Escolar Documentos
Profissional Documentos
Cultura Documentos
d industrial customers through a system of wires (overhead) or cables (underground), switches, protection & control devices and transformers
Sheathing Cores Wires Testing and Packing Bunching Stranding Insulation Finished Cables
Conductor
Wires
Wires
Cores Wires
Bunching Stranding
Insulation
Conductor
Cores Wires
Bunching Stranding
Insulation
Conductor
Bunching Stranding
Conductor
Manufacturing Process
Quality treated wooden / steel Drums for winding the finished cables before final testing & delivery.
Conductor (CU / AL) Drawing Sheathing Taping Laid Up Cables Laying Up (For Multi Core) Sheathing Cores Wires Testing and Packing Bunching Stranding Insulation Finished Cables Inner Sheathed cables Armouring Armoured Cables
Conductor
Emphasis On Design
Four major parameters of cable design to illustrate the proper design Conductor Insulation Armouring Sheathing
Conductor
The heart of the cable is the Conductor.
Conductor
Example of selection of the no of strands in a conductor. WHY 19 STRANDS ARE REQUIRED FOR 70 SQ.MM. CONDUCTOR? NO OF STRAND:-19 SIZE:-2.24mm
d =2.24mm.
d=PITCH CIRCULAR DIAMETER FOR FIRST LAYER = 2X2.24mm = 4.48mm NO. OF WIRES IN FIRST LAYER = dX3.14/d = 4.48X3.14/2.24 6 WIRE
d =2Xd
Conductor
NO. OF WIRES ACCOMODATED IN FIRST LAYER = 6
1 1 0 1 1
d =PITCH CIRCULAR DIAMETER FOR SECOND LAYER = 4X2.24mm =8.96mm NO. OF WIRES IN FIRST LAYER = dX3.14/d = 8.96X3.14/2.24 2 12WIRE
1 1
2 2 2 1 1 2 2 1 0 1 2 2 1 1 2 2 2 2
Conductor
When conductors are not properly shaped, they have gaps , sharp edges in between the wires, which may lead to failures , after a period of time.
Conductor
If the compaction is not proper, it can lead to air gaps, which increase conductor resistance.
A Bad Design of Conductor Can Cause 3% to 9% Transmission loss,Failure due to Sharp Edges.
Insulation
A good Insulation should have: High insulation resistance High dielectric strength Good mechanical properties Tenacity & elasticity should not be affected by chemicals. Should be non hygroscopic.
Insulation
Uniformity of Insulation Thickness & Eccentricity Avoids increase in charging current and lessens the voltage drop If dielectric is not uniform, it leads to increase in the capacitance of the conductor and resultant higher temperature.
Armouring
Apart from mechanical protection, an important feature of Armour design is to provide effective conductance of earth fault current. When designing an armoured cable, the selection of minimum number of armour wire/strips plays a very important role
Armouring
Example : 3.5 C X 240 SQ.MM A2XFY cable. Min. 34 strips require for 100% coverage. And with this the armour resistance at 20 C will be 1.62 ohm/km & short circuit current carrying capacity will be 4.2 kA/Sec, where as the Max requirement as per IS 7098 part I is 1.64 ohm/km If we use 30 strips in place of 34, there will be a gap and the armour resistance will be increased to 1.79 ohm/km & short circuit current carrying capacity will come down to 3.7 kA/sec
Armouring
Armouring protects the cable from mechanical damage. Maintain minimum 95% coverage to protect the cable from any mechanical damage because of sharp edges. Badly Armoured Cables
Outer Sheathing
This Protects the Overall Cable Embossing / printing options on the outer sheath.
Emphasis On Quality
Stringent Quality checks at each and every level. Raw materials. In Process. Finished goods.
Emphasis On Quality
Raw Material Testing The major raw materials in a Cable are : Copper/Aluminium Rods PVC/XLPE Compounds Armour Wires/Strips
Aluminium Rods
Emphasis On Quality
In process quality checks are performed at each and every stage of manufacturing Stage wise details of Quality checks performed are shown in the next set of folios.
