Escolar Documentos
Profissional Documentos
Cultura Documentos
Disclaimer Whilst care was taken in the preparation of the information in this document, and it is provided in good faith, ENERGEX accepts no responsibility or liability (including without limitation, liability to any person by reason of negligence or negligent misstatement) for any loss or damage that may be incurred by any person acting in reliance on this information or assumptions drawn from it, except to the extent that liability under any applicable Queensland or Commonwealth of Australia statute cannot be excluded. This document has been prepared for the sole purpose of complying with ENERGEXs obligations under clause 5.6.2(f) of the National Electricity Rules and has been prepared using information provided by a number of third parties. It contains assumptions regarding, among other things, economic growth and load forecasts which may or may not prove to be correct. The forecasts included in the document involve subjective judgements and analysis which are subject to significant uncertainties and contingencies, many of which are out of the control of ENERGEX. ENERGEX makes no representation or warranty as to the accuracy, reliability, completeness or suitability for any particular purpose of the information in this document. All information should be independently investigated, reviewed, analysed and verified, and must not be relied upon in connection with any investment proposal or decision.
TABLE OF CONTENTS
1.0 INTRODUCTION ........................................................................................................................................1 2.0 EXISTING NETWORK................................................................................................................................1
Introduction ........................................................................................................................1 Approved Capex / Opex Works .........................................................................................4 Applied Service Standard ..................................................................................................4 Limitations of the Existing Network....................................................................................5
Network Options ................................................................................................................9 Non-network Options / Demand Side Solution ..................................................................9 Comparison of Options ....................................................................................................10
Scope of Proposed Works ...............................................................................................13 Impact of Proposed Works ..............................................................................................15 Project Timing Risk..........................................................................................................20 Future Network Development ..........................................................................................21
5.0 APPLICATION OF THE REGULATORY TEST.......................................................................................21 6.0 BUDGET PROVISION..............................................................................................................................22 7.0 DRAFT RECOMMENDATION .................................................................................................................22 8.0 CONSULTATION .....................................................................................................................................22
APPENDICES
Appendix 1 Additional Network Data for Proposed Works
1.0
INTRODUCTION
Buranda, West End, Annerley and East Brisbane is an inner city area of Brisbane defined by large commercial; premises, residential dwellings and significant community infrastructure such as hospitals. Three existing zone substations at West End (SSWED), Annerley (SSALY) and Wellington Road (SSWRD) supply 25,032 customers including the Mater and PA hospitals, Gabba Cricket Ground, and commercial precincts. The area is being redeveloped with projects such as the Pharmacy Australia Centre of Excellence, Gabba Central, Boggo Road development, Queensland Childrens Hospital, Southpoint Commercial Precinct and Translational Research Centre. Organic load growth and the addition of the block loads described above will generate load growth at the three existing zone substations of between 4% and 12% per annum over the next three years. There is residual load at risk (RLAR), after all load transfers, in 2010/11 at SSWED and SSSSALY and 2011/12 at SSWRD. Where Network Service Providers (NSPs), such as ENERGEX, propose to establish new large network assets to address such requirements, they are required to consult with registered participants, NEMMCO and interested parties under clause 5.6.2(f) of the National Electricity Rules (NER). This document has been prepared to comply with clause 5.6.2 of the National Electricity Rules (NER), which requires ENERGEX to: Identify future technical limitations to its network. Conduct an economic cost effectiveness analysis of possible solutions to the limitations in accordance with the Australian Electricity Regulators (AER) Regulatory Test version 3 (November 2007) for projects greater than $1 million. Consult with registered participants, NEMMCO and interested parties on possible options to address the projected limitations of ENERGEXs distribution system, where the cost of system augmentation is greater than $10 million. This project has been considered under the reliability limb of the regulatory test as per the service standards linked to the technical requirements of Schedule 5.1a of the NER. This project was previously identified in ENERGEXs Network Management Plan.
2.0
West End (SSWED), Annerley (SSALY) and Wellington Road substations (SSALY) supply 25,032 customers including the Mater and PA hospitals, Gabba Cricket Ground, and commercial precincts. The area is being redeveloped with projects such as the Pharmacy Australia Centre of Excellence, Gabba Central, Boggo Road development, Queensland Childrens Hospital, Southpoint Commercial Precinct and Translational Research Centre. Figures 1, 2 & 3 below provide geographic and schematic views of the network area under study.
