ID 1 2 3 4 5 6 7 8 9 10 11 12 13

Task Name Amaya Alpha to be dismantle all the utilities line Amaya Beta Move in and positioning - CDA & PN2 Piping Installation - SiH4, NH3 & NF3 Piping Installation Testing & Certification

Duration 25 days 5 days 5 days 7 days 5 days

Start Mon 12/9/11 Mon 24/10/11 Mon 31/10/11 Thu 3/11/11 Mon 14/11/11

Finish Fri 14/10/11 Fri 28/10/11 Fri 4/11/11 Fri 11/11/11

Predecessors

Resource Names

Sep '11 11 Sep '11 18 Sep '11 25 Sep '11 2 Oct '11 9 Oct '11 16 Oct '11 23 Oct '11 30 Oct '11 6 Nov '11 13 Nov '11 20 No MTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMT 0% 0% 0% 0% 0%

Fri 18/11/11 4

PCW Piping Installation - Testing & Certification

2 days 1 day

Mon 7/11/11 Wed 9/11/11

Tue 8/11/11 3 Wed 9/11/11 7

0% 0%

General & Scrubber Exhaust Installation

5 days

Mon 7/11/11

Fri 11/11/11

0%

Electrical Cabling - Testing & Certification

3 days 2 days

Mon 7/11/11 Thu 10/11/11

Wed 9/11/11 Fri 11/11/11 12

0% 0%

Critical
Project: Amaya Schedule Date: Wed 24/8/11

Task Split Task Progress

Baseline Baseline Split Baseline Milestone


Page 1

Milestone Summary Progress Summary

Project Summary External Tasks External Milestone

Deadline

Critical Split Critical Progress