Standard Scaffold Details


_________________________________________________________

OCTOBER 2010

ENGR SREEJIT RAGHU


MEng (Hons) DIC ACGI MIStructE CEng MIEM IntPE (UK)
Standard Scaffold Details

Table of Contents

1. Scaffold Dimensions Summary ......................................................................... 3


2. General Details .............................................................................................. 6
3. Independent Scaffold Details ........................................................................... 7
4. Putlog Scaffold Details .................................................................................... 8
5. Tying In Details.............................................................................................. 9
6. Roof Scaffold Edge Protection ........................................................................ 11

2
Standard Scaffold Details

1. Scaffold Dimensions Summary

3
Standard Scaffold Details

Ledger Cross
Bracing Intervals

Wind speed 21m/s with site


in town >= 100km to sea.

Single standard assumed.

For clarity, not all members


of each type shown.

Tie
Vertical
Façade Bracing
Intervals
Standard Unbraced Height

Ledger Span
Putlog

Steel Base Plate


over Timber Sole
Plate 225.0 x 38.0

Transom Span

Member Section

Scaffold tubes 48.3 x 4.0 steel grade 235MPa and used scaffold tubes (FOS = 2.0)
225.0 x 38.0 timber C16
Timber boards
(max span 1.500m; min overhang 50mm; max overhang 152mm;)

Scaffold Not Sheeted or Sheeted With Pervious Sheeting 0% Impermeability (Debris Netting)
General purpose, brickwork,
Very light duty, inspection,
Activity window fixing, rendering,
painting, stone cleaning, access;
plastering;
Ledger span 2.800m 1.800m
Standard unbraced
2.200m 2.200m
height
1.000m 1.000m
Transom span
(4 timber boards widths) (4 timber boards widths)
Ledger cross bracing
Once every 2 standards Once every 2 standards
intervals
Tie vertical intervals Once every 2 lifts Once every 2 lifts
Once every ledger cross bracing Once every ledger cross bracing
Tie horizontal intervals
intervals intervals
Once every elevation face Once every elevation face
Façade bracing
(on outer face only) (on outer face only)
Timber board span Half of ledger span (1 putlog) Half of ledger span (1 putlog)
Number of lifts of
26 lifts 20 lifts
working platforms
4
Standard Scaffold Details

Scaffold Sheeted With Impervious Sheeting 100% Impermeability (Monarflex) Option 1


General purpose, brickwork,
Very light duty, inspection,
Activity window fixing, rendering,
painting, stone cleaning, access;
plastering;
Ledger span 1.500m 1.300m
Standard unbraced
2.200m 2.200m
height
1.000m 1.000m
Transom span
(4 timber boards widths) (4 timber boards widths)
Ledger cross bracing
Once every 2 standards Once every 2 standards
intervals
Tie vertical intervals Once every 2 lifts Once every 2 lifts
Once every ledger cross bracing Once every ledger cross bracing
Tie horizontal intervals
intervals intervals
Once every elevation face Once every elevation face
Façade bracing
(on outer face only) (on outer face only)
Timber board span Half of ledger span (1 putlog) Half of ledger span (1 putlog)
Number of lifts of
6 lifts 6 lifts
working platforms

Scaffold Sheeted With Impervious Sheeting 100% Impermeability (Monarflex) Option 2


General purpose, brickwork,
Very light duty, inspection,
Activity window fixing, rendering,
painting, stone cleaning, access;
plastering;
Ledger span 2.400m 1.800m
Standard unbraced
2.200m 2.200m
height
1.000m 1.000m
Transom span
(4 timber boards widths) (4 timber boards widths)
Ledger cross bracing
Once every standard Once every standard
intervals
Tie vertical intervals Once every 2 lifts Once every 2 lifts
Once every ledger cross bracing Once every ledger cross bracing
Tie horizontal intervals
intervals intervals
Once every elevation face Once every elevation face
Façade bracing
(on outer face only) (on outer face only)
Timber board span Half of ledger span (1 putlog) Half of ledger span (1 putlog)
Number of lifts of
6 lifts 6 lifts
working platforms

5
Standard Scaffold Details

2. General Details

6
Standard Scaffold Details

3. Independent Scaffold Details

7
Standard Scaffold Details

4. Putlog Scaffold Details

8
Standard Scaffold Details

5. Tying In Details

9
Standard Scaffold Details

10
Standard Scaffold Details

6. Roof Scaffold Edge Protection

11
Standard Scaffold Details

12
Standard Scaffold Details

13