Page 1
WEST END SOUTHPOINT DEVELOPMENT QLD CHILDRENS HOSPITAL BOGGO RD PRECINCT PA UPGRADE PHARMACY AUST PROJECT TRANSLATIONAL RESEARCH CENTRE
SSWRD
BURANDA
ANNERLEY
F905
SSALY
F637 F 638
F5 F5 8 4 79
SSWED
2 23 F7 231 F7
Page 2
H16 Rocklea
SST142 Tennyson
F830 F614
SSCST Charlotte St
F7232 F7231
F7196
TR3 TR2 TR1 TR4 TR3 TR2 TR1
F615 33 kV
TR7 TR6 TR4
110 kV 33 kV
11 kV
11 kV
TR1
TR2
11 kV
SSALY Annerley
Page 3
2.2
Approved works not yet commissioned within the study area include: WR44671 TSN TENNYSON - ALY ANNERLEY Replace Ageing 33 kV Cables F637, F638 and install 33kV Switchgear by October 2009. This project increases the NCC of feeders F637 and F638 to 40MV.A each and installs switchgear at SSALY i.e. prepares the network for the establishment of SSBDA.
2.3
The service standards that are applicable to a consideration of supply constraints affecting this area of study are summarised below: Zone Substations o As per ENERGEX Supply Security Standard, for urban mixed/significant C&I zone substations having greater than or equal to 5 MV.A of load, there shall be no interruption of supply during N-1 conditions.
Distribution Network o As per ENERGEX Distribution Planning Guidelines, no distribution feeder is planned to be operated above 80% of its normal cyclic capacity for a forecast 10% POE load under network normal conditions.
Page 4
2.4
2.4.1
Substation Capacity
SSWRD
SSWRD is equipped with 2 x 60MV.A 110/11kV transformers. The substation capacity is limited by the transformers, providing a normal cyclic capacity of 126MV.A. SSWRD is also equipped with 2 x 25MV.A 33/11kV transformers on hot standby. The 10 year 10% POE and 50% POE load forecasts, and the existing normal cyclic capacity (NCC), emergency cyclic capacity (ECC), 2 hour emergency capacity (2HEC) and residual load at risk (RLAR) of SSWRD, are shown below:
80 60 40 20 0
1 P OE Lo ad 0% Summer NCC 50% P OE Lo ad (SSWRD) Summer ECC (SSWRD) 2HEC RLA R 2008/09 57.40 1 26.00 54.93 69.00 75.00 0.00
Page 5
SSWED
SSWED is equipped with 2 x 60MV.A 110/11kV transformers. The substation capacity is limited by the transformers, providing a normal cyclic capacity of 126MV.A. SSWED is also equipped with 2 x 15MV.A 33/11kV transformers on hot standby. The 10 year 10% POE and 50% POE load forecasts, and the existing normal cyclic capacity (NCC), emergency cyclic capacity (ECC), 2 hour emergency capacity (2HEC) and residual load at risk (RLAR) of SSWED, are shown below:
80 60 40 20 0
1 P OE Lo ad 0% Summer NCC 50% P OE Lo ad (SSWED) Summer ECC (SSWED) Summer 2HEC RLA R 2008/09 72.70 1 26 69.80 69.00 75.00 0.00
Page 6
SSALY
SSALY is equipped with 2 x 25MV.A 33/11kV transformers. The substation capacity is limited by the transformers, providing a normal cyclic capacity of 55MV.A. The 10 year 10% POE and 50% POE load forecasts, and the existing normal cyclic capacity (NCC), emergency cyclic capacity (ECC), 2 hour emergency capacity (2HEC) and residual load at risk (RLAR) of SSWRD, are shown below:
SSALY-Load Forecast 60 50 40
MV.A
2HEC Limitation
30 20 10 0
1 P OE Lo ad (SSA LY) 0% Summer NCC (SSA LY) 50% P OE Lo ad (SSA LY) Summer ECC (SSA LY) Summer 2HEC (SSA LY) RLA R (SSA LY)
Page 7
2.4.2
400 350 300 250 Amps 200 150 100 50 0 Rating (A) Target Utilisation (A) Load (A) % of rating WED6A 379 322 370 98
Figure 7: 11kV Feeder Load Forecast (Existing Network) As outlined above, WED6A, WED10, WED4A, ALY7, ALY11, WRD17A and WRD21A exceed 80% utilisation.
