Primavera P6 Project Management R efe rence Manua l

Preface xix

Table of Contents

Preface ....................................................................... Primavera Products ................................................. Using Documentation and Help.............................. Where to Get Support ............................................. Part 1: Overview and Configuration Understanding Project Management..................... 3 Why Use Project Portfolio Management? ........... 4 Your Role in the Organization .............................. 5 Project Management Process Overview .............. 8 Planning, Controlling, and Managing Projects ... 10 Quick Tour............................................................. 13 Getting Started .................................................... 14 Selecting a Language .......................................... 17 The Workspace .................................................. 18

Preface xix

What Is a Layout? ............................................... 21 Customizing Displays ......................................... 23 Sample Layouts .................................................. 25 Using Wizards..................................................... 27 Defining Administrative Preferences and Categories Defining Default Settings .................................. 30 Defining Standard Categories and Values ......... 40 Defining Currencies ............................................ 46 Setting User Preferences ....................................... 49 Formatting Time Units........................................ 50 Formatting Dates ................................................ 52 Setting View Currency and Symbols .................. 53 Setting Mail Preferences ..................................... 54 Implementing Wizards........................................ 55

29

Creating a Log of Tasks and Setting Startup, Group and Sort, and Column Options 56 Changing Your Password .................................... 58 Setting Profile and Spreadsheet Data Options .... 59 Setting Calculation Options for Resource and Role Assignments......................................................... 61 Selecting Startup Filters....................................... 63 Part 2: Structuring Projects Setting Up the Enterprise Project Structure....... 67 Enterprise Project Structure Overview ................ 68 Setting Up the Enterprise Project Structure ......... 75 Adding a New Project to the Enterprise Project Structure ............................................................................. 77

Preface xix

Using Project Architect........................................ 79 Working with the Enterprise Project Structure ... 84 Defining Enterprise Project Structure Details...... 89 Setting Up the Organizational Breakdown Structure 97 The OBS .............................................................. 98 Viewing an OBS ................................................ 101 Setting Up an OBS............................................. 103 Editing OBS Elements ...................................... 106 Defining Resources and Roles ............................ 109 Resources Overview .......................................... 110 Viewing and Adding Resources......................... 111 Defining Resource Shifts .................................. 118 Defining and Assigning Resource Codes and Values 119 Setting Up Roles ............................................... 122 Assigning Roles to Resources............................ 127 Defining Custom Resource Curves.................... 129 Reviewing Work Breakdown Structures .......... 133 The WBS ........................................................... 134 Viewing a WBS ................................................. 136 Grouping by WBS Path ..................................... 138 Adding WBS Elements and Assigning Properties139 Using WBS Milestones...................................... 143 Assigning WBS Category Values...................... 145 Defining Earned Value Settings for Specific WBS Elements ........................................................................... 146 Assigning Estimation Weights to WBS Elements 148 Defining Budgets.................................................. 151 Tracking Budget Changes.................................... 159 Establishing Funding ........................................... 161

Preface xix

Tracking and Analyzing Budgets ........................ 164 Establishing Project Codes ................................... 165 Defining and Assigning Project Codes ................ 166 Grouping, Summarizing, and Filtering by Codes 170 Working With User-Defined Fields ..................... 175 Creating User-Defined Fields .............................. 176 Working with User-Defined Fields...................... 178 Working with Indicators ..................................... 180 Creating Calendars ............................................... 183 Adding Calendars ............................................... 184 Modifying Calendars .......................................... 186 Part 3: Implementing the Schedule Establishing Activity Codes ................................. 193 Creating Activity Codes and Values.................... 194 Grouping and Summarizing by Codes................. 198 Working with Activities ........................................ 201 Activities Overview ............................................ 202 Adding Activities................................................. 203 Defining General Activity Information .............. 205 Defining Schedule Information ........................... 209 Establishing Relationships................................... 213 Displaying Activity Details for Assignments ...... 218 Assigning Resources and Roles ........................... 219 Assigning Resource Curves to Resource or Role Assignments ............................................................................. 223 Manually Planning Future Period Assignments . 224 Assigning Activity Codes and Adding Expenses 230 Viewing Activity Feedback and Posting Resource Notes 232 Assigning Work Products and Documents ......... 234

