SUPPLY AND INSTALL FRANKLIN LIGHTNING RODS, FITTINGS AND

INSTALLATION OF BRACKET/LIGHTNING ROD/GROUND WORKS


PROPOSED WORK PROGRAM

MONTH L Y 2 0
DATE
WEEKS D A Y 1 D A Y 2 D A Y 3 D A Y 4 D A Y 5
ACTIVITIES

1 MOBILIZATION OF WORKERS AND MATERIAL TO SITE


TOOL BOX

2 ISSUANCE OF WORK PERMIT /SHUTDOWN -2 DAYS


ISSUANCE OF WORK PERMIT WORKS WITHIN
VICINITY OF LIVE CONDITION

A GROUP A AND B( 9 WORKERS)


GROUND WORKS PREPARATION
TRANSPORT AND FIXING LADDER
INSTALLATION OF LIGHTNING ROD AND TAPE 2 MAST
CANCELL W.P.
TO GANTRY COLUM 3 MAST

CANCELLATION OF WP FOR OUTAGE WORKS

GROUP A AND B ( 9 WORKERS)


B GROUND WORKS PREPARATION 3 MAST
FIXING EARTHING ROD, CHAMBER AND PVC PIPE 2 MAST
CONCRETING TO BASE AND INSIDE PVC PIPE

C FINISHING WORKS
ALL 39 TWR
E TESTING OF AND COMMISSIONING
ALL 39 TWR
F SITE CLEARANCE AND DEMOBILIZING

program subject to weather and other


condition beyond control
SUPPLY AND INSTALL FRANKLIN LIGHTNING RODS, FITTINGS AND
INSTALLATION OF BRACKET/LIGHTNING ROD/GROUND WORKS
PROPOSED WORK PROGRAM

MONTH J U L Y 2 0 1 0
DATE
WEEKS D A Y 1 D A Y 2 D A Y 3 D A Y 4 D A Y 5
ACTIVITIES

1 MOBILISATION OF WORKERS AND MATERIAL TO SITE


TOOL BOX

2 ISUANCE OF WORK PERMIT

A GROUP A ( 5 WORKERS)
GROUND WORKS PREPARATION

FIXING EARTHING ROD,CHAMBER AND PVC PIPE 8 MAST


LIFTING OF ROD FOLLOWED BY TAPE 9 MAST
AND CLAMP TO COLUMN 9 MAST
9 MAST 3 MAST
GROUP B ( 5 WORKERS)
B GROUND WORKS PREPARATION
FIXING EARTHING ROD,CHAMBER AND PVC PIPE T11,T12
LIFTING OF ROD FOLLOWED BY TAPE T13,T14,T15
AND CLAMP TO COLUMN T16,T17,T18
TRANSPORT TOWER T22 AND T21 T19,T20

C TESTING OF EARTH RESISTIVITY