundation & equipment WC S
iii. No./dia./length of anchor bolts, depth WC S
of pockets, verticality of pockets
iv. Chipping, roughing & cleaning of pockets/top of
foundation
A. Normal equipments WC S
B. Critical equipments WC HP
v. Acceptance of grouting materials as per WC HP
specifications/ Manufacturer’s recommendations
2. LIFTING TACKLES
Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S
6. DURING ERECTION
Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S
a. Curing of grout WC S
Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S
A. PRIOR TO FABRICATION
1. Review Acceptance Report of the tanks foundation WC HP
2. Incoming Material
- Documents Review WC HP
- Physical verification WC W
4. WPS/PQR
a) Review of proposed procedure WC HP
b) Testing
i) Carbon Steel WC Rw
ii) Alloy Steel/Stainless Steel WC HP
c) Approval of Final WPS/PQR WC HP
B. FABRICATION/ERECTION BOTTOM
(Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S)
3. Sequence of welding WC S
5. Baking of electrodes WC S
6. Inter-pass cleaning WC S
SHELL
Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S
13. Shell to bottom I/S welding root run visual/Oil chalk test WC W
FIXED ROOF
Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S
FLOATING ROOF
4. Buoys fabrications WC S
9. Initial – lift WC S
Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S
C. TESTING
5. Hammer test WC HP
7. Vacuum test WC HP
NOTE : 1) For cleaning & painting, please refer ITP No. 6648-00-19-43-2501
2) For Insulation, please refer ITP No. 6648-00-19-43-2505
Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S
INDICATIVE
FOR
GENERAL WORKS
INDEX
GENERAL WORKS
1. Painting 6648-00-19-43-2501 0
2. Insulation 6648-00-19-43-2505 0
A. BEFORE FABRICATION
7. Wet film thickness and over coating interval for each coat of WC S
paint during application
Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S
B. AFTER INSTALLATION
3. Confirm completion of
Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S
e. Thickness of insulation WC S
i. Inspection windows WC S
k. Final finish WC W
b. Vapour barrier WC S
c. Vapour sealant WC S
d. Insul coat WC S
Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S
DURING LINING
Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S
xii. Pointing WC S
xiii. Curing WC S
Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S
DURING LINING
Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S
INDICATIVE
INSTRUMENTATION WORKS
INDEX
INSTRUMENTATION WORKS
FIELD INSTRUMENTATION WORKS
Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S
5. NDT WC W
7. Shop testing WC W
Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S
Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S
7. Painting of support WC S
Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S
Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S
8. Painting WC S
Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S
Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S
8. Ferrule punching WC S
13. Testing WC HP
Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S
Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S
4. Tightening of fasteners WC S
7. Earthing of JB / LCP WC S
Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S
6. Tightening at joints WC S
Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S
Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S
Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S
9. Loop acceptance WC HP
Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S
A. PRIOR TO FABRICATION
1. Incoming Material
a) Documents (MRIR etc.): Review & acceptance WC HP
b) Physical verification WC W
3. WPS/PQR
a) Review of proposed procedure WC HP
b) Welding of Test Coupens and subsequent testing
i) Carbon Steel, Stainless Steel WC Rw
ii) Alloy Steel WC W
iii) All other Materials including NACE CS and CS for H2 WC W
Service
c) Approval of final WPS/PQR. WC HP
For NACE filler metals, corrosion tests like HIC, SSCC, etc. to be carried out for every batch. However, HIC/SSCC tests
done earlier & duly witnessed by a reputed third party, will be acceptable.
Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S
6. Baking of Electrodes WC S
11. PT/MT WC S
Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S
C PROOF TESTING
(See enclosed checklist in Annex-1)
1. Procedure Review WC HP
Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S
Note : Pre-commissioning activities such as chemical cleaning, card board blasting, system testing
are not covered by these ITP's. The EPCC Contractor shall develop ITP's for such activities
and obtain Owner/ PMC/ Licensor's approval.
Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S
ANNEX – 1
Checklist for Mechanical Clearance - IMPULSE Piping
Line No (Isometric No.) Rev. GAD No. Rev. P&ID No. Rev.
9. Orifice Flanges :
Check for Tag No., tapping orientation, tap valve, jack
screw, straight run length of upstream & downstream
13. Earthings :
a) Check for location
b) Check for dimension of lug welding
Remarks
OWNER/ PMC
Sign :
Date :
Name : Designation :
ANNEX – 2
Piping Hydro Test Release Record – IMPULSE Piping
Sign : Sign:
Date : Date:
Name : Designation Name: Designation:
ANNEX - 3
Punchlist
Description : _________________________________________________________________
____________________________________________________________________________
Priority: 1. Needed for pressure test 2. Needed for commissioning 3. Needed for start up 4.