Emphasis On Quality
Packing & Marking Testing of End sealing. Testing of packing and wooden drums Inspection for marking and scripts Packing Drums
Planning
Cable installation involves selection of cable route, mode of installation i.e. underground, in duct or cable ladder/ trays, associated accessories and man power For cable laying it is very essential to get acquainted with the visible as well as hidden obstacles and following activities are recommended prior to the actual laying work Inspection of cable route Trial holes to check thermal resistivity & underground obstacles. Excavation (Trenching) & preparation of cable bed Laying of necessary pipes Drum handling & cable pulling equipment including pay off jacks Arrangement of filling. Back filling
Trial Holes:
After inspection of the cable route, it is advisable to have the knowledge of the underground obstruction. Trial holes are generally taken at every 50 meters interval along the planned cable route up to 10 cm below the planned depth of laying. The route is then inspected for underground obstruction e.g. water lines, drainage lines, telephone cables, power cables or other utilities etc. After this the cable route is finalized keeping in view that it should be straight as far as possible and proper depth is permissible. It is then marked suitably for trenching
Excavation work
After proper marking of the route, the excavation is started. Generally excavation is done manually, however, depending on the terrain other methods such as mechanical force, thrust bore or trench ploughing can be employed. Compressed air tools are used for breaking rocks & excavation across road.
Depth of laying
As a general rule, the desired depth of cable for underground laying is as under LV Power & Control cables : 0.75 m HV Power cables up to 11 kV : 0.9 m HV Power cable 22 & 33 kV : 1.05 m EHV Power cable : 1.2 m The actual depth of laying is, however, decided depending on the under ground obstacles. The deeper laying cause reduction on current carrying capacity.
Clearances :
The desired minimum clearances are as under Power to Control cables : 0.2 m Power to communication cables : 0.3 m Power cables to gas/water main : 0.3 m Inductive influence on sensitive control cable on account of near by power cable should also be checked.
Width of trench :
The width of trench depends on no & diameter of cables to be laid. For HV & EHV cables the width of excavation is generally as under No. of Cables HV Cables EHV Cables 3 0.65 m 0.8 m 4 0.85 m 1.05 m
Sand bedding:
Sand bedding of minimum 10 cm is provided for the cables laid directly in ground for protection. The grain size of sand should preferably be less than 8 mm. The material with high volume weight ratio has a good distribution among grain sizes and it has normally low thermal resistivity, even when it has lower moisture.
Pulling of cable:
The cable drum shall be placed such that there is minimum inconvenience. Cable drum is normally placed on jacks at starting point, in such a way that direction arrow points to the opposite direction of the pulling, and a wire winch at the other end of the pulling distance of the trench. The pulling wire can be connected to the cable either by a cable stocking or directly to the conductor in such a manner that water or soil cannot enter the cable. Except for wire armoured cables, the cable is normally pulled by the conductor with pulling force limiting to the following Aluminum conductor : 30 N/mm2 Copper conductor : 50 N/mm2 The cable should be pulled from the top of the drum. To prevent crossing of turns on the drum due to sudden stop in pulling, a brake should be arranged at the cable drum as shown in figure and a man should be placed there to operate this brake rapidly.
Pulling of cable:
With temperature below 30C, the cables should be warmed before the laying out, otherwise the bending can damage the insulation/protective covering of cables. The cable laying should be carried out swiftly so that the cable does not cool down too much. Warming of cable may be achieved by storing the cable drum for adequately longer period, not less than 24 hours, in a heated building or in a tent with hot air heaters To protect the cable from damage during pulling out, cable rollers should be used, placed at suitable intervals. Bends must be arranged very carefully and cable is not allowed to bend beyond the limit specified as mention here under. Closely spaced and well fixed angle rollers are skid plates should be used at all corners
Pulling of cable:
MINIMUM PERMISSIBLE BENDING RADIUS PILC Cables PVC/XLPE Cables Cable Voltage single Multi single Multi rating core core core core Up to 1.1 kV 20 D 15 D 3.3 kV to 11 kV 20 D 15 D 22 kV & 33 kV 25 D 20 D Above 33 kV - - 20 D - D = outer diameter of cable 15 D 15 D 20 D 12 D 12 D 15 D
Filling:
After laying the cable, sand should be filled in the trench to completely surround the cable. The grain size of sand shall be less than 8 mm. The thickness of sand in all direction of the cable surface should normally not be less than 10 cm.
Backfilling:
Normally the backfill consists of material excavated earlier from the trench. However, bigger stones or pieces of rock should be removed.
Extra protection:
Important feeders and cables at places where high digging activity is expected can be further protected by means of tubes, slabs or troughs The tubes of non-magnetic material are mainly used at road crossing etc. The tube diameter should not be less than 2 times the cable diameter. The current rating of cables laid in tube is reduced up to 80% of the cable rating in ground. The tubes can be filled with material e.g. Bentonite, having thermal resistivity equal to the ground, to avoid reduction in ground rating.