Page 8
3.0
OPTIONS ANALYSIS
In the process of determining the most cost effective solution to addressing the identified network limitations, ENERGEX has sought to identify a range of technically feasible, alternative options that could satisfy the network requirements in a timely and efficient manner. Those options considered include network solutions, generation options, demand side initiatives and fuel substitution. As a result of this process, ENERGEX has identified a range of options that represent practical alternatives to addressing the network limitations. The alternative options identified through this process are examined below:
3.1
Network Options
The following options have been assessed as meeting the applied service standards.
3.1.1
This option involves establishing 2 x 33 kV feeders from SSALY, a standard double modular substation at Buranda with 2 x 33 kV switchboards, 2 x 25 MV.A 33/11 kV transformers, 2 x 11 kV switchboards, 1 x 5.4Mvar capacitor bank, 5 x 11 kV feeders and reconfiguration of existing SSWED, SSWRD and SSALY 11 kV network.
3.1.2
Disconnect 33/11kV transformers at SSWED from the 11kV bus and establish 2 x 11kV feeders from the 11kV terminals of TR1 & 2 at SSWED to Buranda substation site. Disconnect 33/11kV transformers at SSWRD from the 11kV bus and establish 2 x 11kV feeders from the 11kV terminals of TR4 & TR5 at SSWRD to Buranda substation site. Establish 11kV switchroom at Buranda substation site and reconfigure SSALY, SSWED & SSWRD 11kV distribution network.
3.1.3
Advance the construction of 110kV UG circuits from Rocklea to Woolloongabba, the Woolloongabba 110/11kV zone substation and reconfigure SSALY, SSWED & SSWRD 11kV distribution network.
3.2
In order to satisfy the Regulatory Test, ENERGEX sought to identify demand side solutions (or demand side/network combinations) that address the network limitations at a cost that was less than the proposed network solution. To be considered an alternative demand side option, the proposed solution was required to: have the capacity to defer the proposed network solution by reducing demand below the identified constraint limits, and cost less than the savings gained by deferring or removing the proposed network solution.
This analysis did not identify any feasible demand side alternative options. Options investigated were curtailable loads that are available at time of area peak customer backup generation which can be used at time of area peak installation of small scale generation
Page 9
3.3 3.3.1
A summarised comparison of the advantages and disadvantages of the alternative development options is given in the following table: Option Option 1 Establish SSBDA Advantages Disadvantages
Network Options Higher losses than option 3. Defers subsequent augmentation (ie Woolloongabba project) by 2 years. Lower losses than option 2. Greatest operational flexibility. Is consistent with development plan. Utilises existing 33kV feeder cables currently energised at 11kV. Provides most additional transfer capability between bulk supply networks. Mitigates RLAR at SSWED, SSWRD and SSALY until Woolloongabba project is completed.
Utilises 33/11kV transformers at SSWED and SSWRD. Delays SSBDA until 2012. Mitigates RLAR at SSWED, SSWRD and SSALY until Buranda project is completed Lowest losses. Delays SSBDA until 2017. Mitigates RLAR at SSWED, SSWRD and SSALY until 2017.
Limited operational flexibility i.e. loading on transformers dependant on 33kV network configuration. Highest losses. Not consistent with development plan. Not consistent with development plan. Not a likely alternative option as land is not presently available. Substation site incorporated in redevelopment site and dependant on developer progress.
Table 1: Technical Comparison of Alternative Development Options Based on the above comparison of options, the recommended development is considered to provide the optimum solution to address the forecast ECC limitations at SSWED, SSALY and SSWRD.
Page 10
3.3.2
Cost Comparison
The Regulatory Test requires ENERGEX to identify the option that minimises the present value of costs when compared with alternative options in the majority of reasonable scenarios. Accordingly a base case net present value comparison of the alternative development options has been undertaken. The financial analysis contained anticipated costs of providing, operating and maintaining the options as well as expected costs of compliance and administration associated with each option. The costs of network losses were excluded from the analysis. The table below provides an overview of the initial capital cost and net present value cost over the period of study for each of the development options. Refer to the Net Present Value sensitivity analysis in Appendix 3 for further detail, including the parameters used to develop this base case.
Option
Description
PV of Costs
Rank
NETWORK OPTION 1
Establish 33/11kV zone substation at Buranda Install 2 x feeders from WRD and 2 x feeders from WED Establish Woolloongabba 110/11kV zone substation and reconfigure 11kV Network.
$13,301,897
$93,612,526
$84,650,852
NETWORK OPTION 2
$15,315,113
$119,642,753
$101,610,45 9
NETWORK OPTION 3
$33,504,366
$93,612,526
$89,279,378
Table 2: Base Case Net Present Value Comparison The NPV comparison above includes all direct costs associated with constructing & providing the option. This includes the cost of land/easements currently owned, but not yet utilised for network augmentation.