Needed for plant acceptance
EPCC Contractor : OWNER/ PMC :
Sign : Sign :
Date : Date :
Name : Designation : Name : Designation :
Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S
Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S
9. Ferruling of cables WC S
Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S
Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S
6. System acceptance WC HP
Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S
INDICATIVE
INSPECTION & TEST PLAN (ITP)
CIVIL, STRUCTURAL AND
ARCHITECTURAL WORKS
INDEX
STRUCTURAL WORKS
1. Plain Cement Concrete 6648-00-19-43-2741 0
2. RCC (Sub-Structure) 6648-00-19-43-2742 0
3. RCC (Super Structure) 6648-00-19-43-2743 0
4. Flooring/ Pavement 6648-00-19-43-2745 0
5. Brick Work 6648-00-19-43-2746 0
6. Structural Works 6648-00-19-43-2747 0
ARCHITECTURAL WORKS
1. Plastering 6648-00-19-43-2772 0
2. Roofing Accessories 6648-00-19-43-2779 0
Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S
SITE GRADING
Sl. EPCC Owner/
Activity
No. Contractor PMC
Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S
EXCAVATION
2. Layout checking WC S
3. Taking initial levels WC S
4. Slopes of excavation, benching, overburden, shoring & WC S
strutting (in case of deep excavation)
5. Check for sub-soil water, dewatering requirements as per WC S
specifications.
6. Bottom level of excavation and compaction WC S
7. Stacking of different type of soils separately WC S
8. List of obstacles encountered (cables, pipes, conduits, etc) WC S
9. Barricading of excavated pits for safety & protection from WC S
rain
Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S
BACKFILLING
Sl. EPCC Owner/
Activity
No. Contractor PMC
Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S
1. Checking of material WC W
2. Adequate slope, benching in excavation for safety purposes WC S
(if required)
9. Backfilling in layers WC S
10. Check for MS rungs in proper position, inlet/outlet pipe WC S
levels in manholes
Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S
WBM ROADS
Sl. EPCC Owner/
Activity
No. Contractor PMC
Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S
Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S
TANK PADS
Sl. EPCC Owner/
Activity
No. Contractor PMC
Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S
MICRO GRADING
7. Final inspection WC HP
Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S
A. PRIOR TO FABRICATION
3. WPS/PQR
i) Review of proposed Procedure WC HP
ii) Testing WC W/Rw
iii) Approval of Final WPS WC HP
7. Joint numbering WC Rw
Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S
6. Baking of Electrodes WC S
9. PT/MT WC S
1. Procedure Review WC HP
Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S
D. LAYING
7. Application of primer WC S
Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S
E. SYSTEM COMPLETION
1. Tie in joints * *
3. System testing WC HP
Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S
ANNEXURE – 1
1a Mechanical clearance
- Conformity with drawing WC Rw
- Material as per Specification WC Rw
4. Laying
- Trench leveling WC Rw
- Lowering & checking for damages in WC Rw
wrapping & coating, their repair,
Holiday testing, etc.
- Backfilling WC Rw
Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S
3. Mix proportion WC S
7. Curing WC S
Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S
Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S
5. Design of mix WC Rw
15. Curing WC S
Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S
FLOORING/PAVEMENT
Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S
BRICK MASONRY
Sl. EPCC Owner/
Activity
No. Contractor PMC
2. Cleaning of surface WC S
3. Wetting of bricks WC S
12. Curing WC S
Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S
PLASTERING
Sl. EPCC Owner/
Activity
No. Contractor PMC
8 Curing WC S
Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S
ROOFING ACCESSORIES
Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S
INDICATIVE
ELECTRICAL WORKS
INDEX
S.NO
DESCRIPTION DOCUMENT NO. REV.
Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S
11. Ensure cable connection at the cable and box their colour WC W
coding & tightness (if required, use of spring and flat washers on
the appropriate faces to be confirmed) and cleanliness of
lapping surfaces. For multiple cable connection, check for
correctness of R.R., YY, BB grouping
12. If specified, fill the cable end box with tested transformer oil and WC S
ensure oil levels
13. Check the use of proper size conductors/ cables for HV/LV, WC W
neutral connection and their connection to NGR or earth grid/
earth point. Measure earth resistant of earth points
Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S
24. Check setting of Fan control (auto & manual), OTI, WTI- alarm WC W
and trip
Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S
1. Check for foundation, its level & centre line markings, ensure WC Rw
the depth of anchor grouting pockets and straightness of
anchor bolts. Foundation should be thoroughly cleaned before
placement of motor
10. Ensure all spacers and blockings used for transportation and WC S
erection have been removed
Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S
Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S
1. Check for foundation, its level & centre line markings, ensure WC Rw
the depth of anchor grouting pockets and straightness of
anchor bolts. Foundation should be thoroughly cleaned before
placement of equipment
Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S
Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S
17. Check generator control panel , its wiring as per drg. Relay & WC W
their calibration & setting, functional checks, etc.
c. Short circuit O/C relay operation. Draw short CRT curve & WC W
compare with shop test results.
20. Perform Earth Fault (E/F) test & see the operation of E/F WC W
relay
21. Perform open circuit test & draw the open CRT curve for WC W
comparison
Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S
2. Ensure level and centre lines are within the prescribed limits WC S
and they match with the requirements of incoming Bus-ducts, if
any
Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S
13. Check name plate for each breaker, inspect and test the WC W
operating mechanics (Mechanically), interlocks, contacts, arc
chutes, auxiliary devices and adjustments as required
14. Visually check all relays and meters for removal of shipping WC W
blocks and for mechanical damage. Ensure their range against
approved drawings, inspect calibration, testing and setting for
each relay and meter.