Preface xix

Adding Steps........................................................ 235 Creating and Assigning Activity Step Templates 237 Viewing Activity Summaries............................... 240 Viewing Contract Manager Documents............... 241 Using Global Change........................................... 242 Working with Cost Accounts and Project Expenses Cost Account and Expense Overview ................. 248 Setting Up a Cost Account Structure ................... 249 Adding Expenses and Entering Cost Information 253 Defining Expense Details ................................... 256 Analyzing Costs................................................... 258

247

Performing Top-down Estimation ..................... 261 Performing Top-down Estimation ...................... 262 Applying Saved Top-Down Estimates To a Project 266 Part 4: Updating and Managing the Schedule Managing Baselines ............................................ 271 Creating and Maintaining Baselines .................. 272 Assigning Baselines to Projects .......................... 276 Comparing Current and Baseline Schedules....... 278 Updating Baselines ............................................ 280 Updating, Scheduling, and Leveling .................. 283 The Update Process ............................................ 284 Choosing a Method of Updating......................... 286 Highlighting Activities for Updating ................. 288 Updating Progress for Spotlighted Activities .... 290 Estimating Progress Automatically..................... 292

Preface xix

Updating Using Timesheets ............................... 295 Updating Activities Manually............................. 297 Interrupting Activity Progress ............................ 303 Applying Actuals ............................................... 305 Storing Period Performance (Past Period Actuals) 307 Scheduling Projects............................................. 311 Leveling Resources ............................................ 317 Recalculating Resource and Role Assignment Costs 321 Managing Resource Assignments....................... 323 Summarizing Projects ........................................ 325 Setting Summarization Options ......................... 326 Summarizing Project Data .................................. 327 Managing Risks .................................................... 335 Adding Risks ...................................................... 336 Calculating Exposure Values ............................. 338 Calculating a Risks Impact ............................... 339 Creating and Deleting Risk Types ...................... 340 Customizing Risk Layouts.................................. 341 Project Issues and Thresholds ........................... 343 Adding Issues...................................................... 344 Assigning Tracking Layouts to Issues ............... 348 Using the Is sue Navigator.................................. 349 Adding Thresholds.............................................. 350 Rest of tutorial you can obtained from CADDCENTRE.WS For any queries contact mp.jabalpurgarhard@caddcentre.ws

Preface xix

Primavera Products Primavera provides an integrated project portfolio management (PPM) solution consisting of role-specific tools to satisfy each team members needs, responsibilities, and skills. This solution uses standard Windows interfaces, client/server architecture, Webenabled technology, and stand-alone (SQL Server Express) or network-based (Oracle and Microsoft SQL Server) databases. Primavera offers the following software components: Project Management The Project Management module enables users to track and analyze performance. It is a multiuser, multiproject system with scheduling and resource control capabilities supporting multitiered project hierarchies, resource scheduling

Preface xix

with a focus on roles and skills, recording of actual data, customizable views, and userdefinable data. The module is ideal for organizations that need to simultaneously manage multiple projects and support multiuser access across a department or the entire organization. It supports an enterprise project structure (EPS) with an unlimited number of projects, activities, baselines, resources, work breakdown structures (WBS), organizational breakdown structures (OBS), user-defined codes, and critical-path-method (CPM) scheduling and resource leveling. Large-scale implementations for organization-wide project portfolio management use it with Oracle or SQL Server as the project database. For smaller implementations, you can use SQL Server Express. The module also provides centralized resource management. This includes resource timesheet approval and the ability to communicate with project resources who use the Timesheets module. In addition, the module provides integrated risk management, issue tracking, and management by threshold. The tracking feature enables users to perform dynamic cross-project rollups of cost, schedule, and earned value. Project work products and documents can be

Preface xix

assigned to activities and managed centrally. The Report Wizard creates customized reports that extract specific data from its database. Methodology Management The Methodology Management module is a system for authoring and storing methodologies, or project plan templates, in a central location. Project managers can select, combine, and tailor methodologies to create custom project plans. These customized methodologies can be imported into the Project Management module using the Project Architect wizard and used as templates for new projects. In this way, your organization can continually improve and refine methodology activities, estimates, and other information with each new project.

