The Department of Energy does not warrant the accuracy or suitability of this information.
2
Delays in Implementation
Capacity (GW)
2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018
Actual capacity completed has been shown to be significantly less than proposed capacity; the 2002 report listed 11,455 MW of proposed capacity for the year 2005 when only 329 MW were constructed.
Actual
4
2002 Report
2005 Report
2007 Report
2011 Report
Source: 2007 & 2011 data Ventyx Velocity Suite 2002 2005 data Previous NETL Tracking New Coal-Fired Power Plants Reports
Capacity (GW)
2007
2008
2009
2010
2011
2012
2013
2014
2015
2016
2017
2018
Total Identified Capacity Declines Due to Commissioning, Cancelations, and Fewer Postponements
Actual
Totals
5
Source: Ventyx Velocity Suite 2011 data 7/12/2011
2011
31 GW
2010
32 GW
2009
49 GW
2008
64 GW
14 GW
Number of Plants
Jul 2011
11 1 11
Capacity (MW)
Dec 2010
Net Change
-1 0 +3
Jul 2011
7,384 320 9,621
Net Change
-235 0 +3,175
12 1 8
Progressing Projects
SUB TOTAL Uncertain Potential and Timing Announced (early stages of development) TOTAL Commissioned this Period TOTAL Progressing and Commissioned
Status Listing Under Construction Near Construction Permitted Announced
6
21 36 57
-
23 30 53
2
+2 -6 -4
+2
25
+4
18,160
+3,735
Description
Project is under construction. Project has been approved; majority or all permits are obtained. Sponsor is contracting vendors and Engineering, Procurement and Construction (EPC) contractors. Site preparation has begun. In the permitting phase. Two or more permits approved or fuel or power contracts have been negotiated. Early stages of development to filing for permits. May include a feasibility study.
Source: Ventyx Velocity Suite Data reflects change between 12/13/2010 and 7/12/2011
Capacity (GW)
7 6 5
Commissioned in 2011 Oak Creek-Unit 2 (615 MW) Whelan (220 MW)
4
3 2 1 0
2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 Actual Proposed
Operational Dates
8
Source: Ventyx Velocity Suite (17/12/2011)
Proposed-Announced
14
12 10 8 6 4 2 0 2010 was the largest build since 1985
10
Source: Ventyx Velocity Suite (7/12/2011)
6
4 2 0 -2 -4
11
Source: Ventyx Velocity Suite (7/12/2011)
24% of MWs removed represent Announced projects 66% of MWs removed due to Commissioned plants
Capacity (GW)
2011
2012
2017
Removed Capacity
-1
430 MW canceled 125 MW permitted cancelled 305 MW announcements cancelled 175 MW of new announcements added
-2
Under Construction Near Construction Permitted Announced Added Announcements
Figure 6
Number of Plants
20
12
10
9 4
2 8 6
Announced Progressing
Table 2
Progressing Technology Listings Operational
(Since 2000) (Permitted, Near-, and Under Construction)
Announced
December 2010
Jul 2011
(Change)
December 2010 10 9 4 13
Jul 2011
(Change)
31 12 7 1
5 4 7 5
Source: Ventyx Velocity Suite Data collected (12/13/2010); Current Report data collected (7/12/2011)
14
15
80 70
Capacity (GW)
60 50 40 30 20 10 0
2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 Online Year Planned no date (evenly distributed
over 4 years)
17
Source: USA data - Ventyx Velocity Suite (7/12/2011) China data Platts - UDI WEPPDB June 2011
18
40 35 30 25 20 15 10
5
0 2011 2012 2013 Coal 2014 NG Wind 2015 2016 2017 2018 Nuclear
19
2011
2012
2013
2014
2015
2016
2017
Under Construction
20
Source: Ventyx Velocity Suite 12/13/2010
Near Construction
Permitted
Announced
Capacity (GW)
30 25 20 15 10 5 0
2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
Actual
Proposed
Operational Dates
21
Source: Ventyx Velocity Suite 7/12/2011
Capacity (GW)
30 25 20 15 10 5 0
2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
Actual
Proposed
Operational Dates
22
Source: Ventyx Velocity Suite 7/12/2011
Capacity (GW)
30 25 20
15
10 5 0
2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017
Actual
Proposed
Operational Dates
23
Source: Ventyx Velocity Suite 7/12/2011
Capacity (GW)
30 25 20 15 10 5 0
Watts Bar Unit 2
Construction begun in the 1970s, suspended in 1988 at 80% complete, currently revived with completion due 2012.
2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027
Actual
Proposed
Operational Dates
24
Source: Ventyx Velocity Suite 7/12/2011
Two new coal-plants totaling 835 MW were Commissioned in the first half of 2011 Progressing/Commissioned projects by July 2011 have had a net increase of 4 plants; a net change in capacity of 3,735 MW (+26%) over Progressing projects in December 2010 175 MW of new capacity has been Announced and 430 MW have been canceled
Of 430 MW canceled plants, 71% were Announced phase and 29% were Progressing
Compared to previous years, fewer projects are being Announced to offset recent Commissioning
25