15. Visually check name plates of CT’s and PT’s and ensure their WC W
ratio accuracy, class and proper grounding against approved
drawings. Test their polarity knee point and ratio. Primary
injection tests at three points on the characteristics curve
submitted by the manufacturer’s
16. Test and witness I.R. value of the power and control bus WC HP
Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S
20. Inspect primary injection & check the breaker tripping through WC W
protective relays, check ammeter indications
Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S
1. Check the insulators wall bushing for any damage like chips WC S
or cracks. Ensure proper installation of the insulators &
bushing
7. Check high voltage tests keeping all the CB’s and isolators WC W
closed but PT’s should be disconnected
Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S
CABLE LAYING
Sl. EPCC Owner/
Activity
No. Contractor PMC
16. Ensure cable trenches in hazardous areas are filled with sand WC S
Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S
18. Back fill the trenches with earth and compact properly after WC S
ensuring the completion of earthing works if any as per earthing
layout drawings.
19. Install cover slabs and seal the trenches in plant/offsite areas WC S
after ensuring the completion of earthing works if any.
Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S
5. Check the top level of the earth pit is matched to the finished WC S
grade level.
8 Check all joints for the conductors below the grade level are WC S
welded & suitably protected by application of two coats of
bitumen & rapping with Jute. The earthing strips laid above
ground shall be welded and will be protected by applying two
coats of bitumen.
9. Ensure the joints are inspected before the coat application & WC S
backfilling.
10. Ensure from every earth electrode two distinct connections are WC S
made to the main earth grid.
11. Ensure all the risers are protected against mechanical damage & WC S
are clamped to the walls, columns, etc.
12. Ensure all the MV & HV electrical equipment are doubly earthed WC S
by connecting two points on the equipment to the earth grid. Rest
of the structural, mechanical, piping shall be connected to the
earth grid as per the contract specifications & drawings.
Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S
13. all process pipelines shall be bonded & earthed at entry & exit WC S
points of battery limit of hazardous area.
15. Ensure each lighting fixture & receptacle are earthed through the WC S, Rw
extra core provided in the lighting cable. ( Normally, the third core
of a 3 core cable)
Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S
2. Ensure that the PCCC terminal box & the transformer terminal WC S
boxes are inspected & cleared to proceed with the bus duct
installation.
5. Inspect the bus duct insulators for any physical damage, which WC S
may have occurred during transit.
8. Ensure the bus bars are properly fixed & coupled on the insulator WC Rw
and ensure that the correct phases are connected at both ends.
9. Ensure the bus bar bolts are tightened to the required torque WC S
values (preferably between 60 to 70 N Mtr) using calibrated torque
wrench.
10. Ensure the bus bar joints are insulated using manufacturers WC S
recommended materials, wherever required.
11. Prior to closing of the bus duct cover, ensure that the bus duct WC W
enclosures are cleared of tools/ loose materials and debris.
12. Ensure the enclosure of bus duct & support structures should be WC S
earthed to the earthing grid as per the drawing.
14. Ensure the wall sealing is done & sun shields provided as per the WC S
drawings.
15. Verify the bus bar joints are clean/ polished & not oxidised before WC W
bolt-up connection.
2. Ensure that the cables are laid separately for HT & LT system. WC S
10. Ensure continuity & IR value checks are done on the cable WC W
from panels to equipments.
11. Ensure that unused entries are plugged tightly in panels, motor WC S
terminal boxes, JB’s, etc
14. Ensure all cable openings & GI conduit entries are properly WC S
sealed.
Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S
INDICATIVE
PIPELINE WORKS
INDEX
S.NO DESCRIPTION DOCUMENT NO. REV.
PIPELINE WORKS
1. Handing Over/Taking over of line pipe at 6648-00-19-43-2901 0
Dump Yard
2. Receipt, Handling & Storage of Line pipes 6648-00-19-43-2902 0
and other free issue materials
3. Procurement, Receipt & Storage of EPCC 6648-00-19-43-2903 0
Contractor supplied materials
4. Row Survey, Clearing & Grading 6648-00-19-43-2904 0
5. Trenching 6648-00-19-43-2905 0
6. Blasting 6648-00-19-43-2906 0
6 Repairs, if any WC W
The above activities will be under EIL if warehousing is in EIL scope of work
Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S
9 Electrical items WC W
Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S
Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S
Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S
TRENCHING
10 Restricted ROW WC W
Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S
13 Firing WC S
Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S
3 Survey check WC S
7 Gauge check WC W
8 Holiday checking WC W
9 Disbondment check WC W
Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S
CONCRETE COATING
3 Logging of activities WC S
10 Repairs WC S
12 Cube testing WC S
13 Megger checking WC HP
Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S
2 Filler material
a) Approval of Make WC HP
b) Review of manufacturer’s test certificates/documents WC HP
c) Testing, as required WC HP
3 WPS/PQR
a) Review of proposed WPS WC HP
b) Procedure Qualification Test WC HP
c) Approval of final WPS & PQR WC HP
4 Welders
a) Performance qualification test WC W
b) Review of radiographs of qualification test piece WC HP
c) Final approval of welders WC HP
15 All weld tensile test and bend tests for each batch of WC HP
electrodes (used for other than root pass welding )
Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S
4 Qualification of insulators/application WC HP
8 Application of sleeves/tapes WC S
10 Holiday check WC W
Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S
10 Checking of levels WC S
11 Post padding WC S
Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S
BACK FILLING
Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S
CASED CROSSINGS
11 Boring operation WC S
16 NDT WC *
Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S
19 Installation of insulators WC W
4 NDT WC *
Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S
Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S
2 Fabrication of string WC *
3 NDT clearance WC HP
8 Pressurization WC S
Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S
Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S
2 Approval of WPS WC Rw
4 NDT clearance WC HP
5 Hydro test WC HP
Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S
Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S
CALIBRATION OF INSTRUMENT
Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S
OFC LAYING
4 Trench inspection WC S
7 Cable laying/blowing WC S
10 Joint pit WC W
11 As-Built drawings WC Rw
Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S
1 Drum Testing
1a Physical inspection WC S
2 Jointing
3 Link Testing
Pl. refer document No. 6648-00-19-43-2000 for definition of WC, Rw, HP, W and S
INDICATIVE FORMATS
FOR REPORTING
INDEX
INDICATIVE
FORMATS
FOR
MECHANICAL WORKS
INDEX
8. Tie-In 6648-00-19-43-5108 0
S. Line/ Area Dia. Joint Spool Component Manufacturer Heat/Batch Colour Verified Remarks
No. Heater No. No. No. No. No. Code Contractor PMC/Owner*
*
REPORT NO : ______________
DATE : ____________________
A/R
Sl. Line/Heater Joint Type
Area No. Dia Inspection Remarks
No. No. No. (*)
Clearance
A : Accepted
R : Rejected
(*)
G - BUTT WELD
S - SOCKET WELD
B - BRANCH WELD __________________
M - MITRE WELD EPCC CONTRACTOR
REPORT NO : ______________
DATE : ____________________
Weld
Sl. Heater/Line No./ Area Type Welder Acceptance
Dia Joint Remarks
No. Drawing NO. No. (*) No.(s) Yes/No
No.
(*)
G = BUTT WELD
S = SOCKET WELD TOTAL IN DIA. =
B = BRANCH WELD PREVIOUS =
M = MITRE WELD TILL DATE =
Sl. Heater/ Area Dia Joint Welder Radio- Segment Results Joint
No. Line No. No. No. No. Graphy No. Status
A/R/H
SWSI - SINGLE WALL SINGLE IMAGE, DWDI - DOUBLE WALLL DOUBLE IMAGE
DWSI - DOUBLE WALL SINGLE IMAGE
A - ACCEPTED, R - REPAIR
H - HOLD
Radio-
Stress PMI
Visual graphy PMI Base
(**) Release Hard- Heat/ Accep-
Sl. Area (*) Welder Inpn. Accep- Weld Metal Manuf-
Dia. Joint Chart ness Batch tance Remarks
No. No. Type No. Report tance ACC Comp- acturer
No. No. No. Date
No. Report. Date onent
(Material)
Date
(*)
G - BUTT WELD
S - SOCKET WELD (**) Joint No are to be posted from the dalily
B - BRANCH WELD fit up reports
M - MITRE WELD Where ever lsos are not available
System Area
Loop Nos. Unit
Ref. P&ID No. Test Reports – Enclosed
( ) TOP OF BOLT
( ) TOP OF
CONCRETE
PCO
BOLT HT.
PCD
BOLT HT.
AS PER
DESCRIPTION ACTUAL DEVIATION REMARKS
DRG
N
C/L CO ORDINATES
REMARKS :
Line Size
Material
Chkd by Chkd by
EPCC
S.No. Activity OWNER/PMC Remarks
Contractor
Sign./date
Sign./date
1. Bevel/Thickness
5. Final Welding
8. Radiography check
_______________ _________________
EPCC Contractor OWNER/PMC
INDICATIVE
FORMATS
FOR
INSTRUMENTATION WORKS
INDEX
S.
DESCRIPTION DOCUMENT NO. REV.
NO
Length as per
Sl. Cable/Tube Drum Drum Actual Test
From To Cable/Tube Balance Remarks
No. Size No. Length Length Reports
Schedule
___________________ _____________
(EPCC CONTRACTOR) (OWNER/PMC)
(a) Hysteris with Positioner (Within + 1% FS) …….….. Yes/ No (d) Shutdown Valve Stroke Speed ……………….….
(b) Hysteris without Positioner (within + 5% FS)……… Yes/No (e) Air Fail Action checked ……………. Open/Close
(c) Linearity Checked ……………………………………. Yes/No (f) Solenoid Power Supply …………………………….