Timesheets Primavera also provides a Webbased interproject communication and timekeeping system. As a team-level tool for project participants, Timesheets helps team members focus on the work at hand with a simple cross-project to-do list of their upcoming assignments. It also provides views of project changes and timecards for manager

Preface xix

approval. Because team members use this module to enter up-to-the-minute information about their assignments and record time against their workloads, project leaders can make crucial project decisions with the confidence that they have the most current information possible. Primaveras Web application The Primavera Web application provides browserbased access to project, portfolio, and resource data across the organization. Every web user can create customized dashboards that provide an individualized and focused view of the specific projects and categories of project data that are most relevant to their role in managing project portfolios, projects, and resources. Project Workspaces and Workgroups extend the model of customizable, focused data views by enabling designated project team members to create a uniform team view of data that relates to one specific project or to a subset of activities within a project. The Primavera Web application provides access to a wide range of data views and features that enable Web users to manage their projects from initial concept review and approval through to completion. Primavera Integration API The Primavera Integration API is a Java-based API and server that enables developers to create client code that can seamlessly access Primaveras project

Preface xix

management functionality. Software Development Kit The Primavera Software Development Kit (SDK) enables users to integrate the data in the Project Management module database with external databases and applications. It provides access to the schema and to stored procedures that encapsulate business logic. The SDK supports the Open Database Connectivity (ODBC) standard and ODB C-compliant interfaces, such as OLE-DB and JDBC, for connecting to the project management database. The SDK must be installed on any computer that needs to integrate with the database. Claim Digger Claim Digger provides the capability to compare two projects, or a project and an associated baseline, to determine what data has been added, deleted, or modified from the schedules. Based on the data fields you select for comparison, this feature creates a project plan comparison report in one of three file formats. Claim Digger is automatically installed with the Project Management module. You can access it from the Tools menu.

Preface xix

ProjectLink ProjectLink is a plug-in that enables Microsoft Project (MSP) users to work in the MSP environment while being connected to Primavera's enterprise features. The functionality enables MSP users to open/save projects from/to the Project Management module database from within the MSP application. Moreover, MSP users have the ability to invoke Primavera's resource management within the MSP environment. ProjectLink benefits organizations that have a substantial amount of project data stored in MSP but require some users to have the additional functionality and optimized data organization available within Primavera applications Using Documentation and Help This book guides you through the process of planning and controlling projects using the Project Management module. Read the first chapter to become familiar with the process of PPM, then follow the steps in each successive chapter to build projects and project Part 1: Overview and Configuration Provides an overview of project portfolio management, simple steps for getting started quickly, and information about the standard layouts you can use to view project data. This part also provides a quick tour, including instructions for configuring administrative (module-wide) and user workstation preferences.

Preface xix

Part 2: Structuring Projects Includes the basics about the enterprise project structure (EPS) and describes how to set up this structure, add new projects to build the hierarchy, use and navigate the EPS, open existing projects, and define project properties. In addition, Part 2 describes how to Use an organizational breakdown structure (OBS) in conjunction with the EPS to ensure that each project is effectively managed and that corresponding security measures are in place Establish the personnel and equipment required to perform the work, define unlimited hierarchical resource codes for grouping and rollups, and create a standard set of roles based on skill requirements that you can assign to resources in all projects Establish and use a work breakdown structure (WBS) as the basis for the budget and spending information, specifications, and milestones within the EPS Establish project budgets and the funding sources behind them, monthly spending plans that show how budgets are distributed throughout project life cycles, and layouts that track and analyze variance as projects progress Set up project codes to categorize projects

Preface xix

for organizing, grouping, selecting, and summarizing Define custom fields that enable you to track and report project data in fields customized for your business needs Create calendars that define national and organizational holidays, project-specific work/nonworkdays, and resource vacation days