Page 11
3.3.3
Sensitivity Comparison
Sensitivity analysis was then conducted on this base case to establish the option that remained the lowest cost option in the majority of cases considered. The table below provides the results of this analysis. Details of the parameters utilised in developing the base case and associated scenarios are included in Appendix 3. NETWORK OPTION 1 $79,169,003 ranking 2 3 4 5 6 7 8 9 10 11 12 Low WACC ranking Network CAPEX overspend ranking Network CAPEX underspend ranking Network OPEX over budget ranking Network OPEX under budget ranking NDM options CAPEX overspend ranking NDM options CAPEX underspend ranking NDM OPEX over budget ranking NDM OPEX under budget ranking Low growth scenario ranking High growth scenario ranking 1 $98,047,929 1 $93,115,937 1 $76,185,766 1 $87,307,401 1 $81,994,303 1 $84,650,852 1 $84,650,852 1 $84,650,852 1 $84,650,852 1 $74,064,998 1 $90,781,441 1 NETWORK OPTION 2 $94,217,061 3 $119,874,082 3 $111,771,505 3 $91,449,413 3 $104,738,355 2 $98,482,563 2 $121,842,694 3 $101,610,459 3 $101,610,459 3 $101,610,459 3 $88,543,987 3 $109,177,649 3 NETWORK OPTION 3 $84,726,348 2 $100,818,186 2 $98,207,316 2 $80,351,441 2 $112,666,714 3 $106,977,432 3 $89,279,378 2 $89,279,378 2 $89,279,378 2 $89,279,378 2 $84,124,356 2 $92,728,888 2
Table 3: Sensitivity Analysis - Comparison of Options Option 1 is clearly the lowest cost option in the majority of options considered.
Page 12
4.0
Description of Works
To address the limitations at SSALY, SSWED, SSWRD it is proposed to establish a new zone substation at Buranda. Works include: Extension and energisation at 33kV of existing 11kV feeders ALY7 & ALY11 (constructed at 33kV and energised at 11kV) to the new substation site at Buranda and connect to spare 33 kV CBs at SSALY. Establishment of a double modular Buranda zone substation (SSBDA) with 2 x 25 MV.A 33/11 kV transformers, 2 x 11 kV switchboards and 2 x 33 kV switchboards. Installation of 1 x 5.4Mvar capacitor bank. Establishment of 5 x 11 kV feeders at the proposed SSBDA. Reconfigure existing 11 kV network.
The network requirement date for completion of the recommended development is October 2010. Shown below is a geographic view of the proposed network on completion of the recommended works.
WEST END SOUTHPOINT DEVELOPMENT QLD CHILDRENS HOSPITAL BOGGO RD PRECINCT PA UPGRADE PHARMACY AUST PROJECT TRANSLATIONAL RESEARCH CENTRE SSBDA SITE
F3 F3 460 46 1
SSWRD
EAST BRISBANE
BURANDA
ANNERLEY
F905
SSALY
F637 F638
SST142
F5 F5 84 79
SSWED
Page 13
Shown below is a schematic view of the proposed network on completion of the recommended works.
Figure 9: Proposed Network Arrangement (Schematic View) Shown below is a geographic view of the proposed 11kV network on completion of the recommended works
Page 14
4.2
4.2.1
SSWRD
Subtransmission Network
The 10 year 10% POE and 50% POE load forecasts, and the normal cyclic capacity (NCC), emergency cyclic capacity (ECC), 2 hour emergency capacity (2HEC) and residual load at risk (RLAR) of SSWRD are shown below:
80 60 40 20 0
1 P OE Lo ad 0% Summer NCC 50% P OE Lo ad (SSWRD) Summer ECC (SSWRD) 2HEC RLA R 2008/09 57.40 1 26.00 54.93 69.00 75.00 0.00 2009/1 0 70.40 1 26.00 67.37 69.00 75.00 0.00 201 1 0/1 74.76 1 26.00 71 .54 69.00 75.00 0.00 201 /1 1 2 77.00 1 26.00 73.69 69.00 75.00 0.00 201 3 2/1 79.31 1 26.00 75.90 69.00 75.00 0.00 201 4 3/1 81 .69 1 26.00 78.1 7 69.00 75.00 1 .42 201 5 4/1 84.1 4 1 26.00 80.52 69.00 75.00 3.77 201 6 5/1 86.67 1 26.00 82.94 69.00 75.00 6.1 9 201 7 6/1 89.27 1 26.00 85.42 69.00 75.00 8.67 201 8 7/1 91 .95 1 26.00 87.99 69.00 75.00 1 .24 1 201 9 8/1 94.70 1 26.00 90.63 69.00 75.00 1 3.88
Figure 11: SSWRD Load Forecast (Proposed Network) As outlined above, SSBDA de-loads SSWRD to below 2HEC until 2012/13 (Project WR366224 will de-load SSWRD further).