(g) Solenoid Valve OP Checked …………… Yes/No
REMARKS
___________________ _____________
(EPCC CONTRACTOR) (OWNER/PMC)
___________________ _____________
(EPCC CONTRACTOR) (OWNER/PMC)
Act. Verification by
Sl. Cable Cable Gland Gland
From To Length Dressing Clamping Glanding Ferruling Termination EPCC Owner/ Remarks
No. Tag Type Type Size
(m) Contractor PMC
___________________ _____________
(EPCC CONTRACTOR) (OWNER/PMC)
Remarks :
___________________ _____________
(EPCC CONTRACTOR) (OWNER/PMC)
___________________ _____________
(EPCC CONTRACTOR) (OWNER/PMC)
Remarks :
___________________ _____________
(EPCC CONTRACTOR) (OWNER/PMC)
Remarks:
___________________ _____________
(EPCC CONTRACTOR) (OWNER/PMC)
___________________ _____________
(EPCC CONTRACTOR) (OWNER/PMC)
INDICATIVE
FORMATS
FOR
CIVIL WORKS
INDEX
Name of Work :
Accepted
Name of Next
Sl. Model Certificate Calibrated Calibration EPCC PMC/
Equipment/ Calibration Remarks
No. No. No. By Date Cont- OWN-
Apparatus Due on
ractor ER
Project : Job No :
Name of Work :
Location : Layer No :
S. Test Nos:
Description Relation Remarks
No. 1 2 3 4 5 6
1. Wt. of mould + wt. of wet W1 gm
soil
2. Wt. of mould W2 gm
3. Wt. of wet soil (W1 – W2) gm
4. Volume of mould V cc
5. Density of wet soil Dw = (W1 – W2)/V gm/cc
6. Wt. of wet sample taken Ww gm
7. Wt. of sample after drying Wd gm
8. Moisture Content Mc = (Ww – Wd)/wdx100%
9. Dry density Dd = Dw/(1+Mc) gm/CC
10. Laboratory Max dry gm/cc
density
11. Degree of Compaction %
12. Required degree of %
compaction
13. Optimum Moisture Content %
(OMC)
Date :
Project : Job No :
Name of Work :
FINE AGGREGATE
1. 4.75mm
2. 2.36mm
3. 1.18mm
4. 600 u
5. 300 u
6. 150 u
7. Pan
Date :
Project : Job No :
Owner : PMC :
EPCC Contractor :
Name of Work :
Brand of Cement : Consignment No. :
Wt. of sample taken : Sample Collected on:
Room Temperature :
A. CONSISTENCY
Trial Wt. of Wt. of % of Water Reading Consistency Remarks
No. Cement Water on
(gm) Added Indicator
(gm) (mm)
B. SETTING TIME
Trial Wt. of Wt. of W/C Time Time Initial Final Setting Remarks
No. Cement Water Ratio Recorded Recorded Set Set Set
(gm) Added when at set
(gm) Water
Added
C. FINENESS
Trial No. Wt. of Cement Retained on % Retained Remarks
Sample used 90 µ sieve
in gm
D. COMPRESSIVE STRENGTH
Cube Size : 7.06X7.06X7.06 cm
Trial Mix Date of Age of Crushing Crushing Crushing Remarks
No. Proportion Casting Testing Specimen Surface Load Strength
Area (Cm2) (Kg) (Kg/Cm2)
Date:
Remarks
Remarks
11. The above structure is finally inspected on at AM/PM and found/ not found
satisfactory for concreting.
Remarks, if any
2. Quality of water
Satisfactory Not satisfactory
Details of abnormality :
(Precautions taken for <50C and >400C, rainy season)
10. Number of cubes taken :
11. Quantity of concrete poured :
12. Pour completion time : AM/PM ; Date :
13. Curing method :
Project : Job No :
Cube Id. Type & Date Of Age Dimensions of Vol. Wt. Unit Sur- Crus- Crushing Remarks
No. Mark Location (days) Cube of of WT. ace hing Strength
3 2
on of Struc. Cube Cube (Kg/m ) Area Load (Kg/Cm )
2
cube Cast Test L B H (m3) (Kg) (m ) (Kg)
(m) (m) (m)
Project : Job No :
OWNER : PMC :
EPCC Contractor :
Name of Work :
Date :
INDICATIVE
FORMATS
FOR
ELECTRICAL WORKS
INDEX
2. Transformers 6648-00-19-43-5802 0
7. HV Motor 6648-00-19-43-5807 0
8. MV Motor 6648-00-19-43-5808 0
9. DG Set 6648-00-19-43-5809 0
TEST PROFORMA
HV SWITCHBOARD
2.0 GENERAL CHECKS : (Put tick (9) if satisfactory, otherwise give details)
2.1 Installation
a. Busbars Section-1
Section-2
b. Busduct/Cables Section-1
(Incomer) Section-2
Panel No. :
Feeder Designation :
3.2.1
Protection
Manufacturer's Data Metering
Core 1 Core 2 Core 3
Ratio
VA rating
Accuracy Class
Serial nos.
b. Check CT earthing
d. Test results:
Protection
Tests Metering
Core 1 Core 2 Core 3
i) Ratio measurement
Secondary to Earth
Primary to secondary
Ratio :
VA rating :
Class :
Type :
Serial Nos. :
a) Ratio Measurements
b) Polarity check :
d) Check PT earthing :
e) Insulation resistance
measured :
Primary to earth :
Secondary to earth :
Primary to earth :
3.4 Relays
2.
3.
2.
3.
Note : 1. For each relay, site pre-commissioning checks and tests shall be carried out in
accordance with manufacturer’s instructions manual and test readings are
recorded.
2. IDMTL, and instantaneous relays and other protective relays shall be checked for
proper operation at minimum of 3 settings which shall include relay protection co-
ordination setting values for IDMTL & instantaneous relays.
3. Correctness of CT polarity and connections for differential protection circuit shall
be ensured through 3 phase primary injec5tion transformer kits for in zone & out
zone.
