Activity ID Activity Name Plnd Dur Early Start Early Finish

SALES GAS DISTRIBUTION SYSTEM
PROCUREMENT
Mainline
Long Lead Items (LLI)
Piping
Hot Tap Fittings
Expected Time of Arrival (ETA) to Project Site 19.0d 18‐Jun‐11 10‐Jul‐11
Carbon Steel Pipes ‐ Mainline
Expected Time of Arrival (ETA) to Project Site 22.0d 27‐Jul‐11 22‐Aug‐11
Ball Valves ‐ GOV/ MOV
Expected Time of Arrival (ETA) to Project Site 19.0d 18‐Sep‐11 10‐Oct‐11
Barred Tees (MSTCC)
Expected Time of Arrival (ETA) to Project Site 10.0d 28‐Jun‐11 10‐Jul‐11
Induction Bend Carbon Steel Pipes (MSTCC)
Expected Time of Arrival (ETA) to Project Site 8.0d 30‐Jun‐11 10‐Jul‐11
Mechanical
Filteration Skid
Expected Time of Arrival (ETA) to Project Site 16.0d 16‐Nov‐11 5‐Dec‐11
Scraper Traps & Handling Facilities
Expected Time of Arrival (ETA) to Project Site 18.0d 8‐Sep‐11 29‐Sep‐11
Instrumentation
Sales Gas Metering System
Expected Time of Arrival (ETA) to Project Site 20.0d 7‐Dec‐11 31‐Dec‐11
Emergency Isolation Valve (EIV)
Expected Time of Arrival (ETA) to Project Site 18.0d 10‐Aug‐11 31‐Aug‐11
Leak Detection System (LDS)
Expected Time of Arrival (ETA) to Project Site 12.0d 15‐Sep‐11 29‐Sep‐11
HVAC
HVAC Equipment & Accessories (MSTCC)
Expected Time of Arrival (ETA) to Project Site 12.0d 26‐Jun‐11 10‐Jul‐11
Critical Items
Piping
Carbon Steel Pipes ‐ Other than Main Line (MSTCC)
Expected Time of Arrival (ETA) to Project Site 12.0d 26‐Jun‐11 10‐Jul‐11
Copper Nickel Pipes (MSTCC)
Expected Time of Arrival (ETA) to Project Site 6.0d 3‐Jul‐11 10‐Jul‐11
Gate Valves ‐ Manual (MSTCC)
Expected Time of Arrival (ETA) to Project Site 12.0d 26‐Jun‐11 10‐Jul‐11
Globe Valves (MSTCC)
Expected Time of Arrival (ETA) to Project Site 12.0d 26‐Jun‐11 10‐Jul‐11
Plug Valves ‐ Manual (MSTCC)
Expected Time of Arrival (ETA) to Project Site 12.0d 26‐Jun‐11 10‐Jul‐11
Check Valves (MSTCC)
Expected Time of Arrival (ETA) to Project Site 8.0d 30‐Jun‐11 10‐Jul‐11
Ball Valves ‐ Manual (MSTCC)
Expected Time of Arrival (ETA) to Project Site 8.0d 30‐Jun‐11 10‐Jul‐11
Flanges ‐ 24" & Below (MSTCC)
Expected Time of Arrival (ETA) to Project Site 12.0d 26‐Jun‐11 10‐Jul‐11
Fire Monitor (MSTCC)
Expected Time of Arrival (ETA) to Project Site 7.0d 2‐Jul‐11 10‐Jul‐11
Instrumentation
Analyzer Shelter
Expected Time of Arrival (ETA) to Project Site 18.0d 8‐Dec‐11 29‐Dec‐11
H2S/ LEL Detection System (MSTCC)
Expected Time of Arrival (ETA) to Project Site 8.0d 30‐Jun‐11 10‐Jul‐11
Remote Terminal Unit ‐ RTU
Expected Time of Arrival (ETA) to Project Site 12.0d 17‐Jul‐11 31‐Jul‐11
Scraper Passage Indicators
Expected Time of Arrival (ETA) to Project Site 12.0d 30‐Jun‐11 14‐Jul‐11
Temperature Instruments
Expected Time of Arrival (ETA) to Project Site 6.0d 25‐Aug‐11 6‐Sep‐11
Pressure Instruments
Expected Time of Arrival (ETA) to Project Site 6.0d 30‐Jul‐11 6‐Aug‐11
Electrical
Transformer (MSTCC)
Expected Time of Arrival (ETA) to Project Site 6.0d 3‐Jul‐11 10‐Jul‐11
Switchracks (MSTCC)
Expected Time of Arrival (ETA) to Project Site 6.0d 3‐Jul‐11 10‐Jul‐11
Power Panels (MSTCC)
Expected Time of Arrival (ETA) to Project Site 6.0d 3‐Jul‐11 10‐Jul‐11
UPS System/ Panel (MSTCC)
Expected Time of Arrival (ETA) to Project Site 6.0d 3‐Jul‐11 10‐Jul‐11
Instrument Junction Boxes (MSTCC)
Expected Time of Arrival (ETA) to Project Site 4.0d 5‐Jul‐11 10‐Jul‐11
Cable : Pow Instrumentation & CP (MSTCC)'
Expected Time of Arrival (ETA) to Project Site 3.0d 6‐Jul‐11 10‐Jul‐11
Lighting Material (MSTCC)