Page 15
SSWED
The 10 year 10% POE and 50% POE load forecasts, and the normal cyclic capacity (NCC), emergency cyclic capacity (ECC), 2 hour emergency capacity (2HEC) and residual load at risk (RLAR) of SSWED are shown below:
80 60 40 20 0
1 P OE Lo ad 0% Summer NCC 50% P OE Lo ad (SSWED) Summer ECC (SSWED) Summer 2HEC RLA R 2008/09 72.70 1 26 69.80 69.00 75.00 0.00 2009/1 0 75.61 1 26 72.35 69.00 75.00 0.00 201 1 0/1 68.63 1 26 65.68 69.00 75.00 0.00 201 /1 1 2 71 .38 1 26 68.30 69.00 75.00 0.00 201 3 2/1 74.23 1 26 71 .04 69.00 75.00 0.00 201 4 3/1 77.20 1 26 73.88 69.00 75.00 0.28 201 5 4/1 80.29 1 26 76.83 69.00 75.00 3.33 201 6 5/1 83.50 1 26 79.91 69.00 75.00 6.41 201 7 6/1 86.84 1 26 83.1 0 69.00 75.00 9.60 201 8 7/1 90.32 1 26 86.43 69.00 75.00 1 2.93 201 9 8/1 93.93 1 26 89.88 69.00 75.00 1 6.38
Figure 12: SSWED Load Forecast (Proposed Network) As outlined above, SSBDA de-loads SSWED to below 2HEC until summer 2014/15 (Project WR366224 will de-load SSWED further).
Page 16
SSALY
The 10 year 10% POE and 50% POE load forecasts, and the normal cyclic capacity (NCC), emergency cyclic capacity (ECC), 2 hour emergency capacity (2HEC) and residual load at risk (RLAR) of SSALY are shown below:
30 20 10 0
1 P OE Lo ad (SSA LY) 0% Summer NCC (SSA LY) 50% P OE Lo ad (SSA LY) Summer ECC (SSA LY) Summer 2HEC (SSA LY) RLA R (SSA LY) 2008/09 33.81 55.00 31 .90 28.75 31 .25 0.00 2009/1 0 34.83 55.00 32.86 28.75 31 .25 0.00 201 1 0/1 23.80 55.00 22.45 28.75 31 .25 0.00 201 /1 1 2 24.51 55.00 23.1 3 28.75 31 .25 0.00 201 3 2/1 25.25 55.00 23.82 28.75 31 .25 0.00 201 4 3/1 26.01 55.00 24.53 28.75 31 .25 0.00 201 5 4/1 26.79 55.00 25.27 28.75 31 .25 0.00 201 6 5/1 27.59 55.00 26.03 28.75 31 .25 0.00 201 7 6/1 28.42 55.00 26.81 28.75 31 .25 0.00 201 8 7/1 29.27 55.00 27.61 28.75 31 .25 0.00 201 9 8/1 30.1 5 55.00 28.44 28.75 31 .25 0.00
Figure 13: SSALY Load Forecast (Proposed Network) As outlined above, SSBDA de-loads SSALY to below 2HEC beyond 2018/19.
Page 17
SSBDA
The 10 year 10% POE and 50% POE load forecasts, and the normal cyclic capacity (NCC), emergency cyclic capacity (ECC), 2 hour emergency capacity (2HEC) and residual load at risk (RLAR) of SSBDA are shown below:
SSBDA-Load Forecast 60 50 40
MV.A
30 20 10 0
1 P OE Lo ad 0% Summer NCC 50% P OE Lo ad Summer ECC Summer 2HEC RLA R 2008/09 0.00 55.00 0.00 28.75 31 .25 0.00 2009/1 0 0.00 55.00 0.00 28.75 31 .25 0.00 201 1 0/1 31 .53 55.00 30.1 7 28.75 31 .25 0.00 201 /1 1 2 32.48 55.00 31 .08 28.75 31 .25 0.00 201 3 2/1 33.45 55.00 32.01 28.75 31 .25 0.00 201 4 3/1 34.45 55.00 32.97 28.75 31 .25 0.00 201 5 4/1 35.49 55.00 33.96 28.75 31 .25 0.21 201 6 5/1 36.55 55.00 34.98 28.75 31 .25 1 .23 201 7 6/1 37.65 55.00 36.03 28.75 31 .25 2.28 201 8 7/1 38.78 55.00 37.1 1 28.75 31 .25 3.36 201 9 8/1 39.94 55.00 38.22 28.75 31 .25 4.47
Figure 14: SSALY Load Forecast (Proposed Network) Project WR366224 will de-load SSBDA in summer 2012/13.