4. Enclose Relay Test reports along with the report
4.0 COMMISSIONING
Magnetisining/starting current
TEST PROFORMA
TRANSFORMERS
2.0 GENERAL CHECKS : tick (9) if found satisfactory correct otherwise give
details.
2.1 Installation
Bottom sample
Vector Group:
Tap1
Tab2
Tab3
Tab4
Tab5
Control circuit
Overall relays
Direction of Rotation
Interlocks
Signaling circuit
Alarm/blinkers
LV section isolation
Temperature reading :
12.0 REMARKS :
a)
b)
c)
TEST PROFORMA
ON LOAD TAP CHANGER
Sl.no. :
Voltage : Current :
Motor rating :
2.0 GENERAL CHECKS : (Put tick (9) if satisfactory otherwise give details).
Installation of OLTC :
OLTC earthing :
Installation of associated :
(Remote control panel & earthing)
3.0 TEST
TEST PROFORMA
NEUTRAL GROUNDING RESISTOR
2.0 GENERAL CHECKS : (Put tick (9) if satisfactory, otherwise give details)
Installation of NGR :
General cleanliness :
Condition of bushings :
3.0 TEST
Megger used :
Ambient temperature :
4.0 REMARKS
TEST PROFORMA
MV SWITCH BOARD
Manufacturer : Type :
Bus rating : Fault level :
Section 1 fed from :
Section 2 fed from :
2.0 GENERAL CHECKS : (Put tick (9) if satisfactory, otherwise give details)
2.1 Installation
Circuit breaker closing & tripping Bus trunking and tightness of nut
mechanism and bolt connections
a. Busbars Section-1
Section-2
b. Busduct/ Section-1
Cables
(Incomer) Section-2
Panel No. :
Feeder Designation :
3.2.1
Ratio
VA rating
Accuracy Class
Serial nos.
b. Check CT earthing
d. Test results:
i) Ratio measurement
Secondary to Earth
Primary to secondary
Ratio :
VA rating :
Class :
Type :
Serial Nos. :
a) Ratio Measurements
b) Polarity check :
d) Check PT earthing :
e) Insulation resistance
measured :
Py-G :
Sy-G :
Py-Sy :
3.4 Relays/Releases
2.
3.
2.
3.
Note : 1. Site precommissioning checks and tests shall be carried out in accordance with
manufacturer’s instructions manual and test readings are recorded.
4.0 COMMISSIONING
:
Phasing of bus sections
6.0 REMARKS
TEST PROFORMA
BATTERY SET AND CHARGER
2.0 GENERAL CHECKS : (Put tick (9) if satisfactory, otherwise give details)
CHARGER PANEL
BATTERY SET
All circuit cards are firmly seated in General cleaning & tightness of
their sockets all cables connection
Megger used
Float/boost chargers :
Interlocks
AC input voltage :
DC output voltage, variation :
Operating temperature in cabinet :
(No hot spot)
Battery voltage :
Battery trickle charge current :
Abnormal noise if any :
TEST PROFORMA
H.V. MOTOR
2.0 GENERAL CHECKS : (Put tick (9) if satisfactory, otherwise give details)
2.1 Motor
2.2 Installation
Interlocks
Rotor
Stator Supply cable
Quantity Meggar Remarks
RE YE BE Wegs-E RE YE BE RY YB BR
R15
R60
Resistance
5.0 COMMISSIONING
Test results
Interlocks
TEST PROFORMA
M.V. MOTOR
2.1 Motor
B. STARTER MODULE
3.0 TESTING
UE VE WE UV VW VW
Power cable :
Motor :
Control cable between line to
line:
Relay range :
Tripping time at twice rated current of motor :
4.0 COMMISSIONING
‘At no load’
Vibration : Voltage :
Voltage :
Vibration : RY = YB = BR =
Bimetal relay set at : (after load run) No load run: Load run:
5.0 REMARKS
TEST PROFORMA
D.G. SET
Engine Alternator
Rating :
Type Designation :
Fuel tank capacity :
Battery :
Charging system :
Excitation type :
Method of start : Air/battery
2.0 GENERAL
General cleanliness :
R15
R60
K = R60
------
R15
Stator :
Rotor :
5.0 COMMISSIONING
Interlocks :
Vibrations :
AMF Feature :
Voltage :
Excitation current :
Frequency :
Power factor :
Bearing condition :
8.0 REMARKS
TEST PROFORMA
CABLE INSTALLATION
From : To : Size :
2.0 GENERAL CHECKS : (Put tick (9) if satisfactory, otherwise give details)
Laying :
Earthing of armour/Screen :
Phasing/continuity
Cable support :
Description R to E Y to E B to E RY YB BR
R15
R60
K = R60
R15
** Applicable for H.V. Cables and for those M.V. Cables where st-through
joints are made.