Preface xix

xviii Preface Part 3: Implementing the Schedule Describes how to define a set of codes you can use to categorize project activities for organizing, grouping, selecting, and summarizing. Part 3 also explains how to Establish the activities that compose projects and apply durations, dates, resource information, activity types, activity relationships, and other activity details Set up the expenses, or nonresource costs, associated with a project, and create global cost accounts to track activity costs and earned value according to your organizations specific cost account codes Assign estimation weights to WBS elements and activities to perform top-down estimation Part 4: Updating and Managing the Schedule Describes how to establish baseline plans against which you can track project cost, schedule, and performance data. Part 4 also explains how to Create baselines to use for comparison, summarization, and earned value reporting Update projects by applying actual dates directly to activities or by using timesheet data from the Timesheets module, and

Preface xix

how to schedule and level projects Summarize and save project data onthe-fly or at a regularly scheduled interval you specify Establish issues, or known problems within a project plan, either manually or by defining project thresholds, which monitor project data according to measures you specify Calculate the effect that a project riska concern or uncertainty about a project or one of its componentswill have on a projects schedule, costs, and durations Catalog and track all project-related documents and deliverables, and track the schedule by setting up additional layouts to monitor project status Compare projects and baselines to determine the project data that has been updated Check projects in and out of the module to maintain the most up-to-date project data possible throughout the organization

Preface xix

Part 5: Customizing Projects Describes how to customize layouts for analysis and easier data entry, and to display specific information about projects. Part 5 also describes how to produce reports that detail or summarize project information and answer key questions that arise as the project progresses. In addition, this part discusses how to publish a project on the World Wide Web and how to link and share data with Primaveras Contract Manager module. Project Management Help Provides an extensive online help system to supplement the documentation. Use Help to access general information about program options, detailed descriptions of windows and dialog boxes, and step-by-step instructions for specific project tasks. Help also includes Hint Help for column values in various windows. Access Hint Help by clicking the Display Options bar, choosing Hint Help, and then clicking a value in a column.

xx Prefac e Where to Get Support If you have a question about using Primavera products that you or your network administrator cannot resolve with information in the documentation or Help, contact Primavera Customer Support at the times and locations listed below. Please provide your Primavera product serial number when contacting Primavera. Each interaction is logged to help Primavera resolve your questions quickly. Office Time Zone Hours Address* 8:00 +1-610- +1-610- support@prima 8:00 9:00 668-3030 667-0652 vera.com 2:00 8:30 +44-20- +44-20support@pri 6:30 8:30 8563-5555 8563-5543 mavera.com Hong GMT 5:30 8:00 +852+852support@pri Kong +8 5:00 2111-8299 2111-9477 mavera.com * Primavera's Web site at http:/www.primavera.com/customer/index.asp provides support and product information, such as knowledgebases, file downloads, user group and newsgroup information, and a product enhancement request form. Bala ET Cynwyd, USA London, GMT England, Telephone FAX E-mail

In the United States, Primavera periodicaly and randomly monitors technical support cals to ensure that you receive the highest quality support. All Primavera products are backed by comprehensive support and training. To request product literature in the United States, contact your local dealer, call Primavera at 1-610-667-8600, or send your request via e-mail to info@primavera.com. In the United Kingdom, call 44-20-8563-5500 or e-mail your request to intlinfo@primavera.com.

Part 1

Overview and Configuration In this part Understanding Project Management Quick Tour Defining Administrative Preferences and Categories Setting User Preferences

Read this part to learn more about project portfolio management. Understanding Project Management

discusses Primaveras approach to managing projects. It also defines the various

organization-wide project management roles, explains how these roles can use other Primavera applications to achieve their project goals, and provides an overview of the methods used to successfully manage and control projects. Quick Tour introduces key project portfolio management concepts and explains how to perform basic tasks, such as opening a new project and using wizards.

Defining Administrative Preferences and Categories explains how to apply a series of parameters and values that apply to all projects. The Setting User Preferences chapter explains how to customize the module to fit your special needs.

Understanding Project Management Primavera software products are In this chapter designed to support the project management needs of Why Use Project Portfolio Management? organizations that manage large Your Role in the Organization numbers of projects at one time. Project Management Process
Overview Planning, Controlling, and Managing Projects

These integrated applications use project portfolio management (PPM) to support the management needs of project teams in different locations and at varying levels of the organization. This chapter provides an overview of PPM, the roles used in PPM, and the basic concepts for planning,

managing, and controlling your projects.

