Time of completion Description of Task

(days)
Construction of the restaurant's building
4 Digging and leveling the land parcel
10 Casting and molding the concrete floor slabs
7 Casting and molding the concrete support pillars
15 Fabrication and assembly of the metallic drop beams
5 Casting and molding the concrete slab ceiling
12 Mandatory waiting time for the concrete roof to cure
5 Casting and molding of the internal dividing walls
7 A/C and electricity ducting installation in the drop beams
structure followed by a false double ceiling installation
8 Basic plumbing and sanitary work followed by tiling
12 decorative stone walls casting and assembly Chemlani +
footing stones (cha3riyeh)
2 Finishing of the A/C installations
5 Finishing electrical points & neon sign installation,
Segarit panoramic glass sheets installation
2 Finishing plumbing and sanitary work
2 Cleaning of the whole restaurant

installation of the restaurant's equipements


2 Kitchen industrial equipements installation
1 Sound equipment installation and calibration
1 Floor layout setup (tables and chairs positioning,
tableware preparation)