Description R to E Y to E B to E RY YB BR
R15
R60
K = R60
R15
4.0 REMARKS
TEST PROFORMA
ELECTRICAL HEAT TRACING SYSTEM
PART-I : TRACER
Circuit no. :
LDP No./FDR No. :
Heater type :
Heater cable length :
Drawing no. :
Spiraling details, if any :
Area :
Line no. :
Maintenance temperature :
Heat loss/mt. :
- Heater continuity :
a. FLP JB :
b. Thermostat :
- Tag plates :
Insulation in M Ω
Megger used :
Ambient temperature :
Voltage V :
Load current I :
Pipe temperature :
Power output (V X I) : Watts
Calculated value from guaranteed curve (at the pipe temp.) : Watts
Manufacturer :
Bus rating :
Section fed from :
Feeder rating (Amb.) :
No. of outgoing switchfuse :
feeders with contactor (used)
No. of outgoing spare feeders type : Indoor/outdoor
Fault level :
LDP no. :
Location :
2.1
Vermin proof :
Danger Board :
Fuses :
Control circuits :
Interlocks :
ELCB operation :
I.R. in M Ω
RE YE BE NE RY YB BR RN YN BN
a. Bus bars:
b. Incoming :
Cables
4.0 COMMISSIONING
5.1 Voltage V :
6.0 REMARKS
TEST PROFORMA
LIGHTING INSTALLATION
Rated voltage :
Rated current :
Incomer rating :
2.0 GENERAL CHECKS : (Put tick (9) if satisfactory, otherwise give details)
2.1
Check
Panel Installation Mark
Remarks
Check general cleaning of panels and assembly
Jbs : FLP/Ex(e)
Sockets : FLP
2.2
Check
Lighting Installation Mark
Remarks
Check the operation and setting of time
switches, photo-electric cells, EPCC
CONTRACTORs (wherever provided)
3.1 Panel
Neutral to earth : R, Y, B to N :
RE : RY :
YE : YB :
BE : BR :
NE : R, Y, B to N :
IR :
IY :
IB :
IN :
(If required adjust circuit loads for load balancing in each phase)
5.0 REMARKS
TEST PROFORMA
EARTHING INSTALLATION
Type of electrode :
Total number of electrodes :
Main grid size :
Material :
3.0 TESTS
1. ---------------------
2. ---------------------
3. ---------------------
4. ---------------------
5. ---------------------
4.0 REMARKS
REQUIREMENTS
FOR
AT
CONSTRUCTION SITES
TABLE OF CONTENTS
_________________________________________________________________________
CLAUSE NO. TITLE PAGE NO.
_________________________________________________________________________
1.0 SCOPE 3
2.0 DEFINITIONS 3
4.0 REFERENCES 4
11.0 CALIBRATION 6
16.0 DOCUMENTATION 8
_______________________________________________________________________
1.0 SCOPE
1.1 This specification applies to metallic alloy materials used in piping, heater coils, storage
tanks, vessels etc. at construction sites. Positive Material Identification (PMI) is to be
carried out on owner supplied material as well on materials purchased by the EPCC
contractor.
1.2 Any deviation from this specification must be approved by Owner/PMC in the prescribed
format.
1.3 Carbon steels are excluded from the scope of this specification.
2.0 DEFINITIONS
Chemical spot checking, resistivity testing, eddy current testing, electromagnetic alloy
sorting, thermoelectric testing shall not be considered as PMI for the purpose of this
specification.
3.1 The following items require PMI unless specifically exempted through a Waiver/Deviation
permit by Owner/PMC.
3.1.1 All pressure containing piping components including, thermowells instrument manifolds,
RTJ gaskets, fasteners etc..
3.1.3 Pressure - containing instrument housings (e.g. gauge glass housings, orifice meter tubes).
3.1.4 Internal metallic linings/cladding, and weld overlay, done at site, used for protection against
corrosive environments.
3.1.5 Tubing
3.1.7 Plates
3.1.9 Any other components or materials specifically designated for PMI on the purchase
order/contract.
3.2 Exclusions
The following items are exempted unless specifically designated for PMI in the purchase
order/contract.
3.2.4 Internal non pressure - containing baffles, trays, tray clips, supports, pall-rings, support
rings, etc.
3.2.6 Non pressure - containing welds, including seal welds, piping supports welds, structural
parts.
3.2.8 Compression-type ferrules and fittings for use with 3/4 inch (19mm) outside diameter and
smaller tubing.
4.0 REFERENCES
American Society of Mechanical Engineers (ASME) BPV Code Section-II Part A,B,C and D
ASME B 31.3
Material Verification Program for New and Existing Alloy Piping Systems : API RP 578
5.1 The test methods outlined in this specification are intended to identify the nominal
composition of alloy materials. These test methods are not intended to establish the
conformance of a material to a particular alloy specification.
5.2 PMI shall not be considered as a substitute for required mill test reports listing chemical
composition. In addition, mill test reports shall not be considered as confirming alloy
verification.
5.3 The PMI activity shall be included in the overall quality plan and Inspection & Test Plan for
warehouse and fabrication/erection. The EPCC contractor shall submit to PMC/Owner, a
procedure for PMI to comply with the requirements of this specification. Approval of PMI
procedure shall be obtained from Owner/PMC prior to commencement of
fabrication/erection as the case may be.
5.5 After installation, but prior to hydrostatic testing/painting/insulation, the EPCC contractor
shall examine all components requiring PMI for proper compliance to this specification. A
record of this final check, as specified below, shall be submitted to PMC/Owner and made
part of the permanent inspection records.