4 Part 1: Overview and Configuration

Why Use Project Portfolio Management? Large businesses typically have hundreds even thousandsof projects underway at one time to create the new products and services that build their future. These projects cross normal business hierarchies and chains of command, making project portfolio management (PPM) an organization-wide challenge. The pressure to complete projects on time and within budget, and maintain a competitive edge, is driving corporations to develop and implement PPM processes. They are moving away from a traditional functional structure to a multipleproject organization that must achieve clear, but urgent goals, using limited, shared resources, and they need the fastest business payback from those projects to realize potential revenue and increase shareholder equity. PPM provides comprehensive information on all projects in an organization, from executivelevel summaries to detailed plans by project. Individuals across all levels of the company can analyze, record, and communicate reliable information and make timely, informed decisions that support their corporate mission. By putting the right tool in the right hands, PPM enables an organization to

Understanding Project Management 5

Make strategic business decisions Control the minute detail that is necessary to finish projects Understand current resource demands, set priorities, and evaluate long-term staffing requirements Use skilled resources effectively and productively Reorganize projects to fit shifting priorities without sacrificing quality

Understanding Project Management 6

Your Role in the Organization By definition, PPM must meet the needs of several types of users. The following section describes the roles as they typically apply to the Primavera applications. Roles may vary or overlap depending on the organization. Network administrators Network administrators configure an organizations network environment (local- and wide-area networks) for optimal performance with Primavera applications. They install and maintain the server and client components of the applications. In addition, they manage user access to data and develop and maintain a comprehensive security policy to ensure that PPM data are protected from unauthorized access, theft, or damage. Network administrators ensure that the hardware and software supporting Primavera applications function reliably by Setting up and maintaining the network to ensure reliable connections and the fastest possible data transfer Creating and maintaining accurate lists of network resources and users so that each has a unique network identity Database administrators Database

Understanding Project Management 7

administrators (DBAs) are responsible for setting up, managing, and assigning access rights for the Primavera database. They set and oversee rules governing use of corporate databases, maintain data integrity, and set interoperability standards. Database administrators ensure reliable access to the Primavera database by Installing, configuring, and upgrading database server software and related products as required Creating and implementing the database Implementing and maintaining database security, including creating and maintaining users, roles, and privileges for the database Monitoring database performance and tuning as needed Planning for growth and changes and establishing and maintaining backup and recovery policies and procedures

Understanding Project Management 8

Operations executives Operations executives are responsible for strategic planning and ongoing performance analysis. They use the Project Management module and Primaveras Web Portfolio Management application to analyze schedule, resource, and cost data across projects. Senior executives may be responsible for Prioritizing projects The profit/loss for a specific business entity Funding and go/no-go decisions about projects Strategic planning over the future of the business or division Project controls coordinators Project controls coordinators are responsible for ensuring that Primavera applications are implemented properly and operate smoothly. They play a key role during implementation by Working with operations executives and program/project managers to set up methodologies in the Methodology Management module Working with operations executives and

Understanding Project Management 9

program/project managers to structure project, organizational breakdown structure (OBS), and resource hierarchies, set up basic calendars, and define organizationwide custom fields and codes in the Project Management module Working with the project administrator to create user accounts and user groups for the Project Management module Assigning security rights to users in the Project Management module Program managers Program managers oversee several high-level project managers; they are responsible for multiple projects and use the Project Management and Methodology Management modules, along with Primaveras Web application to: Perform cross-project analysis Manage projects to on-time and on-budget completion Prioritize resources across projects Plan projects before they are funded

Understanding Project Management 10

Project managers Project managers manage multiple small, repetitive projects or a single, complex project. They are responsible for ontime/onbudget completion of the projects and use the Project Management module and Primavera Web application to Allocate specific named resources to a project in conjunction with the functional manager of those resources Communicate project information both up and down the chain of command Manage resources related to the project Resource/cost managers Resource managers allocate resources across projects and distribute their workloads. They are responsible for resource planning, including recruiting, hiring, and training resources, and they may be responsible for loading resource information in the Project Management, Methodology Management, and Web Resource Management modules. Cost managers perform detailed financial analysis of projects, handle project billing, and integrate financial information within the company. Team leaders Team leaders manage the work for a portion of a larger project. They are managers who produce work and manage a team, and they often use the Project

Understanding Project Management 11

Management and Timesheets modules, and the Primavera Web application, to prioritize shortterm tasks or objectives, typically when the duration is less than the planning period of the project. Team members Team members are trained in a specific skill required on a project. They work with their manager to develop activities and durations for incorporation into the schedule. Once activities are added to the schedule, team members update them using the Timesheets module to indicate the work they performed during designated accounting periods. Team members may also use personalized dashboards in the Primavera Web application to quickly access their projects, activities, documents, and events.