In trenches, normally extra protection is achieved by providing flat concrete slabs of size selected according to the expected damage. Generally slab is 50 mm thick and of sufficient width to cover the cables. The slabs are placed directly on the sand as shown here below
A very efficient protection against cable damage can be obtained by using concrete troughs. The trough should be completely filled with the sand.
The cables do not have to be bound/clamped when laid in ground. Single core cables should not be installed individually in protective steel ducts; instead all the three cores should be laid together in one single duct. Following scheme should be followed when number of single core cables are in use to ensure balanced current distribution.
BIRD CAGING
If the drum is kept on the flange or lifted from one side & cable unwound, there is all likelihood of twists in the armour, which would cause deformation of cores & outer-sheath. This process of deformation is called BIRD CAGING & is normally perceived as a manufacturing defect which is normally a HANDLING defect.
This can be prevented by unwinding the cable by loading the drum on jacks & pulling in the proper direction with stocking or pulling eye. Proper Handling of cables is very important, both from safety as well as long life of the installation.
The most common causes of cable failure are due to mishandling of the product at installation stage.
In the following slides we show you some of the effects of mishandling of the cables.
GROUP RATING FACTOR FOR SINGLE CORE CABLES LAID IN TREFOIL FORMATION
B. Cables laid on Racks/Trays in covered trench with removable covers where air circulation is restricted, trefoils are separated by 2 cable dia. horizontally and the trays are in tiers with 300 mm. gap between them.
NO. OF RACKS/TRAYS IN TIERS 1 2 3 6 NO. OF TREFOILS IN HORIZONTAL FORMATION 1 0.95 0.90 0.88 0.86 2 0.90 0.85 0.83 0.81 3 0.88 0.83 0.81 0.79
A. Cables laid in ground in horizontal formation SPACING BETWEEN TREFOILS 33 KV CABLES NUMBER OF 3.3 TO 22 KV CABLES TREFOILS IN GROUP 45 TOUCH 15 45 TOUCH 15 30 30 cm cm cm cm ING cm ING cm 2 3 4 5 0.78 0.68 0.61 0.56 0.81 0.71 0.65 0.61 0.85 0.77 0.72 0.68 0.88 0.81 0.76 0.73 0.80 0.68 0.62 0.57 0.82 0.71 0.65 0.60 0.85 0.76 0.71 0.67 0.88 0.79 0.75 0.72
NO. OF CABLES
1 0.95 0.90
2 0.90 0.85
3 0.88 0.83
6 0.85 0.81
9 0.84 0.80
1 2 3 6
3 6
0.88 0.86
0.83 0.81
0.81 0.79
0.79 0.77
0.78 0.76
B. Cables laid on cable trays exposed to air, the cables spaced by one cable diameter and trays in tiers by 300 mm. The clearance between the wall and the cables is 25 mm.
NO. OF CABLES 1 1 1 1 1 2 0.98 0.95 0.94 0.93 3 0.96 0.93 0.92 0.90 6 0.93 0.90 0.89 0.87 9 0.92 0.89 0.88 0.86
SPACING OF CALBLES TOUCHING 0.79 0.69 0.62 0.58 0.54 15 cm 0.82 0.75 0.69 0.65 0.61 30 cm 0.87 0.79 0.74 0.72 0.69 45 cm 0.90 0.83 0.79 0.76 0.75
RATING FACTOR
C. Rating factors for depth of laying A. Rating factors for ambient air temperature variation ( for cables laid direct in the ground)
25
30
35
40
45
50
1.14
1.10
1.04
1.00
0.95
0.90
D. Rating factors for variation in Thermal Resistivity of soil THERMAL RESISTIVITY OF SOIL (ccm/w) FACTOR
15
20
25
30
35
40
45
100
120
150
200
250
300
1.12
1.08
1.03
1.00
0.96
0.91
CABLE ACCESSORIES
SEPARABLE CONNECTORS LOADBREAK DEADBREAK OTHER CONNECTORS CABLE JOINTS CABLE TERMINATIONS
While Cable Basics uses the Cable Termination as the base example, the same principles apply anywhere a shielded medium or high voltage cable is terminated. Elbows, Joints, etc.
Conductor
+ Conductor shield
Conductor
+ Insulation
+ Conductor shield
Conductor
+ Semi-Con Shield
+ Insulation
+ Conductor shield
Conductor
The addition of a stress control tube tends to smooth the stress concentrations in case of heat shrink terminations
Thank You