Records signed by EPCC contractor and certified by an approved third party inspection
agency.
5.6 After acceptance, all components shall be marked with a suitable paint mark. Markings
must be permanent and readily visible. These markings are in addition to markings
required by other codes/specifications/Technical Notes.
5.7 Controls shall be established to keep the non conforming items identified till proper
resolution of non conformity.
5.8 PMC/Owner shall have the right to witness the performance of any PMI test.
PMI shall be done on each component (100 percent PMI inspection) including welds,
unless specifically exempted by Owner/PMC.
However, one stud & nut assembly for each flange joint shall require PMI. All studs & nuts
in a piping hydro test loop shall require PMI, if any non conformity is detected.
The extent of PMI shall be as specified in 6.0. However, if PMI testing has been carried out
at vendor/manufacturer’s shop and relevant certified records and correlation with incoming
material is available, PMI testing at warehouse need not be done.
PMI testing done as a part of receiving Inspection shall not be regarded as an alternative to
PMI testing of the installed system.
PMI testing (irrespective of PMI done at earlier stages) shall be carried out when piping
loops/heater coils have been cleared for hydrostatic testing by PMC/Owner. Hydrostatic
Testing shall be carried out only when non conforming components have been
replaced with conforming components and subsequent Non Destructive Testing, Post Weld
Heat-Treatment, Hardness checking etc., as required by specifications have been
completed. PMI records shall form a part of piping/heater inspection records. EPCC
contractor shall demonstrate to PMC that each & every component of the piping system
and heater coils has been subjected to PMI by providing line wise records of PMI.
In general, portable X-Ray Fluorescence (XRF) type alloy analyzers such as Oxford
Instruments’ X-Met 3000 TX, X-Met 2000 Metal Master, NITON’s XLt or NITON II or
similar analyzer shall be used for carrying out PMI. Identification of characteristic alloying
elements (see 10.0 for examples), which distinguishes the material from other materials,
will be sufficient. However, in case of doubt, Owner/PMC may insist on complete analysis.
The surface of the component to be subjected to PMI shall be free from grease, oil, paint or
oxides. Testing shall be done after proper surface cleaning and other requirements outlined
by the manufacturer of the portable alloy analyzer. Modification, if any, of these procedures
must be approved by Owner/PMC.
Characteristic elements for materials not listed above shall be proposed by the EPCC
contractor for approval of the owner/PMC
11.0 CALIBRATION
11.1 Instruments used for PMI shall have the sensitivity to detect the alloying elements in the
specified ranges. Instruments or methods used for examination shall be of the type that will
provide quantitative, recordable, elemental composition results for positive identification of
the alloy elements present.
11.2 Each alloy analyzer shall be calibrated using known alloy standards for intended materials
to be checked by PMI. A calibration certification from the Manufacturer or his authorized
agency shall be submitted to PMC/Owner for records. As such, calibration at site is not
envisaged.
11.3 PMC/Owner shall review the procedure and qualification and witness sample alloy
verification tests to confirm that the procedures, equipment and personnel are capable of
providing consistent and accurate results.
Verification using Standard samples supplied by institutes such as ASM (American Society
of Metals) for the intended materials type and grade shall be performed each day before
using the analyzer. Such a verification shall be done again if PMI test is to be performed
on different grade or type of material.
The persons performing the PMI test should be knowledgeable about properties of
material, all aspects of operation of PMI equipment including the method of testing.
Qualification/experience documents of the person performing the PMI test including his
training and experience shall be submitted to PMC/owner for review and approval.
PMI test results showing presence of characteristic elements upto 10% less than the
minimum specified value in the material specification or upto 10% more than the maximum
specified value in the material specification shall be acceptable.
For deposited weld metal between base metals of the same specification using matching
consumables, the recorded presence of characteristic elements upto 12.5% less than the
minimum specified value in the welding consumables specification and upto 12.5% more
than the maximum specified value in the welding consumable specification shall be
acceptable.
15.1 If the PMI test results fall outside the acceptable range as given in 14.0 above, the EPCC
contractor shall obtain a quantitative check analysis performed by a laboratory acceptable
to PMC/owner for a complete chemical analysis. Results of this analysis shall be submitted
to PMC/Owner, with EPCC contractor’s recommendation, for final decision.
15.2 If any material component or weld is found unacceptable all other represented materials (
e.g. in case of fasteners, supports ) or weld shall be considered suspect. The EPCC
contractor has the following options.
15.2.1 Scrapping all those represented materials and components and replacing with new
components or welds.
15.2.2 Performing 100% examination of the remainder of the represented materials/ components
and replacing each item that fails the PMI check..
16.0 DOCUMENTATION
16.1 Print out from alloy analyzer, in original, duly certified by the EPCC contractor.
16.3 Basis and action for resolving and documenting PMI non conformances .
16.4 EPCC contractor shall demonstrate to PMC/owner that all components requiring PMI have
been subjected to PMI testing and accepted.
Line No. /ISO Drg. No_____________ Make & Serial No. _______________
/Heater No./Drawing No
Result
Sr. Material Material
Part Identification (Accepted/Rejected
No. As per Drg./spec as per PMI
/Retest)