COLUMN AND FOOTING SCHEDULE FOR PROPOSED FLAT AT ANAND, GUNJ AREA
SCHEDULE OF FOOTINGS
SR.
COLUMN COL. FOOTING PEDESTAL FOOT. EDGE R/F
NO.
NO. SIZE SQ. SIZE SIZE DEPTH DEPTH BOTH WAYS
CA X CB L" X B" " D" d"
1 C16, C17 12" X 24" 7'6" X 8'6" 18" X 30" 30" 12" 10F- 3" C/C
2 C10, C12, C15, C18, C23 12" X 24" 7'6" X 8'0" 18" X 30" 27" 12" 10F- 3" C/C
3 C5, C6, C9, C21, C22, C24 12" X 24" 7'0" X 8'0" 18" X 30" 27" 12" 10F- 3" C/C
4 C1, C2, C7, C11, C13, C14 12" X 24" 6'6"X7'6" 18" X 30" 24" 9" 10F- 4" C/C
5 C3, C4, C8, 19 12" X 24" 5'0"X6'0" 18" X 30" 21" 9" 10F- 4" C/C
6 C20, C25 24" DIA 7'0"X7'0" 18" X 30" 24" 9" 10F- 4" C/C
CA X CB " C/C
8F-4"/6"
2 C11, C15, C18 {3} 12" X 24" 14 -16F
3Nos.
C1, C4, C5, C8, C14, C16,
8F-4"/6"
3 C17, C19, C21, C22, C23, 12" X 24" 16 -16F
3Nos.
C24 {12}
8F-4"/6"
6 C20, C25 {2} 24" DIA 14 -20F
3Nos.
7 LIFT CABIN 8" TH 10F, 6" C/C B/W
* USE M20 CONCRETE FOR ALL THE COLUMNS AND FOOTINGS.
Page 1