Expected Time of Arrival (ETA) to Project Site 4.0d 5‐Jul‐11 10‐Jul‐11
Cathodic Protection Rectifier (MSTCC)
Expected Time of Arrival (ETA) to Project Site 3.0d 6‐Jul‐11 10‐Jul‐11
Communication
Fibre Optic Cable
Expected Time of Arrival (ETA) to Project Site 7.0d 27‐Jun‐11 5‐Jul‐11
Bulk
Electrical
Fire Alarm Panels (MSTCC)
Expected Time of Arrival (ETA) to Project Site 4.0d 5‐Jul‐11 10‐Jul‐11
Civil
Structural Steel (MSTCC)
Expected Time of Arrival (ETA) to Project Site 6.0d 3‐Jul‐11 10‐Jul‐11
Anchor Bolts (MSTCC)
Expected Time of Arrival (ETA) to Project Site 1.0d 28‐Apr‐11 30‐Apr‐11
Fence (MSTCC)
Expected Time of Arrival (ETA) to Project Site 2.0d 12‐May‐11 15‐May‐11
RTR Pipe Materials (MSTCC)
Expected Time of Arrival (ETA) to Project Site 6.0d 3‐Jul‐11 10‐Jul‐11
Piping
Galvanized Steel Pipes (MSTCC)
Expected Time of Arrival (ETA) to Project Site 4.0d 5‐Jul‐11 10‐Jul‐11
RTR Pipes ‐ Fibre Reinforced Epoxy Coated (MSTCC)
Expected Time of Arrival (ETA) to Project Site 3.0d 6‐Jul‐11 10‐Jul‐11
Threaded/ Socket Weld Fittings (MSTCC)
Expected Time of Arrival (ETA) to Project Site 4.0d 5‐Jul‐11 10‐Jul‐11
Threaded/ Socket Weld Valves (MSTCC)
Expected Time of Arrival (ETA) to Project Site 4.0d 5‐Jul‐11 10‐Jul‐11
Stud & Machine Bolts (MSTCC)
Expected Time of Arrival (ETA) to Project Site 2.0d 7‐Jul‐11 10‐Jul‐11
Butt Weld Fittings ‐ 24" & Below (MSTCC)
Expected Time of Arrival (ETA) to Project Site 2.0d 7‐Jul‐11 10‐Jul‐11
Gaskets & Insulating Kits (MSTCC)
Expected Time of Arrival (ETA) to Project Site 2.0d 7‐Jul‐11 10‐Jul‐11
FBE Coating
Expected Time of Arrival (ETA) to Project Site 10.0d 10‐Aug‐11 22‐Aug‐11
RTR Pipe Fittings  ‐ Fibre Reinforced Epoxy Fittings (MSTCC)
Expected Time of Arrival (ETA) to Project Site 6.0d 3‐Jul‐11 10‐Jul‐11
 Galvanized Pipe Fittings (MSTCC)
Expected Time of Arrival (ETA) to Project Site 4.0d 5‐Jul‐11 10‐Jul‐11
Copper Nickel Fittings (MSTCC)
Expected Time of Arrival (ETA) to Project Site 4.0d 5‐Jul‐11 10‐Jul‐11
Communication
Communication Materials
Expected Time of Arrival (ETA) to Project Site 6.0d 3‐Jul‐11 10‐Jul‐11
Bypass Line
Long Lead Items ‐ LLI
Piping
Ball Valves: 20" & 24"
Expected Time of Arrival (ETA) to Project Site 12.0d 26‐Sep‐11 10‐Oct‐11
Critical Items
Piping
Carbon Steel Pipe ‐ 20"
Expected Time of Arrival (ETA) to Project Site 14.0d 15‐Aug‐11 31‐Aug‐11
Flanges ‐ 20" & Below (MSTCC)
Expected Time of Arrival (ETA) to Project Site 8.0d 30‐Jun‐11 10‐Jul‐11
Instrumentation
Temperature Instruments
Expected Time of Arrival (ETA) to Project Site 6.0d 18‐Aug‐11 25‐Aug‐11
Orifice Flange Assembly
Expected Time of Arrival (ETA) to Project Site 12.0d 8‐Aug‐11 22‐Aug‐11
Straightening Vane
Expected Time of Arrival (ETA) to Project Site 12.0d 14‐Aug‐11 28‐Aug‐11
Remote Terminal Unit ‐ RTU
Expected Time of Arrival (ETA) to Project Site 10.0d 19‐Jul‐11 31‐Jul‐11
Flow Computer
Expected Time of Arrival (ETA) to Project Site 6.0d 11‐Aug‐11 18‐Aug‐11
Bulk Items
Piping
Butt Weld Fittings: 24" & Below (MSTCC)
Expected Time of Arrival (ETA) to Project Site 6.0d 4‐Jul‐11 11‐Jul‐11
Threaded/ Socket Weld Valve (MSTCC)
Expected Time of Arrival (ETA) to Project Site 6.0d 23‐Jul‐11 30‐Jul‐11
Threaded/ Socket Weld Fittings (MSTCC)
Expected Time of Arrival (ETA) to Project Site 6.0d 2‐Jun‐11 9‐Jun‐11
Stud & Machine Bolts (MSTCC)
Expected Time of Arrival (ETA) to Project Site 6.0d 26‐May‐11 2‐Jun‐11
Gaskets (MSTCC)
Expected Time of Arrival (ETA) to Project Site 6.0d 29‐May‐11 5‐Jun‐11