Você está na página 1de 9

DOCUMENT TITLE:

METHOD STATEMENT FOR PNEUMATIC TESTING FOR PIPING SYSTEM

CONTRACTOR :

SEA GULF OIL & GAS DEVELOPMENT COMPANY


P.O. BOX: 92714, DOHA QATAR TEL: 00974 44604964 FAX: 00974 44582528 Email: hasifm@seagulfwll.com Website: www.seagulfwll.com
REV. NO. DATE REASON FOR REVISION ISSUE FOR COMMENTS PREPARED HYDROTEST ENGINEER REVIEWED CONSTRUCTIO N MANAGER APPROVED APPD.

PROJECT MANAGER

METHOD STATEMENT FOR PNEUMATIC TESTING FOR PIPING SYSTEMS

TABLE OF CONTENTS
METHOD STATEMENT FOR ........................................................................................ 1 1 INTRODUCTION ........................................................................................................ 3 1.1 SCOPE .................................................................................................................. 3 1.2 LIAISONS/COMMUNICATIONS ........................................................................... 3 1.3 REFERENCES ...................................................................................................... 3
1.3.1 Standards/codes/Regulations ......................................................................................... 3

2 SAFETY ...................................................................................................................... 3 1.4 GENERAL SAFETY STATEMENT........................................................................ 3 3 EQUIPMENT PRE-MOBILISATION CHECKS & FUNCTION TESTING ................... 4 4 PIPE LINE PNEUMATIC TESTING ............................................................................ 5 5 PNEUMATIC TESTING MANIFOLD CONNECTION DRAWING .............................. 9

Document No.
0051 - 1104

Revision No.
0

Date
25.03.2011

Page
2 of 9

METHOD STATEMENT FOR PNEUMATIC TESTING FOR PIPING SYSTEMS

1
1.1 SCOPE

INTRODUCTION

The Scope of this method statement is to define the methodology for Pneumatic Testing of piping system.
1.2 LIAISONS/COMMUNICATIONS

During the activity and works, there will be communicated between Project Management Team, Hydro test engineer and all personnel involved on site. 1.3 REFERENCES

1.3.1 Standards/codes/Regulations

Document No.
ASME B 31.3

Document Title
Process Piping

2
2.1 GENERAL SAFETY STATEMENT

SAFETY

The work sites safety representative will induct all personnel. Project Engineer will ensure all requirements of the permit are met before commencing works. Barriers and Warning signs will be erected to cordon off the area of testing or other hazard and only authorized personnel allowed within the area. All hoses, temporary fittings and instrument will be tested to 1.25 times of test pressure. Ensure valve status confirmed. Should any leaks occur, pressurization will be stopped, and the leak is to be isolated. If the leak cannot be isolated, the system will be depressurized to atmospheric pressure before rectification work may be allowed. Valve under pressure should be opened and closed gradually. All hoses should be secured at regular intervals to prevent flailing in the event of failure. On completion of Pneumatic testing operations, all barriers should be removed.

Document No.
0051 - 1104

Revision No.
0

Date
25.03.2011

Page
3 of 9

METHOD STATEMENT FOR PNEUMATIC TESTING FOR PIPING SYSTEMS All personnel will wear personal protective equipment at all times on the work site. Additional protective equipment will be worn in accordance with details of any hazardous substances being handled.

2.2 PROJECT SPECIFIC SAFETY REQUIRMENTS The following safety requirement will be reviewed and implemented prior to the commencement of each phase of operational activities. Prior to commencement of operations all personnel will attend a site safety meeting, and during operations they will adhere to site safety rules. All requirements are defined in the Contractor Project Construction HSE Manual shall be complied with in carrying out the works. Prior to start operation the Hydrotest Engineer will ensure that all work permit requirements have been completed and the site supervisors are aware of safety hazards. Prior to commencement of operation the test supervisor will ensure those safety equipment requirements have been identified and adequately provided. Prior to commencement of each new activity, or at each oncoming shift charge, a tool box safety talk shall be carried out by the site supervisor. Prior to commencement of new shift a hand over form shall be filled out by supervisor. All the personnel involved in the pressure testing and rigging operations shall be briefed about all the possible risks involved with the operation during the tool box meetings. As the piping systems are pressurized the area of the pressure testing shall be barricade suitably restricting the entry of personnel not involved in the testing operations. At the boundaries Notice / Sign boards shall be displayed with caution notes like System Under Pressure do not enter / Pressure Test in Progress etc. Valid test certificates by Third Party Inspection on all safety devices shall be available On completion of activity, all barriers should be removed.

EQUIPMENT PRE-MOBILISATION CHECKS & FUNCTION TESTING

The following describes the checks & function tests that will be carried out prior to mobilization to site. ITEMS
3.1 3.2

DESCRIPTION
Collate all Equipments/ Instruments certification and cross reference serial numbers against instruments. Pressure test hoses to their rated working pressure for a minimum of one hour prior to

Document No.
0051 - 1104

Revision No.
0

Date
25.03.2011

Page
4 of 9

METHOD STATEMENT FOR PNEUMATIC TESTING FOR PIPING SYSTEMS


mobilization from yard 3.3 3.4 3.5 3.6 3.7 3.8 Check instruments are indicating correct pressure compared to other instruments. Hoses shall be rated for a minimum of 1.25 times the hydrostatic pressure anticipated for the operations Check all the consumable are of the correct quantity and quality. Ensure all equipment lubricants are topped up and uncontaminated. Check setting of equipment pressure relief valve are set at appropriate pressure All test instruments shall be calibrated and certified by third party inspection with six months validity to be shown before filling and testing operations.

