S U p p ly c H a i n
Figure 1.
Figure 2.
leading to higher orders at the end of month. So, returning to my question, what level would you design the system for? Middle of the trend line, top of the trend line, or do you still need more information?
Figure 3.
picking velocity
The most prominent driver of warehouse design is velocity. Velocity is the rate at which goods flow through a warehouse. In the ensuing case study, we consider picking velocity which is normally measured in terms of bin hits per day. By definition, a bin hit is a visit by an order picker to a picking location, whereupon a product is picked in single or multiple units. Our exercise covers July 2011 data from Hogwartz Enterprises, suppliers of sporting equipment to Quidditch Players. Data was downloaded from the Hogwartz ERP system and is graphed in Figure 1. From the chart, for what quantity of bin hits per day would you design an order picking system? I sincerely hope you said need more information or let me check that data more closely. However, if you already have an answer, read on to check your assumptions.
STATISTICS
minimum maximum mean Std Deviation range No of Days
table 1.
UnITS
1,137 4,970 3,359 1,105 3,833 27
endless aspects of life, including warehousing, the aggregate of random events tend to follow the shape of the bell curve. By now, nausea will be setting in, so why I am telling you this? Simple! This predictive model will save you both money and angst. Read on.
cost of system
Suppose you wish to obtain a quotation for your picking system. You ask the supplier to quote for a system to handle your maximum bin hits per day, i.e. 4,970 bin hits. Its price is $3m. With this system you can handle any surge in picking up to your maximum. You proudly tell Ellerby, who turns white and tells you in colourful language to find something cheaper, or find another job. With wilting self-esteem, you ask the supplier to quote for a system to handle your average bin hits i.e. 3,359. Its price is $1m. You advise Ellerby and his colour returns, but quizzes
Order patterns
Mr Ellerby, who is the manufacturing director at Hogwartz, advises that most of the orders are picked at the end of the month. Whats your view? To assist, I have added a linear trend line using the mathematical method of least squares (Figure 2). This method was developed by Carl Friedrich Gauss in 1794. Dont worry, his work is entombed in standard Excel spread sheets and there is no need to crunch numbers to use it. But the results bring clarity and vindicate Ellerbys statement. There is a definite trend
34 mHD SUPPLY CHAIN SOLUTIONS
S U p p ly c H a i n
35
you about system performance. You do some mental arithmetic and tell him that for 50% of the time it will cope without adding extra labour. But for the other 50% you will need to add resources to complete your daily picking task. Ellerby is not happy. What do you do? You review your mean and standard deviation and calculate the 84.2% level of operation. How? The mean is 3,359 hits per day. To this you add your standard deviation of 1,105 giving a total of 4,464 hits per day. You figure from the bell curve that at the 4,464 hits per day design level, your system will meet 84.2% of your daily picking tasks. See Figure 3. For the remaining 15.8% of times, i.e. five days per month, you will need to add extra resources. You decide that this is an easy addition and will cause no financial or operational stress. You get on the phone and ask your supplier to quote for a system to meet the 84.2% performance level. The quote is for $1.4m. With this information you compare the marginal capital cost for each design level against the marginal labour cost benefit. Suddenly you see things in a new dimension. Alas, you will not achieve a marginal
payback from installing the maximum level system, for over 11 years. But with the system designed to the 84.2% performance level, you marginal payback is within 1 year. This will meet both the capital budget of Howgartz, and achieve the substantial productivity boost you need. You are so elated that you eagerly update your graph with the maximum, average plus standard deviation and average design levels, along with the quoted capital costs. You approach Ellerby with confidence, tell him you are going to save Hogwartz $1.6m and are satisfied that you will achieve your daily picking with eight people plus an additional two to cover peak periods. Ellerby is pleased, knowing that delivery of Quidditch accessories is in good stewardship. So what does all this prove? If you are confused, dazed and delirious from such heavy deciphering, please allow me to conclude by explaining the lessons learned. Firstly, use of averages for design purposes is perilous. (This is the most common mistake warehouse designers can make and should be avoided.) Secondly, check your data using the mean and standard deviation in order to really
understand what is happening. Thirdly, beware of the high capital cost of designing for peaks, as opposed to designing for the majority of occurrences. Fourthly, check the marginal cost and benefit for solution comparisons, before making your decision. I trust this has helped you to be more astute in your warehouse analysis and design. However, should you have any rebuffs, questions, or complaints, please drop me a line. this article is an extract from mals warehousing design workshop given at Smart conference 2011. mal Walker is manager, consulting with logistics bureau, where he leads the Warehousing and Distribution centre Design practice. He works with local and international organisations and has over 30 years experience in warehouse design and performance and holds qualifications in engineering, logistics and business administration. If you would like a free download of the warehousing chapter from the new book Supply chain Secrets, visit www.logisticsbureau.com/ picking. this chapter has lots more great tips and advice. contact mal at mwalker@logisticsbureau.com or call 0412 271 503.
CONVEYOR TECHNOLOGIES PTY LTD Designers & Manufacturers of Conveyor Systems and Equipment.
ABN 17 089 670 557
Making it Work
Making it Pay
SYDNEY Head Office & Factory 6-8 Amour Street, Milperra, NSW 2214 P.O. Box 225, North Revesby, NSW 2212 Phone: (02) 9771 4655 Fax: (02) 9771 3682 Email: sales@adeptconveyor.com.au MELBOURNE OFFICE Unit 1, 116 National Boulevard, Campbellfield, VIC 3061 Phone: (03) 9357 8814 Fax: (03) 9357 8105
Doing it Righ t
Copyright of MHD Supply Chain Solutions is the property of Intermedia Group Pty Ltd and its content may not be copied or emailed to multiple sites or posted to a listserv without the copyright holder's express written permission. However, users may print, download, or email articles for individual use.