Page 18
4.2.2
Distribution Network
Figure 15: 11kV Feeder Load Forecast (Proposed Network) As outlined above, the 11kV feeders are below target utilisation.
4.2.3
Network Reliability
The expected improvement to the urban network reliability is forecast to be 0.26 SAIDI minutes on an average 3 year basis.
4.2.4
Network Losses
To date ENERGEX has voluntarily reported its greenhouse gas emissions under the Greenhouse Challenge. Commencing in 2008/2009, ENERGEX is required, under the National Greenhouse and Energy Reporting Act 2007 to compulsorily report its contribution to the national greenhouse inventory. Network losses have been identified by quantification of greenhouse gas emissions as one of the significant control opportunities associated with reducing these emissions. The expected savings in network losses are forecast to be negligible.
Page 19
4.3
Project Timing
As the date of practical completion is consistent with the network requirement date, the level of network risk associated with this project can be managed using existing network contingency plans
2008/09 2 2 Low
2009/10 2 2 Low
2010/11 3 3
2011/12 3 3
Moderate Moderate
2008/09 1 1 Low
2009/10 2 2 Low
2010/11 3 3
2011/12 3 3
Moderate Moderate
2008/09 1 1
2009/10 2 2
2010/11 3 3
2011/12 3 3
Table 6: SSWRD Risk Rating As outlined in the table above, it has been determined that it results in a Moderate risk to defer the date of practical completion beyond the network requirement date.
Page 20
4.4
The following projects that affect SSALY, SSWRD, and SSWED have been identified: WR366224 WOOLOONGABBA Establish 110/11kV 2x60MVA Zone Substation by 2013. This project will de-load the CBD East network in particular 110kV feeders F7288 & F7287 as well as de-loading zone substations SSBDA, SSWED and SSWRD. DP20459 ANNERLEY SSALY Establish new 11kV feeder to the west by 2010. This project will utilise 11kV feeder ALY7 or ALY11.
5.0
Page 21
6.0
BUDGET PROVISION
The Budget Provision is outlined in the following table in 2008/09 dollars: Budget Composition Cost Component (in 08/09 dollars) $9,824,939 Transmission Distribution TOTAL $1,176,958 $11,001,897 Financial Year Provision Cost FY (in 08/09 dollars) $53,187 2007/08 2008/09 2009/10 20010/11 Total Project Cost Table 7: Budget Provision $60,414 $4,652,485 $6,235,811 $11,001,897
7.0
DRAFT RECOMMENDATION
Based on the conclusions drawn from the analysis and the Rules requirements relating to New Large Distribution Network Augmentation, it is recommended that the following action be taken to address the future supply requirements of the Gympie area:
1.
Establish a 33/11kV 25MV.A double modular zone substation at Buranda (SSBDA) and reconfigure the 11kV network by October 2010, for a total estimated cost of $11,001,897 at 2008/09 prices.
8.0
CONSULTATION
In accordance with Rules requirements, ENERGEX invites submissions from Registered Participants and interested parties on this Consultation Report. Submissions are due by Friday 19 December 2008. Please address submissions to: Bevan Holcombe Network Performance Reporting Manager ENERGEX Limited GPO Box 1461 Brisbane QLD 4001 Tel: (07) 3407 4061 bevanholcombe@energex.com.au Following consideration of submissions, ENERGEX expects to publish a Final Report in January 2009.
Page 22
5 10 16
Rating (A)
SN WD WN
379 303 277 NA NA 277 277 379 379 379 379 379
379 303 277 NA NA 277 277 379 379 379 379 379
410 328 300 NA NA 300 300 410 410 410 410 410
410 328 300 NA NA 300 300 410 410 410 410 410
Table 9: 11kV Feeder Load Forecast and Ratings in 20010/11 (Proposed Network)
Page 23
Existing
(kW)
Proposed
(kW)
Saving
(kW)
Page 24