PIPE LINE PNEUMATIC TESTING

4.1 EXTENT OF SUPPLY


Work permits and site passes if required. Prompt inspection facilities during mobilization and on completion of each stage of operation. Clear and safe access to work areas. Construction of temporary staging/scaffolding for access to work areas and all mechanical work, such as spading, blinding etc. Flange cross over connections to facilitate temporary equipment to permanent and temporary pipeline facilities. Supervision when operating permanent valve and equipment. Communication between crews on same or adjacent work sites Lighting of work area for night work. Manifold.

4.1.1 The following hydrostatic personnel provision shall be common to all operations Discipline
Lead supervisor Supervisor Operator

Qty
1 1 2

Document No.
0051 - 1104

Revision No.
0

Date
25.03.2011

Page
5 of 9

METHOD STATEMENT FOR PNEUMATIC TESTING FOR PIPING SYSTEMS

4.2.2 The following equipment will be supplied Description


Air Cylinder 6 Manifold with & connections Pressure - Temperature recorder Set of hand tools Pressure Relief Valve Set of other valves & fittings as per test specification 20 m air hose Set of pressure gauges

Qty.
1 1 1 1 1 1 2 2

4.3 PNEUMATIC TESTING PRE JOB PREPARATIONS Item 4.3.1 4.3.2 4.3.3 4.3.4 4.3.5 4.3.6 Description ALL permanent in line instrument probes shall be removed and /or otherwise isolated Equipments will be set up at work site. Temporary barriers and warning tape will be erected around the work site. Air Cylinder / Air Compressor is properly connected to the Manifold Proper connections to be made to the manifold, Globe Valve to be connected to the inlet and outlet of the manifold Pressure relief device shall be provided, having a set pressure not higher than the test pressure plus the lesser of 345 kPa (50psi) or 10% of the test pressure pressure gauges shall be fitted Make sure that all flanged joints and threaded joints are properly tightened. Gain approval from Site Manager/Safety advisor/Clint Rep.

4.3.7 4.3.8 4.3.8

Document No.
0051 - 1104

Revision No.
0

Date
25.03.2011

Page
6 of 9

METHOD STATEMENT FOR PNEUMATIC TESTING FOR PIPING SYSTEMS 4.3.9 Before start of operation a safety meeting shall be held to discuss on topic of operating pressure hazards and precautions to safe working, highlighting as minimum the following topic: Safety Review JSAs Operation Pressure Equipment Layout Duration of operations

4.4 INITIAL PRESSURIZATION AND LEAK TEST Item 4.4.1 Description Filling and Pressurization Pressure shall be gradually increased until a gauge pressure which is the lesser of one half the test pressure or 170kPa (25psi) is attained. Which time a preliminary check shall be made, including examination of joints in accordance with para 341.4.1 (a) of ANSI B 31.3. Thereafter, the pressure shall be gradually increased in steps until the test pressure is reached, holding the pressure at each step long enough to equalize piping strains. The pressure shall then be reduced to design pressure. A leak test shall be maintained for at least 10 min, and all joints and connections shall be examined for leaks. A manual pressure relief valve shall be installed on the manifold and test pressure shall be monitored accordingly by testing Engineer / Supervisor. On reaching the test pressure, the connection of the air compressor / air cylinder shall be isolated from the system. Pressure Readings Two Calibrated pressure gauges shall be installed. Inspection Soap solution shall be applied to all threaded and/or welded joints under air pressure test. Access to all joints under test shall be provided. If any leaks are found, the line shall be depressurized completely from the location of the leak by suitably closing the valves. Necessary repair/replacement shall be carried out. All NDE to the original line class requirement are completed and approval from contractor shall be obtained before the system is retested. If the leaks are from flange / gaskets / bolting, the pressure shall be reduced to 10-20% of test pressure, before retightening of the bolts.

4.4.2 4.4.3

Document No.
0051 - 1104

Revision No.
0

Date
25.03.2011

Page
7 of 9

METHOD STATEMENT FOR PNEUMATIC TESTING FOR PIPING SYSTEMS 4.4.4 Test Records After witnessing the pressure test, all parties shall sign the Original Piping Pressure Test Report. Depressurization After successful completion of test, the line shall be depressurized by gradually opening vent valve/ depressurizing valve. Ensure that nearby erected items are not affected by heavy blow of air during depressurizing the system. Reinstatement All the items which are removed for pneumatic test, shall be reinstated and the Pipe Post test Critical Component Reinstatement shall be signed off by all the concerned. The signed format shall be passed on to the Contractors QA/QC Manager. After the reinstatement, all instruments shall be visually checked & recorded.

4.4.5

4.4.6

Document No.
0051 - 1104

Revision No.
0

Date
25.03.2011

Page
8 of 9

METHOD STATEMENT FOR PNEUMATIC TESTING FOR PIPING SYSTEMS

PNEUMATIC TESTING MANIFOLD CONNECTION DRAWING


VENT

PG FD

CR

OUTLET

INLET

6 MANIFOLD

1. PRESSURE RELIEF VALVE 2. GATE VALVE 3. NEEDLE VALVE 4. GLOBE VALVE PG PRESSURE GAUGE CR CHART RECORDER R PRESSURE REGULATOR

AIR CYLINDER

Document No.
0051 - 1104

Revision No.
0

Date
25.03.2011

Page
9 of 9

Você também pode gostar