12 Part 2: Structuring Projects

Project Management Process Overview When contractors develop plans for a building, one of the first steps is laying a foundation. This is also a true for building projects using the Project Management module. The hierarchical structuring of data serves as the foundation before the addition of actual project data. The following is a suggested sequence for setting up these structures: Set up the organizational structure (OBS), which is the arrangement of your management structure, either individuals. breakdown hierarchical companys as roles or

Set up the enterprise project structure (EPS), which is the hierarchical structure that identifies the company-wide projects and enables organization and management of those projects in your organization. Set up a resource hierarchy that reflects your organizations resource structure and supports the assignment of resources to activities. For each project, set up the work breakdown structure (WBS), which is a hierarchical arrangement of the products and services produced during and by a

project. For information about setting up security, see the Administrators Guide. Project controls coordinators, working with operations executives and program/project managers, structure the OBS and EPS hierarchies. Setting up the OBS first enables association of the responsible managers with their areas of the EPSeither nodes or Once the OBS is established, the EPS can be set up. An EPS can consist of multiple root nodes, which enable particular types of projects to be grouped together, such as project templates or high-risk projects. Within each root node, you can further break down an EPS into multiple EPS nodes, such as Capital Improvement projects and Manufacturing projects, to categorize the types of templates projects.

The Workspace When you first open a project, the Home workspace displays the main functions available in the module. For example, click Activities to focus on activity data and customize layouts. The workspace for each main window consists of a menu bar, navigation bar, directory bar, toolbar, and command bar.

Assigning Estimation Weights to WBS Elements You can assign estimation weights to work breakdown structure (WBS) elements and activities to perform Top-down estimation. You can assign estimation weights directly in the Project Management module or import them from the Methodology Management module using Project Architect. The Project Management module uses the estimation weights to calculate the number of units that each WBS element receives in relation to its lower-level elements in the WBS hierarchy. For example, if 1,000 days of labor are applied top down to three WBS elements with estimation weights of 30, 30, and 40, then Top-down estimation uses the WBS Estimated Weight field to determine how to push down the units within each branch of the WBS. The algorithm is: WBS 1.1 Weight WBS 1.1 Units = Sum of All WBS Weights at WBS Level x Est Units where: WBS 1.1 Weight = Weight of WBS 1.1 WBS 1.1 Units = Number of Units Allocated to WBS Element 1.1

Sum of All WBS Weights at WBS Level = Sum of Weight of All WBSs at Same Level of Hierarchy as WBS 1.1 Est Units = Number of Estimated Units Distributed Among All WBSs at WBS Level 1.N For example, if you select a WBS with three, level-one WBS elements beneath it, and each of those elements has a weight of 1 with an estimate of 100 days, the module calculates each WBS as having 33.3 days, as follows: 1_ Units = 1 + 1 + 1 x 100d = 33.3d Alternatively, if the weights for each WBS element vary, such as 6 for one element and 2 each for the other two elements, the result is 60 days for the first element, and 20 days each for the other two elements: Units = 6 + 2 + 2 x 100d=60d

Reviewing Work Breakdown Structures 149 The algorithm continues to calculate any lower-level WBS elements in the WBS branch to distribute the units accordingly. This process continues until all WBS levels in the branch have been considered; it then continues with the next branch in the hierarchy. The module ignores any WBS element that does not have activity assignments when distributing units within a branch of the WBS. If an activity has multiple resources assigned, If an activity is completed, that activity is alocated zero remaining units. If al activities

Assign estimation weights to WBS elements Choose Project, WBS. Click the Display Options bar, then choose Columns, Customize. In the Est Weight column, enter the applicable weights for each element listed.