INTERNAL QUALITY / ENVIRONMENTAL & SAFETY AUDIT SCHEDULE YEAR : 2009

X REF NUMBER

DOC No. Rev. No Date

QA 17-03 0 02/01/07

QUALITY SYSTEM PROCEDURES

Responsibility

JAN

FEB

MAR

APR

MAY

JUNE

JULY

AUG

SEPT

OCT

NOV

DEC

1 2 3 4 5 6 7 8 9 10 11 12

Quality System Audit (all departments) and management Review process Process Audit Internal Product Audit External Audits Environmental Audit Legal & Other Requirements Audit Management Review Meeting Safety Audit Review of Customer Specific Requirements (Formula Q) Suppliers Product Audit Review of Quality Manual MSA Study

Man Man Operator SABS Man Man Man Team Man Man Supplier Q.M

U U X

X X X X X X

X N/A X X N/A X X X X O RE - SCHEDULED U Unscheduled Audit Note:- Process Audit will cover All shifts

X SCHEDULED

Approved by:

Ian Pearce. Quality Manager


C : Bonding Mode: FORMS QA 17-03