CAPACITY ADDITION FOR MARCH' 08 AND APRIL'07-MARCH' 08


(MW)
Schemes Status of Target MARCH' 08 APRIL'07- MARCH' 08 Deviation
Schemes 2007-08 Programme Achievement Programme Achievement (+) / (-)
Thermal Central 4650.00 660.00 500.00 4650.00 1990.00 -2660.00
State 5017.20 0.00 300.00 5017.20 3880.00 -1137.20
Pvt. 3037.00 250.00 250.00 3037.00 750.00 -2287.00
Total 12704.20 910.00 1050.00 12704.20 6620.00 -6084.20
Hydro Central 1030.00 0.00 340.00 1030.00 1030.00 0.00
State 1721.00 0.00 190.00 1721.00 1393.00 -328.00
Pvt. 0.00 0.00 0.00 0.00 0.00 0.00
Total 2751.00 0.00 530.00 2751.00 2423.00 -328.00
Nuclear Central 880.00 0.00 0.00 880.00 220.00 -660.00
Total 880.00 0.00 0.00 880.00 220.00 -660.00
State
RES @ Pvt.
Total

All India Central 6560.00 660.00 840.00 6560.00 3240.00 -3320.00


State 6738.20 0.00 490.00 6738.20 5273.00 -1465.20
Pvt. 3037.00 250.00 250.00 3037.00 750.00 -2287.00
Total 16335.20 910.00 1580.00 16335.20 9263.00 -7072.20
@ Renewable Energy Sources (RES) includes Small Hydro Project(SHP), Biomass Gas(BG), Biomass Power(BP),
Urban & Industrial waste Power(U&I), and Wind Energy.
PROGRAMME & ACHIEVEMENT ( MW ) DURING APRIL'07-MARCH' 08
16335

18000
12704

15000

12000
9263

9000
6620

6000
2751

2423

3000
880

220

0
Thermal Hydro Nuclear Wind Total
Programme Achievement