supply, Installation and implementation of a Mid Range Integrated Financial

Management System (Tier 2 IFMS) for Local Governments (Bid Subm date:30th
April 2010 15hr)
1 P R No. MoFPED/FINMAP/SUPP/09-10/00014
Pre Bid Meeting Date: 18 March 2010, 10:00
Opening date 30th april 2010 15:30 hr
2 Must have at least five (05) years experience in the implementation of similar information systems
Must have undertaken at least two successful implementations in public sector of the proposed
3 system with a similar nature and complexity during the last 10 years . Each with a minamum
value of US$ 3,000,000
4 Financiall stable, with a minimum average annual turnover of US$ 2,500,000. with in last 3 years
In case of joint venture one partner should fullfill at least 50% 0f the specified turnover amount
5
while each of the other partner fulfill: 50/(n-1), n= number of partners in a JV
6 Must submit the audited balance sheet for the past three years
7 must have cash flow amount of at least US$ 300,000 in each of the last 3years

The bidders project team must have the competencise and skills:
Project Management,
Quality Assurance
Public Sector Fiscal Management
change mangement
8 Neworking
Operation Systems
Systems Security
Database Management
Software Development and Design &
Application Expertse.

Bidders entirly from outside Uganda Must Demonstrate ther capabilities for providing effective
9
in-country support
12 Preliminary Project Plan Must addressthe folling
1.Project organization and Management Plan
2.Delivery and Instalation plan
3.Training Plan
4.Pre-commissioning and Operational Acceptance Testing plan
5.Warranty Service Plan
6.Task,Time and Resource Scheduls
7.Post-warranty service plan
8.Technical Support Plan
9.change Control Support Plan
10.Risk Management Plsn
13 Bid security in form of bank gurantee is : 2% of the bid price.
Bid validity period shall be 120 days (31 Augst 2010),bid security that expaires twenty eight
14
(28) days after the end of bid validity period
15 Required No. of copies ,one original and five (5) copies and one CD
16 Evaluation : the weight of price=65%
17 post warranty 36 months
The supplier agree to supply spare parts required for the operation and maintenance of the
18 system,as stated below,for the three years beginning with Operational Acceptance(Memory
Modules,HDD,Tape drive,Disk controllers…..so on )
stems